Calendario Valorizado 15-03-2024
Calendario Valorizado 15-03-2024
Calendario Valorizado 15-03-2024
CREACION DEL SERVICIO DE PRÁCTICA DEPORTIVA Y/O RECREATIVA EN EL AA.HH. 27 DE NOVIEMBRE DEL DISTRITO DE YANACANCHA DE LA PROVINCIA DE PASCO DEL DEPARTAMENTO DE PASCO
PROYECTO:
CLIENTE: Municipalidad Distrital de Yanacancha
UBICACION: Av. Las Americas S/N
FECHA BASE: 3/15/2024
MONEDA: SOLES
COSTOS METRADOS
Item Partida Unidad Metrado PU Parcial MES 1 MES 2 MES 3 MES 4 MES 1 MES 2 MES 3 MES 4
1 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD 14,839.03 9,444.59 3,847.79 1,141.57 405.08 0.00 0.00
1.1 OBRAS PROVISIONALES 8,015.87 3,312.81 3,559.72 843.89 299.45 0.00 0.00
1.1.1 CARTEL DE IDENTIFICACION DE OBRA 2.40X3.60m und 1.00 994.11 994.11 994.11 1.00 0.00 0.00 0.00
1.1.2 ALQUILER DE LOCAL PARA ALMACEN, GUARDIANIA Y OFICINA DE OBRA mes 3.00 250.00 750.00 150.00 250.00 258.33 91.67 0.60 1.00 1.03 0.37
1.1.3 FLETE TERRESTRE glb 1.00 4,571.76 4,571.76 1,828.70 2,743.06 0.40 0.60 0.00 0.00
1.1.4 INSTALACION DEL SERVICIO DE AGUA Y DESAGUE GLB 1.00 850.00 850.00 170.00 283.33 292.78 103.89 0.20 0.33 0.34 0.12
1.1.5 INSTALACION DEL SERVICIO DE ENERGIA ELECTRICA GLB 1.00 850.00 850.00 170.00 283.33 292.78 103.89 0.20 0.33 0.34 0.12
1.2 TRABAJOS PRELIMINARES 5,958.94 5,958.94 0.00 0.00 0.00 0.00
1.2.1 LIMPIEZA MANUAL DE TERRENO M2 846.44 2.01 1,701.34 1,701.34 846.44 0.00 0.00 0.00
1.2.2 TRAZO Y REPLANTEO PRELIMINAR m2 846.44 2.63 2,226.14 2,226.14 846.44 0.00 0.00 0.00
1.2.3 TRAZO Y REPLANTEO DE NIVELES DURANTE EL PROCESO DE EJECUCION m2 846.44 2.40 2,031.46 2,031.46 846.44 0.00 0.00 0.00
1.3 SEGURIDAD Y SALUD 864.22 172.84 288.07 297.68 105.63 0.00 0.00 0.00 0.00
1.3.1 SEÑALIZACION DE SEGURIDAD m 90.00 8.19 737.10 147.42 245.70 253.89 90.09 18.00 30.00 31.00 11.00
1.3.2 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TR glb 1.00 127.12 127.12 25.42 42.37 43.79 15.54 0.20 0.33 0.34 0.12
2 CONSTRUCCION DE LA LOSA DEPORTIVA CON GRASS SINTETICO 107,721.31 1,977.98 105,358.87 384.47 0.00 0.00 0.00 0.00
2.1 MOVIMIENTO DE TIERRAS 31,360.74 1,977.98 29,382.77 0.00 0.00 0.00 0.00
2.1.1 CORTE DE NIVEL DE SUB RASANTE EN TERRENO SEMIRROCOSO m3 253.10 15.63 3,955.95 1,977.98 1,977.98 0.00 126.55 126.55 0.00
2.1.2 NIVELACION, PERFILADO Y COMPACTADO DEL TERRENO m2 626.18 2.73 1,709.47 1,709.47 0.00 0.00 626.18 0.00
2.1.3 RELLENO Y COMPACTADO DE BASE PARA GRASS m2 622.38 34.24 21,310.29 21,310.29 0.00 0.00 622.38 0.00
2.1.4 ELIMINACION DE MATERIAL EXCEDENTE m3 316.38 13.86 4,385.03 4,385.03 0.00 0.00 316.38 0.00
2.2 SARDINEL DE BORDE 5,083.02 4,698.55 384.47 0.00 0.00 0.00 0.00
2.2.1 CONCRETO SIMPLE 4,698.55 4,698.55 0.00 0.00 0.00 0.00
2.2.1.1 CONCRETO FC=175 KG/CM2 EN SARDINEL M3 3.46 364.48 1,261.10 1,261.10 0.00 0.00 3.46 0.00
2.2.1.2 ENCOFRADO Y DESENCOFRADO EN SARDINEL m2 69.15 49.71 3,437.45 3,437.45 0.00 0.00 69.15 0.00
2.2.2 PINTURA 384.47 384.47 0.00 0.00 0.00 0.00
2.2.2.1 PINTURA ESMALTE EN SARDINEL M 69.15 5.56 384.47 384.47 0.00 0.00 0.00 69.15
2.3 SUMINISTRO E INSTALACION DE GRASS SINTETICO MONOFILAMENTO 42,664.15 42,664.15 0.00 0.00 0.00 0.00
2.3.1 SUMINISTRO E INSTALACION DE GRASS SINTETICO DE 50 mm VERDE INCL. LINEAS BLANCAS m2 622.38 68.55 42,664.15 42,664.15 0.00 0.00 622.38 0.00
2.4 VARIOS 6,076.76 6,076.76 0.00 0.00 0.00 0.00
2.4.1 ARCO METALICO CON MALLA OLIMPICA und 2.00 2,345.11 4,690.22 4,690.22 0.00 0.00 2.00 0.00
2.4.2 NET DE VOLEY N° 90 CON BANDA REFORZADA UND 1.00 369.59 369.59 369.59 0.00 0.00 1.00 0.00
2.4.3 CONTENEDORES DE MALLA PARA RECICLAJE DE BOTELLAS DE PLASTICO 400L UND 1.00 1,016.95 1,016.95 1,016.95 0.00 0.00 1.00 0.00
2.5 SISTEMA DE EVACUACION PLUVIAL 22,536.64 22,536.64 0.00 0.00 0.00 0.00
2.5.1 MOVIMIENTO DE TIERRAS 2,161.48 2,161.48 0.00 0.00 0.00 0.00
2.5.1.1 EXCAVACION DE ZANJA EN TERRENO SEMIRROCOSO m3 33.31 15.63 520.64 520.64 0.00 0.00 33.31 0.00
2.5.1.2 RELLENO Y COMPACTADO DE ZANJAS DE 0.20X0.30 PARA TUBERIA DE DESAGUE D=4" M3 14.88 88.82 1,321.64 1,321.64 0.00 0.00 14.88 0.00
2.5.1.3 ELIMINACION DE MATERIAL EXCEDENTE m3 23.03 13.86 319.20 319.20 0.00 0.00 23.03 0.00
2.5.2 CANAL COLECTOR DE AGUAS PLUVIALES 2,386.07 2,386.07 0.00 0.00 0.00 0.00
2.5.2.1 SUMINISTRO Y COLOCACION DE TUBERIA PARA DRENAJE PVC SAP 4" m 104.70 15.67 1,640.65 1,640.65 0.00 0.00 104.70 0.00
2.5.2.2 SUMINISTRO Y COLOCACION DE TUBERIA PVC SAP 6" P/EMPALME DE CAJAS DE REGISTRO ML 21.60 34.51 745.42 745.42 0.00 0.00 21.60 0.00
2.5.3 CANAL COLECTOR DE AGUAS PLUVIALES 13,192.13 13,192.13 0.00 0.00 0.00 0.00
2.5.3.1 CONCRETO FC=175 KG/CM2 M3 17.95 364.48 6,542.42 6,542.42 0.00 0.00 17.95 0.00
2.5.3.2 ENCOFRADO Y DESENCOFRADO m2 133.77 49.71 6,649.71 6,649.71 0.00 0.00 133.77 0.00
CALENDARIO VALORIZADO DE OBRA
CREACION DEL SERVICIO DE PRÁCTICA DEPORTIVA Y/O RECREATIVA EN EL AA.HH. 27 DE NOVIEMBRE DEL DISTRITO DE YANACANCHA DE LA PROVINCIA DE PASCO DEL DEPARTAMENTO DE PASCO
PROYECTO:
CLIENTE: Municipalidad Distrital de Yanacancha
UBICACION: Av. Las Americas S/N
FECHA BASE: 3/15/2024
MONEDA: SOLES
COSTOS METRADOS
Item Partida Unidad Metrado PU Parcial MES 1 MES 2 MES 3 MES 4 MES 1 MES 2 MES 3 MES 4
2.5.4 CAJA DE REGISTRO PARA DRENAJE PLUVIAL 1,448.74 1,448.74 0.00 0.00 0.00 0.00
2.5.4.1 CONCRETO FC=175 KG/CM2 M3 2.57 364.48 936.71 936.71 0.00 0.00 2.57 0.00
2.5.4.2 ENCOFRADO Y DESENCOFRADO m2 9.56 53.56 512.03 512.03 0.00 0.00 9.56 0.00
2.5.5 VARIOS 3,348.22 3,348.22 0.00 0.00 0.00 0.00
2.5.5.1 REJILLA METALICA M 70.40 47.56 3,348.22 3,348.22 0.00 0.00 70.40 0.00
3 CONSTRUCCION DE TRIBUNA CON COBERTURA METALICA 47,639.78 773.05 27,441.15 19,425.58 0.00 0.00 0.00 0.00
3.1 MOVIMIENTO DE TIERRAS 2,668.84 2,668.84 0.00 0.00 0.00 0.00
3.1.1 CORTE DE NIVEL DE SUB RASANTE EN TERRENO SEMI ROCOSO m3 75.95 15.63 1,187.10 1,187.10 0.00 0.00 75.95 0.00
3.1.2 NIVELACION, PERFILADO Y COMPACTADO DEL TERRENO m2 60.76 2.73 165.87 165.87 0.00 0.00 60.76 0.00
3.1.3 ELIMINACION DE MATERIAL EXCEDENTE m3 94.94 13.86 1,315.87 1,315.87 0.00 0.00 94.94 0.00
3.2 CONCRETO SIMPLE 27,771.51 9,036.77 18,734.74 0.00 0.00 0.00 0.00
3.2.1 CONCRETO 1:8+25%P.M. PARA TRIBUNAS m3 75.95 277.60 21,083.72 4,216.74 16,866.98 0.00 0.00 15.19 60.76
3.2.2 ENCOFRADO Y DESENCOFRADO DE TRIBUNAS m2 78.26 61.59 4,820.03 4,820.03 0.00 0.00 78.26 0.00
3.2.3 PISO CON ACABADO FROTACHADO m2 121.52 15.37 1,867.76 1,867.76 0.00 0.00 0.00 121.52
3.3 CARPINTERIA METALICA 16,508.59 773.05 15,735.54 0.00 0.00 0.00 0.00
3.3.1 VIGAS METALICAS DE TUBO NEGRO 4" X 4" X 3MM M 49.50 109.32 5,411.34 773.05 4,638.29 0.00 7.07 42.43 0.00
3.3.2 CORREAS DE TUBO DE FIERRO NEGRO DE 2" X 2" X 2.00MM M 182.28 31.69 5,776.45 5,776.45 0.00 0.00 182.28 0.00
3.3.3 COBERTURA CON ALUZINC TR4 M2 101.80 38.45 3,914.21 3,914.21 0.00 0.00 101.80 0.00
3.3.4 CANALETA GALVANIZADA 6" M 60.76 23.15 1,406.59 1,406.59 0.00 0.00 60.76 0.00
3.4 PINTURA 690.84 690.84 0.00 0.00 0.00 0.00
3.4.1 PINTURA DE CONTRAPASOS EN TRIBUNA M2 60.76 11.37 690.84 690.84 0.00 0.00 0.00 60.76
4 AREA DE CIRCULACION 11,079.52 11,079.52 0.00 0.00 0.00 0.00
4.1 MOVIMIENTO DE TIERRAS 2,022.22 2,022.22 0.00 0.00 0.00 0.00
4.1.1 CORTE DE NIVEL DE SUB RASANTE EN TERRENO SEMI ROCOSO m3 17.51 15.63 273.68 273.68 0.00 0.00 17.51 0.00
4.1.2 NIVELACION, PERFILADO Y COMPACTADO DEL TERRENO m2 87.54 2.73 238.98 238.98 0.00 0.00 87.54 0.00
4.1.3 SUB BASE AFIRMADO DE E=0.10M EN VEREDA m2 87.54 13.78 1,206.30 1,206.30 0.00 0.00 87.54 0.00
4.1.4 ELIMINACION DE MATERIAL EXCEDENTE m3 21.88 13.86 303.26 303.26 0.00 0.00 21.88 0.00
4.2 OBRAS DE CONCRETO SIMPLE 5,597.52 5,597.52 0.00 0.00 0.00 0.00
4.2.1 CONCRETO FC=175 KG/CM2 EN VEREDAS M2 87.54 56.14 4,914.50 4,914.50 0.00 0.00 87.54 0.00
4.2.2 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 13.74 49.71 683.02 683.02 0.00 0.00 13.74 0.00
4.3 INSTALACION DE LUMINARIAS 3,459.78 3,459.78 0.00 0.00 0.00 0.00
4.3.1 LUMINARIA SOLAR TIPO PASTORAL 400W UND 6.00 576.63 3,459.78 3,459.78 0.00 0.00 6.00 0.00
5 CERCO PERIMETRICO 88,016.37 9,943.31 32,699.21 20,918.80 24,455.05 0.00 0.00 0.00 0.00
5.1 MOVIMIENTO DE TIERRAS 1,364.04 582.53 781.51 0.00 0.00 0.00 0.00
5.1.1 EXCAVACION DE ZANJA EN TERRENO SEMI ROCOSO m3 37.27 15.63 582.53 582.53 37.27 0.00 0.00 0.00
5.1.2 RELLENO CON MATERIAL PROPIO m3 5.30 15.53 82.31 82.31 0.00 5.30 0.00 0.00
5.1.3 NIVELACION, PERFILADO Y COMPACTADO DEL TERRENO m2 53.24 2.73 145.35 145.35 0.00 53.24 0.00 0.00
5.1.4 ELIMINACION DE MATERIAL EXCEDENTE m3 39.96 13.86 553.85 553.85 0.00 39.96 0.00 0.00
5.2 CONCRETO SIMPLE 13,275.39 13,275.39 0.00 0.00 0.00 0.00
5.2.1 CONCRETO CICLÓPEO 1:10+30% PG PARA CIMIENTOS M3 24.26 209.57 5,084.17 5,084.17 0.00 24.26 0.00 0.00
5.2.2 CONCRETO 1:8+25%P.M. PARA SOBRECIMIENTOS m3 8.71 277.60 2,417.90 2,417.90 0.00 8.71 0.00 0.00
5.2.3 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTO m2 116.14 49.71 5,773.32 5,773.32 0.00 116.14 0.00 0.00
5.3 CONCRETO ARMADO 27,720.85 9,360.78 11,859.42 6,500.65 0.00 0.00 0.00 0.00
CALENDARIO VALORIZADO DE OBRA
CREACION DEL SERVICIO DE PRÁCTICA DEPORTIVA Y/O RECREATIVA EN EL AA.HH. 27 DE NOVIEMBRE DEL DISTRITO DE YANACANCHA DE LA PROVINCIA DE PASCO DEL DEPARTAMENTO DE PASCO
PROYECTO:
CLIENTE: Municipalidad Distrital de Yanacancha
UBICACION: Av. Las Americas S/N
FECHA BASE: 3/15/2024
MONEDA: SOLES
COSTOS METRADOS
Item Partida Unidad Metrado PU Parcial MES 1 MES 2 MES 3 MES 4 MES 1 MES 2 MES 3 MES 4
5.3.1 ZAPATAS 362.85 362.85 0.00 0.00 0.00 0.00
5.3.1.1 CONCRETO PARA ZAPATAS F´C=210 KG/CM2 M3 0.64 441.13 282.32 282.32 0.00 0.64 0.00 0.00
5.3.1.2 ACERO CORRUGADO F´Y = 4200 KG/CM2 KG 13.86 5.81 80.53 80.53 0.00 13.86 0.00 0.00
5.3.2 COLUMNAS 11,248.32 8,299.97 2,948.35 0.00 0.00 0.00 0.00
5.3.2.1 CONCRETO F'C=210 KG/CM2 PARA COLUMNAS M3 5.23 461.41 2,413.17 861.85 1,551.32 0.00 1.87 3.36 0.00
5.3.2.2 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2 43.84 59.75 2,619.44 1,222.41 1,397.03 0.00 20.46 23.38 0.00
5.3.2.3 ACERO CORRUGADO F´Y = 4200 KG/CM2 KG 1,069.83 5.81 6,215.71 6,215.71 0.00 1,069.83 0.00 0.00
5.3.3 VIGAS 6,748.90 3,196.60 3,552.30 0.00 0.00 0.00 0.00
5.3.3.1 CONCRETO F'C=210 KG/CM2 PARA VIGAS M3 3.34 461.41 1,541.11 1,541.11 0.00 0.00 3.34 0.00
5.3.3.2 ENCOFRADO Y DESENCOFRADO PARA VIGAS m2 33.66 59.75 2,011.19 2,011.19 0.00 0.00 33.66 0.00
5.3.3.3 ACERO CORRUGADO F´Y = 4200 KG/CM2 KG 550.19 5.81 3,196.60 3,196.60 0.00 550.19 0.00 0.00
5.3.4 MURO DE CONTENCION 9,360.78 9,360.78 0.00 0.00 0.00 0.00
5.3.4.1 CONCRETO F'C=210 KG/CM2 PARA MURO DE CONTENCION M3 8.69 461.41 4,009.65 4,009.65 8.69 0.00 0.00 0.00
5.3.4.2 ENCOFRADO Y DESENCOFRADO PARA MURO DE CONTENCION m2 36.30 59.75 2,168.93 2,168.93 36.30 0.00 0.00 0.00
5.3.4.3 ACERO CORRUGADO F´Y = 4200 KG/CM2 KG 547.71 5.81 3,182.20 3,182.20 547.71 0.00 0.00 0.00
5.4 MUROS Y TABIQUES DE ALBAÑILERIA 11,304.82 6,782.89 4,521.93 0.00 0.00 0.00 0.00
5.4.1 MURO DE LADRILLO KK DE ARCILLA, N-SOG. MEZCLA 1:4 M2 150.31 75.21 11,304.82 6,782.89 4,521.93 0.00 90.19 60.12 0.00
5.5 REVOQUES, ENLUCIDOS Y MOLDURAS 14,074.48 14,074.48 0.00 0.00 0.00 0.00
5.5.1 TARRAJEO EN COLUMNAS CON C.A. 1:5, E=1.5CM M2 41.60 29.18 1,213.89 1,213.89 0.00 0.00 0.00 41.60
5.5.2 TARRAJEO EN VIGAS CON C:A-1:5 E=1.5CM M2 34.53 29.18 1,007.59 1,007.59 0.00 0.00 0.00 34.53
5.5.3 TARRAJEO EN SOBRECIMIENTO CON C:A-1:5 E=1.5CM M2 115.73 27.03 3,128.18 3,128.18 0.00 0.00 0.00 115.73
5.5.4 TARRAJEO INTERIOR EN MUROS CON C:A-1:5 E=1.5CM M2 149.50 29.18 4,362.41 4,362.41 0.00 0.00 0.00 149.50
5.5.5 TARRAJEO EXTERIOR EN MUROS CON C:A-1:5 E=1.5CM M2 149.50 29.18 4,362.41 4,362.41 0.00 0.00 0.00 149.50
5.6 PINTURA 6,986.83 6,986.83 0.00 0.00 0.00 0.00
5.6.1 PINTURA LATEX LAVABLE 02 MANOS EN COLUMNAS M2 41.60 11.37 472.99 472.99 0.00 0.00 0.00 41.60
5.6.2 PINTURA LATEX LAVABLE 02 MANOS EN VIGAS M2 34.53 11.99 414.01 414.01 0.00 0.00 0.00 34.53
5.6.3 PINTURA LATEX LAVABLE 02 MANOS EN SOBRECIMIENTO M2 115.73 10.82 1,252.20 1,252.20 0.00 0.00 0.00 115.73
5.6.4 PINTURA LATEX LAVABLE 02 MANOS EN INTERIOR MUROS M2 149.50 11.37 1,699.82 1,699.82 0.00 0.00 0.00 149.50
5.6.5 PINTURA LATEX LAVABLE 02 MANOS EN EXTERIOR MUROS M2 149.50 11.37 1,699.82 1,699.82 0.00 0.00 0.00 149.50
5.6.6 PINTURA ESMALTE SINTETICO ANTICORROSIVO EN CARPINTERIA METALICA M2 76.13 19.02 1,447.99 1,447.99 0.00 0.00 0.00 76.13
5.7 VARIOS 890.47 43.01 847.46 0.00 0.00 0.00 0.00
5.7.1 JUNTA DE DILATACION CON TEKNOPORT E=1" M 11.20 3.84 43.01 43.01 0.00 0.00 11.20 0.00
5.7.2 PLACA RECORDATORIA UND 1.00 847.46 847.46 847.46 0.00 0.00 0.00 1.00
5.8 CARPINTERIA METALICA 12,399.49 9,853.21 2,546.28 0.00 0.00 0.00 0.00
5.8.1 CERCO METALICO m 33.10 297.68 9,853.21 9,853.21 0.00 0.00 33.10 0.00
5.8.2 PUERTA METALICA DE ACCESO PRINCIPAL SEGUN DISEÑO UND 1.00 2,546.28 2,546.28 2,546.28 0.00 0.00 0.00 1.00
6 SERVICIOS HIGIENICOS 44,076.67 187.09 28,781.99 11,129.64 3,977.95 0.00 0.00 0.00 0.00
6.1 ESTRUCTURAS 17,409.21 17,409.21 0.00 0.00 0.00 0.00
6.1.1 MOVIMIENTO DE TIERRAS 226.30 226.30 0.00 0.00 0.00 0.00
6.1.1.1 EXCAVACION DE ZANJA EN TERRENO SEMI ROCOSO m3 6.05 15.63 94.56 94.56 0.00 6.05 0.00 0.00
6.1.1.2 RELLENO CON MATERIAL PROPIO m3 0.33 15.53 5.12 5.12 0.00 0.33 0.00 0.00
6.1.1.3 NIVELACION, PERFILADO Y COMPACTADO DEL TERRENO m2 10.08 2.73 27.52 27.52 0.00 10.08 0.00 0.00
6.1.1.4 ELIMINACION DE MATERIAL EXCEDENTE m3 7.15 13.86 99.10 99.10 0.00 7.15 0.00 0.00
CALENDARIO VALORIZADO DE OBRA
CREACION DEL SERVICIO DE PRÁCTICA DEPORTIVA Y/O RECREATIVA EN EL AA.HH. 27 DE NOVIEMBRE DEL DISTRITO DE YANACANCHA DE LA PROVINCIA DE PASCO DEL DEPARTAMENTO DE PASCO
PROYECTO:
CLIENTE: Municipalidad Distrital de Yanacancha
UBICACION: Av. Las Americas S/N
FECHA BASE: 3/15/2024
MONEDA: SOLES
COSTOS METRADOS
Item Partida Unidad Metrado PU Parcial MES 1 MES 2 MES 3 MES 4 MES 1 MES 2 MES 3 MES 4
6.1.2 CONCRETO SIMPLE 2,332.13 2,332.13 0.00 0.00 0.00 0.00
6.1.2.1 CONCRETO PARA SOLADOS, E=0.10 M. C:H, 1:12 M2 5.12 25.17 128.87 128.87 0.00 5.12 0.00 0.00
6.1.2.2 CONCRETO CICLÓPEO 1:10+30% PG PARA CIMIENTOS M3 2.98 209.57 624.52 624.52 0.00 2.98 0.00 0.00
6.1.2.3 CONCRETO 1:8+25%P.M. PARA SOBRECIMIENTOS m3 1.15 277.60 319.24 319.24 0.00 1.15 0.00 0.00
6.1.2.4 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTO m2 15.30 49.71 760.56 760.56 0.00 15.30 0.00 0.00
6.1.2.5 CONCRETO PARA FALSO PISO E=4" MEZCLA 1:8 C:H M2 15.64 27.59 431.51 431.51 0.00 15.64 0.00 0.00
6.1.2.6 CONCRETO FC=175 KG/CM2 EN SARDINEL DE URINARIO M3 0.05 364.48 18.22 18.22 0.00 0.05 0.00 0.00
6.1.2.7 ENCOFRADO Y DESENCOFRADO EN SARDINEL DE URINARIO m2 0.99 49.71 49.21 49.21 0.00 0.99 0.00 0.00
6.1.3 CONCRETO ARMADO 14,850.78 14,850.78 0.00 0.00 0.00 0.00
6.1.3.1 ZAPATAS 1,460.58 1,460.58 0.00 0.00 0.00 0.00
6.1.3.1.1 CONCRETO PARA ZAPATAS F´C=210 KG/CM2 M3 2.56 441.13 1,129.29 1,129.29 0.00 2.56 0.00 0.00
6.1.3.1.2 ACERO CORRUGADO F´Y = 4200 KG/CM2 KG 57.02 5.81 331.29 331.29 0.00 57.02 0.00 0.00
6.1.3.2 COLUMNAS 6,689.71 6,689.71 0.00 0.00 0.00 0.00
6.1.3.2.1 CONCRETO F'C=210 KG/CM2 PARA COLUMNAS M3 2.85 461.41 1,315.02 1,315.02 0.00 2.85 0.00 0.00
6.1.3.2.2 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2 42.24 59.75 2,523.84 2,523.84 0.00 42.24 0.00 0.00
6.1.3.2.3 ACERO CORRUGADO F´Y = 4200 KG/CM2 KG 490.68 5.81 2,850.85 2,850.85 0.00 490.68 0.00 0.00
6.1.3.3 VIGAS 3,529.09 3,529.09 0.00 0.00 0.00 0.00
6.1.3.3.1 CONCRETO F'C=210 KG/CM2 PARA VIGAS M3 1.99 461.41 918.21 918.21 0.00 1.99 0.00 0.00
6.1.3.3.2 ENCOFRADO Y DESENCOFRADO PARA VIGAS m2 25.06 59.75 1,497.34 1,497.34 0.00 25.06 0.00 0.00
6.1.3.3.3 ACERO CORRUGADO F´Y = 4200 KG/CM2 KG 191.66 5.81 1,113.54 1,113.54 0.00 191.66 0.00 0.00
6.1.3.4 LOSA ALIGERADA 3,171.40 3,171.40 0.00 0.00 0.00 0.00
6.1.3.4.1 CONCRETO F'C=210 KG/CM2 PARA LOSA ALIGERADA M3 0.84 461.41 387.58 387.58 0.00 0.84 0.00 0.00
6.1.3.4.2 ENCOFRADO Y DESENCOFRADO PARA LOSA ALIGERADA m2 24.06 59.75 1,437.59 1,437.59 0.00 24.06 0.00 0.00
6.1.3.4.3 ACERO CORRUGADO F´Y = 4200 KG/CM2 KG 172.68 5.81 1,003.27 1,003.27 0.00 172.68 0.00 0.00
6.1.3.4.4 LADRILLO HUECO DE ARCILLA H = 15 CM PARA LOSA ALIGERADA PZA 158.78 2.16 342.96 342.96 0.00 158.78 0.00 0.00
6.2 ARQUITECTURA 8,933.47 3,662.34 4,679.78 591.35 0.00 0.00 0.00 0.00
6.2.1 ALBAÑILERIA 2,319.48 2,319.48 0.00 0.00 0.00 0.00
6.2.1.1 MURO DE LADRILLO KK DE ARCILLA, N-SOG. MEZCLA 1:4 M2 30.84 75.21 2,319.48 2,319.48 0.00 30.84 0.00 0.00
6.2.2 REVOQUES, ENLUCIDOS Y MOLDURAS 1,209.22 1,209.22 0.00 0.00 0.00 0.00
6.2.2.1 TARRAJEO INTERIOR EN MUROS CON C:A-1:5 E=1.5CM M2 30.84 29.18 899.91 899.91 0.00 30.84 0.00 0.00
6.2.2.2 TARRAJEO EXTERIOR EN MUROS CON C:A-1:5 E=1.5CM M2 10.60 29.18 309.31 309.31 0.00 10.60 0.00 0.00
6.2.3 CIELORASOS 133.64 133.64 0.00 0.00 0.00 0.00
6.2.3.1 TARRAJEO EN CILORASOS CON C:A-1:5 E=1.5CM M2 4.58 29.18 133.64 133.64 0.00 4.58 0.00 0.00
6.2.4 PISOS Y PAVIMENTOS 640.83 640.83 0.00 0.00 0.00 0.00
6.2.4.1 CONTRAPISO DE 2" M2 9.16 22.20 203.35 203.35 0.00 0.00 9.16 0.00
6.2.4.2 PISO LOSETA VENECIANA 30 X 30CM M2 9.16 47.76 437.48 437.48 0.00 0.00 9.16 0.00
6.2.5 CONTRAZOCALOS 226.17 226.17 0.00 0.00 0.00 0.00
6.2.5.1 CONTRAZÓCALO VENECIANO 10X30CM ML 26.00 7.38 191.88 191.88 0.00 0.00 26.00 0.00
6.2.5.2 ACABADO CERAMICO EN SARDINEL DE URINARIO M2 1.16 29.56 34.29 34.29 0.00 0.00 1.16 0.00
6.2.6 ZOCALOS 2,295.54 2,295.54 0.00 0.00 0.00 0.00
6.2.6.1 ZOCALO DE CERAMICAS 30X30 CM M2 46.80 49.05 2,295.54 2,295.54 0.00 0.00 46.80 0.00
6.2.7 CARPINTERIA DE MADERA 860.56 860.56 0.00 0.00 0.00 0.00
6.2.7.1 PUERTA CONTRAPLACADA 2.20 M X 0.90M UND 2.00 430.28 860.56 860.56 0.00 0.00 2.00 0.00
CALENDARIO VALORIZADO DE OBRA
CREACION DEL SERVICIO DE PRÁCTICA DEPORTIVA Y/O RECREATIVA EN EL AA.HH. 27 DE NOVIEMBRE DEL DISTRITO DE YANACANCHA DE LA PROVINCIA DE PASCO DEL DEPARTAMENTO DE PASCO
PROYECTO:
CLIENTE: Municipalidad Distrital de Yanacancha
UBICACION: Av. Las Americas S/N
FECHA BASE: 3/15/2024
MONEDA: SOLES
COSTOS METRADOS
Item Partida Unidad Metrado PU Parcial MES 1 MES 2 MES 3 MES 4 MES 1 MES 2 MES 3 MES 4
6.2.8 CARPINTERIA METALICA 295.32 295.32 0.00 0.00 0.00 0.00
6.2.8.1 VENTANA METALICA 2.20MX0.50M UND 2.00 147.66 295.32 295.32 0.00 0.00 2.00 0.00
6.2.9 CERRAJERIA 278.64 278.64 0.00 0.00 0.00 0.00
6.2.9.1 BISAGRA TIPO CAPUCHINA ALUMINIZADA 3 1/2" PZA 8.00 16.43 131.44 131.44 0.00 0.00 8.00 0.00
6.2.9.2 CERRADURA PARA BAÑO BRONCE PZA 2.00 73.60 147.20 147.20 0.00 0.00 2.00 0.00
6.2.10 VIDRIOS CRISTALES Y SIMILARES 82.72 82.72 0.00 0.00 0.00 0.00
6.2.10.1 VIDRIO INCOLORO SEMIDOBLE M2 2.20 37.60 82.72 82.72 0.00 0.00 2.20 0.00
6.2.11 PINTURA 591.35 591.35 0.00 0.00 0.00 0.00
6.2.11.1 PINTURA LATEX LAVABLE 02 MANOS EN INTERIOR MUROS M2 30.84 11.37 350.65 350.65 0.00 0.00 0.00 30.84
6.2.11.2 PINTURA LATEX LAVABLE 02 MANOS EN EXTERIOR MUROS M2 10.60 11.37 120.52 120.52 0.00 0.00 0.00 10.60
6.2.11.3 PINTURA LATEX LAVABLE 02 MANOS EN CIELORASOS M2 9.16 13.12 120.18 120.18 0.00 0.00 0.00 9.16
6.3 INSTALACIONES ELECTRICAS 3,516.34 187.09 1,634.33 1,694.92 0.00 0.00 0.00 0.00
6.3.1 SALIDA PARA ALUMBRADO, TOMACORRIENTE 3,516.34 187.09 1,634.33 1,694.92 0.00 0.00 0.00 0.00
6.3.1.1 SALIDA PARA CENTRO DE LUZ PTO 2.00 104.00 208.00 208.00 0.00 2.00 0.00 0.00
6.3.1.2 CONDUCTOR N2XH (6mm2) M 28.52 6.56 187.09 187.09 28.52 0.00 0.00 0.00
6.3.1.3 LUMINARIA CIRCULAR 24W UND 4.00 33.06 132.24 132.24 0.00 4.00 0.00 0.00
LETRERO LUMINOSO PRE FABRICADO (NOMBRE DE LUGAR EN
6.3.1.4 GLB 1.00 1,694.92 1,694.92 1,694.92 0.00 0.00 0.00 1.00
INGRESO PRINCIPAL)
6.3.1.5 INTERRUPTOR SIMPLE UND 2.00 11.78 23.56 23.56 0.00 2.00 0.00 0.00
6.3.1.6 POZO A TIERRA UND 1.00 794.88 794.88 794.88 0.00 1.00 0.00 0.00
6.3.1.7 TABLERO ELECTRICO DE METAL DE 12 POLOS UND 1.00 475.65 475.65 475.65 0.00 1.00 0.00 0.00
6.4 INSTALACIONES SANITARIAS 14,217.65 6,076.11 6,449.86 1,691.68 0.00 0.00 0.00 0.00
6.4.1 APARATOS Y ACCESORIOS SANITARIOS 3,553.36 3,553.36 0.00 0.00 0.00 0.00
6.4.1.1 INODORO TOP PIECE BLANCO COMERCIAL PZA 4.00 585.00 2,340.00 2,340.00 0.00 0.00 4.00 0.00
6.4.1.2 LAVATORIO SONET BLANCO STANDARD PZA 4.00 303.34 1,213.36 1,213.36 0.00 0.00 4.00 0.00
6.4.2 SISTEMA DE DESAGÜE 6,307.72 4,440.70 1,867.02 0.00 0.00 0.00 0.00
6.4.2.1 SALIDA DE DESAGUE PVC-SAL 2" PTO 6.00 68.98 413.88 413.88 0.00 6.00 0.00 0.00
6.4.2.2 SALIDA DE DESAGUE PVC-SAL 4" PTO 4.00 88.48 353.92 353.92 0.00 4.00 0.00 0.00
6.4.2.3 SALIDA DE VENTILACION PVC-SAL 2" PTO 2.00 92.76 185.52 185.52 0.00 2.00 0.00 0.00
6.4.2.4 TUBERIA PVC - U UF NTP ISO 4435 SERIE 25 DN 200mm, INCL. ANILLO + 2% DESPERDICIOS ML 55.43 59.06 3,273.70 3,273.70 0.00 55.43 0.00 0.00
6.4.2.5 DIVISION DE ALUMINIO EN SERVICIOS HIGIENICOS M2 18.76 95.32 1,788.20 1,788.20 0.00 0.00 18.76 0.00
6.4.2.6 REGISTRO DE BRONCE 4" UND 2.00 39.41 78.82 78.82 0.00 0.00 2.00 0.00
6.4.2.7 CAJA REGISTRO DE DESAGÜE 12" X 24" UND 2.00 106.84 213.68 213.68 0.00 2.00 0.00 0.00
6.4.3 BUZON DE REUNION 1,029.48 1,029.48 0.00 0.00 0.00 0.00
6.4.3.1 CONCRETO F'C=210 KG/CM2 PARA BUZON DE REUNION M3 0.93 461.41 429.11 429.11 0.00 0.00 0.93 0.00
6.4.3.2 ENCOFRADO Y DESENCOFRADO PARA BUZON DE REUNION m2 3.96 59.75 236.61 236.61 0.00 0.00 3.96 0.00
6.4.3.3 ACERO CORRUGADO F´Y = 4200 KG/CM2 KG 62.61 5.81 363.76 363.76 0.00 0.00 62.61 0.00
6.4.4 SISTEMA DE AGUA FRIA 3,327.09 1,635.41 1,691.68 0.00 0.00 0.00 0.00
6.4.4.1 SALIDA DE AGUA FRIA TUBERIA PVC CLASE 10, D = 1/2" PTO 3.00 46.12 138.36 138.36 0.00 3.00 0.00 0.00
6.4.4.2 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC CLASE 10 DE 1/2" M 15.92 6.95 110.64 110.64 0.00 15.92 0.00 0.00
6.4.4.3 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC CLASE 10 DE 3/4" M 72.43 9.32 675.05 675.05 0.00 72.43 0.00 0.00
6.4.4.4 VALVULA COMPUERTA Y ACCESORIOS DE 1/2" UND 2.00 68.85 137.70 137.70 0.00 2.00 0.00 0.00
6.4.4.5 VALVULA COMPUERTA Y ACCESORIOS DE 3/4" UND 2.00 102.91 205.82 205.82 0.00 2.00 0.00 0.00
CALENDARIO VALORIZADO DE OBRA
CREACION DEL SERVICIO DE PRÁCTICA DEPORTIVA Y/O RECREATIVA EN EL AA.HH. 27 DE NOVIEMBRE DEL DISTRITO DE YANACANCHA DE LA PROVINCIA DE PASCO DEL DEPARTAMENTO DE PASCO
PROYECTO:
CLIENTE: Municipalidad Distrital de Yanacancha
UBICACION: Av. Las Americas S/N
FECHA BASE: 3/15/2024
MONEDA: SOLES
COSTOS METRADOS
Item Partida Unidad Metrado PU Parcial MES 1 MES 2 MES 3 MES 4 MES 1 MES 2 MES 3 MES 4
6.4.4.6 CAJA DE REGISTRO DE AGUA UND 4.00 91.96 367.84 367.84 0.00 4.00 0.00 0.00
6.4.4.7 TANQUE DE AGUA 1000 LITROS UND 2.00 845.84 1,691.68 1,691.68 0.00 0.00 0.00 2.00
7 PLAN DE MANEJO AMBIENTAL 3,420.84 3,420.84 0.00 0.00 0.00 0.00
7.1 MITIGACION DE IMPACTO AMBIENTAL GLB 1.00 2,816.83 2,816.83 2,816.83 0.00 0.00 0.00 1.00
7.2 ACOMODO DE MATERIAL EXCEDENTE EN BOTADEROS M3 503.34 1.20 604.01 604.01 0.00 0.00 0.00 503.34
COSTO DIRECTO 316,793.52 19,574.99 68,080.02 177,069.55 52,068.97
GASTOS GENERALES 10% 31,679.35 1,957.50 6,808.00 17,706.95 5,206.90
UTILIDAD 10% 31,679.35 1,957.50 6,808.00 17,706.95 5,206.90
SUB TOTAL 380,152.22 23,489.99 81,696.02 212,483.46 62,482.76
IGV 18% 68,427.40 4,228.20 14,705.28 38,247.02 11,246.90
COSTO TOTAL DE EJECUCION 448,579.62 27,718.18 96,401.30 250,730.48 73,729.66
AVANCE MENSUAL 6.18% 21.49% 55.89% 16.44%
AVANCE ACUMULADO 6.179% 27.67% 83.56% 100.00%