Modelo Matemático para Calcular Hidrogramas de Crecientes Asociados A Diferentes Periodos de Retornos Utilizando Información Hidrométrica
Modelo Matemático para Calcular Hidrogramas de Crecientes Asociados A Diferentes Periodos de Retornos Utilizando Información Hidrométrica
Modelo Matemático para Calcular Hidrogramas de Crecientes Asociados A Diferentes Periodos de Retornos Utilizando Información Hidrométrica
Tesis de Maestría
CON GRIN SUS CONOCIMIENTOS
VALEN MAS
Bibliographic information published by the German National Library:
The German National Library lists this publication in the National Bibliography;
detailed bibliographic data are available on the Internet at http://dnb.dnb.de .
This book is copyright material and must not be copied, reproduced, transferred,
distributed, leased, licensed or publicly performed or used in any way except as
specifically permitted in writing by the publishers, as allowed under the terms and
conditions under which it was purchased or as strictly permitted by applicable
copyright law. Any unauthorized distribution or use of this text may be a direct
infringement of the author s and publisher s rights and those responsible may be
liable in law accordingly.
Imprint:
Copyright © 2015 GRIN Verlag
ISBN: 9783668660328
GRIN Verlag
GRIN - Your knowledge has value
Since its foundation in 1998, GRIN has specialized in publishing academic texts by
students, college teachers and other academics as e-book and printed book. The
website www.grin.com is an ideal platform for presenting term papers, final papers,
scientific essays, dissertations and specialist books.
http://www.facebook.com/grincom
http://www.twitter.com/grin_com
MICA 2012 –I-1
______________________________________________________________________
PRESENTADO POR:
FACULTAD DE INGENIERÍA
Y AMBIENTAL
CARTAGENA - BOLÍVAR
2014
1
MICA 2012 –I-1
______________________________________________________________________
INFORMACIÓN HIDROMÉTRICA
PRESENTADO POR:
CIVIL Y AMBIENTAL
FACULTAD DE INGENIERÍA
AMBIENTAL
(GISAM)
CARTAGENA - BOLÍVAR
2014
2
MICA 2012 –I-1
______________________________________________________________________
Nota de aceptación
_____________________
_____________________
_____________________
______________________________________
FIRMA DEL PRESIDENTE DEL JURADO
_______________________
FIRMA DEL JURADO
_______________________
FIRMA DEL JURADO
3
MICA 2012 –I-1
______________________________________________________________________
DEDICATORIA Y AGRADECIMIENTOS
Gracias a las personas que me han acompañado, en esta nueva etapa de mi vida, inicialmente
a Dios le doy gracia por permitirme y guiarme por este sendero, gracias a mi director de tesis
Ingeniero Oscar Enrique Coronado, con su amplio manejo en el tema, me apoyo y guio en la
realización de esta investigación.
4
MICA 2012 –I-1
______________________________________________________________________
TABLA DE CONTENIDO
5
MICA 2012 –I-1
______________________________________________________________________
6
MICA 2012 –I-1
______________________________________________________________________
5.1.4.3 Envolventes de las crecientes método flujo base Constant Slope .......................................................... 102
5.1.5 Cálculos método Concave Base Slope. ...................................................................................................... 103
5.1.5.1 Generación de hidrogramas método Concave Base Slope: .................................................................... 104
5.1.5.2 Validación del método flujo base Concave Base Slope: ........................................................................ 105
5.1.5.3 Envolventes de las crecientes método flujo base Concave Base Slope:................................................. 107
5.1.6 Cálculos método Master Depletion: .......................................................................................................... 108
5.1.6.1 Generación de hidrogramas método Master Depletion: ........................................................................ 109
5.1.6.2 Validación del método flujo base Master Depletion. ............................................................................. 111
5.1.6.3 Envolventes de las crecientes método flujo base Master Depletion: ..................................................... 112
5.2 ANALISIS DE RESULTADOS ............................................................................................................... 113
6.0 CONCLUSIONES Y RECOMENDACIONES ........................................................................................ 130
7.0 REFERENCIAS .......................................................................................................................................... 133
ANEXOS ............................................................................................................................................................. 135
7
MICA 2012 –I-1
______________________________________________________________________
LISTA DE FIGURAS
8
MICA 2012 –I-1
______________________________________________________________________
Figura 30 Generación de crecientes método Master Depletion, combinación G-G-G ...................... 109
Figura 31 Generación de crecientes método Master Depletion, combinación Gumbel-Logpearson-
Weibull ................................................................................................................................................ 110
Figura 32 Validación del método con la creciente de 1997Metodo Master Depletion Combinación
Gumbel-Gumbel-Gumbel.. .................................................................................................................. 111
Figura 33 Envolventes Método Master Depletion Combinación Gumbel-Gumbel-Gumbel .............. 112
9
MICA 2012 –I-1
______________________________________________________________________
LISTA DE TABLAS
10
MICA 2012 –I-1
______________________________________________________________________
1.0 GENERALIDADES
1.1 INTRODUCCION
Los proyectos para la construcción de nuevos embalses, ductos, vías, están aumentando a
nivel mundial y local, como una forma de solucionar problemas de comunicación,
abastecimiento y generación de energía, por tanto, las economías mundiales realizan esfuerzos
en la construcción de estas mega estructuras, la cual son muy costosas, pero necesarias.
Por consiguiente, los registros y estudios de los caudales máximos anuales permiten
determinar, bajo cierto supuesto, la probabilidad de ocurrencia del caudal en una cierta
magnitud, se deben tener en cuenta que, los caudales son fenómenos originados por el carácter
aleatorio de las descargas de los ríos. La ocurrencia de crecidas de los ríos se describe en
términos probabilísticos, es decir, que cada caudal va asociado una probabilidad de ocurrencia.
11
MICA 2012 –I-1
______________________________________________________________________
Los métodos que relacionan la lluvia con la escorrentía dependen de las características de
la cuenca tales como área de la cuenca, tipo de cobertura de suelo, tiempo de concentración,
entre otras, de la distribución de la lluvia espacio-temporal y de la información registrada en
las estaciones hidrométricas. La aplicación de estos métodos resulta muy compleja en países
en los cuales no existe una cobertura suficiente de estaciones de lluvias y de caudales que
logren relacionar de manera adecuada los procesos lluvia-escorrentía.
12
MICA 2012 –I-1
______________________________________________________________________
Los hidrogramas de crecientes asociados a diferentes períodos de retorno son utilizados para
el diseño de las estructuras hidráulicas con capacidad de atenuación, por lo cual es importante
que estos sean representativos en términos de caudal pico, volumen total, caudal base, tiempo
al pico, tiempo base y su forma.
Actualmente, los métodos para estimar hidrogramas de crecientes con diferentes periodos
de retornos utilizando únicamente información hidrométrica, son muy simples y no consideran
distintos aspectos de una creciente, como volumen total, caudal base y su forma.
13
MICA 2012 –I-1
______________________________________________________________________
1.4 OBJETIVOS
1.4.1 GENERAL
1.4.2 ESPECÍFICOS
¾ Incluir nuevas ecuaciones de flujo base, al modelo planteado por Coronado y Triana,
con el fin de evaluar las bondades de ajuste de cada uno de ello.
¾ Comparar los resultados de bondad de ajuste del modelo utilizado diferentes ecuaciones
de flujo base, para analizar la confiabilidad de cada uno de ellos.
14
MICA 2012 –I-1
______________________________________________________________________
Los ajustes estadísticos son distribuciones de probabilidad que permiten determinar los
caudales máximos asociados a diferentes períodos de retorno a partir de los caudales máximos
instantáneos en una serie anual. Adicionalmente, también es posible determinar los volúmenes
máximos asociados a diferentes períodos de retorno. Este método se utiliza cuando se tiene
una estación hidrométrica que permita registrar los niveles máximos instantáneos en un río.
Para estimar los caudales asociados a diferentes períodos de retorno se debe seguir el siguiente
procedimiento:
15
MICA 2012 –I-1
______________________________________________________________________
16
MICA 2012 –I-1
______________________________________________________________________
17
MICA 2012 –I-1
______________________________________________________________________
ݑൌ ି ݂ݔሺݔሻ݀ ݔ----------------------------------------------------------------------------------------2
18
MICA 2012 –I-1
______________________________________________________________________
¾ Método de la máxima verosimilitud: este método fue desarrollado por R.A. Fisher
(1922). El mejor valor de un parámetro de una distribución de probabilidad debería ser el valor
que maximizara la verosimilitud o probabilidad conjunta de ocurrencia de la muestra
observada. Supóngase que el espacio muestral se divide en intervalos de longitudes dx y se
toma una muestra de observaciones independientes e idénticamente distribuidas x1, x2., xn. El
valor de la densidad de probabilidad para X=xi es f(xi), y la probabilidad de que la variable
aleatoria ocurra en el intervalo que incluye xi es f(xi) dx. Debido a que las observaciones son
independientes, su probabilidad de ocurrencia conjunta está dada por la ecuación ሺ תሻ ൌ
19
MICA 2012 –I-1
______________________________________________________________________
Dónde:
: Número de intervalos
ሺሻ: Número de ocurrencias observadas en el intervalo i.
ሺሻ : Número esperado de ocurrencias en el intervalo i.
Para describir la prueba X2, debe definirse la distribución de probabilidad X2. Una
distribución con v grados de libertad es la distribución para la suma de los cuadrados de v
variables aleatorias normales estándar independientes zi; esta suma es la variable aleatoria
(Chow, Maidment, & Mays, Hidrología aplicada, 1994):
ݔ௩ଶ ൌ σୀଵ ݐݖଶ ------------------------------------------------------------------------------------------- 5
20
MICA 2012 –I-1
______________________________________________________________________
ݔൌ ᓃ ݏܭ---------------------------------------------------------------------------------------------- 6
Dónde:
: Valor estimado para un período de retorno
ᓃ: Media de la serie muestral
: Desviación estándar de la serie muestral
: Factor de frecuencia que depende del tipo de distribución y del número de datos de la serie
muestral.
21
MICA 2012 –I-1
______________________________________________________________________
lognormal). Entonces para N muestras la variable X tiene una distribución de valores extremos
tipo I, o distribución Gumbel. (Gumbel, 1958). Por ejemplo, las precipitaciones máximas
anuales a menudo se describen por una distribución Gumbel.
షഀሺషഁሻ
ܨሺܺሻ ൌ ݁ ି --------------------------------------------------------------------------------------- 7
షഀሺషഁሻ ൧
݂ሺܺሻ ൌ ߙ݁ ൣିఈሺିఉሻି ------------------------------------------------------------------------ 8
Donde D y E son los parámetros de la función. Los parámetros D y E se estiman (Kite, 1977)
como:
ଵǤଶ଼ଶହ
ߙൌ ------------------------------------------------------------------------------------------------ 9
ௌ
ఙ
ߙൌ --------------------------------------------------------------------------------------------------- 11
ௌ
ߚ ൌ ݔҧ െ ߤ௬ Τߙ ----------------------------------------------------------------------------------------- 12
Para muestras relativamente pequeñas.
ܳ ൌ ݁ ---------------------------------------------------------------------------------------------------13
22
MICA 2012 –I-1
______________________________________________________________________
Donde X tiene una distribución Pearson tipo 3 con parámetros de forma, escala y
ubicaciónD, E y [. Por lo tanto la distribución de los logaritmos de X se describe por las
ecuaciones.
ߙ ൌ ͶΤߛ ଶ ݔ-----------------------------------------------------------------------------------------------14
ଶ
ߚൌ --------------------------------------------------------------------------------------------------15
ఙೣ ఊೣ
ఈ ఙ
ߦ ൌ ߤ௫ െ ൌ ߤ௫ െ ʹ ఊೣ --------------------------------------------------------------------------------16
ఉ ೣ
Los momentos de los productos de Q son calculados para E>r o E<0 usando
ఉ ఈ
ܧሾܳ ሿ ൌ ݁ క ቀ ቁ ------------------------------------------------------------------------------------19
ఉି
Produciendo,
ఉ ఈ ఉ ఈ ఉ ଶఈ
ߤொ ൌ ݁ క ቀఉିଵቁ ߪொ ଶ ൌ ݁ ଶక ቀఉିଶቁ െ ቀఉିଵቁ ൨ ---------------------------------------------20
y,
ாൣொ య ൧ିଷఓೂ ாൣொ మ ൧ାଶఓయ
ߛொ ൌ య -------------------------------------------------------------------------------21
ఙೂ
23
MICA 2012 –I-1
______________________________________________________________________
El método del hidrograma unitario fue desarrollado originalmente por Sherman en 1932
(Sherman, 1932), y está basado en las siguientes hipótesis:
¾ Tiempo base constante: Para una cuenca dada, la duración total de escurrimiento directo
o tiempo base es la misma para todas las tormentas con la misma duración de lluvia efectiva,
independientemente del volumen total escurrido. Todo hidrograma unitario está ligado a una
duración de la lluvia en exceso.
El concepto del hidrograma unitario se puede aplicar de diversas formas, tales como:
hidrograma unitario tradicional, curva S, hidrogramas unitarios sintéticos y métodos
matriciales.
24
MICA 2012 –I-1
______________________________________________________________________
------------------------------------------------------- 22
25
MICA 2012 –I-1
______________________________________________________________________
1. Se obtienen los estimadores univariados por máxima verosimilitud de los parámetros de las
distribuciones ajustadas a las variables Qp, Vt, Vp, y Vd, los cuales servirán como valores
iniciales dentro del proceso de cálculo de los estimadores de las distribuciones Bivariada.
2. Se obtienen los estimadores por máxima verosimilitud de los parámetros para cada una de
las relaciones Bivariada Qp-Vt, Qp-Vp, Qp-Vd y Vp-Vd, de acuerdo con procedimientos
propuestos por Raynal (1985) o Raynal (1985) o Escalante (1998b) dependiendo del tipo de
distribución marginal utilizada.
26
MICA 2012 –I-1
______________________________________________________________________
de diseño, en caso contrario, se ajustarán estos valores paso a paso hasta que se logre la
tolerancia seleccionada.
4. Para darle forma al hidrograma se propone que el valor del tiempo de pico y el tiempo de
vaciado (tiempo base menos tiempo de pico) se calculan regionalmente a través de una técnica
de correlación y regresión múltiple. Las variables independientes serán las características
fisiográficas y/o climatológicas de las cuencas que pertenecen a la misma región
meteorológicamente homogénea.
27
MICA 2012 –I-1
______________________________________________________________________
ࡽ
ࡽ࢚ ൌ ቀ ቁ ࡽ࢘ ࢘ሺࢊሻ ------------------------------------------------------------------------------23
ࡽష
Donde (Qi / Q-i) es el valor estimado para un periodo retorno T, mediante el ajuste de la
mejor distribución de probabilidad para cada sitio analizado. Q-i es el promedio de los gastos
máximos registrados Qi · Qprom se estima al ajustar los Qi a las características fisiográficas
y/o climatológicas de los sitios en la región en estudio; r(d) es la tasa de reducción que se
obtiene de la Figura 1. En esta figura se aprecian ejemplos de curvas que corresponden a tres
sitios diferentes dentro de una misma región hidrológica.
Para estimar el volumen total de la avenida de diseño se puede considerar que el hidrograma
es del tipo triangular y los tiempos de pico (tp) y base (tb) son función del tiempo de
concentración de la cuenca, el cual puede estimarse a través de la fórmula de Kirpich:
ۺǤૠૠ
܋ ܜൌ Ǥ ሺ܁Ǥૡ ሻ ---------------------------------------------------------------------------------24
28
MICA 2012 –I-1
______________________________________________________________________
¾ Para la separación del flujo base de los Hidrogramas registrados, se mencionan dos
métodos (Chow y otros, 1994): constante y lineal.
29
MICA 2012 –I-1
______________________________________________________________________
30
MICA 2012 –I-1
______________________________________________________________________
Hay varias técnicas para separar el flujo base de la escorrentía directa, la más antigua es la
curva de abatimiento normal descrita por Horton (1933). La curva de abatimiento normal, o
curva maestra de recesión de flujo base, es una gráfica características de las recesiones que se
observan en una corriente dada. Usualmente las curvas de recesión toman la forma del
decaimiento exponencial:
2.4.1 Método de la línea recta: Consiste en dibujar una línea horizontal desde el punto en el
cual empieza la escorrentía directa superficial hasta la intersección con el segmento de recesión
del hidrograma en el cual se reinicia el flujo base. (Richard H. 1998, 489)
Su ecuación es:
Donde;
31
MICA 2012 –I-1
______________________________________________________________________
ࡽሺ࢚ሻ ൌ --------------------------------------------------------------------------------------------27
Donde;
݊ǣCaudal base constante.
2.4.3 Método de flujo base para cuencas pequeñas y alta vegetación: Este método se utiliza
para cuencas pequeñas cubiertas por vegetación en regiones húmedas, propuesto por Hewlett
y Hibbert (1967), sugirieron que pueden suponer que el flujo base dentro de una tormenta se
incremente a una tasa de 0. 005 l/s*ha*h. (Richard H. 1998, 488)
Su ecuación para calcular el flujo base es:
Donde;
݊ǣCaudal base constante
݉ǣ Pendiente del caudal base.
ݐǣ Tiempo duración de la tormenta
ܣൌ Area en hectáreas.
32
MICA 2012 –I-1
______________________________________________________________________
2.4.4 Método de concave baseflow separation: Para este método, los puntos de inicio y fin
para la separación de línea de flujo de base y la escorrentía directa son las mismas que para el
método de pendiente constante. Sin embargo, para el método cóncava, caudal base continua
decreciendo hasta el momento de la descarga pico del hidrograma de tormenta.
En ese momento, la línea de separación es recta entre ese punto y el punto de inflexión de
la recesión. Mientras que el método cóncava puede requerir un poco más de esfuerzo de definir
que los otros dos métodos, es probable que sea una representación más realista de la separación
real de flujo según lo determinado por los procesos físicos que el flujo de control durante las
tormentas. Matemáticamente, (Richard H. 1998, 488), la función del flujo de base es:
ࢌ࢚࢘ ൏ ࢚࢙
ۓ ࢙ି
ۖ
ۖ ࢙ ሺ࢚ ࢚࢙ሻ ቂ ቃ ࢌ࢚࢙࢘
࢚࢙ି࢚
ࡽሺ࢚ሻ ൌ ሺ࢚ െ ࢚ሻ ቂ ቃ ࢌ࢚࢘ ----------------------------29
࢘ି
۔ ࢚࢘ି࢚
ۖ
ۖ ࢌ࢚࢘࢘ ൏ ࢚
ە
33
MICA 2012 –I-1
______________________________________________________________________
En la que N es el número de días desde el tiempo hasta el pico del hidrograma de escorrentía
medido hasta el final de la escorrentía directa y A es el área de drenaje en millas cuadradas. Un
tercer método se llama el método de la curva maestra agotamiento, que se discute a
continuación. Mientras que estas tres opciones son bastante objetivo, el punto se selecciona a
menudo subjetivamente usando un gráfico de la hidrograma de escorrentía. Una vez que el
tiempo en el que se ha identificado extremos escorrentía directa, escorrentía directa del flujo
de base y se separan mediante la conexión de una línea recta que se extiende desde el punto de
la velocidad de descarga más bajo en el inicio de la descarga de la inundación hasta el punto
en la recesión. El método de constante-pendiente también se muestra en la Figura 9-2. El flujo
de base depende del tiempo (ts) y de descarga (qs,) en el punto de la función de descarga (qr),
y el tiempo (t) y de descarga (qs) en el punto de inflexión bajo. (Richard H. 1998, 488),
Matemáticamente, la función del flujo de base es:
ࢌ࢚࢘ ൏ ࢚࢙
ۓ ࢘ି࢙
ۖ ࢙ ሺ࢚ ࢚࢙ሻ ቂ ቃ ࢌ࢚࢙࢘ ࢚ ࢚࢘
ࡽሺ࢚ሻ ൌ ࢚࢙ି࢚࢙
--------------------------31
۔
ۖ ࢌ࢚࢘࢘ ൏ ࢚
ە
34
MICA 2012 –I-1
______________________________________________________________________
1. El uso de papel semi-log, log q en función del tiempo, trazar las curvas de recesión para cada
evento de tormenta en hojas separadas de papel de calcar.
2. En una hoja principal con una q contra el sistema tiempo-eje de registro (papel semi-log),
trazar la recesión para el evento de tormenta que tiene los valores más pequeños de log q.
3. Utilizando la curva de recesión, con los siguientes valores mínimos de registro de valores de
q, coloque el papel vegetal de tal manera que la curva parece extenderse a lo largo de una línea
que coincide con la recesión del primer evento planeado.
4. Continúe este proceso con cada vez más grandes de magnitud LOG q recesiones hasta que
se representan todos los eventos de tormenta.
5. Construir una curva de agotamiento del principal que se extiende a través de las recesiones
de las tormentas observadas. A continuación, ajustar un modelo matemático para la curva de
agotamiento maestro; la siguiente forma funcional a menudo proporciona un ajuste razonable
para los datos:
ࢋିࢋ࢚
ൌ ------------------------------------------------------------------------------------------33
࢚
35
MICA 2012 –I-1
______________________________________________________________________
σ
స ࢚ሺࢋିࢋሻ
ൌ σ -----------------------------------------------------------------------------------34
స ࢚
En esta ecuación se puede hallar QBn(t) o Qs, conociendo los demás valores. El valor de
caudal total se mide directamente, la concentración de la escorrentía subterránea, Co, se obtiene
al analizar el agua del río en periodos prolongados de ausencia de lluvias (caudal base) y la
concentración de la escorrentía superficial se toma en periodos de lluvias fuertes.
En este caso se utiliza el deuterio y oxigeno 18, que son los isótopos estables del agua, y
cuyas desviaciones isotópicas permiten expresar la anterior ecuación asi:
ࢾ࢚ିࢾ࢙
ࡽሺ࢚ሻ ൌ ࡽ࢚ሺ ሻ -----------------------------------------------------------------------------------36
ࢾିࢾ࢙
Las desviaciones isotópicas requeridas por la ecuación anterior (1) (ߜ = ݐdesviación
isotópica de la escorrentía total; ߜ = desviación isotópica del flujo base, compuesta por el
agua subterránea y el agua subsuperficial y ߜ = ݏdesviación isotópica de la escorrentía
superficial), demandan la realización de muestreos que permitan la caracterización de los tres
componentes involucrados. (Gomez. 2006, p.23)
36
MICA 2012 –I-1
______________________________________________________________________
Observe que el error medio cuadrático mide el promedio de los cuadrados de la diferencia
entre el estimador ߠ y el parámetro ߠ, una medida algo razonable de rendimiento para un
estimador. En general, cualquier función creciente de la distancia absoluta หߠ െ ߠห sirve para
medir la bondad de un estimador, el error medio absoluto, ܧ൫หߠ െ ߠห൯, es una alternativa
razonable. Pero el EMC tiene al menos dos ventajas sobre otras medidas de distancia: En primer
lugar, es analíticamente tratable y, en segundo lugar, tiene la interpretación, (DeGroot, M., &
Schervish, M, 2010).
ଶ ଶ ଶ
ܥܯܧఏ ൌ ܧ൫ߠ െ ߠ൯ ൌ ܸܽݎ൫ߠ൯ ൫ܧ൫ߠ൯ െ ߠ൯ ൌ ܸܽݎ൫ߠ൯ ൫ܵ݁ߠ݁݀݃ݏ൯ -----------------37
ଶ
ܥܯܧఏ ൌ ܧ൫ߠ െ ߠ൯ ൌ ܸܽݎ൫ߠ൯ ----------------------------------------------------------------------38
37
MICA 2012 –I-1
______________________________________________________________________
En este capítulo se deducen y se amplían las ecuaciones de separación de flujo base del
modelo matemático propuesto por Coronado, Triana y Coronado. El procedimiento se
deduce a partir de un balance de masa entre los volúmenes de escorrentía, volúmenes de flujo
base y el volumen total.
38
MICA 2012 –I-1
______________________________________________________________________
Luego:
௧ୀ் ௧ୀ்
ܸ ݊ܧൌ ቀ௧ୀ ܳ݊ܧሺݐሻ݀ݐቁ ൌ ቀ௧ୀ ሾܳܲ݊ െ ܳ݊ܤሺݐሻሿݍሺݐሻ݀ݐቁ------------------------------------41
Donde;
௧ୀ்
ܸ ݊ܤൌ ቀ௧ୀ ܳ݊ܤሺݐሻ݀ݐቁ------------------------------------------------------------------------------42
39
MICA 2012 –I-1
______________________________________________________________________
௧ୀ் ௧ୀ்
ܸ ݊ܯൌ ܸ ݊ܧ ܸ ݊ܤൌ ቀ௧ୀ ሾܳܲ݊ െ ܳ݊ܤሺݐሻሿݍሺݐሻ݀ ݐ ௧ୀ ܳ݊ܤሺݐሻ݀ݐቁ-------------------43
La ecuación anterior se puede resolver por medio de intervalo, tal como se presenta a
continuación:
ܸ ݊ܯൌ σ்௧ୀ ܸ݊ܤܳ݊ܯǡ ݐο ݐ ܳܲ݊ σ்௧ୀ ݐݍο ݐെ σ்௧ୀ ܳ݊ܤǡ ݐݍݐοݐ------------------------------45
Con este procedimiento y las ecuaciones del flujo base antes descritas, se procede a
calcular los volúmenes modelados de cada ecuación. (Coronado, 2010, p.29)
40
MICA 2012 –I-1
______________________________________________________________________
La estimación del tiempo al pico y de las ecuaciones de flujo base se deben realizar teniendo
en cuenta que el volumen de una creciente es igual al volumen medio que se presenta en un
mismo período de tiempo. Estas variables se determinan mediante un proceso de minimización
del Error Medio Cuadrático (EMC) para la serie volúmenes medios diarios máximos asociados
a diferentes períodos de retorno y la serie de volúmenes máximos asociadas a diferentes
períodos de retorno obtenida con la ecuación 21. La función objetivo a utilizar se presenta a
continuación:
ଵ
ܼ ൌ ݉݅݊݅݉݅ݎܽݖሺܯܥܧሻ ൌ ට σே
ே ିଵሺܸ ݊ܯെ ܸܴ݊ሻ
ଶ ------------------------------------------------------------47
Dónde:
EMC: Error Medio Cuadrático.
N: Numero de hidrogramas asociados a diferentes periodos de retorno.
VMn: Volumen de la creciente asociada a un periodo de retorno modelado.
VRn: Volumen de la creciente registrada asociada a un periodo de retorno.
41
MICA 2012 –I-1
______________________________________________________________________
En este ítem se presenta el cálculo de los hidrogramas para diferentes períodos de retorno
considerando el caudal base constante. Para la solución de este ejercicio se realizaron las
siguientes simplificaciones a la ecuación inicial:
ܸ ݊ܯൌ σ்௧ୀ ܳ݊ܤሺݐሻο ݐ σ்௧ୀ ݍሺݐሻο ݐ σ்௧ୀ ܳ݊ܤሺݐሻݍሺݐሻο ݐ----------------------------------------------48
Pero,
ܳ݊ܤሺݐሻ ൌ ݊-------------------------------------------------------------------------------------------- 49
Dónde:
݊ǣCaudal base constante para cada periodo.
Luego,
ܸ ݊ܯൌ σ்௧ୀ ο ݐ ܳܲ݊ σ்௧ୀ ݍሺݐሻο ݐെ ݊σ்௧ୀ ݍሺݐሻο ݐ------------------------------------------------------50
ܸ ݊ܯൌ ܶ݊ σ்௧ୀ ݍሺݐሻο ݐ ܳܲ݊ σ்௧ୀ ݍሺݐሻο ݐെ ݊σ்௧ୀ ݍሺݐሻο ݐ------------------------------------------51
ܸ ݊ܯൌ σ்௧ୀ ܳ݊ܤሺݐሻο ݐ ܳܲ݊ σ்௧ୀ ݍሺݐሻο ݐെ σ்௧ୀ ܳ݊ܤሺݐሻο ݐ----------------------------------------------52
Objetivo
Minimizar el error medio cuadrático de los volúmenes modelados con respecto a los
registrados de los hidrogramas de crecientes, considerando el flujo base constante.
42
MICA 2012 –I-1
______________________________________________________________________
Conjuntos
n € N: Número de crecientes asociada a un período de retorno.
t € T: Intervalo de tiempo de la duración de la creciente.
Parámetros
QPn: Vector del caudal máximo asociado a un período de retorno.
VRn: Vector de volumen registrado máximo de la creciente asociada a un período de retorno.
pn: Vector de flujo base constante asociado a un período de retorno.
Δt: Escalar del tamaño del intervalo seleccionado.
q(t’) : Hidrograma adimensional en caudal y tiempo promedio de las crecientes registradas.
tp-min: Tiempo al pico mínimo registrado de las crecientes.
T: Duracion de la creciente
Variables
FO: Función Objetivo.
EMC: Error medio cuadrático.
VMn: Volumen modelado de la creciente asociado a un período de retorno.
tp: Tiempo al pico de los hidrogramas asociados a un período de retorno.
Q(t): Hidrograma adimensional en caudal.
௧ୀ்
ܸ ݊ܯൌ ܶ݊ ቀ௧ୀ ݍሺݐሻ݀ݐቁ ሺܳܲ݊ െ ܲ݊ ---------------------------------------------------------55
tp-min≤tp
tp€Z+
43
MICA 2012 –I-1
______________________________________________________________________
ܸ ݊ܯൌ σ்௧ୀ ܳ݊ܤሺݐሻο ݐ σ்௧ୀ ݍሺݐሻο ݐ σ்௧ୀ ܳ݊ܤሺݐሻݍሺݐሻο ݐ----------------------------------------------57
Pero,
ܳ݊ܤሺݐሻ ൌ ݉ ݐ כ ݊---------------------------------------------------------------------------------58
Dónde:
݊ǣCaudal base constante para cada periodo.
Luego,
௧ୀ் ் మ ் మ
σ்௧ୀ ܳ݊ܤሺݐሻο ݐൌ σ்௧ୀሺ݉ ݐ ݊ሻο ݐൌ ܳܲ݊ ௧ୀ ሺ݉ ݐ ݊ሻ݀ ݐൌ ല ܶ݊ല ൌ ܶ݊-------------59
ଶ ଶ
Finalmente,
் మ ௧ୀ் ௧ୀ்
ܸ ݊ܯൌ ଶ
ܶ݊ ܳܲ݊ ௧ୀ ݍሺݐሻ݀ ݐെ ௧ୀ ܳ݊ܤሺݐሻݍሺݐሻ݀ݐ---------------------------------------60
Dónde:
T: Duración de las crecientes.
A continuación se presenta el método planteado para la estimación de los hidrogramas de
crecientes:
Objetivo
Minimizar el error medio cuadrático de los volúmenes modelados con respecto a los
registrados de los hidrogramas de crecientes, considerando el flujo base de línea recta.
Conjuntos
n € N: Número de crecientes asociada a un período de retorno.
t € T: Intervalo de tiempo de la duración de la creciente.
Parámetros
44
MICA 2012 –I-1
______________________________________________________________________
் మ ௧ୀ் ௧ୀ்
ܸ ݊ܯൌ ଶ
ܶ݊ ܳܲ݊ ௧ୀ ݍሺݐሻ݀ ݐെ ௧ୀ ܳ݊ܤሺݐሻݍሺݐሻ݀ ݐ--------------------------------------62
mminm ≤mmax
tp-mintp
tp€Z+
q(t)ൌ ݍሺݐƲݐݔሻ ------------------------------------------------------------------------------------------- 64
45
MICA 2012 –I-1
______________________________________________________________________
3.2.3 Ecuación para el volumen modelado con método Cuencas pequeñas y alta
vegetación:
En este ítem se presenta el cálculo de los hidrogramas para diferentes períodos de retorno
considerando el método de separación de flujo base para cuencas pequeñas y alta vegetación,
el área está limitada para cuencas 50km2. Para la solución de este ejercicio se realizaron las
siguientes simplificaciones a la ecuación inicial:
ܸ ݊ܯൌ σ்௧ୀ ܳ݊ܤሺݐሻο ݐ σ்௧ୀ ݍሺݐሻο ݐ σ்௧ୀ ܳ݊ܤሺݐሻݍሺݐሻοݐ ----------------------------------------------65
Pero,
ሺሻ ൌ ͷǤͷ ିͲͳ כ -------------------------------------------------------------------------66
Donde;
݊ǣCaudal base constante
ݐǣ Tiempo duración de la tormenta
ܣൌ Area en hectáreas.
Luego,
െ ݐൌܶ െ
σ்௧ୀ ܳ݊ܤሺݐሻο ݐൌ σ்௧ୀ ቀʹǤͷ Ͳͳ כ ݐܣ ݊ቁ ο ݐൌ ܳܲ݊ ݐൌͲ ቀʹǤͷ ݐܣ Ͳͳ כ ݊ቁ ݀ ݐൌ ലʹǤͷ כ
࢚ୀࢀ ࢚ୀࢀ
ࢂࡹ ൌ Ǥ ૠ כି ࢀ ࢀ ࡽࡼ ࢚ୀ ሺ࢚ሻࢊ࢚ െ ࢚ୀ ࡽሺ࢚ሻሺ࢚ሻࢊ࢚ ----------------------------68
Donde:
T: Duración de las crecientes.
A continuación se presenta el método planteado para la estimación de los hidrogramas de
crecientes:
Objetivo
Minimizar el error medio cuadrático de los volúmenes modelados con respecto a los
registrados de los hidrogramas de crecientes, considerando el flujo base con el método
Cuencas pequeñas y alta vegetación.
Conjuntos
n € N: Número de crecientes asociada a un período de retorno.
46
MICA 2012 –I-1
______________________________________________________________________
Parámetros
QPn: Vector del caudal máximo asociado a un período de retorno.
VRn: Vector de volumen máximo de creciente asociado a un período de retorno.
Bn: Vector de flujo base inicial asociado a un período de retorno.
࢚ୀࢀ ࢚ୀࢀ
ࢂࡹ ൌ Ǥ ૠ כି ࢀ ࢀ ࡽࡼ ࢚ୀ ሺ࢚ሻࢊ࢚ െ ࢚ୀ ࡽሺ࢚ሻሺ࢚ሻࢊ࢚ ------------------------------70
0A ≤50km2
tp-mintp
47
MICA 2012 –I-1
______________________________________________________________________
tp€Z+
q(t)ൌ ݍሺݐƲݐݔሻ ------------------------------------------------------------------------------------------72
3.2.4 Ecuación para el volumen modelado con metodo de concave baseflow separation.
En este ítem se presenta el cálculo de los hidrogramas para diferentes períodos de retorno
considerando el método de separación de flujo base con el método de concave baseflow
separation. Para la solución de este ejercicio se realizaron las siguientes simplificaciones a la
ecuación inicial:
ܸ ݊ܯൌ σ்௧ୀ ܳ݊ܤሺݐሻο ݐ σ்௧ୀ ݍሺݐሻο ݐ σ்௧ୀ ܳ݊ܤሺݐሻݍሺݐሻοݐ ---------------------------------------------73
Teniendo en cuenta la siguiente gráfica;
Tenemos:
ࢌ࢚࢘ ൏ ࢚࢙
ۓ ࢙ି
ۖ
ۖ ࢙ ሺ࢚ ࢚࢙ሻ ቂ ቃ ࢌ࢚࢙࢘
࢚࢙ି࢚
ࡽሺ࢚ሻ ൌ ሺ࢚ െ ࢚ሻ ቂ ቃ ࢌ࢚࢘ ---------------------------74
࢘ି
۔ ࢚࢘ି࢚
ۖ
ۖ ࢌ࢚࢘࢘ ൏ ࢚
ە
Donde;
݀ݍǣCaudal base
ݍǣCaudal base al inicio de la tormenta
ݏݍǣCauda Inicial de la descarga
݉ݍǣCaudal base asociado con el tiempo al pico
ݐǣ Tiempo al pico
Luego,
48
MICA 2012 –I-1
______________________________________________________________________
࢙ି ሺࢀିࢀ࢙ሻ ࢘ି ሺࢀିࢀሻ ݐൌܶ
σ்௧ୀ ܳ݊ܤሺݐሻο ݐൌ σ்௧ୀ ቀ࢙ࢀ ቂ ቃ ሺࢀ െ ࢀሻ ቂ ቃ ࢀቁ ο ݐൌ ܳܲ݊ ݐൌͲ ቀ࢙ࢀ
ࢀ࢙ିࢀ ࢚࢘ି࢚
Donde:
T: Duración de las crecientes.
A continuación se presenta el método planteado para la estimación de los hidrogramas de
crecientes:
Objetivo
Minimizar el error medio cuadrático de los volúmenes modelados con respecto a los
registrados de los hidrogramas de crecientes, considerando el flujo base con el método de
concave baseflow separation.
Conjuntos
n € N: Número de crecientes asociada a un período de retorno.
t € T: Intervalo de tiempo de la duración de la creciente.
Parámetros
QPn: Vector del caudal máximo asociado a un período de retorno.
VRn: Vector de volumen máximo de creciente asociado a un período de retorno.
Bn: Vector de flujo base inicial asociado a un período de retorno.
49
MICA 2012 –I-1
______________________________________________________________________
Variables
FO: Función Objetivo.
EMC: Error medio cuadrático.
VRn: Volumen simulado de la creciente.
tp: Tiempo al pico de los hidrogramas asociados a un período de retorno.
݀ݍǣCaudal base
ݍǣCaudal base al inicio de la tormenta
ݏݍǣCauda Inicial de la descarga
݉ݍǣCaudal base asociado con el tiempo al pico
ݐǣ Tiempo al pico
q(t): Hidrograma adimensional en caudal.
QBn: Funcion del flujo base.
tp-mintp
tp€Z+
q(t)ൌ ݍሺݐƲݐݔሻ ----------------------------------------------------------------------------------------80
50
MICA 2012 –I-1
______________________________________________________________________
ܸ ݊ܯൌ σ்௧ୀ ܳ݊ܤሺݐሻο ݐ σ்௧ୀ ݍሺݐሻο ݐ σ்௧ୀ ܳ݊ܤሺݐሻݍሺݐሻοݐ ---------------------------------------------81
Pero,
ࢌ࢚࢘ ൏ ݏݐ
ۓ ࢘ି࢙
ۖ ࢙ ሺ࢚ ࢚࢙ሻ ቂ ቃ ࢌ࢚࢙࢘ ࢚ ࢚࢘
ࡽሺ࢚ሻ ൌ ࢚࢙ି࢚࢙
-------------------------82
۔
ۖ ࢌ࢚࢘࢘ ൏ ݐ
ە
Donde;
݀ݍǣCaudal base
ݍǣCaudal base al inicio de la tormenta
ݏݍǣCauda Inicial de la descarga
݉ݍǣCaudal base asociado con el tiempo al pico
ݐǣ Tiempo al pico
ݐǣ Tiempo al pico
Luego,
ʹ
ݎݍെ ݏݍሺܶെܶݏሻ ݐൌܶ ࢙ି ሺࢀିࢀ࢙ሻ ࢙ି ሺࢀିࢀ࢙ሻ
σ்௧ୀ ܳ݊ܤሺݐሻο ݐൌ σ்௧ୀ ቆ ܶݏݍ ቂ ቃ ቇ ο ݐൌ ܳܲ݊ ݐൌͲ ቀ࢙ࢀ ቂࢀ࢙ିࢀቃ ቁ ݀ ݐൌ ല࢙ࢀ ቂࢀ࢙ିࢀቃ
ܶݏെܶݏ ʹ
ࢀ ൌ ࢙ࢀ ቂ
࢙ି ሺࢀିࢀ࢙ሻ
ࢀ࢙ିࢀ
ቃ
ࢀ ---------------------------------------------------------------------------83
Finalmente,
Donde:
T: Duración de las crecientes.
51
MICA 2012 –I-1
______________________________________________________________________
Objetivo
Minimizar el error medio cuadrático de los volúmenes modelados con respecto a los
registrados de los hidrogramas de crecientes, considerando el flujo base con el método
constant-slope baseflow separation.
Conjuntos
n € N: Número de crecientes asociada a un período de retorno.
t € T: Intervalo de tiempo de la duración de la creciente.
Parámetros
QPn: Vector del caudal máximo asociado a un período de retorno.
VRn: Vector de volumen máximo de creciente asociado a un período de retorno.
Bn: Vector de flujo base inicial asociado a un período de retorno.
Variables
FO: Función Objetivo.
EMC: Error medio cuadrático.
VRn: Volumen simulado de la creciente.
tp: Tiempo al pico de los hidrogramas asociados a un período de retorno.
݀ݍǣCaudal base
ݍǣCaudal base al inicio de la tormenta
ݏݍǣCauda Inicial de la descarga
52
MICA 2012 –I-1
______________________________________________________________________
tp-mintp
tp€Z+
q(t)ൌ ݍሺݐƲݐݔሻ ------------------------------------------------------------------------------------------ 88
53
MICA 2012 –I-1
______________________________________________________________________
Luego,
࢚ୀࢀ
σࢀ࢚ୀ ࡽሺ࢚ሻο࢚ ൌ σࢀ࢚ୀ൫ࢋି࢚ ܖܘ൯ο࢚ ൌ ࡽࡼ ࢚ୀ ൫ࢋି࢚ ൯ࢊ࢚ ൌ ല ሾ െ ࢋିࢀ ሿ ࢀല ൌ
ሾ െ ࢋିࢀ ሿ ࢀ -------------------------------------------------------------------------------------91
Finalmente,
࢚ୀࢀ ࢚ୀࢀ
ࢂࡹ ൌ
ሾ െ ࢋିࢀ ሿ ࢀ ࡽࡼ ࢚ୀ ሺ࢚ሻࢊ࢚ െ ࢚ୀ ࡽሺ࢚ሻሺ࢚ሻࢊ࢚ ---------------------------------92
Donde:
T: Duración de las crecientes.
A continuación se presenta el método planteado para la estimación de los hidrogramas de
crecientes:
Objetivo
Minimizar el error medio cuadrático de los volúmenes modelados con respecto a los
registrados de los hidrogramas de crecientes, considerando el flujo base con el master-
depletion-curve method.
Conjuntos
n € N: Número de crecientes asociada a un período de retorno.
t € T: Intervalo de tiempo de la duración de la creciente.
Parámetros
QPn: Vector del caudal máximo asociado a un período de retorno.
VRn: Vector de volumen máximo de creciente asociado a un período de retorno.
Bn: Vector de flujo base inicial asociado a un período de retorno.
54
MICA 2012 –I-1
______________________________________________________________________
Variables
FO: Función Objetivo.
EMC: Error medio cuadrático.
VRn: Volumen simulado de la creciente.
tp: Tiempo al pico de los hidrogramas asociados a un período de retorno.
ݍǣCaudal base al inicio de la tormenta
݇ǣCoeficiente de ajuste de la curva.
ݐǣ Tiempo de la tormenta
q(t): Hidrograma adimensional en caudal.
QBn: Función del flujo base.
࢚ୀࢀ ࢚ୀࢀ
ࢂࡹ ൌ ሾ െ ࢋିࢀ ሿ ࢀ ࡽࡼ ࢚ୀ ሺ࢚ሻࢊ࢚ െ ࢚ୀ ࡽሺ࢚ሻሺ࢚ሻࢊ࢚ -------------------------------- 94
Donde;
ܳ݊ܤሺݐሻ ൌ ି ݁ݍ௧ ------------------------------------------------------------------------------------- 95
tp-mintp
tp€Z+
q(t)ൌ ݍሺݐƲݐݔሻ ----------------------------------------------------------------------------------------- 96
3.2.7 Ecuación para el volumen modelado con método isotópico:
Durante las últimas décadas se ha empezado a utilizar métodos químicos basados en la
aplicación de la ecuación de conservación de masa a trazadores como cloruros o isótopos
estables del agua sobre el volumen de control de la corriente, en este caso se tiene en cuenta
las variaciones en la composición química del agua a lo largo de las corrientes relacionadas
con el acuífero en contacto. El flujo base representa el flujo subterráneo en contacto con la
corriente. A diferencia de los métodos anteriores este no es un modelo matemático ni gráfico,
este método depende en gran medida de las características propias de cada fuente, para lo
55
MICA 2012 –I-1
______________________________________________________________________
anterior se define la ecuación que se utilizara teniendo en cuenta los componentes de caudal
base, caudal de escorrentía y caudal total.
Donde:
்ܥൌ ݈ܽݐ݈ܶܽ݀ݑܽܥ݊݅ܿܽݎݐ݊݁ܿ݊ܥ
ܥ ൌ ݁ݏܽܤ݈ܽ݀ݑܽܥ݊݅ܿܽݎݐ݊݁ܿ݊ܥ
ܥா ൌ ܽ݅ݐ݊݁ݎݎܿݏܧ݈ܽ݀ݑܽܥ݊݅ܿܽݎݐ݊݁ܿ݊ܥ
De la ecuación 104 tenemos:
ொ ିಳ ொಳ
ܳா ൌ
ಶ
---------------------------------------------------------------------------------------- 99
ொ ಳ ொಳ
்ܳ ൌ ܳ
ಶ
െ ಶ
-------------------------------------------------------------------------------100
ಳ
்ܳ െ ்ܳ ൌ ܳ െ ܳ -----------------------------------------------------------------------------101
ಶ ಶ
்ܳ ሺͳ െ ሻ ൌ ܳ ሺͳ െ ಳ ሻ---------------------------------------------------------------------------102
ಶ ಶ
ಶ ି ಶ ିಳ
்ܳ ሺ ሻ ൌ ܳ ሺ ሻ----------------------------------------------------------------------------103
ಶ ಶ
ି
ܳ ൌ ሺಶି ሻ------------------------------------------------------------------------------------------104
ಶ ಳ
56
MICA 2012 –I-1
______________________________________________________________________
A partir de esta ecuación calculamos el caudal base del afluente, pero debemos recordar
para poder realizar el hidrograma necesitamos obtener los siguientes datos de campos;
Concentración del Caudal de escorrentía (ܥா ሻ, Concentración del Caudal Total ( ்ܥሻ y la
Concentración del caudal Base (ܥ ሻ, lo que nos indica que estos valor tienen un
comportamiento constante, para lo cual este método tiene un comportamiento constante del
flujo base.
57
MICA 2012 –I-1
______________________________________________________________________
Ensayo y Error
5. Algoritmo de optimización EMC:
Otros: Gradiente, Montecarlo.
Cumple?
SI
58
MICA 2012 –I-1
______________________________________________________________________
La aplicación del procedimiento propuesto se realizó con los registros hidrométricos de las
estaciones río Lengupá – Páez, las cual tiene un área de drenaje de 1090 km², localizada en
Colombia.
Esta estación limnigráfica cuenta con un período de registro disponible de 28 años (1976 a
2003).
A partir de los registros hidrométricos de la estación río Lengupá – Páez, se realizó el ajuste
estadístico con diferentes la distribuciones de probabilidad Gumbel, Logpearson, Normal
Weibull (método de Máxima Verosimilitud), empleando el programa Hyfran (Chaire en
Hydrologie Statistique (CHS). Hyfran, 2002) para el caudal base, el caudal máximo instantáneo
y el volumen total para diferentes períodos de retorno. En las siguientes tablas se presentan los
resultados obtenidos. Debido a que no se obtuvieron todos los registros de las crecientes
máximas anuales registradas, la serie anual de volúmenes totales se calculó a partir de los
caudales medios diarios máximos en 24 horas (duración aproximada de las crecientes).
4.1.1 Ajuste para Caudal máximo, Caudal base y Volumen máximo, empleando la
distribución Gumbel:
Periodo de Caudal Máximo (m3/s) - Caudal base (m3/s) - Volumen máximo 24 hr(hm3) -
Retorno Gumbel Gumbel Gumbel
10000 1793.00 316.50 96
2000 1564.00 277.30 84
1000 1465.00 260.50 79
59
MICA 2012 –I-1
______________________________________________________________________
Periodo de Caudal Máximo (m3/s) - Caudal base (m3/s) - Volumen máximo 24 hr(hm3) -
Retorno Gumbel Gumbel Gumbel
200 1235.00 221.20 67
100 1136.00 204.30 61
50 1036.00 187.30 56
20 903.40 164.60 49
10 800.80 147.00 44
5 693.80 128.80 38
Los datos son obtenidos, a aplicar el ajuste estadísticos descritos a los datos de la estación,
que son Series de caudales máximos instantáneos, con estos datos obtenemos lo caudales
máximos, Serie de caudales medios mes más húmedo, con estos datos estimamos los caudales
bases y con la serie de volúmenes máximos en un dia, estimamos los volúmenes máximos en
24 horas.
El cálculo del caudal base, se forja a partir de las series de caudales medios de los meses
más húmedos registrados en la estación en total se consolidaron 26 datos a partir del año 1976
hasta el año 2001, los cuales se analizaron mediante el programa Hyfran.
4.1.2 Ajuste para Caudal máximo, Caudal base y Volumen máximo, con las
distribuciones Gumbel, Weibull y Log-pearson, respectivamente.
Gumbel-Weibull-Log-pearson
Periodo de Caudal Máximo (m3/s) - Caudal base (m3/s) - Volumen máximo 24 hr(hm3) -
Retorno Gumbel Weibull Logpearson
10000 1793.00 208.00 96.20
2000 1564.00 198.00 83.20
1000 1465.00 194.00 77.80
200 1235.00 181.00 65.60
100 1136.00 174.00 60.50
50 1036.00 167.00 55.40
60
MICA 2012 –I-1
______________________________________________________________________
Gumbel-Weibull-Log-pearson
Periodo de Caudal Máximo (m3/s) - Caudal base (m3/s) - Volumen máximo 24 hr(hm3) -
Retorno Gumbel Weibull Logpearson
20 903.40 156.00 48.70
10 800.80 146.00 43.50
5 693.80 133.00 38.00
Al utilizar Weibull para ajustar el caudal base se nota una diferencia en cuanto a los
resultados obtrenido con Gumbel, esto se debe a la naturaleza del método estadísticos ya que
este tipo de distribución depende de un parámetro de forma y un parámetro de escala el cual
está asociada con el conjunto de datos por tal motivo existe diferencias con el ajuste por
Gumbel, ya que este método es más eficiente para el cálculo de los caudales máximos anuales,
pero conduce a errores cuando los caudales máximos provienen evidentemente de dos
poblaciones. Al utilizar Log-pearson para el cálculo de los volúmenes máximos diarios, se
observa que los resultados son muy similares a los obtenidos por el método de Gumbel, el
método de log-pearson III, considera una función de distribución la cual propone calcular los
parámetros estadísticos correspondientes a partir de los logaritmos decimales de los caudales
máximos registrados.
4.1.3 Ajuste para Caudal máximo, Caudal base y Volumen máximo, con (Weibull-
Weibull-Normal):
Weibull-Weibull-Normal
Periodo de Caudal Máximo (m3/s) - Caudal base (m3/s) - Volumen máximo 24 hr(hm3) -
Retorno Weibull Weibull Normal
10000 1220.00 208.00 66.10
2000 1160.00 198.00 62.10
1000 1120.00 194.00 60.20
200 1040.00 181.00 55.30
100 995.00 174.00 53.00
50 947.00 167.00 50.40
20 874.00 156.00 46.60
10 808.00 146.00 43.10
5 726.00 133.00 39.00
61
MICA 2012 –I-1
______________________________________________________________________
En esta tabla se observa una diferencia entre las estimaciones de los volúmenes máximos
en 24 horas, al utilizar el método de ajuste de distribución Normal, este método es muy poco
utilizado, debido que este tipo de distribución surge del teorema del límite central, el cual
establece que si una secuencia de variables aleatorias, son independientes y están idénticamente
distribuidas con media y varianza, entonces la distribución de la suma de n de estas variables
aleatorias es la sumatoria de las n variables por la secuencia de las variable, la cual tiende a una
distribución normal. Con relación a las precipitaciones y a los caudales máximos este tipo de
efecto simétrico no se aplica necesariamente, y por tal motivo puedan que existan diferencias
entre las distribuciones de Gumbel y la de Log-Pearson.
4.1.4 Ajuste para Caudal máximo, Caudal base y Volumen máximo, con (Log-pearson-
Gev-Log-pearson):
Tabla 6 Ajuste Log-pearson-Gev-Log-pearson
Log-pearson-Gev-Log-pearson
Se observa que el ajuste de los datos de caudal base con la distribución Gev, los datos tiende
a ser muy similares, a los resultados obtenidos con la distribución Gumbel y Log-Pearson.
62
MICA 2012 –I-1
______________________________________________________________________
4.1.5 Ajuste para Caudal máximo, Caudal base y Volumen máximo, con (Gumbel-Gev-
Log-pearson):
Tabla 7 Ajuste Gumbel-Gev-Log-pearson
Gumbel-Gev-Log-pearson
Se observa la diferencia de los valores obtenidos al utilizar este tipo de distribuciones para
el ajuste de los datos.
4.1.6 Ajuste para Caudal máximo, Caudal base y Volumen máximo, con (Log-pearson-
Log-pearson-Log-pearson):
Log-pearson- Log-pearson-Log-pearson
Periodo de Caudal Máximo (m3/s) -Log- Caudal base (m3/s) -Log- Volumen máximo 24 hr(hm3) - Log-
Retorno pearson pearson pearson
10000 1930.00 305.00 96.20
2000 1630.00 267.00 83.20
1000 1520.00 251.00 77.80
200 1260.00 214.00 65.60
100 1150.00 198.00 60.50
50 1040.00 183.00 55.40
20 906.00 162.00 48.70
10 802.00 146.00 43.50
5 694.00 129.00 38.00
Los resultados de la tabla 8, está dentro de la tendencia de los datos obtenidos de las
distribuciones de las tablas 3, 4 y 7.
63
MICA 2012 –I-1
______________________________________________________________________
4.1.7 Ajuste para Caudal máximo, Caudal base y Volumen máximo, con (Gumbel-
Weibull-Normal):
Tabla 9 Ajuste Gumbel-Weibull-Normal
Gumbel-Weibull-Normal
Periodo de Caudal Máximo (m3/s) - Caudal base (m3/s) Volumen máximo 24 hr(hm3)
Retorno Gumbel -Weibull - Normal
10000 1793.00 208.00 66.10
2000 1564.00 198.00 62.10
1000 1465.00 194.00 60.20
200 1235.00 181.00 55.30
100 1136.00 174.00 53.00
50 1036.00 167.00 50.40
20 903.40 156.00 46.60
10 800.80 146.00 43.10
5 693.80 133.00 39.00
64
MICA 2012 –I-1
______________________________________________________________________
4.2.1 Características de los parámetros de las crecientes utilizada en cada una de los
métodos utilizados:
En la siguiente tabla, se obtienen los parámetros físicos de cada creciente utilizada por cada
uno de los métodos, estas características son los valores de entrada del algoritmo de cada
método.
Tabla 10 Características físicas de los métodos
4 9 5 T(p)
273.35 152.30 123.36 Caudal base. (m3/s)
Constante 896.0 818.8 1012.0 Caudal Max. (m3/s)
16 35 31 Duración (hr).
30.73 44.26 37.26 Volumen (Hm)
4 9 5 T(p)
Incremento del flujo
0.0005500 0.0005500 0.0005500 base l/s*hect
Cuencas pequeñas
896.0 818.8 1012.0 Caudal Max. (m3/s)
16 35 31 Duración (hr).
30.73 44.26 37.26 Volumen (Hm)
4 9 5 T(p)
896.00 818.80 1012.00 Caudal Max. (m3/s)
16.00 35.00 31.00 Duración (hr).
30.73 44.26 37.26 Volumen (Hm)
Concave base slope 323.50 184.74 152.30 qs (m3/s)
1.00 1.00 1.00 ts (hr)
273.40 172.15 278.65 q0 (m3/s)
0.00 19.00 14.00 t0 (hr)
173.20 173.20 173.20 qm (m3/s)
65
MICA 2012 –I-1
______________________________________________________________________
4 9 5 T(p)
896.00 818.80 1012.00 Caudal Max. (m3/s)
16.00 35.00 31.00 Duracion (hr).
30.73 44.26 37.26 Volumen (Hm)
Constant Slope
323.50 184.74 152.30 qs (m3/s)
1.00 1.00 1.00 ts (hr)
378.50 378.50 378.50 qr (m3/s)
12.00 12.00 12.00 tr (hr)
4 9 5 T(p)
896.00 818.80 1012.00 Caudal max. (m3/s)
16.00 35.00 31.00 Duracion (hr).
Master Depletion
30.73 44.26 37.26 Volumen (Hm)
273.35 172.15 123.36 qo (m3/s)
0.004070 0.004070 0.004070 K
4.2.2 Aplicación de los métodos de separación de flujo base a la creciente de julio de 1996:
En las siguientes graficas se muestran, los datos obtenidos en campos que son las columnas;
-Fecha de la creciente, Nivel (cms), Hora de las lecturas, Delta de tiempo (h) de los incrementos
y/o cambios de niveles, Caudal Total (m3/s).
Las columnas sombreadas son los resultados de la aplicación del método, por ejemplo en la
tabla siguiente se aplica el método de separación de línea recta con valor inicial de 273.4 m3/s.
66
MICA 2012 –I-1
______________________________________________________________________
Tabla 11 Separación de flujo base método línea recta creciente julio de 1996
Caudal 1000
(m3/s)
Delta 900
Nivel Tiempo Q/QE
Fecha Hora tiempo Metodo Linea t/tp
(cm) (h) max
(h) Recta 800
Caudal (m3/s)
21/07/1996 233 11 0 0 273.4 273.4 0.0 0.00 0.00 600
251 12 1 1 323.5 275.9 47.6 0.25 0.08 500
321 13 1 2 564.9 278.5 286.3 0.50 0.43 400
399 15 2 4 896.0 283.7 612.3 1.00 1.00
300
383 16 1 5 842.8 286.3 556.5 1.25 0.91
200
295 21 5 10 466.5 299.3 167.2 2.50 0.27
100
269 23 2 12 378.5 304.5 74.0 3.00 0.12
0
259 24 1 13 347.4 307.1 40.3 3.25 0.07
0 5 10 15 20
22/07/1996 254 1 1 14 332.4 309.7 22.7 3.50 0.04 Tiempo (horas)
248 3 2 16 314.9 314.9 0.0 4.00 0.00
De la tabla 11, se observan los valores del caudal base, Caudal de escorrentía, además de la
forma del hidrograma conformado por los caudales base y los caudales de escorrentía, al
integral el área bajo esta curva se calculan los volúmenes de agua. De esta forma se construyen
todos los hidrogramas los cuales se muestran en las figuras siguientes.
Caudal 1000
(m3/s)
Delta Tiempo Q/QE 900
t/tp
tiempo (h) (h) Metodo Constante max
800
Total Base Escorrentía 700
CAUDAL (M3/S)
67
MICA 2012 –I-1
______________________________________________________________________
De la tabla 12, se observan los valores del caudal base, Caudal de escorrentía, además de la
forma del hidrograma conformado por los caudales base y los caudales de escorrentía, al
integral el área bajo esta curva se calculan los volúmenes de agua. El caudal ante del evento
de la precipitación es de 273.4 m3/s.
Tabla 13 Separación de flujo base método cuencas pequeñas creciente julio de 1996
Caudal
(m3/s) 1000.0
Delta
Tiempo Metodo Cuencas 900.0
Hora tiempo t/tp
(h) pequeñas
(h) 800.0
Q/QE max
Total Base Escorrentía
700.0
11 0 0 273.4 273.4 0.0 0.00 0.00
Caudal (m3/s)
600.0
12 1 1 323.5 275.3 48.2 0.25 0.08
500.0
13 1 2 564.9 277.3 287.6 0.50 0.47
400.0
15 2 4 896.0 281.3 614.7 1.00 1.00
300.0
16 1 5 842.8 283.3 559.6 1.25 0.91
200.0
21 5 10 466.5 293.2 173.3 2.50 0.28
100.0
23 2 12 378.5 297.1 81.4 3.00 0.13
0.0
24 1 13 347.4 299.1 48.3 3.25 0.08
0 5 10 15 20
1 1 14 332.4 301.1 31.3 3.50 0.05 Tiempo (horas)
3 2 16 314.9 305.0 9.8 4.00 0.02
De la tabla 13, obtenemos los resultados de los caudales utilizando el método de separación de flujo
base para cuencas pequeñas, de aquí se obtienen El caudal ante del evento de la precipitación es de
273.4 m3/s, y el caudal después de la recesión es de 305.0 m3/s.
Tabla 14 Separación de flujo base método Concave Baseflow creciente julio de 1996
Caudal
(m3/s) 1000.0
Delta
Tiempo Metodo Concave 900.0
tiempo t/tp
(h) Baseflow
(h) 800.0
Q/QE max
Total Base Escorrentía
700.0
(m3/s)
68
MICA 2012 –I-1
______________________________________________________________________
En esta tabla observamos que hay un caudal pico de 896.0 m3/s con un tiempo al pico de 4
horas, el caudal antes de la precipitación es de 273.4 m3/s y después de la recesión es de 314.9
m3/s, se observa que la escorrentía ocurre entre el tiempo 1 (h) y 12 (h).
Tabla 15 Separación de flujo base método Constant slope creciente julio de 1996
Caudal
(m3/s) Q/QE max 1000.0
Delta
Tiempo Metodo Constant 900.0
tiempo t/tp
(h) slope
(h) 800.0
Total Base Escorrentía 700.0
Caudal (m3/s)
0 0 273.4 273.4 0.0 0.00 0.00 600.0
1 1 323.5 335.5 0.0 0.25 0.00 500.0
1 2 564.9 340.5 226.4 0.50 0.41 400.0
2 4 896.0 350.5 547.5 1.00 1.00 300.0
1 5 842.8 353.5 489.3 1.25 0.89 200.0
5 10 466.5 372.5 88.0 2.50 0.16
100.0
2 12 378.5 382.5 6.0 3.00 0.01
0.0
1 13 347.4 341.4 6.0 3.25 0.01 0 5 10 15 20
1 14 332.4 326.4 6.0 3.50 0.01 Tiempo (horas)
2 16 314.9 308.9 6.0 4.00 0.01
En esta tabla observamos que hay un caudal pico de 896.0 m3/s con un tiempo al pico de 4
horas, el caudal antes de la precipitación es de 273.4 m3/s y después de la recesión es de 308.9
m3/s, se observa que la escorrentía ocurre entre el tiempo 2 (h) y 14 (h).
Tabla 16 Separación de flujo base método Master depletion creciente julio de 1996
Q 1000.0
(m3/s
) 900.0
Delta
Tiemp
tiempo Metodo Master t/tp
o (h) 800.0
(h) depletion
Escorrentí Q/QE max 700.0
Total Base
a
Caudal (m3/s)
600.0
0 0 273.4 273.4 0.0 0.00 0.00
500.0
1 1 323.5 272.2 51.3 0.25 0.08
1 2 564.9 271.1 293.8 0.50 0.47 400.0
2 4 896.0 268.9 627.1 1.00 1.00 300.0
1 5 842.8 267.8 575.0 1.25 0.92 200.0
5 10 466.5 262.3 204.1 2.50 0.33
100.0
2 12 378.5 260.2 118.3 3.00 0.19
0.0
1 13 347.4 259.1 88.2 3.25 0.14 0 5 10 15 20
1 14 332.4 258.1 74.3 3.50 0.12 Tiempo (horas)
2 16 314.9 256.0 58.9 4.00 0.09
69
MICA 2012 –I-1
______________________________________________________________________
En la tabla 16, realizamos la separación der flujo base con el método de master Depletion, con
un caudal antes del evento de 273.4 m3/S, y el caudal después de la recesión de 256.0 m3/s, a
diferencia de los otros métodos la escorrentía sigue después del evento, como una de las
características físicas importantes de las cuencas con alta vegetación.
De acuerdo a las investigaciones este método tiene en cuenta parámetros de retención.
Tabla 17 Separación de flujo base método línea recta creciente julio de 1997
Caudal (m3/s)
900
Delta
Nivel Tiempo Metodo Linea
Fecha Hora tiempo t/tp
(cm) (h) Recta 800
(h) Q/QE max
Total Base Escorrentía
700
12/07/1997 190 3 0.0 172.1 172.1 0.0 0.00 0.00
196 5 2 2.0 184.7 170.9 13.8 0.22 0.02 600
Caudal (m3/s)
70
MICA 2012 –I-1
______________________________________________________________________
Caudal (m3/s)
2 2.0 184.7 172.1 12.4 0.22 0.05
1 3.0 211.4 172.1 39.1 0.33 0.09 500
2 5.0 391.4 172.1 219.1 0.56 0.36
400
1 6.0 484.6 172.1 312.3 0.67 0.50
3 9.0 818.8 172.1 646.5 1.00 1.00 300
4 13.0 545.1 172.1 372.8 1.44 0.59
200
1 14.0 585.0 172.1 412.7 1.56 0.65
3 17.0 470.1 172.1 297.8 1.89 0.48 100
2 19.0 332.4 172.1 160.1 2.11 0.27
0
2 21.0 281.4 172.1 109.1 2.33 0.19
0 10 20 30 40
1 22.0 250.0 172.1 77.7 2.44 0.15
4 26.0 193.4 172.1 21.1 2.89 0.06 Tiempo (horas)
7 33.0 152.3 172.1 0.0 3.67 0.00
En la tabla 18, observamos que la forma del hidrograma tiene dos picos con caudales de
818.8 m3/s y un segundo pico de 585.0 m3/s, se aplicó el método de separación de flujo base
constante, con un caudal base constante de 172.1 m3/s.
71
MICA 2012 –I-1
______________________________________________________________________
Tabla 19 Separación de flujo base método línea recta creciente mayo de 1998
Caudal (m3/s)
1200
Delta
Nivel Tiempo Metodo Linea
Fecha Hora tiempo t/tp Q/QE max
(cm)
(h)
(h) Recta
Total Base Escorrentía 1000
Caudal (m3/s)
296 22 1 3 470.1 127.8 342.3 0.60 0.39
600
424 24 2 5 1012.0 130.7 881.3 1.00 1.00
29/05/1998 413 1 1 6 999.8 132.2 867.6 1.20 0.98
345 3 2 8 665.1 135.2 529.9 1.60 0.60 400
72
MICA 2012 –I-1
______________________________________________________________________
Se aplicaran los métodos desarrollado en esta investigación a las crecientes de 1996, 1998
y el promedio de estas crecientes. Con relaciona los resultados obtenidos por información
hidrométrica, tales como caudal máximo, mes más húmedo y volumen máximo en un dia, se
le aplicara diferentes ajustes estadísticos que son ajustes por Gumbel, Logpearson, Normal,
Weibul, Gev.
Los resultados más importantes de la modelación será el EMC (error medio cuadrático),
donde el resultado más confiable es aquel cercano a cero (0), se utilizaran 9 periodos de
retornos (5, 10, 20, 50, 100, 200, 1000, 2000 y 10000) años respectivamente. Posteriormente
se generaran las crecientes asociadas a los diferentes periodos de retornos, por cada
combinación de ajustes estadísticos.
Con el objetivo de tener más información del comportamiento del método, fue oportuno
realizar modelaciones con combinaciones de ajustes estadísticos, es decir el modelo tiene 3
entradas de datos para el ajuste estadístico que son: - Caudal Máximo Anual, - Caudal Medio
mes más húmedo y – Volumen máximo en un día, para entender el tipo de combinación la
primera es del volumen máximo, la segunda es del caudal medio mes más húmedo y la tercera
73
MICA 2012 –I-1
______________________________________________________________________
De las siguientes tablas obtenemos el EMC al comparar los volúmenes proyectados por
métodos estadísticos y la aplicación del método Coronado – Triana, donde el objetivo es
obtener el menor resultado del EMC, es decir que tienda a cero. Se subrayan los EMC con
mejor resultado.
74
MICA 2012 –I-1
______________________________________________________________________
Tabla 21 Calculo del EMC método flujo base Línea recta Combinación Gumbel-Gumbel-
Gumbel
75
MICA 2012 –I-1
______________________________________________________________________
Tabla 22 Calculo del EMC método flujo base Línea recta Combinación Gumbel-Log-pearson-
Weibull
76
MICA 2012 –I-1
______________________________________________________________________
En la tabla 21, se obtuvo para el método lineal, con la combinación de ajustes estadísticos
Gumbel, Logpearson, Weibull para datos con la creciente de junio de 1996 un EMC de 0.84
Hm3, Ademas se observan que existen dispersiones entre los datos de los volúmenes
registrados y proyectados por métodos estadísticos a diferentes periodos de retorno.
Entre los datos más dispersos encontramos el volumen registrado para un periodo de
retronó para 10000 años, existe una desviación de -6.76 hm3. Lo que indica una alta
dispersión.
En la tabla 22, obtenemos los resultados para el método lineal, con combinación Gumbel,
Normal y Logperarson, observamos una altísima dispersión entre los datos de volúmenes
registrados y los volúmenes modelados, esto ocurre para las crecientes de 1996, 1998 y la
combinación entre estas crecientes, el resultado no es el esperado debido al tipo de ajuste que
está dando resultados muy diferentes con las combinaciones, Gumbel, Gumbel y Gumbel.
77
MICA 2012 –I-1
______________________________________________________________________
Tabla 23 Calculo del EMC método flujo base Línea recta Combinación Gumbel-Normal-
Logpearson
78
MICA 2012 –I-1
______________________________________________________________________
De esta grafica se aprecia que mantienen la misma forma del hidrograma con tiempo al pico
de 10 horas para las crecientes de 1996 y la creciente promedio, para las crecientes generadas
a partir de la creciente de 1998 el tiempo al pico es 9 horas.
79
MICA 2012 –I-1
______________________________________________________________________
De la figura 8 se obtiene que el tiempo al pico para la generación para los años 1996, 1998
y las crecientes promedio es de 11 horas, para las crecientes generadas con la combinación de
las crecientes de 1996 y 1998, el tiempo al pico es de 12 horas, además la forma del
hidrograma muestra que la recesión empieza a partir de la hora 24, y mantiene de la hora 12 a
la 14 se darán la mayor creciente.
80
MICA 2012 –I-1
______________________________________________________________________
De la figura 9 se obtiene que el tiempo al pico para la generación para los años 1996, 1998
y las crecientes promedio es de 9 horas, con la combinación Weibull-Normal-Weibull. La
forma del hidrograma con la creciente de 1996, tiene una forma triangular que no se había
observado con las otras combinaciones estadísticas para la generación de hidrograma.
La validación del método se realiza con la creciente registrada en julio de 1997, con una
creciente modelada con un periodo de retorno de 11,28 Años. En la figura 15, Podemos
81
MICA 2012 –I-1
______________________________________________________________________
Figura 10 Validación del método con la creciente de 1997Metodo lineal Combinacion Gumbel-
Gumbel-Gumbel.
De la figura 10 se concluye que las validaciones con los datos de creciente de 1996 y la
promediada tienen mejor ajuste en cuanto al tiempo al pico y a la forma general del hidrograma,
con los datos de la creciente 1998 el ajuste no es el deseado ya que no coinciden en el tiempo
al pico y la forma del hidrograma
82
MICA 2012 –I-1
______________________________________________________________________
Figura 11 Validación del método con la creciente de 1997Metodo lineal Combinacion Gumbel-
Logpearson-Weibull.
En la figura 11, se observa que las validaciones tienen un ajuste similar en el tiempo al pico,
pero en el recorrido del hidrograma, la tendencia no es la deseada, por tanto necesita aún más
optimizar con este tipo de combinaciones. A demás se sale del rango en la recesión de la
creciente.
83
MICA 2012 –I-1
______________________________________________________________________
Figura 12 Validación del método con la creciente de 1997Metodo lineal Combinacion Weibulll-
Normal-Weibull.
En la figura 12, se observa un mejor ajuste tanto en forma y en tiempo al pico, el tiempo al
pico es de 9 horas.
84
MICA 2012 –I-1
______________________________________________________________________
Con las gráficas de las envolventes, tenemos los rangos mínimos y máximo permitido en
los cuales se dará la creciente con su periodo de retorno, por tanto estamos analizando para los
siguientes perdidos: 10000, 2000, 1000, 200, 100, 50, 20, 10, 5 años. Dentro de las envolventes
están las crecientes con los datos de creciente de 1996, 1998 y la combinación.
Para la anterior grafica es rango fue de mas o menos 20 M3/S.
85
MICA 2012 –I-1
______________________________________________________________________
Para la generaciones de bandas existen ciertas diferencias en cuanto al ancho de las bandas
de confianzas o envolventes, la diferencia radica en las combinaciones para el cálculo de los
hidrogramas, se observa la que mejor forma tiene es la Figura 15 Envolventes Método lineal
Combinación Gumbel-Logpearson-Gumbel.
86
MICA 2012 –I-1
______________________________________________________________________
Tabla 24 Calculo del EMC método flujo base Constante Combinación Gumbel-Gumbel-Gumbel
87
MICA 2012 –I-1
______________________________________________________________________
En el anexo se encuentran todas las combinaciones estadísticas para calcular el EMC de este
método constante.
88
MICA 2012 –I-1
______________________________________________________________________
La anterior gráfica, nos muestra el tiempo al pico para la generación de hidrogramas para
los años 1996, es de 9 horas y la forma del hidrograma es triangular, la recesión empieza a las
24 horas. Para la generación de hidrogramas con la creciente de 1998 se observa una forma
irregular del hidrograma muy distinta de la obtenida por el método lineal, su tiempo al pico es
de 15 horas, representado en una meseta a partir de las 14 hasta las 16 horas.
89
MICA 2012 –I-1
______________________________________________________________________
La anterior gráfica, nos muestra el tiempo al pico para la generación de hidrogramas para
los años 1996, 1998 y la combinación de las crecientes ocurrida en estos años es de 10 años, la
forma de los hidrogramas obtenidos son muy similares ya que su recesión empieza a las 24
horas.
90
MICA 2012 –I-1
______________________________________________________________________
La validación del método se realiza con la creciente registrada en julio de 1997, con una
creciente modelada con un periodo de retorno de 11,28 Años. En la figura 35, Podemos
observar que el comportamiento de la curva modelada se ajusta a la curva de la creciente
registrada.
Figura 18 Validación del método con la creciente de 1997 Metodo Constante Combinación Gumbel-
Gumbel-Gumbel..
91
MICA 2012 –I-1
______________________________________________________________________
En las gráficas representadas en la imagen anterior se concluye que el promedio del ancho
de bandas para el cálculo de las envolventes es de 30 m3/s. como se observó en los resultados
obtenidos en el método lineal, se agrega que la combinación de G-G-G es la que mejores
resultados arroja tanto para el método lineal como el constante.
92
MICA 2012 –I-1
______________________________________________________________________
De las siguientes tablas obtenemos el EMC al comparar los volúmenes proyectados por
métodos estadísticos y la aplicación del método Coronado – Triana, donde el objetivo es
obtener el menor resultado del EMC, es decir que tienda a cero. Se subrayan los EMC con
mejor resultado.
Tabla 25 Calculo del EMC método flujo base Cuencas pequeñas Combinación Gumbel-
Gumbel-Gumbel
93
MICA 2012 –I-1
______________________________________________________________________
94
MICA 2012 –I-1
______________________________________________________________________
De esta grafica se aprecia que mantienen la misma forma del hidrograma con tiempo al pico
de 10 horas, para los hidrogramas con creciente de 1996, 1998 y la combinación.
Al igual que en los métodos anteriores antes descripto (método de separación de flujo base
lineal y constante), se obtienen todos los hidrogramas asociados a diferentes periodos de
retronó y con diferentes combinaciones de ajustes estadísticos, de esta forma se analizan todos
los hidrogramas.
95
MICA 2012 –I-1
______________________________________________________________________
La validación del método se realiza con la creciente registrada en julio de 1997, con una
creciente modelada con un periodo de retorno de 11,28 Años. En la figura 15, Podemos
observar que el comportamiento de la curva modelada se ajusta a la curva de la creciente
registrada.
Figura 21 Validación del método con la creciente de 1997Metodo cuencas pequeñas Combinación
Gumbel-Gumbel-Gumbel..
96
MICA 2012 –I-1
______________________________________________________________________
Figura 22 Validación del método con la creciente de 1997Metodo cuencas pequeñas Combinación
Gumbel-Logpearson-Weibull.
97
MICA 2012 –I-1
______________________________________________________________________
98
MICA 2012 –I-1
______________________________________________________________________
Tabla 26 Calculo del EMC método flujo base Constant Slope Combinación Gumbel-Gumbel-
Gumbel
99
MICA 2012 –I-1
______________________________________________________________________
En las siguientes graficas se obtienen las crecientes a diferentes periodos de retorno, (5, 10,
20, 50, 100, 200, 1000, 2000, 10000), teniendo en cuenta las combinaciones para el ajuste
estadístico.
100
MICA 2012 –I-1
______________________________________________________________________
La validación del método se realiza con la creciente registrada en julio de 1997, con una
creciente modelada con un periodo de retorno de 11,28 Años. En las siguientes figuras, Se
observa que el comportamiento de la curva modelada se ajusta a la curva de la creciente
registrada.
Figura 25 Validación del método con la creciente de 1997Metodo Constant Slope Combinación
Gumbel-Gumbel-Gumbel.
101
MICA 2012 –I-1
______________________________________________________________________
La figura 25 nos muestra una excelente validación del método utilizando la combinación
Gumbel para el caudal máximo, mes más húmedo y volúmenes máximo diarios, además de
observa en especial la creciente de 1998 y la combinada que hay un excelente ajuste en tiempo
al pico, caudal y forma.
En esta grafica se observa que el ancho de la banda tiene un promedio de 15 m3/s, para la
creciente con un Tr=10 años, y 5 años el ancho de banda al inicio del hidrograma es de 20
m3/s.
102
MICA 2012 –I-1
______________________________________________________________________
Tabla 27 Calculo del EMC método flujo base Concave Base Slope Combinación Gumbel-
Gumbel-Gumbel
Periodo de retorno Volumen simulado (hm3) Volumen registrado (hm3) Error medio EMC
10000 97.90 96.36 1.54
2000 84.98 84.17 0.81
1000 79.38 78.91 0.47
200 66.98 66.71 0.27
100 61.69 61.44 0.25 0.73
Periodo de retorno Volumen simulado (hm3) Volumen registrado (hm3) Error medio EMC
Periodo de retorno Volumen simulado (hm3) Volumen registrado (hm3) Error medio EMC
10000 91.50 96.36 -4.86 2.61
103
MICA 2012 –I-1
______________________________________________________________________
En los anexos se encuentran todos los resultados obtenidos utilizando este método (Concave
base slope), este método tiene una particularidad que adiere mas variables a la función, la cual
permite una mejor representación de la cuenca que tributa a este rio, por tanto algunos
resultados pueden variar entre si.
104
MICA 2012 –I-1
______________________________________________________________________
De esta grafica se aprecia que los hidrogramas con la creciente de 1996 tienen un tiempo al
pico de 11 horas, la creciente de 1998 tiene un tiempo al pico de 12 horas y la creciente
combinada tiene un tiempo al pico de 12 horas, las formas de los hidrogramas son diferentes
como causa de los distintos tp.
La validación del método se realiza con la creciente registrada en julio de 1997, con una
creciente modelada con un periodo de retorno de 11,28 Años. En la figura 15, Podemos
observar que el comportamiento de la curva modelada se ajusta a la curva de la creciente
registrada.
105
MICA 2012 –I-1
______________________________________________________________________
Figura 28 Validación del método con la creciente de 1997Metodo Concave Base Slope Combinación
Gumbel-Gumbel-Gumbel..
106
MICA 2012 –I-1
______________________________________________________________________
5.1.5.3 Envolventes de las crecientes método flujo base Concave Base Slope:
107
MICA 2012 –I-1
______________________________________________________________________
Tabla 28 Calculo del EMC método flujo base Master Depletion Combinación Gumbel-
Gumbel-Gumbel
108
MICA 2012 –I-1
______________________________________________________________________
Los resultados obtenidos con este método son muy confiables ya que el EMC promedio de
todas las combinaciones de ajustes estadísticos es muy bajo, además por literatura y experiencia
se sabe que este método junto con el método lineal son los que mejor describen el
comportamiento matemático del flujo base.
109
MICA 2012 –I-1
______________________________________________________________________
De esta grafica se aprecia que mantienen la misma forma del hidrograma con tiempo al pico
de 10 horas, esta tendencia se observa en todos los métodos antes descriptos.
De esta grafica se aprecia que los hidrogramas con la creciente de 1996, 1998 y el
combinado tienen un tiempo al pico de 12 horas, las formas de los hidrogramas son diferentes
como causa de los distintos tp
110
MICA 2012 –I-1
______________________________________________________________________
La validación del método se realiza con la creciente registrada en julio de 1997, con una
creciente modelada con un periodo de retorno de 11,28 Años. En la figura 15, Podemos
observar que el comportamiento de la curva modelada se ajusta a la curva de la creciente
registrada.
Figura 32 Validación del método con la creciente de 1997Metodo Master Depletion Combinación
Gumbel-Gumbel-Gumbel..
La validación del método Master Depletion, con la creciente de 1997, arroja resultados
satisfactorios ya que se observan en las gráficas el ajuste que tiene el método con la creciente
de 1997, por tanto este método es junto al lineal el de mejores resultados tanto en EMC, como
en la validación.
111
MICA 2012 –I-1
______________________________________________________________________
112
MICA 2012 –I-1
______________________________________________________________________
5.2.1 Análisis de resultados EMC: En la siguiente tabla se muestran los resultados de los seis métodos propuestos en esta investigación, teniendo
en cuenta las crecientes de junio de 1996, Julio de 1998 y la combinación de estas crecientes, utilizando las combinaciones de ajustes antes
mencionadas (Weibul, Normal, Logpearson, Gumbel, Gev). Con el siguiente resumen, observamos cuales son los métodos que presenta un menor
Error Medio Cuadrático (EMC) y por tanto los métodos de separación de flujo base que tiene mejor ajuste.
10000 97.11 96.36 0.75 99.05 96.36 2.69 100.60 96.36 4.24 96.83 96.36 0.47 97.90 96.36 1.54 101.11 97.60 3.51
2000 84.72 84.17 0.55 86.44 84.17 2.27 87.84 84.17 3.67 85.80 84.17 1.63 84.98 84.17 0.81 88.60 85.30 3.30
1000 79.37 78.91 0.46 81.00 78.91 2.09 82.28 78.91 3.37 77.32 78.91 -1.59 79.38 78.91 0.47 79.38 77.67 1.71
200 66.93 66.71 0.22 68.34 66.71 1.63 69.46 66.71 2.75 65.47 66.71 -1.24 66.98 66.71 0.27 66.64 63.43 3.21
0.38 1.67 2.76 1.20 0.73 2.63
100 61.57 61.44 0.13 62.90 61.44 1.46 63.89 61.44 2.45 59.81 61.44 -1.63 61.69 61.44 0.25 62.08 59.12 2.96
50 56.17 56.15 0.02 57.40 56.15 1.25 58.34 56.15 2.19 55.39 56.15 -0.76 56.57 56.15 0.42 56.74 55.45 1.29
20 48.99 49.09 -0.10 50.10 49.09 1.01 50.93 49.09 1.84 48.55 49.09 -0.54 49.83 49.09 0.74 46.67 45.90 0.77
10 43.44 43.64 -0.20 44.45 43.64 0.81 45.19 43.64 1.55 44.10 43.64 0.46 44.20 43.64 0.56 43.07 40.10 2.97
5 37.65 37.95 -0.30 38.57 37.95 0.62 39.18 37.95 1.23 39.47 37.95 1.52 38.58 37.95 0.63 38.24 35.78 2.46
Hidrograma Q1998 - Método Hidrograma Q1998 - Método Cuencas Hidrograma Q1998 - Concave Base-
Hidrograma Q1998 - Método lineal Constante Pequeñas Hidrograma Q1998 - Constant Slope Slope Hidrograma Q1998 - Master Depletion
113
MICA 2012 –I-1
______________________________________________________________________
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 96.43 96.36 -10.62 96.49 96.36 0.13 95.84 96.36 -0.52 84.53 96.36 -11.83 91.28 96.36 -5.08 97.68 96.36 1.32
2000 84.23 84.17 0.06 84.21 84.17 0.04 83.70 84.17 -0.47 75.97 84.17 -8.20 80.95 84.17 -3.22 85.26 84.17 1.09
1000 78.96 78.91 0.05 78.91 78.91 0.00 78.40 78.91 -0.51 72.27 78.91 -6.64 76.49 78.91 -2.42 79.90 78.91 0.99
200 66.71 66.71 0.00 66.59 66.71 -0.12 66.20 66.71 -0.51 63.67 66.71 -3.04 66.12 66.71 -0.59 67.43 66.71 0.72
3.54 0.22 0.52 5.89 2.80 0.77
100 61.44 61.44 0.00 61.28 61.44 -0.16 60.90 61.44 -0.54 59.98 61.44 -1.46 61.66 61.44 0.22 62.06 61.44 0.62
50 56.12 56.15 -0.03 55.93 56.15 -0.22 55.62 56.15 -0.53 56.24 56.15 0.09 57.15 56.15 1.00 56.65 56.15 0.50
20 49.05 49.09 -0.04 48.82 49.09 -0.27 48.57 49.09 -0.52 51.28 49.09 2.19 51.17 49.09 2.08 49.46 49.09 0.37
10 43.58 43.64 -0.06 43.32 43.64 -0.32 43.11 43.64 -0.53 47.45 43.64 3.81 46.55 43.64 2.91 43.89 43.64 0.25
5 37.89 37.95 -0.06 37.59 37.95 -0.36 37.39 37.95 -0.56 43.45 37.95 5.50 41.72 37.95 3.77 38.09 37.95 0.14
Hidrograma Q PROMEDIO - Método Hidrograma Q PROMEDIO - Método Hidrograma Q PROMEDIO - Constant Hidrograma Q PROMEDIO - Concave Hidrograma Q PROMEDIO - Master
Hidrograma Q PROMEDIO - Método lineal Constante Pequeñas Slope Base-Slope Depletion
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 96.11 96.36 -0.25 96.02 96.36 -0.34 95.08 96.36 -1.28 89.76 96.36 -6.60 91.50 96.36 -4.86 97.95 96.36 1.59
2000 84.03 84.17 -0.14 83.80 84.17 -0.37 83.03 84.17 -1.14 80.33 84.17 -3.84 81.05 84.17 -3.12 85.46 84.17 1.29
1000 78.81 78.91 -0.10 78.53 78.91 -0.38 77.78 78.91 -1.13 76.25 78.91 -2.66 76.53 78.91 -2.38 80.06 78.91 1.15
200 66.68 66.71 -0.03 66.26 66.71 -0.45 65.68 66.71 -1.03 66.77 66.71 0.06 66.03 66.71 -0.68 67.52 66.71 0.81
0.13 0.46 1.03 4.20 2.61 0.89
100 61.46 61.44 0.02 60.98 61.44 -0.46 60.43 61.44 -1.01 62.70 61.44 1.26 61.51 61.44 0.07 62.12 61.44 0.68
50 56.19 56.15 0.04 55.66 56.15 -0.49 55.19 56.15 -0.96 58.58 56.15 2.43 56.94 56.15 0.79 56.67 56.15 0.52
20 49.20 49.09 0.11 48.58 49.09 -0.51 48.19 49.09 -0.90 53.11 49.09 4.02 50.89 49.09 1.80 49.44 49.09 0.35
10 43.78 43.64 0.14 43.11 43.64 -0.53 42.77 43.64 -0.87 48.88 43.64 5.24 46.20 43.64 2.56 43.84 43.64 0.20
5 38.14 37.95 0.19 37.41 37.95 -0.54 37.10 37.95 -0.85 44.48 37.95 6.53 41.32 37.95 3.37 38.01 37.95 0.06
114
MICA 2012 –I-1
______________________________________________________________________
Hidrograma Q1996 - Método Hidrograma Q1996 - Método Cuencas Hidrograma Q1996 - Concave Base-
Hidrograma Q1996 - Método lineal Constante Pequeñas Hidrograma Q1996 - Constant Slope Slope Hidrograma Q1996 - Master Depletion
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 101.07 96.20 4.87 94.19 96.20 -2.01 96.75 96.20 0.55 92.44 96.20 -3.76 91.31 96.20 -4.89 91.98 96.20 -4.22
2000 88.77 83.20 5.57 82.73 83.20 -0.47 84.70 83.20 1.50 82.47 83.20 -0.73 84.54 83.20 1.34 80.57 83.20 -2.63
1000 83.46 77.80 5.66 77.79 77.80 -0.01 79.45 77.80 1.65 78.17 77.80 0.37 74.20 77.80 -3.60 75.66 77.80 -2.14
200 71.00 65.60 5.40 66.17 65.60 0.57 67.30 65.60 1.70 68.11 65.60 2.51 62.56 65.60 -3.04 64.09 65.60 -1.51
4.76 0.80 1.23 1.97 2.71 3.01
100 65.59 60.50 5.09 61.12 60.50 0.62 62.00 60.50 1.50 63.76 60.50 3.26 58.33 60.50 -2.17 61.04 60.50 0.54
50 60.13 55.40 4.73 56.03 55.40 0.63 56.72 55.40 1.32 57.00 55.40 1.60 52.69 55.40 -2.71 59.99 55.40 4.59
20 52.83 48.70 4.13 49.21 48.70 0.51 49.64 48.70 0.94 49.24 48.70 0.54 50.26 48.70 1.56 52.45 48.70 3.75
10 47.13 43.50 3.63 43.89 43.50 0.39 44.14 43.50 0.64 43.59 43.50 0.09 43.52 43.50 0.02 46.55 43.50 3.05
5 41.10 38.00 3.10 38.25 38.00 0.25 38.31 38.00 0.31 37.57 38.00 -0.43 39.91 38.00 1.91 40.29 38.00 2.29
10000 89.44 96.20 -6.76 88.21 96.20 -7.99 91.73 96.20 -4.47 92.06 96.20 -4.14 86.25 96.20 -9.95 90.33 96.20 -5.87
2000 78.86 83.20 -4.34 78.31 83.20 -4.89 81.13 83.20 -2.07 83.35 83.20 0.15 78.26 83.20 -4.94 79.34 83.20 -3.86
1000 74.29 77.80 -3.51 74.06 77.80 -3.74 76.53 77.80 -1.27 79.60 77.80 1.80 74.82 77.80 -2.98 74.60 77.80 -3.20
200 63.54 65.60 -2.06 63.88 65.60 -1.72 65.69 65.60 0.09 64.32 65.60 -1.28 66.68 65.60 1.08 63.42 65.60 -2.18
3.11 3.44 1.80 2.26 4.62 2.98
100 58.86 60.50 -1.64 59.38 60.50 -1.12 60.89 60.50 0.39 60.81 60.50 0.31 56.81 60.50 -3.69 58.55 60.50 -1.95
50 54.12 55.40 -1.28 54.84 55.40 -0.56 56.11 55.40 0.71 57.27 55.40 1.87 53.58 55.40 -1.82 53.62 55.40 -1.78
20 47.78 48.70 -0.92 48.68 48.70 -0.02 49.62 48.70 0.92 52.52 48.70 3.82 43.21 48.70 -5.49 47.01 48.70 -1.69
10 42.81 43.50 -0.69 43.79 43.50 0.29 44.50 43.50 1.00 43.91 43.50 0.41 40.21 43.50 -3.29 41.82 43.50 -1.68
5 37.51 38.00 -0.49 38.48 38.00 0.48 38.97 38.00 0.97 40.35 38.00 2.35 37.01 38.00 -0.99 36.29 38.00 -1.71
115
MICA 2012 –I-1
______________________________________________________________________
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 94.31 96.20 -1.89 90.83 96.20 -5.37 94.61 96.20 -1.59 95.61 96.20 -0.59 95.44 96.20 -0.76 94.77 96.20 -1.43
2000 82.87 83.20 -0.33 80.17 83.20 -3.03 83.27 83.20 0.07 87.01 83.20 3.81 77.75 83.20 -5.45 83.01 83.20 -0.19
1000 77.93 77.80 0.13 75.58 77.80 -2.22 78.34 77.80 0.54 74.98 77.80 -2.82 74.23 77.80 -3.57 77.94 77.80 0.14
200 66.33 65.60 0.73 64.70 65.60 -0.90 66.82 65.60 1.22 67.09 65.60 1.49 65.96 65.60 0.36 66.02 65.60 0.42
0.84 2.22 1.11 2.67 2.74 0.58
100 61.28 60.50 0.78 59.94 60.50 -0.56 61.76 60.50 1.26 63.64 60.50 3.14 62.36 60.50 1.86 60.83 60.50 0.33
50 56.18 55.40 0.78 55.14 55.40 -0.26 56.72 55.40 1.32 56.81 55.40 1.41 58.72 55.40 3.32 55.60 55.40 0.20
20 49.36 48.70 0.66 48.67 48.70 -0.03 49.91 48.70 1.21 49.31 48.70 0.61 47.86 48.70 -0.84 48.60 48.70 -0.10
10 44.02 43.50 0.52 43.58 43.50 0.08 44.58 43.50 1.08 46.03 43.50 2.53 44.47 43.50 0.97 43.13 43.50 -0.37
5 38.36 38.00 0.36 38.12 38.00 0.12 38.88 38.00 0.88 42.53 38.00 4.53 40.86 38.00 2.86 37.33 38.00 -0.67
METODO Concave Base-Slope
METODO LINEAL COMBINACION WEIBULL-NORMAL- METODO CONSTANTE COMBINACION METODO CONSTANTE COMBINACION METODO Constant Slope COMBINACION COMBINACION WEIBULL-NORMAL- METODO CONSTANTE COMBINACION
WEIBULL WEIBULL-NORMAL-WEIBULL WEIBULL-NORMAL-WEIBULL WEIBULL-NORMAL-WEIBULL WEIBULL WEIBULL-NORMAL-WEIBULL
Hidrograma Q1996 - Método Hidrograma Q1996 - Método Cuencas Hidrograma Q1996 - Concave Base-
Hidrograma Q1996 - Método lineal Constante Pequeñas Hidrograma Q1996 - Constant Slope Slope Hidrograma Q1996 - Master Depletion
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 65.22 66.10 -0.88 66.37 66.10 0.27 66.33 66.10 0.23 102.91 96.20 6.71 63.64 66.10 -2.46 62.61 66.10 -3.49
2000 62.06 62.10 -0.04 63.11 62.10 1.01 63.11 62.10 1.01 92.12 83.20 8.92 61.14 62.10 -0.96 59.46 62.10 -2.64
1000 60.03 60.20 -0.17 61.03 60.20 0.83 61.02 60.20 0.82 80.15 77.80 2.35 59.52 60.20 -0.68 57.50 60.20 -2.70
200 55.82 55.30 0.52 56.70 55.30 1.40 56.73 55.30 1.43 66.02 65.60 0.42 56.18 55.30 0.88 53.32 55.30 -1.98
0.52 1.08 1.11 4.02 2.36 2.69
100 53.47 53.00 0.47 54.28 53.00 1.28 54.28 53.00 1.28 60.90 60.50 0.40 54.31 53.00 1.31 52.68 53.00 -0.32
50 50.97 50.40 0.57 51.71 50.40 1.31 51.75 50.40 1.35 54.42 55.40 -0.98 52.32 50.40 1.92 53.91 50.40 3.51
20 47.16 46.60 0.56 47.78 46.60 1.18 47.84 46.60 1.24 51.48 48.70 2.78 49.29 46.60 2.69 49.72 46.60 3.12
10 43.71 43.10 0.61 44.24 43.10 1.14 44.31 43.10 1.21 44.27 43.50 0.77 46.56 43.10 3.46 45.93 43.10 2.83
5 39.40 39.00 0.40 39.81 39.00 0.81 39.86 39.00 0.86 40.37 38.00 2.37 43.14 39.00 4.14 41.19 39.00 2.19
116
MICA 2012 –I-1
______________________________________________________________________
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 62.79 66.10 -3.31 62.53 66.10 -3.57 61.82 66.10 -4.28 65.29 66.10 -0.81 61.06 66.10 -5.04 60.97 66.10 -5.13
2000 59.84 62.10 -2.26 59.47 62.10 -2.63 58.83 62.10 -3.27 62.91 62.10 0.81 58.94 62.10 -3.16 57.92 62.10 -4.18
1000 58.03 60.20 -2.17 57.61 60.20 -2.59 56.98 60.20 -3.22 61.42 60.20 1.22 57.61 60.20 -2.59 56.06 60.20 -4.14
200 54.11 55.30 -1.19 53.56 55.30 -1.74 53.00 55.30 -2.30 58.26 55.30 2.96 54.79 55.30 -0.51 52.01 55.30 -3.29
1.64 2.08 2.61 2.89 3.08 3.55
100 51.93 53.00 -1.07 51.29 53.00 -1.71 50.75 53.00 -2.25 50.85 53.00 -2.15 53.21 53.00 0.21 49.76 53.00 -3.24
50 49.62 50.40 -0.78 48.92 50.40 -1.48 48.43 50.40 -1.97 49.17 50.40 -1.23 51.55 50.40 1.15 47.38 50.40 -3.02
20 46.10 46.60 -0.50 45.27 46.60 -1.33 44.84 46.60 -1.76 40.91 46.60 -5.69 49.00 46.60 2.40 43.75 46.60 -2.85
10 42.91 43.10 -0.19 41.98 43.10 -1.12 41.59 43.10 -1.51 38.87 43.10 -4.23 46.70 43.10 3.60 40.46 43.10 -2.64
5 38.91 39.00 -0.09 37.84 39.00 -1.16 37.49 39.00 -1.51 36.32 39.00 -2.68 43.82 39.00 4.82 36.33 39.00 -2.67
10000 63.05 66.10 -3.05 64.07 66.10 -2.03 64.83 66.10 -1.27 72.31 66.10 6.21 71.52 66.10 5.42 65.45 66.10 -0.65
2000 60.03 62.10 -2.07 60.93 62.10 -1.17 61.69 62.10 -0.41 62.72 62.10 0.62 69.13 62.10 7.03 62.17 62.10 0.07
1000 58.13 60.20 -2.07 58.97 60.20 -1.23 59.70 60.20 -0.50 61.23 60.20 1.03 60.89 60.20 0.69 60.15 60.20 -0.05
200 54.11 55.30 -1.19 54.80 55.30 -0.50 55.53 55.30 0.23 58.09 55.30 2.79 58.04 55.30 2.74 55.79 55.30 0.49
1.58 0.94 0.52 2.97 3.49 0.35
100 51.87 53.00 -1.13 52.47 53.00 -0.53 53.15 53.00 0.15 56.34 53.00 3.34 56.45 53.00 3.45 53.36 53.00 0.36
50 49.49 50.40 -0.91 50.01 50.40 -0.39 50.70 50.40 0.30 54.48 50.40 4.08 51.73 50.40 1.33 50.80 50.40 0.40
20 45.86 46.60 -0.74 46.25 46.60 -0.35 46.91 46.60 0.31 45.91 46.60 -0.69 46.41 46.60 -0.19 46.87 46.60 0.27
10 42.58 43.10 -0.52 42.84 43.10 -0.26 43.48 43.10 0.38 43.63 43.10 0.53 44.34 43.10 1.24 43.32 43.10 0.22
5 38.48 39.00 -0.52 38.59 39.00 -0.41 39.16 39.00 0.16 40.78 39.00 1.78 41.76 39.00 2.76 38.88 39.00 -0.12
METODO CONSTANTE COMBINACION LOG- METODO CONSTANTE COMBINACION LOG- METODO Constant Slope COMBINACION METODO CONSTANTE COMBINACION LOG- METODO CONSTANTE COMBINACION LOG-
METODO LINEAL COMBINACION LOG-LOG-GEV LOG-GEV LOG-GEV LOG-LOG-GEV LOG-GEV LOG-GEV
117
MICA 2012 –I-1
______________________________________________________________________
Hidrograma Q1996 - Método Hidrograma Q1996 - Método Cuencas Hidrograma Q1996 - Concave Base-
Hidrograma Q1996 - Método lineal Constante Pequeñas Hidrograma Q1996 - Constant Slope Slope Hidrograma Q1996 - Master Depletion
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000.00 102.65 96.20 6.45 100.12 96.20 3.92 100.01 96.20 3.81 91.59 96.20 -4.61 102.91 96.20 6.71 95.00 96.20 -1.20
2000.00 87.06 83.20 3.86 84.74 83.20 1.54 84.69 83.20 1.49 80.13 83.20 -3.07 92.12 83.20 8.92 80.31 83.20 -2.89
1000.00 81.23 77.80 3.43 79.02 77.80 1.22 78.95 77.80 1.15 75.82 77.80 -1.98 80.15 77.80 2.35 74.82 77.80 -2.98
200.00 67.60 65.60 2.00 65.60 65.60 0.00 65.58 65.60 -0.02 65.77 65.60 0.17 66.02 65.60 0.42 61.97 65.60 -3.63
2.88 1.78 1.75 2.20 4.02 2.07
100.00 61.81 60.50 1.31 59.91 60.50 -0.59 59.86 60.50 -0.64 61.50 60.50 1.00 60.90 60.50 0.40 58.39 60.50 -2.11
50.00 56.05 55.40 0.65 54.24 55.40 -1.16 54.23 55.40 -1.17 53.82 55.40 -1.58 54.42 55.40 -0.98 56.76 55.40 1.36
20.00 48.96 48.70 0.26 47.28 48.70 -1.42 47.28 48.70 -1.42 46.81 48.70 -1.89 51.48 48.70 2.78 49.33 48.70 0.63
10.00 43.46 43.50 -0.04 41.87 43.50 -1.63 41.89 43.50 -1.61 43.15 43.50 -0.35 44.27 43.50 0.77 43.56 43.50 0.06
5.00 37.77 38.00 -0.23 36.27 38.00 -1.73 36.26 38.00 -1.74 39.36 38.00 1.36 40.37 38.00 2.37 37.59 38.00 -0.41
Hidrograma Q1998 - Método Hidrograma Q1998 - Método Cuencas Hidrograma Q1998 - Constant Slope Hidrograma Q1998 - Concave Base-
Hidrograma Q1998 - Método lineal Constante Pequeñas GUMBEL-LOGPEARSON-WEIBULL Slope Hidrograma Q1998 - Master Depletion
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 101.70 96.20 5.50 96.30 96.20 0.10 95.92 96.20 -0.28 93.33 96.20 -2.87 98.45 96.20 2.25 97.16 96.20 0.96
2000 86.36 83.20 3.16 81.79 83.20 -1.41 81.52 83.20 -1.68 82.02 83.20 -1.18 86.33 83.20 3.13 82.32 83.20 -0.88
1000 80.60 77.80 2.80 76.27 77.80 -1.53 76.00 77.80 -1.80 77.69 77.80 -0.11 81.75 77.80 3.95 76.67 77.80 -1.13
200 67.15 65.60 1.55 63.47 65.60 -2.13 63.30 65.60 -2.30 67.67 65.60 2.07 71.08 65.60 5.48 63.56 65.60 -2.04
2.39 2.25 2.38 3.96 3.04 2.43
100 61.43 60.50 0.93 58.01 60.50 -2.49 57.84 60.50 -2.66 57.06 60.50 -3.44 59.88 60.50 -0.62 57.98 60.50 -2.52
50 55.75 55.40 0.35 52.62 55.40 -2.78 52.50 55.40 -2.90 47.34 55.40 -8.06 55.83 55.40 0.43 52.46 55.40 -2.94
20 48.74 48.70 0.04 45.91 48.70 -2.79 45.82 48.70 -2.88 48.52 48.70 -0.18 44.60 48.70 -4.10 45.58 48.70 -3.12
10 43.30 43.50 -0.20 40.69 43.50 -2.81 40.63 43.50 -2.87 39.85 43.50 -3.65 41.17 43.50 -2.33 40.24 43.50 -3.26
5 37.67 38.00 -0.33 35.31 38.00 -2.69 35.26 38.00 -2.74 31.92 38.00 -6.08 37.64 38.00 -0.36 34.73 38.00 -3.27
118
MICA 2012 –I-1
______________________________________________________________________
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 101.70 96.20 5.50 101.16 96.20 4.96 99.55 96.20 3.35 95.96 96.20 -0.24 102.38 96.20 6.18 97.38 96.20 1.18
2000 86.36 83.20 3.16 85.81 83.20 2.61 84.40 83.20 1.20 84.55 83.20 1.35 80.56 83.20 -2.64 82.28 83.20 -0.92
1000 80.60 77.80 2.80 80.02 77.80 2.22 78.68 77.80 0.88 72.17 77.80 -5.63 76.21 77.80 -1.59 76.62 77.80 -1.18
200 67.15 65.60 1.55 66.53 65.60 0.93 65.42 65.60 -0.18 63.08 65.60 -2.52 66.06 65.60 0.46 63.39 65.60 -2.21
2.39 2.10 1.62 2.76 2.60 2.66
100 61.43 60.50 0.93 60.79 60.50 0.29 59.74 60.50 -0.76 59.20 60.50 -1.30 61.74 60.50 1.24 57.76 60.50 -2.74
50 55.75 55.40 0.35 55.10 55.40 -0.30 54.16 55.40 -1.24 52.29 55.40 -3.11 57.45 55.40 2.05 52.18 55.40 -3.22
20 48.74 48.70 0.04 48.05 48.70 -0.65 47.23 48.70 -1.47 44.97 48.70 -3.73 46.37 48.70 -2.33 45.29 48.70 -3.41
10 43.30 43.50 -0.20 42.58 43.50 -0.92 41.85 43.50 -1.65 41.66 43.50 -1.84 42.71 43.50 -0.79 39.93 43.50 -3.57
5 37.67 38.00 -0.33 36.93 38.00 -1.07 36.26 38.00 -1.74 38.26 38.00 0.26 38.94 38.00 0.94 34.40 38.00 -3.60
METODO Concave Base-Slope
METODO CONSTANTE COMBINACION METODO Método Cuencas Pequeñas METODO Constant Slope COMBINACION COMBINACION GUMBEL-LOGPEARSON- METODO CONSTANTE COMBINACION
METODO LINEAL COMBINACION GUMBEL-LOG-GEV. GUMBEL-LOG-GEV. COMBINACION LOG-LOG-GEV LOG-LOG-GEV WEIBULL GUMBEL-LOGPEARSON-WEIBULL
Hidrograma Q1996 - Método Hidrograma Q1996 - Método Cuencas Hidrograma Q1996 - Concave Base-
Hidrograma Q1996 - Método lineal Constante Pequeñas Hidrograma Q1996 - Constant Slope Slope Hidrograma Q1996 - Master Depletion
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 95.57 96.20 -0.63 93.59 96.20 -2.61 100.01 96.20 3.81 91.59 96.20 -4.61 92.44 96.20 -3.76 95.00 96.20 -1.20
2000 83.42 83.20 0.22 81.59 83.20 -1.61 84.69 83.20 1.49 80.13 83.20 -3.07 82.47 83.20 -0.73 80.31 83.20 -2.89
1000 78.15 77.80 0.35 76.40 77.80 -1.40 78.95 77.80 1.15 75.82 77.80 -1.98 78.17 77.80 0.37 74.82 77.80 -2.98
200 66.02 65.60 0.42 64.41 65.60 -1.19 65.58 65.60 -0.02 65.77 65.60 0.17 68.11 65.60 2.51 61.97 65.60 -3.63
0.36 1.64 1.75 2.20 1.97 2.07
100 60.78 60.50 0.28 59.24 60.50 -1.26 59.86 60.50 -0.64 61.50 60.50 1.00 63.76 60.50 3.26 58.39 60.50 -2.11
50 55.53 55.40 0.13 54.05 55.40 -1.35 54.23 55.40 -1.17 53.82 55.40 -1.58 57.00 55.40 1.60 56.76 55.40 1.36
20 48.56 48.70 -0.14 47.16 48.70 -1.54 47.28 48.70 -1.42 46.81 48.70 -1.89 49.24 48.70 0.54 49.33 48.70 0.63
10 43.16 43.50 -0.34 41.82 43.50 -1.68 41.89 43.50 -1.61 43.15 43.50 -0.35 43.59 43.50 0.09 43.56 43.50 0.06
5 37.55 38.00 -0.45 36.28 38.00 -1.72 36.26 38.00 -1.74 39.36 38.00 1.36 37.57 38.00 -0.43 37.59 38.00 -0.41
Hidrograma Q1998 - Método Hidrograma Q1998 - Método Cuencas Hidrograma Q1998 - Constant Slope Hidrograma Q1998 - Concave Base-
Hidrograma Q1998 - Método lineal Constante Pequeñas GUMBEL-LOGPEARSON-WEIBULL Slope Hidrograma Q1998 - Master Depletion
119
MICA 2012 –I-1
______________________________________________________________________
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 95.50 96.20 -0.70 95.56 96.20 -0.64 95.92 96.20 -0.28 93.33 96.20 -2.87 92.06 96.20 -4.14 97.16 96.20 0.96
2000 83.37 83.20 0.17 83.24 83.20 0.04 81.52 83.20 -1.68 82.02 83.20 -1.18 83.35 83.20 0.15 82.32 83.20 -0.88
1000 78.11 77.80 0.31 77.88 77.80 0.08 76.00 77.80 -1.80 77.69 77.80 -0.11 79.60 77.80 1.80 76.67 77.80 -1.13
200 66.02 65.60 0.42 65.68 65.60 0.08 63.30 65.60 -2.30 67.67 65.60 2.07 64.32 65.60 -1.28 63.56 65.60 -2.04
0.35 0.48 2.38 3.96 2.26 2.43
100 60.80 60.50 0.30 60.40 60.50 -0.10 57.84 60.50 -2.66 57.06 60.50 -3.44 60.81 60.50 0.31 57.98 60.50 -2.52
50 55.57 55.40 0.17 55.15 55.40 -0.25 52.50 55.40 -2.90 47.34 55.40 -8.06 57.27 55.40 1.87 52.46 55.40 -2.94
20 48.63 48.70 -0.07 48.17 48.70 -0.53 45.82 48.70 -2.88 48.52 48.70 -0.18 52.52 48.70 3.82 45.58 48.70 -3.12
10 43.24 43.50 -0.26 42.74 43.50 -0.76 40.63 43.50 -2.87 39.85 43.50 -3.65 43.91 43.50 0.41 40.24 43.50 -3.26
5 37.66 38.00 -0.34 37.15 38.00 -0.85 35.26 38.00 -2.74 31.92 38.00 -6.08 40.35 38.00 2.35 34.73 38.00 -3.27
Hidrograma Q PROMEDIO - Constant
Hidrograma Q PROMEDIO - Método Hidrograma Q PROMEDIO - Método Slope GUMBEL-LOGPEARSON- Hidrograma Q PROMEDIO - Concave Hidrograma Q PROMEDIO - Master
Hidrograma Q PROMEDIO - Método lineal Constante Pequeñas WEIBULL Base-Slope Depletion
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 95.50 96.20 -0.70 95.88 96.20 -0.32 99.55 96.20 3.35 95.96 96.20 -0.24 95.61 96.20 -0.59 97.38 96.20 1.18
2000 83.37 83.20 0.17 83.57 83.20 0.37 84.40 83.20 1.20 84.55 83.20 1.35 87.01 83.20 3.81 82.28 83.20 -0.92
1000 78.11 77.80 0.31 78.22 77.80 0.42 78.68 77.80 0.88 72.17 77.80 -5.63 74.98 77.80 -2.82 76.62 77.80 -1.18
200 66.02 65.60 0.42 65.95 65.60 0.35 65.42 65.60 -0.18 63.08 65.60 -2.52 67.09 65.60 1.49 63.39 65.60 -2.21
0.35 0.44 1.62 2.76 2.67 2.66
100 61.80 60.50 0.30 60.66 60.50 0.16 59.74 60.50 -0.76 59.20 60.50 -1.30 63.64 60.50 3.14 57.76 60.50 -2.74
50 55.70 55.40 0.17 55.36 55.40 -0.04 54.16 55.40 -1.24 52.29 55.40 -3.11 56.81 55.40 1.41 52.18 55.40 -3.22
20 48.63 48.70 -0.07 48.32 48.70 -0.38 47.23 48.70 -1.47 44.97 48.70 -3.73 49.31 48.70 0.61 45.29 48.70 -3.41
10 43.52 43.50 -0.26 42.87 43.50 -0.63 41.85 43.50 -1.65 41.66 43.50 -1.84 46.03 43.50 2.53 39.93 43.50 -3.57
5 37.36 38.00 -0.34 37.21 38.00 -0.79 36.26 38.00 -1.74 38.26 38.00 0.26 42.53 38.00 4.53 34.40 38.00 -3.60
METODO CONSTANTE COMBINACION LOG- METODO Método Cuencas Pequeñas METODO Constant Slope COMBINACION METODO Concave Base-Slope METODO CONSTANTE COMBINACION LOG-
METODO LINEAL COMBINACION LOG-LOG-LOG. LOG-LOG. COMBINACION LOG-LOG-LOG. LOG-LOG-LOG. COMBINACION LOG-LOG-LOG. LOG-LOG.
120
MICA 2012 –I-1
______________________________________________________________________
Hidrograma Q1996 - Método Hidrograma Q1996 - Método Cuencas Hidrograma Q1996 - Concave Base-
Hidrograma Q1996 - Método lineal Constante Pequeñas Hidrograma Q1996 - Constant Slope Slope Hidrograma Q1996 - Master Depletion
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 108.28 96.20 12.08 99.46 96.20 3.26 99.53 96.20 3.33 98.06 96.20 1.86 100.05 96.20 3.85 99.15 96.20 2.95
2000 91.78 83.20 8.58 84.27 83.20 1.07 84.32 83.20 1.12 84.94 83.20 1.74 85.12 83.20 1.92 83.73 83.20 0.53
1000 85.68 77.80 7.88 78.64 77.80 0.84 78.66 77.80 0.86 76.43 77.80 -1.37 79.51 77.80 1.71 78.01 77.80 0.21
200 71.27 65.60 5.67 65.36 65.60 -0.24 65.39 65.60 -0.21 64.28 65.60 -1.32 66.88 65.60 1.28 64.52 65.60 -1.08
6.38 1.58 1.60 1.42 1.92 1.93
100 65.16 60.50 4.66 59.73 60.50 -0.77 59.72 60.50 -0.78 58.58 60.50 -1.92 61.58 60.50 1.08 60.76 60.50 0.26
50 59.08 55.40 3.68 54.13 55.40 -1.27 54.14 55.40 -1.26 54.15 55.40 -1.25 56.50 55.40 1.10 59.02 55.40 3.62
20 51.60 48.70 2.90 47.23 48.70 -1.47 47.23 48.70 -1.47 47.76 48.70 -0.94 50.27 48.70 1.57 51.23 48.70 2.53
10 45.81 43.50 2.31 41.88 43.50 -1.62 41.89 43.50 -1.61 43.63 43.50 0.13 45.00 43.50 1.50 45.19 43.50 1.69
5 39.78 38.00 1.78 36.32 38.00 -1.68 36.29 38.00 -1.71 39.35 38.00 1.35 39.76 38.00 1.76 38.91 38.00 0.91
Hidrograma Q1998 - Método Hidrograma Q1998 - Método Cuencas Hidrograma Q1998 - Constant Slope Hidrograma Q1998 - Concave Base-
Hidrograma Q1998 - Método lineal Constante Pequeñas GUMBEL-LOGPEARSON-WEIBULL Slope Hidrograma Q1998 - Master Depletion
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 98.22 96.20 2.02 97.31 96.20 1.11 96.04 96.20 -0.16 91.19 96.20 -5.01 90.79 96.20 -5.41 97.87 96.20 1.67
2000 83.55 83.20 0.35 82.91 83.20 -0.29 81.81 83.20 -1.39 80.57 83.20 -2.63 79.96 83.20 -3.24 82.98 83.20 -0.22
1000 78.08 77.80 0.28 77.47 77.80 -0.33 76.42 77.80 -1.38 76.58 77.80 -1.22 75.89 77.80 -1.91 77.43 77.80 -0.37
200 65.18 65.60 -0.42 64.67 65.60 -0.93 63.81 65.60 -1.79 67.19 65.60 1.59 66.32 65.60 0.72 64.35 65.60 -1.25
1.06 1.22 1.83 4.86 4.24 1.74
100 59.71 60.50 -0.79 59.23 60.50 -1.27 58.41 60.50 -2.09 63.20 60.50 2.70 62.25 60.50 1.75 58.81 60.50 -1.69
50 54.29 55.40 -1.11 53.87 55.40 -1.53 53.14 55.40 -2.26 59.26 55.40 3.86 58.23 55.40 2.83 53.30 55.40 -2.10
20 47.56 48.70 -1.14 47.13 48.70 -1.57 46.49 48.70 -2.21 54.33 48.70 5.63 53.21 48.70 4.51 46.48 48.70 -2.22
10 42.35 43.50 -1.15 41.92 43.50 -1.58 41.36 43.50 -2.14 50.52 43.50 7.02 49.33 43.50 5.83 41.20 43.50 -2.30
5 36.92 38.00 -1.08 36.48 38.00 -1.52 35.97 38.00 -2.03 46.55 38.00 8.55 45.27 38.00 7.27 35.69 38.00 -2.31
121
MICA 2012 –I-1
______________________________________________________________________
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 104.19 96.20 7.99 98.82 96.20 2.62 100.00 96.20 3.80 95.37 96.20 -0.83 94.83 96.20 -1.37 102.29 96.20 6.09
2000 88.54 83.20 5.34 83.85 83.20 0.65 85.01 83.20 1.81 83.70 83.20 0.50 83.23 83.20 0.03 86.41 83.20 3.21
1000 82.71 77.80 4.91 78.28 77.80 0.48 79.36 77.80 1.56 79.34 77.80 1.54 78.89 77.80 1.09 80.52 77.80 2.72
200 68.98 65.60 3.38 65.14 65.60 -0.46 66.15 65.60 0.55 69.08 65.60 3.48 68.68 65.60 3.08 66.62 65.60 1.02
3.99 1.42 1.58 5.01 4.75 2.64
100 63.16 60.50 2.66 59.56 60.50 -0.94 60.51 60.50 0.01 64.72 60.50 4.22 64.34 60.50 3.84 60.73 60.50 0.23
50 57.38 55.40 1.98 54.03 55.40 -1.37 54.97 55.40 -0.43 60.40 55.40 5.00 60.05 55.40 4.65 54.87 55.40 -0.53
20 50.22 48.70 1.52 47.18 48.70 -1.52 48.05 48.70 -0.65 55.04 48.70 6.34 54.71 48.70 6.01 47.64 48.70 -1.06
10 44.69 43.50 1.19 41.87 43.50 -1.63 42.69 43.50 -0.81 50.88 43.50 7.38 50.58 43.50 7.08 42.04 43.50 -1.46
5 38.92 38.00 0.92 36.34 38.00 -1.66 37.07 38.00 -0.93 46.56 38.00 8.56 46.27 38.00 8.27 36.21 38.00 -1.79
METODO CONSTANTE COMBINACION METODO Método Cuencas Pequeñas METODO Constant Slope GUMBEL- METODO Concave Base-Slope METODO CONSTANTE COMBINACION
METODO LINEAL COMBINACION GUMBEL-NORMAL-LOG GUMBEL-NORMAL-LOG COMBINACION GUMBEL-NORMAL-LOG NORMAL-LOG COMBINACION GUMBEL-NORMAL-LOG GUMBEL-NORMAL-LOG
Hidrograma Q1996 - Método Hidrograma Q1996 - Método Cuencas Hidrograma Q1996 - Concave Base-
Hidrograma Q1996 - Método lineal Constante Pequeñas Hidrograma Q1996 - Constant Slope Slope Hidrograma Q1996 - Master Depletion
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 70.88 66.10 4.78 85.17 66.10 19.07 90 66 24 89.74 66.10 23.64 93.10 66.10 27.00 67.48 66.10 1.38
2000 61.88 62.10 -0.22 74.61 62.10 12.51 80 62 18 79.97 62.10 17.87 81.60 62.10 19.50 62.57 62.10 0.47
1000 57.99 60.20 -2.21 70.06 60.20 9.86 72 60 12 72.27 60.20 12.07 76.60 60.20 16.40 61.43 60.20 1.23
200 48.93 55.30 -6.37 59.40 55.30 4.10 62 55 6 61.67 55.30 6.37 65.52 55.30 10.22 58.26 55.30 2.96
8.12 8.73 10.97 10.97 13.30 1.57
100 45.03 53.00 -7.97 54.79 53.00 1.79 57 53 4 56.55 53.00 3.55 60.76 53.00 7.76 53.43 53.00 0.43
50 41.09 50.40 -9.31 50.13 50.40 -0.27 53 50 2 52.61 50.40 2.21 56.17 50.40 5.77 51.11 50.40 0.71
20 35.85 46.60 -10.75 43.91 46.60 -2.69 46 47 0 46.41 46.60 -0.19 50.11 46.60 3.51 48.74 46.60 2.14
10 31.80 43.10 -11.30 39.08 43.10 -4.02 42 43 -1 42.41 43.10 -0.69 44.96 43.10 1.86 42.95 43.10 -0.15
5 27.56 39.00 -11.44 33.98 39.00 -5.02 38 39 -1 38.21 39.00 -0.79 39.79 39.00 0.79 36.92 39.00 -2.08
Hidrograma Q1998 - Método Hidrograma Q1998 - Método Cuencas Hidrograma Q1998 - Constant Slope Hidrograma Q1998 - Concave Base-
Hidrograma Q1998 - Método lineal Constante Pequeñas GUMBEL-LOGPEARSON-WEIBULL Slope Hidrograma Q1998 - Master Depletion
122
MICA 2012 –I-1
______________________________________________________________________
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 77.11 66.10 11.01 73.40 66.10 7.30 74.16 66.10 8.06 75.40 66.10 9.30 76.43 66.10 10.33 70.82 66.10 4.72
2000 67.86 62.10 5.76 64.60 62.10 2.50 65.09 62.10 2.99 67.66 62.10 5.56 68.62 62.10 6.52 62.85 62.10 0.75
1000 63.87 60.20 3.67 60.81 60.20 0.61 61.14 60.20 0.94 64.32 60.20 4.12 65.25 60.20 5.05 59.43 60.20 -0.77
200 54.48 55.30 -0.82 51.88 55.30 -3.42 51.96 55.30 -3.34 56.51 55.30 1.21 57.34 55.30 2.04 57.63 55.30 2.33
5.99 6.20 6.47 3.97 4.49 1.98
100 50.39 53.00 -2.61 47.99 53.00 -5.01 47.95 53.00 -5.05 53.13 53.00 0.13 53.91 53.00 0.91 53.56 53.00 0.56
50 46.27 50.40 -4.13 44.05 50.40 -6.35 43.94 50.40 -6.46 49.71 50.40 -0.69 50.44 50.40 0.04 49.44 50.40 -0.96
20 40.74 46.60 -5.86 38.78 46.60 -7.82 38.56 46.60 -8.04 45.16 46.60 -1.44 45.81 46.60 -0.79 48.73 46.60 2.13
10 36.41 43.10 -6.69 34.65 43.10 -8.45 34.36 43.10 -8.74 41.61 43.10 -1.49 42.20 43.10 -0.90 43.80 43.10 0.70
5 31.81 39.00 -7.19 30.25 39.00 -8.75 29.90 39.00 -9.10 37.89 39.00 -1.11 38.37 39.00 -0.63 38.45 39.00 -0.55
Hidrograma Q PROMEDIO - Constant
Hidrograma Q PROMEDIO - Método Hidrograma Q PROMEDIO - Método Slope GUMBEL-LOGPEARSON- Hidrograma Q PROMEDIO - Concave Hidrograma Q PROMEDIO - Master
Hidrograma Q PROMEDIO - Método lineal Constante Pequeñas WEIBULL Base-Slope Depletion
Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen Volumen
Período simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error simulado registrado Error
de retorno (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC (hm3) (hm3) medio EMC
10000 78.82 66.10 12.72 77.78 66.10 11.68 85.38 66.10 19.28 80.46 66.10 14.36 82.23 66.10 16.13 67.06 66.10 0.96
2000 69.36 62.10 7.26 68.18 62.10 6.08 74.77 62.10 12.67 71.70 62.10 9.60 73.22 62.10 11.12 63.44 62.10 1.34
1000 65.28 60.20 5.08 64.04 60.20 3.84 70.14 60.20 9.94 67.91 60.20 7.71 69.33 60.20 9.13 66.04 60.20 5.84
200 55.67 55.30 0.37 54.34 55.30 -0.96 59.43 55.30 4.13 59.09 55.30 3.79 60.25 55.30 4.95 55.65 55.30 0.35
6.27 6.44 8.47 6.50 7.51 2.35
100 51.49 53.00 -1.51 50.13 53.00 -2.87 54.76 53.00 1.76 55.29 53.00 2.29 56.32 53.00 3.32 53.72 53.00 0.72
50 47.28 50.40 -3.12 45.89 50.40 -4.51 50.10 50.40 -0.30 51.45 50.40 1.05 52.36 50.40 1.96 48.96 50.40 -1.44
20 41.63 46.60 -4.97 40.22 46.60 -6.38 43.85 46.60 -2.75 46.35 46.60 -0.25 47.08 46.60 0.48 44.66 46.60 -1.94
10 37.21 43.10 -5.89 35.81 43.10 -7.29 39.00 43.10 -4.10 42.39 43.10 -0.71 42.98 43.10 -0.12 41.29 43.10 -1.81
5 32.52 39.00 -6.48 31.16 39.00 -7.84 33.86 39.00 -5.14 38.26 39.00 -0.74 38.68 39.00 -0.32 37.18 39.00 -1.82
123
MICA 2012 –I-1
______________________________________________________________________
Se realizaron modelaciones con las combinaciones para los ajustes estadísticos, arrojando
los resultados en la tabla anterior, podemos observar que al utilizar los métodos de separación
visto con la combinación para Caudales máximo con (Gumbel), Mes más Humedo (Gumbel)
y Volumen máximo en un dia (Gumbel), Observamos muy buenos resultados para la
generación de Volumenes máximo diario con las creciente de 1996, 1998 y la combinada, el
parámetro más sensible para este tipo de combinación es Tp, duración de la creciente (h),
Caudal de escorrentía Qe, para la utilización del método lineal el valor a calibrar fue la
pendiente de la línea del flujo base y la duración de la creciente, para el método constante la
variable sensible y a calibrar es el tiempo al pico, para el método de cuencas pequeñas, la
variable a calibrar y sensible es Tp, para el método Constant slope y base slope las variables
sensibles son . Discharge at Maximun flow rate (qr), Time at star of direct runoff (ts), Time at
inflection point (tr) y Tiempo al pico. Para el método Master Depletion las variables a calibrar
fueron: Tiempo al pico, Caudal inicial, Constante de graficacion K.
Debido a la complejidad de los métodos base slope y constant slope que dependen de
muchas variables que están explicitas en el marco teórico, estas representan condiciones
generalizadas de las cuencas, las cuales hacen una representación matemática y física más
exacta de las características de las cuencas, por consiguiente existen diferencias entre estos
métodos, ya que con el método constante solo es necesario calibrar una sola variable, pero con
los métodos siguientes es necesario realizar calibración y optimización más variables, por tal
motivo se observa la diferencia existente entre los métodos pero en términos generales estos
métodos arrojan resultados muy parecidos entre sí, y con muy poca varianza entre los
resultados.
Los resultados obtenidos con la combinación Weibull, Normal, Weibull, son diferentes a
los resultados obtenidos con los métodos donde se utilizaron las combinaciones de Gumbel y
Logpearson. Los resultados obtenidos en los volúmenes registrados y simulados son muy bajos
al compáralos con los resultados utilizando las combinaciones de Gumbel y Logpearson, pero
al calcular el EMC entre estos volúmenes se observa que hay significancia entre los volúmenes
por tanto el EMC es muy bajo. Y este comportamiento se debe a la sensibilidad de las variables
de Tiempo al pico y Caudal inicial, las cuales están dentro del rango optimizable.
124
MICA 2012 –I-1
______________________________________________________________________
125
MICA 2012 –I-1
______________________________________________________________________
El método lineal y de cuencas pequeñas presentan los mejores resultados en cuanto al EMC,
Pero en síntesis, los métodos utilizado en esta investigación han dado resultados muy positivos
al utilizar el EMC, ya que no superan el 10% de desviación con respecto a los datos medidos y
proyectados.
Estos métodos tuvieron mejor resultados con los ajustes estadísticos realizados por Gumbel
y Logpearson, con las combinaciones entre estos ajustes estadísticos se obtuvo los mejores
resultados para el EMC, tal cual como se refleja en el resumen de la tabla 30.
126
MICA 2012 –I-1
______________________________________________________________________
1998 818.00 m3/s 818.80 m3/s -0.80 m3/s 11.00 h 10.00 h 1.00 h
Combinación 808.20 m3/s 818.80 m3/s -10.60 m3/s 11.50 h 10.00 h 1.50 h
1996 808.10 m3/s 818.80 m3/s -10.70 m3/s 7.00 h 10.00 h -3.00 h
G-N-W 1998 818.00 m3/s 818.80 m3/s -0.80 m3/s 9.00 h 10.00 h -1.00 h
Combinación 808.20 m3/s 818.80 m3/s -10.60 m3/s 8.00 h 10.00 h -2.00 h
1996 818.00 m3/s 818.80 m3/s -0.80 m3/s 9.00 h 10.00 h -1.00 h
G-G-G 1998 814.00 m3/s 818.80 m3/s -4.80 m3/s 10.00 h 10.00 h 0.00 h
Combinación 811.00 m3/s 818.80 m3/s -7.80 m3/s 9.50 h 10.00 h -0.50 h
1996 802.00 m3/s 818.80 m3/s -16.80 m3/s 9.50 h 10.00 h -0.50 h
G-L-W 1998 811.00 m3/s 818.80 m3/s -7.80 m3/s 10.00 h 10.00 h 0.00 h
Combinación 790.00 m3/s 818.80 m3/s -28.80 m3/s 10.00 h 10.00 h 0.00 h
1996 812.00 m3/s 818.80 m3/s -6.80 m3/s 9.00 h 10.00 h -1.00 h
G-L-W 1998 818.10 m3/s 818.80 m3/s -0.70 m3/s 10.00 h 10.00 h 0.00 h
Combinación 811.30 m3/s 818.80 m3/s -7.50 m3/s 10.50 h 10.00 h 0.50 h
1996 808.12 m3/s 818.80 m3/s -10.68 m3/s 9.50 h 10.00 h -0.50 h
CONSTANTE L-L-GEV. 1998 812.00 m3/s 818.80 m3/s -6.80 m3/s 10.50 h 10.00 h 0.50 h
Combinación 816.00 m3/s 818.80 m3/s -2.80 m3/s 11.00 h 10.00 h 1.00 h
1996 808.12 m3/s 818.80 m3/s -10.68 m3/s 9.00 h 10.00 h -1.00 h
G-L-GEV. 1998 812.00 m3/s 818.80 m3/s -6.80 m3/s 11.00 h 10.00 h 1.00 h
Combinación 808.20 m3/s 818.80 m3/s -10.60 m3/s 9.50 h 10.00 h -0.50 h
1996 809.12 m3/s 818.80 m3/s -9.68 m3/s 10.50 h 10.00 h 0.50 h
L-L-L. 1998 818.00 m3/s 818.80 m3/s -0.80 m3/s 10.00 h 10.00 h 0.00 h
Combinación 818.00 m3/s 818.80 m3/s -0.80 m3/s 9.00 h 10.00 h -1.00 h
1996 803.00 m3/s 818.80 m3/s -15.80 m3/s 8.00 h 10.00 h -2.00 h
G-N-W 1998 798.00 m3/s 818.80 m3/s -20.80 m3/s 9.00 h 10.00 h -1.00 h
Combinación 803.00 m3/s 818.80 m3/s -15.80 m3/s 7.50 h 10.00 h -2.50 h
1996 815.00 m3/s 818.80 m3/s -3.80 m3/s 10.00 h 10.00 h 0.00 h
G-G-G 1998 816.00 m3/s 818.80 m3/s -2.80 m3/s 10.00 h 10.00 h 0.00 h
Combinación 818.80 m3/s 818.80 m3/s 0.00 m3/s 10.00 h 10.00 h 0.00 h
1996 814.99 m3/s 818.80 m3/s -3.81 m3/s 9.00 h 10.00 h -1.00 h
G-L-W 1998 815.84 m3/s 818.80 m3/s -2.96 m3/s 9.50 h 10.00 h -0.50 h
Combinación 816.30 m3/s 818.80 m3/s -2.50 m3/s 10.00 h 10.00 h 0.00 h
1996 817.30 m3/s 818.80 m3/s -1.50 m3/s 9.50 h 10.00 h -0.50 h
CUENCAS G-L-W 1998 818.10 m3/s 818.80 m3/s -0.70 m3/s 12.00 h 10.00 h 2.00 h
PEQUEÑAS
Combinación 811.30 m3/s 818.80 m3/s -7.50 m3/s 12.50 h 10.00 h 2.50 h
1996 808.12 m3/s 818.80 m3/s -10.68 m3/s 10.00 h 10.00 h 0.00 h
L-L-GEV. 1998 803.20 m3/s 818.80 m3/s -15.60 m3/s 9.00 h 10.00 h -1.00 h
Combinación 802.00 m3/s 818.80 m3/s -16.80 m3/s 10.50 h 10.00 h 0.50 h
1996 808.12 m3/s 818.80 m3/s -10.68 m3/s 13.00 h 10.00 h 3.00 h
G-L-GEV. 1998 812.00 m3/s 818.80 m3/s -6.80 m3/s 11.50 h 10.00 h 1.50 h
Combinación 808.20 m3/s 818.80 m3/s -10.60 m3/s 10.00 h 10.00 h 0.00 h
L-L-L. 1996 809.12 m3/s 818.80 m3/s -9.68 m3/s 10.50 h 10.00 h 0.50 h
127
MICA 2012 –I-1
______________________________________________________________________
1998 818.00 m3/s 818.80 m3/s -0.80 m3/s 10.00 h 10.00 h 0.00 h
Combinación 808.20 m3/s 818.80 m3/s -10.60 m3/s 11.50 h 10.00 h 1.50 h
1996 808.10 m3/s 818.80 m3/s -10.70 m3/s 9.00 h 10.00 h -1.00 h
G-N-W 1998 818.00 m3/s 818.80 m3/s -0.80 m3/s 9.50 h 10.00 h -0.50 h
Combinación 808.20 m3/s 818.80 m3/s -10.60 m3/s 9.50 h 10.00 h -0.50 h
1996 809.20 m3/s 818.80 m3/s -9.60 m3/s 10.50 h 10.00 h 0.50 h
G-G-G 1998 810.50 m3/s 818.80 m3/s -8.30 m3/s 13.00 h 10.00 h 3.00 h
Combinación 811.00 m3/s 818.80 m3/s -7.80 m3/s 10.00 h 10.00 h 0.00 h
1996 814.99 m3/s 818.80 m3/s -3.81 m3/s 11.50 h 10.00 h 1.50 h
G-L-W 1998 815.84 m3/s 818.80 m3/s -2.96 m3/s 11.50 h 10.00 h 1.50 h
Combinación 811.50 m3/s 818.80 m3/s -7.30 m3/s 12.00 h 10.00 h 2.00 h
1996 813.00 m3/s 818.80 m3/s -5.80 m3/s 9.00 h 10.00 h -1.00 h
G-L-W 1998 813.00 m3/s 818.80 m3/s -5.80 m3/s 9.00 h 10.00 h -1.00 h
Combinación 811.30 m3/s 818.80 m3/s -7.50 m3/s 11.30 h 10.00 h 1.30 h
1996 808.12 m3/s 818.80 m3/s -10.68 m3/s 9.50 h 10.00 h -0.50 h
CONCAVE L-L-GEV. 1998 803.20 m3/s 818.80 m3/s -15.60 m3/s 10.50 h 10.00 h 0.50 h
Combinación 802.00 m3/s 818.80 m3/s -16.80 m3/s 10.50 h 10.00 h 0.50 h
1996 800.45 m3/s 818.80 m3/s -18.35 m3/s 9.00 h 10.00 h -1.00 h
G-L-GEV. 1998 800.30 m3/s 818.80 m3/s -18.50 m3/s 11.50 h 10.00 h 1.50 h
Combinación 808.20 m3/s 818.80 m3/s -10.60 m3/s 12.00 h 10.00 h 2.00 h
1996 802.00 m3/s 818.80 m3/s -16.80 m3/s 11.50 h 10.00 h 1.50 h
L-L-L. 1998 812.00 m3/s 818.80 m3/s -6.80 m3/s 11.00 h 10.00 h 1.00 h
Combinación 816.00 m3/s 818.80 m3/s -2.80 m3/s 11.50 h 10.00 h 1.50 h
1996 808.10 m3/s 818.80 m3/s -10.70 m3/s 10.00 h 10.00 h 0.00 h
G-N-W 1998 818.00 m3/s 818.80 m3/s -0.80 m3/s 10.50 h 10.00 h 0.50 h
Combinación 808.20 m3/s 818.80 m3/s -10.60 m3/s 9.50 h 10.00 h -0.50 h
1996 818.80 m3/s 818.80 m3/s 0.00 m3/s 10.50 h 10.00 h 0.50 h
G-G-G 1998 818.80 m3/s 818.80 m3/s 0.00 m3/s 13.00 h 10.00 h 3.00 h
Combinación 818.80 m3/s 818.80 m3/s 0.00 m3/s 10.00 h 10.00 h 0.00 h
1996 814.99 m3/s 818.80 m3/s -3.81 m3/s 11.50 h 10.00 h 1.50 h
G-L-W 1998 815.84 m3/s 818.80 m3/s -2.96 m3/s 11.50 h 10.00 h 1.50 h
Combinación 813.00 m3/s 818.80 m3/s -5.80 m3/s 12.00 h 10.00 h 2.00 h
1996 805.34 m3/s 818.80 m3/s -13.46 m3/s 12.00 h 10.00 h 2.00 h
CON. BASE G-L-W 1998 808.00 m3/s 818.80 m3/s -10.80 m3/s 12.50 h 10.00 h 2.50 h
SLOPE
Combinación 808.00 m3/s 818.80 m3/s -10.80 m3/s 12.50 h 10.00 h 2.50 h
1996 796.00 m3/s 818.80 m3/s -22.80 m3/s 11.50 h 10.00 h 1.50 h
L-L-GEV. 1998 818.00 m3/s 818.80 m3/s -0.80 m3/s 11.00 h 10.00 h 1.00 h
Combinación 812.00 m3/s 818.80 m3/s -6.80 m3/s 9.50 h 10.00 h -0.50 h
1996 808.12 m3/s 818.80 m3/s -10.68 m3/s 9.50 h 10.00 h -0.50 h
G-L-GEV. 1998 813.00 m3/s 818.80 m3/s -5.80 m3/s 10.00 h 10.00 h 0.00 h
Combinación 810.00 m3/s 818.80 m3/s -8.80 m3/s 9.50 h 10.00 h -0.50 h
L-L-L. 1996 816.00 m3/s 818.80 m3/s -2.80 m3/s 11.00 h 10.00 h 1.00 h
128
MICA 2012 –I-1
______________________________________________________________________
1998 803.00 m3/s 818.80 m3/s -15.80 m3/s 11.00 h 10.00 h 1.00 h
Combinación 805.00 m3/s 818.80 m3/s -13.80 m3/s 11.50 h 10.00 h 1.50 h
1996 808.10 m3/s 818.80 m3/s -10.70 m3/s 9.00 h 10.00 h -1.00 h
G-N-W 1998 818.00 m3/s 818.80 m3/s -0.80 m3/s 9.50 h 10.00 h -0.50 h
Combinación 812.00 m3/s 818.80 m3/s -6.80 m3/s 12.00 h 10.00 h 2.00 h
1996 816.00 m3/s 818.80 m3/s -2.80 m3/s 11.40 h 10.00 h 1.40 h
G-G-G 1998 813.00 m3/s 818.80 m3/s -5.80 m3/s 12.50 h 10.00 h 2.50 h
Combinación 811.00 m3/s 818.80 m3/s -7.80 m3/s 10.00 h 10.00 h 0.00 h
1996 814.99 m3/s 818.80 m3/s -3.81 m3/s 12.00 h 10.00 h 2.00 h
G-L-W 1998 815.84 m3/s 818.80 m3/s -2.96 m3/s 11.00 h 10.00 h 1.00 h
Combinación 820.00 m3/s 818.80 m3/s 1.20 m3/s 10.50 h 10.00 h 0.50 h
1996 802.00 m3/s 818.80 m3/s -16.80 m3/s 9.50 h 10.00 h -0.50 h
G-L-W 1998 805.00 m3/s 818.80 m3/s -13.80 m3/s 9.00 h 10.00 h -1.00 h
Combinación 797.00 m3/s 818.80 m3/s -21.80 m3/s 11.30 h 10.00 h 1.30 h
1996 814.00 m3/s 818.80 m3/s -4.80 m3/s 11.50 h 10.00 h 1.50 h
MASTER
L-L-GEV. 1998 803.20 m3/s 818.80 m3/s -15.60 m3/s 13.00 h 10.00 h 3.00 h
DEPELTION
Combinación 802.00 m3/s 818.80 m3/s -16.80 m3/s 13.00 h 10.00 h 3.00 h
1996 808.00 m3/s 818.80 m3/s -10.80 m3/s 12.00 h 10.00 h 2.00 h
G-L-GEV. 1998 819.00 m3/s 818.80 m3/s 0.20 m3/s 13.00 h 10.00 h 3.00 h
Combinación 818.00 m3/s 818.80 m3/s -0.80 m3/s 11.00 h 10.00 h 1.00 h
1996 798.00 m3/s 818.80 m3/s -20.80 m3/s 11.00 h 10.00 h 1.00 h
L-L-L. 1998 802.34 m3/s 818.80 m3/s -16.46 m3/s 11.00 h 10.00 h 1.00 h
Combinación 805.00 m3/s 818.80 m3/s -13.80 m3/s 11.50 h 10.00 h 1.50 h
1996 802.00 m3/s 818.80 m3/s -16.80 m3/s 7.00 h 10.00 h -3.00 h
G-N-W 1998 805.00 m3/s 818.80 m3/s -13.80 m3/s 9.00 h 10.00 h -1.00 h
Combinación 815.00 m3/s 818.80 m3/s -3.80 m3/s 8.00 h 10.00 h -2.00 h
De la anterior tabla observamos que los datos varían al orden del 2.5%, lo cual es un valor
aceptable para la hipótesis, tiene un nivel de confianza del 95%. Por tanto la validación de los
datos arroja resultados positivos y se comprueba la validez de estos métodos de separación de
flujo base.
Por tanto la utilización de estos hidrogramas que resultaron de estos métodos son confiable
para desarrollar proyectos hidráulicos tales como presas, obras de captación puentes, canales
de riego, es importante contar con métodos suficientes que para el cálculo de hidrograma.
129
MICA 2012 –I-1
______________________________________________________________________
1- Se lograron adicionar nuevas ecuaciones de flujo base (separación de flujo base para
cuencas pequeñas y alta vegetación, método de concave baseflow separation,
método constant-slope baseflow separation, master depletion), al método
desarrollado por Coronado-Triana, 2012. Con cada una de estas ecuaciones se
establecieron los respectivos algoritmos para determinar los hidrogramas de crecientes
asociados a los diferentes periodos de retorno.
3- los mejores resultados con ajuste de EMC fueron: - el método lineal utilizando la
combinación Gumbel, Gumbel, Gumbel, para ajustar los datos de caudal máximo
instantáneo, Volumen máximo en un día y series de Caudales medios mes más húmedo,
con un EMC=0.13 HM3, con la creciente promediada de 1996 y 1998, - método
Constante utilizando la combinación Gumbel, Gumbel, Gumbel, para ajustar los datos
de caudal máximo instantáneo, Volumen máximo en un día y series de Caudales medios
mes más húmedo, con un EMC=0.22 HM3, con creciente de mayo 1998,- método
Cuencas Pequeñas utilizando la combinación Gumbel, Logpearson, Weibull con un
EMC=0.58 HM3, con la creciente promediada de 1996 y 1998, - método Master
Depletion utilizando la combinación Weibull, Normal, Weibull con un EMC=0.35
HM3, con la creciente promediada de 1996 y 1998, - Método Lineal utilizando la
combinación Gumbel, Logpearson, Gev, con un EMC=0.35 HM3, con la creciente de
Mayo de 1998 y la promediada de 1996 y 1998. En la tabla 72 (métodos con mejores
EMC), están los métodos con resultados inferiores 2.38 HM3.
Al igual se informa los métodos con peores resultados que superan los 5.00 HM3, -
método Cuencas Pequeñas con la combinación de ajustes estadísticos Gumbel, Normal,
130
MICA 2012 –I-1
______________________________________________________________________
4- Las mejores validaciones con la creciente de 1997 se obtuvieron: - método Lineal con
la combinación Gumbel, Gumbel, Gumbel, con una variación no mas del 2.0%, método
Constante con la combinación Gumbel, Logpearson, Weibull, con una variación del
1.5% y un desviación del tiempo al pico de 0.5h, %, %, método Constante con la
combinación Gumbel, Logpearson, Weibull, con una variación del 1.5% y un
desviación del tiempo al pico de 0.5h, %, método Cuencas Pequeñas con la
combinación Gumbel, Gumbel, Gumbel, con una variación del 0.5% y un desviación
del tiempo al pico de 0.0h, método Master Depletion con la combinación Gumbel,
Logpearson, Weibull, con una variación del 0.5% y un desviación del tiempo al pico de
1.4h.
131
MICA 2012 –I-1
______________________________________________________________________
132
MICA 2012 –I-1
______________________________________________________________________
7.0 REFERENCIAS
Chaire en Hydrologie Statistique (CHS). Hyfran. (2002). Logiciel pour l’analyse fre´quentielle
en hydrologie. INRS-Eau, rapport tech-nique. Water Resources Publications.
Chow, V. T., Maidment, D., & Mays, L. (1994). Hidrología aplicada. Bogotá: Mc Graw Hill.
CNEGP. (1997). Guías técnicas de seguridad de presas - 4 . Avenida de proyecto. Madrid.
Domínguez, M., Fuentes, O., & Franco, V. (1980). Manual de diseño de obras civiles.
Comisión Federal de Electricidad. México.
Ingetec S.A. (2008). Informe de crecientes para diseño de la presa y obras anexas. Documento
No. PHEQDPLA- DOC-0005. Bogotá.
Ingetec S.A, Simco Ltda y Cimilec Ingenieros Ltda. (1997). Estudio de factibilidad para el
desarrollo hidroeléctrico El Quimbo en el alto Magdalena. Estudio de Factibilidad. Bogotá.
Rivera, F., & Escalante, C. (1999). Análisis comparativo de técnicas de estimación de avenidas
de diseño. Ingeniería del agua Vol. 6 Núm. 1, 49-54.
133
MICA 2012 –I-1
______________________________________________________________________
Vázquez C. Ma. T., Jiménez E. M., Domínguez M. R., Fuentes M. O., “Avenidas de diseño
para presas de gran capacidad”. Cuadernos de Investigación N° 28. CENAPRED. México,
1996.
S. Gómez* Nueva técnica de separación de flujo base aplicada a la cuenca superior del
río Lebrija Escuela de Ing. Civil, GPH, Universidad Industrial de Santander, Colombia
RAYNAL J. A.., 1985. Bivariate extreme value distributions applied to flood frequency
analysis Ph.D. dissertation, Civil Engineering Department, Colorado State University, USA,
273 pp.
S. Gómez* Nueva técnica de separación de flujo base aplicada a la cuenca superior del
río Lebrija Escuela de Ing. Civil, GPH, Universidad Industrial de Santander, Colombia.
134
MICA 2012 –I-1
______________________________________________________________________
ANEXOS
135
MICA 2012 –I-1
______________________________________________________________________
136
MICA 2012 –I-1
______________________________________________________________________
137
MICA 2012 –I-1
______________________________________________________________________
Figura 88 Validación del método con la creciente de 1997Metodo Constant Slope Combinación
Weibulll-Normal-Weibull. ................................................................................................................... 196
Figura 89 Validación del método con la creciente de 1997Metodo Constant Slope Combinación
Logpearson-Logpearson-Gev. ............................................................................................................ 197
Figura 90 Validación del método con la creciente de 1997 Metodo Constant Slope Combinación
Gumbel-Logpearson-Gev .................................................................................................................... 197
Figura 91 Validación del método con la creciente de 1997 Metodo Constant Slope Combinación
Logpearson-Logpearson-Logpearson................................................................................................. 198
Figura 92 Validación del método con la creciente de 1997 Metodo Constant Slope Combinación
Gumbel-Normal-Weibull..................................................................................................................... 198
Figura 93 Envolventes Constant Slope Combinación Gumbel-Logpearson-Weibull. ........................ 199
Figura 94 Envolventes Método Constant Slope Combinación Weibull-Normal-Weibull................... 199
Figura 95 Envolventes Método Constant Slope Combinación Logpearson-Logpearson-Gev ........... 200
Figura 96 Envolventes Método Constant Slope Combinación Gumbel-Logpearson-Gumbel ........... 200
Figura 97 Envolventes Método Constant Slope Combinación Logpearson-Logpearson-Logpearson
............................................................................................................................................................ 201
Figura 98 Envolventes Método Constant Slope Combinación Gumbel-Normal-Weibull. ................. 201
Figura 99 Generación de crecientes método Concave Base Slope, combinación Gumbel-Logpearson-
Weibull ................................................................................................................................................ 209
Figura 100 Generación de crecientes método Concave Base Slope, combinación Weibull-Normal-
Weibull ................................................................................................................................................ 209
Figura 101 Generación de crecientes método Concave Base Slope, combinación Logpearson-
Lorpearson-Gev. ................................................................................................................................. 210
Figura 102 Generación de crecientes método Concave Base Slope, combinación Gumbel-Logpearson-
Gev.. .................................................................................................................................................... 210
Figura 103 Generación de crecientes método Concave Base Slope, combinación Logpearson -
Logpearson- Logpearson. ................................................................................................................... 211
Figura 104 Generación de crecientes método Concave Base Slope, combinación Gumbel-Normal-
Weibull ................................................................................................................................................ 211
Figura 105 Validación del método con la creciente de 1997Metodo Concave Base Slope Combinación
Gumbel-Logpearson-Weibull. ............................................................................................................. 212
Figura 106 Validación del método con la creciente de 1997Metodo Concave Base Slope Combinación
Weibulll-Normal-Weibull. ................................................................................................................... 212
Figura 107 Validación del método con la creciente de 1997Metodo Concave Base Slope Combinación
Logpearson-Logpearson-Gev. ............................................................................................................ 213
Figura 108 Validación del método con la creciente de 1997 Metodo Concave Base Slope Combinación
Gumbel-Logpearson-Gev .................................................................................................................... 213
Figura 109 Validación del método con la creciente de 1997 Metodo Concave Base Slope Combinación
Logpearson-Logpearson-Logpearson................................................................................................. 214
Figura 110 Validación del método con la creciente de 1997 Metodo Concave Base Slope Combinación
Gumbel-Normal-Weibull..................................................................................................................... 214
Figura 111 Envolventes Concave Base Slope Combinación Gumbel-Logpearson-Weibull. ............. 215
Figura 112 Envolventes Método Concave Base Slope Combinación Weibull-Normal-Weibull. ....... 215
Figura 113 Envolventes Método Concave Base Slope Combinación Logpearson-Logpearson-Gev . 216
Figura 114 Envolventes Método Concave Base Slope Combinación Gumbel-Logpearson-Gumbel . 216
138
MICA 2012 –I-1
______________________________________________________________________
139
MICA 2012 –I-1
______________________________________________________________________
Tabla 32 Separación de flujo base método cuencas pequeñas creciente julio de 1997 ..................... 136
Tabla 33 Separación de flujo base método Concave Baseflow creciente julio de 1997 ..................... 142
Tabla 34 Separación de flujo base método Constant slope creciente julio de 1997 .......................... 143
Tabla 35 Separación de flujo base método Master depletion creciente julio de 1997 ....................... 143
Tabla 36 Separación de flujo base método cuencas pequeñas creciente mayo de 1998 .................... 144
Tabla 37 Separación de flujo base método Concave Baseflow creciente mayo de 1998 ................... 144
Tabla 38 Separación de flujo base método Constant slope creciente mayo de 1998 ......................... 145
Tabla 39 Separación de flujo base método Master depletion creciente mayo de 1998 ...................... 145
Tabla 40 Calculo del EMC método flujo base Línea recta Combinación Weibull-Normal-Weibull.. 146
Tabla 41 Calculo del EMC método flujo base Línea recta Combinación Log-Log-Gev .................... 147
Tabla 42 Calculo del EMC método flujo base Línea recta Combinación Gumbel-Log-pearson-Gev148
Tabla 43 Calculo del EMC método flujo base Línea recta Combinación Log-pearson-Logpearson-
Logpearson ......................................................................................................................................... 149
Tabla 44 Calculo del EMC método flujo base Constante Combinación Gumbel-Log-pearson-Weibull
............................................................................................................................................................ 157
Tabla 45 Calculo del EMC método flujo base Constante Combinación Weibull-Normal-Weibull .... 158
Tabla 46 Calculo del EMC método flujo base Constante Combinación Log-Log-Gev ...................... 159
Tabla 47 Calculo del EMC método flujo base Constante Combinación Gumbel-Log-pearson-Gev. 160
Tabla 48 Calculo del EMC método flujo base Constante Combinación Log-pearson-Logpearson-
Logpearson ......................................................................................................................................... 161
Tabla 49 Calculo del EMC método flujo base Constante Combinación Gumbel-Normal-Logpearson
............................................................................................................................................................ 162
Tabla 50 Calculo del EMC método flujo base Cuencas pequeñas Combinación Gumbel-Log-pearson-
Weibull ................................................................................................................................................ 172
Tabla 51 Calculo del EMC método flujo base Cuencas pequeñas Combinación Weibull-Normal-
Weibull ................................................................................................................................................ 173
Tabla 52 Calculo del EMC método flujo base Cuencas pequeñas Combinación Log-Log-Gev ........ 174
Tabla 53 Calculo del EMC método flujo base Cuencas pequeñas Combinación Gumbel-Log-pearson-
Gev. ..................................................................................................................................................... 175
Tabla 54 Calculo del EMC método flujo base Cuencas pequeñas Combinación Log-pearson-
Logpearson-Logpearson. .................................................................................................................... 176
Tabla 55 Calculo del EMC método flujo base Cuencas pequeñas Combinación Gumbel-Normal-
Logpearson. ........................................................................................................................................ 177
Tabla 56 Calculo del EMC método flujo base Constant Slope Combinación Gumbel-Log-pearson-
Weibull ................................................................................................................................................ 187
Tabla 57 Calculo del EMC método flujo base Constant Slope Combinación Weibull-Normal-Weibull
............................................................................................................................................................ 188
Tabla 58 Calculo del EMC método flujo base Constant Slope Combinación Log-Log-Gev .............. 189
Tabla 59 Calculo del EMC método flujo base Constant Slope Combinación Gumbel-Log-pearson-Gev.
............................................................................................................................................................ 190
Tabla 60 Calculo del EMC método flujo base Constant Slope Combinación Log-pearson-Logpearson-
Logpearson ......................................................................................................................................... 191
140
MICA 2012 –I-1
______________________________________________________________________
Tabla 61 Calculo del EMC método flujo base Constant Slope Combinación Gumbel-Normal-
Logpearson ......................................................................................................................................... 192
Tabla 62 Calculo del EMC método flujo base Concave Base Slope Combinación Gumbel-Log-pearson-
Weibull ................................................................................................................................................ 202
Tabla 63 Calculo del EMC método flujo base Concave Base Slope Combinación Weibull-Normal-
Weibull ................................................................................................................................................ 203
Tabla 64 Calculo del EMC método flujo base Concave Base Slope Combinación Log-Log-Gev ..... 204
Tabla 65 Calculo del EMC método flujo base Concave Base Slope Combinación Gumbel-Log-pearson-
Gev. ..................................................................................................................................................... 205
Tabla 66 Calculo del EMC método flujo base Concave Base Slope Combinación Log-pearson-
Logpearson-Logpearson ..................................................................................................................... 206
Tabla 67 Calculo del EMC método flujo base Concave Base Slope Combinación Gumbel-Normal-
Logpearson ......................................................................................................................................... 207
Tabla 68 Calculo del EMC método flujo base Master Depletion Combinación Gumbel-Log-pearson-
Weibull ................................................................................................................................................ 217
Tabla 69 Calculo del EMC método flujo base Master Depletion Combinación Weibull-Normal-Weibull
............................................................................................................................................................ 218
Tabla 70 Calculo del EMC método flujo base Master Depletion Combinación Log-Log-Gev .......... 219
Tabla 71 Calculo del EMC método flujo base Master Depletion Combinación Gumbel-Log-pearson-
Gev. ..................................................................................................................................................... 220
Tabla 72 Calculo del EMC método flujo base Master Depletion Combinación Log-pearson-
Logpearson-Logpearson ..................................................................................................................... 221
Tabla 73 Calculo del EMC método flujo base Master Depletion Combinación Gumbel-Normal-
Logpearson ......................................................................................................................................... 222
141
MICA 2012 –I-1
______________________________________________________________________
Tabla 32 Separación de flujo base método cuencas pequeñas creciente julio de 1997
Caudal
(m3/s) 900
Delta
Tiempo Metodo Cuencas
tiempo t/tp
(h) pequeñas 800
(h)
Q/QE
Total Base Escorrentía max
700
0.0 172.1 172.1 0.0 0.00 0.00
2 2.0 184.7 176.1 8.6 0.22 0.01 600
Caudal (m3/s)
1 3.0 211.4 178.1 33.3 0.33 0.05
2 5.0 391.4 182.0 209.3 0.56 0.33
500
142
MICA 2012 –I-1
______________________________________________________________________
Tabla 34 Separación de flujo base método Constant slope creciente julio de 1997
Caudal
(m3/s) 900
Delta
Tiempo Metodo Constant Q/QE
tiempo t/tp
(h) slope max 800
(h)
Total Base Escorrentía
700
0.0 172.1 172.1 0.0 0.00 0.00
2 2.0 184.7 184.7 0.0 0.22 0.00 600
Caudal (m3/s)
1 3.0 211.4 211.4 0.0 0.33 0.00
500
2 5.0 391.4 180.5 210.8 0.56 0.33
143
MICA 2012 –I-1
______________________________________________________________________
Tabla 36 Separación de flujo base método cuencas pequeñas creciente mayo de 1998
Caudal 1200
(m3/s)
Delta
Tiempo
tiempo Metodo Cuencas t/tp Q/QE max
(h)
(h) pequeñas
1000
Total Base Escorrentía
Caudal (m3/s)
1 2 237.5 127.3 110.2 0.40 0.13
1 3 470.1 129.3 340.8 0.60 0.39 600
2 5 1012.0 133.3 878.7 1.00 1.00
1 6 999.8 135.2 864.6 1.20 0.98
400
2 8 665.1 139.2 525.9 1.60 0.60
2 10 438.3 143.2 295.2 2.00 0.34
1 11 341.3 145.1 196.2 2.20 0.22 200
3 14 278.7 151.1 127.6 2.80 0.15
3 17 232.7 157.0 75.6 3.40 0.09
0
5 22 237.5 166.9 70.6 4.40 0.08
0 10 20 30 40
1 23 186.9 186.9 0.0 4.60 0.00 Tiempo (horas)
6 29 166.1 166.1 0.0 5.80 0.00
Tabla 37 Separación de flujo base método Concave Baseflow creciente mayo de 1998
Caudal
(m3/s) 1200
Delta
Tiempo Metodo Concave
tiempo t/tp
(h) Baseflow
(h)
1000
Total Base Escorrentía Q/QE max
0 123.4 123.4 0.0 0.00 0.00
1 1 152.3 152.3 0.0 0.20 0.00 800
Caudal (m3/s)
144
MICA 2012 –I-1
______________________________________________________________________
Tabla 38 Separación de flujo base método Constant slope creciente mayo de 1998
Caudal 1200
(m3/s)
Delta
Tiempo
tiempo Metodo Constant t/tp Q/QE max
(h)
(h) slope 1000
Total Base Escorrentía
Caudal (m3/s)
1 2 237.5 181.5 56.1 0.40 0.07
1 3 470.1 191.2 278.9 0.60 0.35 600
2 5 1012.0 210.6 801.4 1.00 1.00
1 6 999.8 220.3 779.5 1.20 0.97
400
2 8 665.1 239.8 425.3 1.60 0.53
2 10 438.3 259.2 179.1 2.00 0.22
1 11 341.3 268.9 72.4 2.20 0.09 200
3 14 278.7 278.7 0.0 2.80 0.00
3 17 232.7 232.7 0.0 3.40 0.00
0
5 22 237.5 237.5 0.0 4.40 0.00 0 10 20 30 40
1 23 186.9 186.9 0.0 4.60 0.00 Tiempo (horas)
6 29 166.1 166.1 0.0 5.80 0.00
Tabla 39 Separación de flujo base método Master depletion creciente mayo de 1998
Caudal 1200
(m3/s)
Delta
Tiempo Metodo Master
tiempo t/tp
(h) depletion
(h)
1000
Total Base Escorrentía Q/QE max
0 123.4 123.4 0.0 0.00 0.00
800
1 1 152.3 122.9 29.4 0.20 0.03
Caudal (m3/s)
145
MICA 2012 –I-1
______________________________________________________________________
Tabla 40 Calculo del EMC método flujo base Línea recta Combinación Weibull-Normal-
Weibull
146
MICA 2012 –I-1
______________________________________________________________________
Tabla 41 Calculo del EMC método flujo base Línea recta Combinación Log-Log-Gev
147
MICA 2012 –I-1
______________________________________________________________________
Tabla 42 Calculo del EMC método flujo base Línea recta Combinación Gumbel-Log-pearson-
Gev
148
MICA 2012 –I-1
______________________________________________________________________
Tabla 43 Calculo del EMC método flujo base Línea recta Combinación Log-pearson-
Logpearson-Logpearson
149
MICA 2012 –I-1
______________________________________________________________________
De la figura 34, se observa que los tiempos al pico varían para cada hidrograma de creciente
generado a diferentes periodos de retornos, con los datos de caudal de 1996, el tiempo al pico
es de 9 horas, con los datos de caudal de 1998, el tiempo al pico es de 12 horas y para la
creciente promedio el tiempo al pico es de 10 horas.
De la figura 35, se observa que los tiempos al pico varían para cada hidrograma de creciente
generado a diferentes periodos de retornos, con los datos de caudal de 1996, el tiempo al pico
150
MICA 2012 –I-1
______________________________________________________________________
es de 9 horas, con los datos de caudal de 1998, el tiempo al pico es de 12 horas y para la
creciente promedio el tiempo al pico es de 10 horas.
En esta Figura se observa que el tiempo al pico para la generación de los hidrogramas es
de 11 horas.
De la figura 37, se observa que los tiempos al pico varían para cada hidrograma de creciente
generado a diferentes periodos de retornos, con los datos de caudal de 1996, el tiempo al pico
151
MICA 2012 –I-1
______________________________________________________________________
es de 7 horas, con los datos de caudal de 1998, el tiempo al pico es de 9 horas y para la creciente
promedio el tiempo al pico es de 8 horas.
Figura 38 Validación del método con la creciente de 1997Metodo lineal Combinacion Logpearson-
Logpearson-Gev.
En la figura 38, se observa que la validación para el año 1998 no se ajusta, pero la de 1996
y la promediada se ajusta.
Figura 39 Validación del método con la creciente de 1997Metodo lineal Combinacion Gumbel-
Logpearson-Gev
152
MICA 2012 –I-1
______________________________________________________________________
Figura 40 Validación del método con la creciente de 1997Metodo lineal Combinacion Logpearson-
Logpearson-Logpearson
Figura 41 Validación del método con la creciente de 1997Metodo lineal Combinacion Gumbel-
Normal-Weibull
153
MICA 2012 –I-1
______________________________________________________________________
Como lo muestran las figuras anteriores, se observa un buen ajuste con todas las
combinaciones de ajuste de los datos, con un periodo de retorno de 11,28 años.
154
MICA 2012 –I-1
______________________________________________________________________
155
MICA 2012 –I-1
______________________________________________________________________
156
MICA 2012 –I-1
______________________________________________________________________
Tabla 44 Calculo del EMC método flujo base Constante Combinación Gumbel-Log-pearson-
Weibull
157
MICA 2012 –I-1
______________________________________________________________________
Tabla 45 Calculo del EMC método flujo base Constante Combinación Weibull-Normal-Weibull
158
MICA 2012 –I-1
______________________________________________________________________
Tabla 46 Calculo del EMC método flujo base Constante Combinación Log-Log-Gev
159
MICA 2012 –I-1
______________________________________________________________________
Tabla 47 Calculo del EMC método flujo base Constante Combinación Gumbel-Log-pearson-
Gev.
160
MICA 2012 –I-1
______________________________________________________________________
Tabla 48 Calculo del EMC método flujo base Constante Combinación Log-pearson-
Logpearson-Logpearson
161
MICA 2012 –I-1
______________________________________________________________________
Tabla 49 Calculo del EMC método flujo base Constante Combinación Gumbel-Normal-
Logpearson
162
MICA 2012 –I-1
______________________________________________________________________
163
MICA 2012 –I-1
______________________________________________________________________
164
MICA 2012 –I-1
______________________________________________________________________
Se observa, en las gráficas la tendencia del tiempo al pico entre (8 y 10) horas.
165
MICA 2012 –I-1
______________________________________________________________________
Figura 52 Validación del método con la creciente de 1997 Metodo Constante Combinacion Gumbel-
Logpearson-Weibull.
Figura 53 Validación del método con la creciente de 1997 Metodo Constante Combinacion Weibulll-
Normal-Weibull.
166
MICA 2012 –I-1
______________________________________________________________________
Figura 54 Validación del método con la creciente de 1997 Metodo Constante Combinación
Logpearson-Logpearson-Gev.
Figura 55 Validación del método con la creciente de 1997 Metodo Constante Combinación Gumbel-
Logpearson-Gev
167
MICA 2012 –I-1
______________________________________________________________________
Figura 56 Validación del método con la creciente de 1997 Metodo constante Combinacion
Logpearson-Logpearson-Logpearson
Figura 57 Validación del método con la creciente de 1997 Metodo Constante Combinacion Gumbel-
Normal-Weibull
168
MICA 2012 –I-1
______________________________________________________________________
169
MICA 2012 –I-1
______________________________________________________________________
170
MICA 2012 –I-1
______________________________________________________________________
171
MICA 2012 –I-1
______________________________________________________________________
Tabla 50 Calculo del EMC método flujo base Cuencas pequeñas Combinación Gumbel-Log-
pearson-Weibull
172
MICA 2012 –I-1
______________________________________________________________________
Tabla 51 Calculo del EMC método flujo base Cuencas pequeñas Combinación Weibull-Normal-
Weibull
173
MICA 2012 –I-1
______________________________________________________________________
Tabla 52 Calculo del EMC método flujo base Cuencas pequeñas Combinación Log-Log-Gev
174
MICA 2012 –I-1
______________________________________________________________________
Tabla 53 Calculo del EMC método flujo base Cuencas pequeñas Combinación Gumbel-Log-
pearson-Gev.
175
MICA 2012 –I-1
______________________________________________________________________
Tabla 54 Calculo del EMC método flujo base Cuencas pequeñas Combinación Log-pearson-
Logpearson-Logpearson.
176
MICA 2012 –I-1
______________________________________________________________________
Tabla 55 Calculo del EMC método flujo base Cuencas pequeñas Combinación Gumbel-Normal-
Logpearson.
177
MICA 2012 –I-1
______________________________________________________________________
178
MICA 2012 –I-1
______________________________________________________________________
179
MICA 2012 –I-1
______________________________________________________________________
180
MICA 2012 –I-1
______________________________________________________________________
Figura 70 Validación del método con la creciente de 1997Metodo cuencas pequeñas Combinación
Weibulll-Normal-Weibull.
Figura 71 Validación del método con la creciente de 1997Metodo cuencas pequeñas Combinación
Logpearson-Logpearson-Gev.
181
MICA 2012 –I-1
______________________________________________________________________
Figura 72 Validación del método con la creciente de 1997Metodo cuencas pequeñas Combinación
Gumbel-Logpearson-Gev
Figura 73 Validación del método con la creciente de 1997Metodo cuencas pequeñas Combinación
Logpearson-Logpearson-Logpearson
182
MICA 2012 –I-1
______________________________________________________________________
Figura 74 Validación del método con la creciente de 1997Metodo cuencas pequeñas Combinación
Gumbel-Normal-Weibull
183
MICA 2012 –I-1
______________________________________________________________________
184
MICA 2012 –I-1
______________________________________________________________________
185
MICA 2012 –I-1
______________________________________________________________________
186
MICA 2012 –I-1
______________________________________________________________________
Tabla 56 Calculo del EMC método flujo base Constant Slope Combinación Gumbel-Log-
pearson-Weibull
187
MICA 2012 –I-1
______________________________________________________________________
Tabla 57 Calculo del EMC método flujo base Constant Slope Combinación Weibull-Normal-
Weibull
188
MICA 2012 –I-1
______________________________________________________________________
Tabla 58 Calculo del EMC método flujo base Constant Slope Combinación Log-Log-Gev
189
MICA 2012 –I-1
______________________________________________________________________
Tabla 59 Calculo del EMC método flujo base Constant Slope Combinación Gumbel-Log-
pearson-Gev.
190
MICA 2012 –I-1
______________________________________________________________________
Tabla 60 Calculo del EMC método flujo base Constant Slope Combinación Log-pearson-
Logpearson-Logpearson
191
MICA 2012 –I-1
______________________________________________________________________
Tabla 61 Calculo del EMC método flujo base Constant Slope Combinación Gumbel-Normal-
Logpearson
192
MICA 2012 –I-1
______________________________________________________________________
193
MICA 2012 –I-1
______________________________________________________________________
194
MICA 2012 –I-1
______________________________________________________________________
195
MICA 2012 –I-1
______________________________________________________________________
Figura 87 Validación del método con la creciente de 1997Metodo Constant Slope Combinación
Gumbel-Logpearson-Weibull.
Figura 88 Validación del método con la creciente de 1997Metodo Constant Slope Combinación
Weibulll-Normal-Weibull.
196
MICA 2012 –I-1
______________________________________________________________________
Figura 89 Validación del método con la creciente de 1997Metodo Constant Slope Combinación
Logpearson-Logpearson-Gev.
Figura 90 Validación del método con la creciente de 1997 Metodo Constant Slope Combinación
Gumbel-Logpearson-Gev
197
MICA 2012 –I-1
______________________________________________________________________
Figura 91 Validación del método con la creciente de 1997 Metodo Constant Slope Combinación
Logpearson-Logpearson-Logpearson
Figura 92 Validación del método con la creciente de 1997 Metodo Constant Slope Combinación
Gumbel-Normal-Weibull
198
MICA 2012 –I-1
______________________________________________________________________
199
MICA 2012 –I-1
______________________________________________________________________
200
MICA 2012 –I-1
______________________________________________________________________
201
MICA 2012 –I-1
______________________________________________________________________
obtenidas para otros períodos de retorno presentan formas similares, por tanto la incertidumbre
es muy baja.
Tabla 62 Calculo del EMC método flujo base Concave Base Slope Combinación Gumbel-
Log-pearson-Weibull
202
MICA 2012 –I-1
______________________________________________________________________
Tabla 63 Calculo del EMC método flujo base Concave Base Slope Combinación Weibull-
Normal-Weibull
203
MICA 2012 –I-1
______________________________________________________________________
Tabla 64 Calculo del EMC método flujo base Concave Base Slope Combinación Log-Log-Gev
204
MICA 2012 –I-1
______________________________________________________________________
Tabla 65 Calculo del EMC método flujo base Concave Base Slope Combinación Gumbel-Log-
pearson-Gev.
205
MICA 2012 –I-1
______________________________________________________________________
Tabla 66 Calculo del EMC método flujo base Concave Base Slope Combinación Log-pearson-
Logpearson-Logpearson
206
MICA 2012 –I-1
______________________________________________________________________
Tabla 67 Calculo del EMC método flujo base Concave Base Slope Combinación Gumbel-
Normal-Logpearson
207
MICA 2012 –I-1
______________________________________________________________________
208
MICA 2012 –I-1
______________________________________________________________________
Figura 100 Generación de crecientes método Concave Base Slope, combinación Weibull-Normal-
Weibull
209
MICA 2012 –I-1
______________________________________________________________________
Figura 101 Generación de crecientes método Concave Base Slope, combinación Logpearson-
Lorpearson-Gev.
Figura 102 Generación de crecientes método Concave Base Slope, combinación Gumbel-
Logpearson-Gev..
210
MICA 2012 –I-1
______________________________________________________________________
Figura 103 Generación de crecientes método Concave Base Slope, combinación Logpearson -
Logpearson- Logpearson.
Figura 104 Generación de crecientes método Concave Base Slope, combinación Gumbel-Normal-
Weibull
211
MICA 2012 –I-1
______________________________________________________________________
Figura 105 Validación del método con la creciente de 1997Metodo Concave Base Slope
Combinación Gumbel-Logpearson-Weibull.
Figura 106 Validación del método con la creciente de 1997Metodo Concave Base Slope
Combinación Weibulll-Normal-Weibull.
212
MICA 2012 –I-1
______________________________________________________________________
Figura 107 Validación del método con la creciente de 1997Metodo Concave Base Slope
Combinación Logpearson-Logpearson-Gev.
Figura 108 Validación del método con la creciente de 1997 Metodo Concave Base Slope
Combinación Gumbel-Logpearson-Gev
213
MICA 2012 –I-1
______________________________________________________________________
Figura 109 Validación del método con la creciente de 1997 Metodo Concave Base Slope
Combinación Logpearson-Logpearson-Logpearson
Figura 110 Validación del método con la creciente de 1997 Metodo Concave Base Slope
Combinación Gumbel-Normal-Weibull
En la gráfica 104, se dan los mejores ajustes con cada una de las crecientes.
214
MICA 2012 –I-1
______________________________________________________________________
215
MICA 2012 –I-1
______________________________________________________________________
216
MICA 2012 –I-1
______________________________________________________________________
217
MICA 2012 –I-1
______________________________________________________________________
Tabla 69 Calculo del EMC método flujo base Master Depletion Combinación Weibull-
Normal-Weibull
218
MICA 2012 –I-1
______________________________________________________________________
Tabla 70 Calculo del EMC método flujo base Master Depletion Combinación Log-Log-Gev
219
MICA 2012 –I-1
______________________________________________________________________
Tabla 71 Calculo del EMC método flujo base Master Depletion Combinación Gumbel-Log-
pearson-Gev.
220
MICA 2012 –I-1
______________________________________________________________________
Tabla 72 Calculo del EMC método flujo base Master Depletion Combinación Log-pearson-
Logpearson-Logpearson
221
MICA 2012 –I-1
______________________________________________________________________
Tabla 73 Calculo del EMC método flujo base Master Depletion Combinación Gumbel-
Normal-Logpearson
222
MICA 2012 –I-1
______________________________________________________________________
223
MICA 2012 –I-1
______________________________________________________________________
224
MICA 2012 –I-1
______________________________________________________________________
225
MICA 2012 –I-1
______________________________________________________________________
226
MICA 2012 –I-1
______________________________________________________________________
Figura 122 Validación del método con la creciente de 1997Metodo Master Depletion Combinación
Gumbel-Logpearson-Weibull.
Figura 123 Validación del método con la creciente de 1997Metodo Master Depletion Combinación
Weibulll-Normal-Weibull.
227
MICA 2012 –I-1
______________________________________________________________________
Figura 124 Validación del método con la creciente de 1997Metodo Master Depletion Combinación
Logpearson-Logpearson-Gev.
Figura 125 Validación del método con la creciente de 1997 Metodo Master Depletion Combinación
Gumbel-Logpearson-Gev
228
MICA 2012 –I-1
______________________________________________________________________
Figura 126 Validación del método con la creciente de 1997 Metodo Master Depletion Combinación
Logpearson-Logpearson-Logpearson
Figura 127 Validación del método con la creciente de 1997 Metodo Master Depletion Combinación
Gumbel-Normal-Weibull
229
MICA 2012 –I-1
______________________________________________________________________
230
MICA 2012 –I-1
______________________________________________________________________
231
MICA 2012 –I-1
______________________________________________________________________
232
CON GRIN SUS CONOCIMIENTOS
VALEN MAS