Tarea 2 de Programación de Obras
Tarea 2 de Programación de Obras
Tarea 2 de Programación de Obras
Metrado
Tiempo
N° Descripción INICIO FIN
Q 02.05.01 TIJERAL DE MADERA PARA TECHO 11.48 m und 4 días sab 03/12/22 mie 07/12/22
R 02.05.02 CORREAS Y TIRANTES MADERA 2" x 3" m 4días jue 09/12/22 mar 13/12/22
02.05.03 COBERTURA CON TEJA ANDINA m2 1 días mie 14/12/22 mié 14/12/22
S 02.05.04 CUMBRERA CON TEJA ANDINA m 1 días jue 15/12/22 jue 15/12/22
03 ARQUITECTURA 35 días vie 16/12/2022 mié 25/01/23
FF 04.06.07.01 PUESTA EN OPERACIÓN DE TODOS LOS SISTEMAS und 1 días jue 11/05/23 jue 11/05/23
COSTO DIRECTO
GASTOS GENERALES 20%
SUB TOTAL
COSTO DE SUPERVISIÓN
TOTAL PRESUPUESTO
Predesesor
Costos
1282.98
30.38
30.38
1010.02
1010.02
242.58
242.58
67648.99
2452.18
1118.02
1118.02
214.46
188.30
1119.70
119.59
10239.92
1636.00
1636.00
1770.80
1770.80
2143.01
2143.01
4690.11 HA.1.2=11-(0+1)=10 HA.6.5=12-(11+1)=0
4105.56 Hs2=10 Hs5=0
54956.88
5091.05 2 5
2795.00
1 11 12 12
A
2296.05
1
15857.20
6652.10 E 1
5204.30 HA.1.3=11-(0+1)=10 HA.4.6=0
Hs1=0 Hs3=10
4000.80 Hs6=0
15838.46
1 3 6
3967.46 B
6708.00 0 0 1 1 11 11 11
5163.00
15675.08
D
10
D
2833.90 F 1
10
4639.70 HA.1.4=1-(0+1)=0 HA.6.7=12-(11+1)=
C Hs4=0
Hs7=0
4288.48 1
2495.10 4 7
676.80
1 1 12 12
670.80
1147.50
15979.75
2610.00
2089.80
9250.45
2029.50
43354.29
10512.50
3651.50
6861.00
3615.90
464.10
2386.80
315.00
450.00
657.45
657.45
519.40
519.40
9346.30
1507.90
7838.40
930.81
930.81
1112.03
675.00
437.03
11209.90
9306.62
1903.28
973.02
420.00
3811.31
829.75
2233.00
748.56
665.67
665.67
9821.35
898.30
245.76
155.94
133.90
362.70
207.80
33.90
90.00
33.90
50.00
3999.59
873.60
873.60
1375.28
942.80
432.48
678.27
218.16
128.31
102.60
26.40
202.80
1072.44
459.60
306.40
306.44
4715.66
218.00
218.00
1078.16
462.80
615.36
237.36
237.36
1782.24
1252.80
529.44
732.08
155.44
166.48
211.20
59.52
139.44
441.20
208.16
233.04
226.62
226.62
426.00
211999.41
42399.88
254399.29
79524.00
333923.29
A.6.5=12-(11+1)=0
5 HA.9.10=21-(13+1)=7
Hs10=7
12 12
10
E 1 14 21
I
HA.6.8=12-(11+1)=0 HA.11.12=21-(15+6)=0
HA.4.6=0
1
13 13
Hs11=0
F K
1 J 6
11
HA.6.7=12-(11+1)=0
2
Hs7=0 15 15
12 12
HA.16.17=52-(36+4)=12
Hs17=12
17
40 52
HA.13.14=36-(25+3)=8
Hs14=8
Q
4
14
28 36
LL
12 13 16 18
L R
21 21 4 25 25 36 36 4 40 52
HA.13.15=30-(25+1)=0
Hs15=0
P
O 6
15
1
30 30
16 18
36 36 40 52
Hs15=0
P
O 6
15
1 HA.16.19=37-(36+1)=0
30 30
S Hs19=0
1
19
37 37
HA.20.21=77-(52+7)=18
HA.16.17=52-(36+4)=12
Hs17=12 Hs21=18
17 21 HA.25.24=92-(77+2)=13
40 52 59 77 Hs24=13
24
U
7 79 92
X
5
18 20 22 25 26
40 52 52 52 59 77 77 77 92 92
X
5
T
HA.16.19=37-(36+1)=0 HA.20.23=72-(52+20)=0
15
W
Hs19=0 Hs23=0
20
19 23
37 37 72 72
2)=13
HA.28.29=101-(95+5)=1
Hs29=1
29
100 101
CC
HA.26.27=94-(92+2)=0 HA.27.28=95-(94+1)=0
5
A.25.26=92-(77+15)=0
Hs26=0 Hs27=0 Hs28=0
26 27 28
AA BB
92 92 2 94 94 1 95 95
HA.28.30=101-(95+6)=0
Hs30=0
DD
6
26 28
BB
92 92 1 95 95
Hs30=0
DD
30
6 EE
101 101 2
01-(95+5)=1
01-(95+6)=0 HA.31.32=104-(103+1)=0
HA.30.31=103-(101+2)=0
Hs31=0 Hs32=0
HA.30.31=103-(101+2)=0
Hs31=0 Hs32=0
31 32
EE FF
2 103 103 1 104 104
PROGRAMACION PERT/CPM SOBRE PROYECTO DE MEJORAMIENTO RED AGUA POTABLE
Actividad (6 meses) Enero - Junio 2023
Tiempo
N° Descripción Predesesor Costo
33 67 I 57 76
2
HA.2.3=25-(5+1)=19 HA.3.6=43-(6+18)=19 HA.6.9=44-(24+1)=19 HA.13.18=67-(31+17)=19 HA.35.34=100-(84+6)=0
Hs6=19 Hs9=19 HA.9.13=19 Hs18=19 HA.18.21=19 J 5 HA.26.27=81-(57+5)=19
HS3=19 F 2 Hs13=19 Hs34=10
Hs21=19 Hs27=19
3 6 9 13 18 21 27 34
C D E G H
6 25 18 24 43 1 25 44 6 31 50 17 48 67 7 55 74 62 81 90 100
B HA.39.40=153-(136+16)=1
1 HA.42.43=169-(153+16)=0
LL 6 Hs40=1 Hs43=0
HA.15.14=61-(23+1)=37 40 43
N Hs14=37 HA.19.22=73-(31+12)=30
IO Hs22=30 152 153 M 169 169
AC 14 "
PT 16
CA 24 61 K" HA.41.42=0
HA.1.2=5-(0+5)=0 C- HA.7.10=30 HA.15.19=30 22
HA.22.28=75-(43+2)=30
HA.28.30=81-(45+6)=19 HA.36.37=100-(91+9)=0 16 HA.43.46=188-(169+19)=0 HA.46.47=0 HA.47.48=190-(189+1)=0
HA.2.4=36-(5+1)=30 HA.4.7=48-(6+1)=20 Q Hs30=19 HA.30.33=84-(62+3)=19 HA.32.35=84-(57+27)=0 HA.37.38= HA.38.39=0 Hs42=0 HA.42.44=30
Hs1=0 Hs3=0 Hs7=20 Hs10=30 HA.10.15=30 Hs19=30 Hs28=30 Hs33=19 Hs35=0
H437=0 Hs39=0 Hs44=30 Hs46=0 Hs47=0 Hs48=0
Hs4=30 Hs15=30 1 43 73 0 Hs38=0 O"
19
R - 01 38
S
1 2 4 7 10 15 19 28 30 33 35 37 39 42 44 46 47 48
U
A N F O P R V w L-C I"2 J" N" P" Q"
12
5 1 1 1 HA.19.23=40 3 100 100 8 128 128 8 153 153 5 1
2
0 0 5 5 6 36 18 48 19 49 4 23 53 8 31 61 45 75 62 81 65 84 84 84 136 136 158 188 188 188 189 189 1 190 190
Hs23=40
6
T
23 K 27 LL"
4
M R-D HA.39.40=137-(136+1)=0 16 HA.42.45=25
35 75 9 L" Hs41=0 Ñ" Hs45=25
R
-0
1
10
2
HA.29.31=57-(45+6)=0 41 45
Hs31=0
137 137 163 188
L 7
HA.2.5=6-(5+1)=0 HA.8-11=19-(18+1)=0 HA.16.20= HA.20.24=43-(31+12)=20 HA.24.29=0 31 HA.35.36=91-(84+7)=0
HA.5.8=18-(6+12)=0 HA.11.16=0
Hs6=0 Hs8=0 Hs11=0 Hs16=0 0 Hs20=0 Hs24=0 Hs29=0 Hs36=0
1 X 51 57
5 8 11 16 20 24 29 G" 36
A" C"8 D"1 6
Y Z F" HA.4.7=48-(6+1)=20
6 6 12 18 18 19 19 4 23 23 31 31 2 43 43 2 45 45 H 91 91
1 12 " Hs32=0
32
B" 1 HA.16.17=7 E" HA.20.25=10
Hs17=7 Hs25=10 57 57
4
17 25
24 31 35 45
PROGRAMACION PERT/CPM SOBRE PROYECTO DE MEJORAMIENTO RED DE DESAGÜE
(6 meses) Julio - Diciembre 2023
Actividad
Tiempo
N° Descripción Predesesor Costo
14 19
Ñ
111 126 8 119 134
N 8 O 8
HA.1.2=18-(0+1)=17 HA.4.5=24-(18+6)=0 HA.21.24=155-(142+5)=8
HA.8.9=78-(71+6)=1 HA.16.15=118-(95+8)=15
Hs2=17 Hs5=0 Hs15=15 HA.19.20=142-(119+8)=15 Hs24=8
Hs9=1
Hs20=15 HA.27.28=170-(159+11)=0
2 5 9 15 20 24 Hs28=0
1 18 24 24 77 78 103 118 127 142 147 155
H U 28
D 5
6 Y
6 170 170
A 1 M 8 11
HA.3.4=18-(1+17)=0 F HA.5.7=66-(24+42)=0 HA.8.10=78-(71+7)=0 HA.10.12=83-(78+65)=0 HA.25.26=155-(147+8)=0 HA.29.30=0 HA.30.31=187-(186+1)=0
42 HA.7.8=0 HA.12.16=95-(83+12)=0 HA.28.29=0
Hs1=0 Hs4=0 Hs7=0 Hs10=0 Hs12=0 Hs16=0 Hs26=0 HA.26.27=0 Z 15 Hs30=0 Hs31=0
Hs8=0 HA.22.21=142-(127+15)=0 Hs29=0
Hs27=0
Hs21=0
1 4 7 8 10 12 16 21 26 27 29 30 31
G I L LL X A" B"
0 0 18 18 66 66 5 71 71 7 78 78 83 83 12 95 95 142 142 155 155 4 159 159 185 185 1 186 186 1 187 187
5
C W
B 1 17 T 15
HA.4.6=66-(18+8)=41 P 8 HA.21.25=147-(142+5)=0 8
HA.8.11=82-(71+2)=9 HA.11.13=83-(73+1)=9
HA.1.3=1-(0+1)=0 HA.23.22=0 Hs25=0
Hs3=0 E Hs6=41 J Hs11=9 Hs13=9 HA.16.17=103-(95+8)=0
8 Hs17=0 Hs22=0
2
3 6 11 13 17 22 V 25
K 5
1 1 25 66 73 82 1 74 83 103 103 127 127 147 147
Q 8 S 8
HA.18.23=119-(111+8)=0
HA.17.18=111-(103+8)=0 Hs23=0
Hs18=0
18 23
R
111 111 8 119 119