Matrices de Precios Unitarios
Matrices de Precios Unitarios
Matrices de Precios Unitarios
MATERIALES
Placa de acero de 3/8" de espesor KG $21.50 * 0.086670 $1.86 4.19%
Varilla #3 (3/8") Ton $15,593.96 0.000011 $0.17 0.37%
PTR de 2" x 2" KG $19.78 * 1.050000 $20.77 46.67%
Sodadura electrodo 6013 DE 1/8" KG $45.00 * 0.107800 $4.85 10.90%
Primario anticorrosivo gris. LT $150.00 * 0.014010 $2.10 4.72%
Thiner estandar LT $35.00 * 0.002804 $0.10 0.22%
Taquete Expansivo s/Tornillo 1/4" x 3" PZA $12.00 * 0.300400 $3.60 8.10%
MATERIALES
TRIPLAY TIPO COMÚN 1.22x2.44 MTS PZA $420.00 * 0.084175 $35.35 5.37%
(16mm) 1.8
PTR 2"X2" PZA $758.62 * 0.095000 $72.07 10.95% 4.75
TORNILLOS ROSCA CORRIDA PZA $30.00 * 0.083333 $2.50 0.38% 4
DESMOLDANTE LTS $21.00 * 0.220000 $4.62 0.70%
TORNILLO CABEZA DE GOTA PZA $5.00 * 0.416667 $2.08 0.32% 20
TEXTURA M2 $80.00 * 0.233333 $18.67 2.84% 0.7
MALLA EXAGONAL M2 $15.00 * 0.600000 $9.00 1.37%
CLAVO P/CONCRETO PZA $1.50 * 6.000000 $9.00 1.37%
FESTERBOND LTS $127.04 * 0.150000 $19.06 2.90%
CONCRETO BLANCO FC=150KG/CM2 REV M3 $3,500.00 * 0.049875 $174.56 26.52%
18 TMA 3/8" 0.049875
SERVICIO DE BOMBEO M3 $230.00 * 0.049875 $11.47 1.74%
0.00%
SUBTOTAL: MATERIALES $358.38 54.46%
MANO DE OBRA
CUADRILLA NO. 1 (1 OF. HERRERO + 1 JOR $1,567.50 * 0.010000 $15.68 2.38%
AYUDANTE) 100
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,567.50 * 0.100000 $156.75 23.82%
AYUDANTE) cimbra y decimbra 10
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.055556 $87.08 13.23%
AYUDANTE) COLADO 18
CUADRILLA ACARREO (%)mo $259.51 * 0.050000 $12.98 1.97%
CUADRILLA DE LIMPIEZA (%)mo $259.51 * 0.050000 $12.98 1.97%
412.93103448
75
991.37931034
13.218390805
336.20689655
2185.3448276
1 0.01
1 0.1
1 0.0555555556
$ 849,449.51
MATERIALES
TRIPLAY TIPO FENOLICO 1.22x2.44 MTS PZA $732.70 * 0.084175 $61.68 7.24%
(16mm)
PTR 2"X2" PZA $758.62 * 0.095000 $72.07 8.46%
TORNILLOS ROSCA CORRIDA PZA $30.00 * 0.083333 $2.50 0.29%
DESMOLDANTE LTS $21.00 * 0.220000 $4.62 0.54%
TORNILLO CABEZA DE GOTA PZA $5.00 * 0.416667 $2.08 0.24%
TEXTURA M2 $80.00 * 0.233333 0.00%
MALLA EXAGONAL M2 $15.00 * 0.600000 $9.00 1.06%
CLAVO P/CONCRETO PZA $1.50 * 6.000000 $9.00 1.06%
FESTERBOND LTS $127.04 * 0.150000 $19.06 2.24%
CONCRETO BLANCO FC=150KG/CM2 REV M3 $3,500.00 * 0.049875 $174.56 20.50%
18 TMA 3/8"
SERVICIO DE BOMBEO M3 $230.00 * 0.049875 $11.47 1.35%
PIE DERECHO PZA $12.00 * 2.000000 $24.00 2.82%
TORNILLO BASE PZA $3.00 * 4.000000 $12.00 1.41%
TORNILLO CABEZAL PZA $3.00 * 4.000000 $12.00 1.41%
SUBTOTAL: MATERIALES $414.04 48.62%
MANO DE OBRA
CUADRILLA NO. 1 (1 OF. HERRERO + 1 JOR $1,567.50 * 0.010000 $15.68 1.84%
AYUDANTE)
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,567.50 * 0.125000 $195.94 23.01%
AYUDANTE) cimbra y decimbra
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.100000 $156.75 18.41%
AYUDANTE) COLADO
CUADRILLA ACARREO (%)mo $368.36 * 0.050000 $18.42 2.16%
CUADRILLA DE LIMPIEZA (%)mo $368.36 * 0.050000 $18.42 2.16%
MATERIALES
MADERA DE PINO DE 3RA PT $12.00 * 0.009000 $0.11 1.06%
CLAVO DE 2" A 4" P/CONCRETO KG $47.41 * 0.020000 $0.95 9.28%
PINTURA EN AEROSOL PZA $38.79 * 0.010000 $0.39 3.80%
HILO #10 ROLLO $35.26 * 0.002000 $0.07 0.69%
21.7028784
$157.35
4.431024197
0.117647059
1.149425287
76 0.014473684
34.16467373
0.025
MANO DE OBRA
CUADRILLA NO. 4 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.015385 $24.12 18.49%
AYUDANTE CADENEROS)
CABO (%)mo $24.12 * 0.100000 $2.41 1.85%
MATERIALES
CONCRETO FC=150 KG/CM2, RESISTENCIA
NORMAL, TMA. 19MM, PREFABRICADO M3 $1,565.00 * 0.052500 $82.16 47.50% 1
REV. 14. BOMBEABLE
SERVICIO DE BOMBEO M3 $225.00 * 0.052500 $11.81 6.83%
MATERIALES
CONCRETO FC=150 KG/CM2, RESISTENCIA
NORMAL, TMA. 19MM, PREFABRICADO M3 $1,984.03 * 0.031500 $62.50 48.70% 1
REV. 14. BOMBEABLE
SERVICIO DE BOMBEO M3 $225.00 * 0.031500 0.00%
MANO DE OBRA
CUADRILLA NO. 2 (2 AYUDANTES) JOR $1,011.95 * 1.000000 $1011.95 86.58%
CABO (%)mo $1,011.95 * 0.100000 $101.20 8.66%
TOTAL $1,379.19
MANO DE OBRA
CUADRILLA NO. 2 (2 AYUDANTES) JOR $1,011.95 * 0.100000 $101.20 60.64%
CABO (%)mo $101.20 * 0.100000 $10.12 6.06%
TOTAL $196.92
MATERIALES
BOQUILLA SIN ARENA DE 5 KG BULTO $125.00 * 0.100000 $12.50 5.16% 1
ADHESIVO PEGA MARMOL PERDURA 20 BULTO $72.90 * 0.800000 $58.32 24.09%
KG
SUBTOTAL: MATERIALES $70.82 29.25%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. COLOCADOR + 1 JOR $1,709.62 * 0.080000 $136.77 56.49%
AYUDANTE)
CABO (%)mo $136.77 * 0.100000 $13.68 5.65%
ACARREO (%)mo $136.77 * 0.050000 $6.84 2.82%
LIMPIEZA (%)mo $136.77 * 0.050000 $6.84 2.82%
MATERIALES
KERACOLR BULTO $1.00 * 0.525000 $0.53 0.10% 2
FUGOLASTIC GARRAFA $1.00 * 0.525000 $0.53 0.10% 2
ULTRAFLEX 2 BULTO $347.00 * 0.800000 $277.60 50.81%
1 0.125
MATERIALES
KERACOLR BULTO $1.00 * 0.525000 0.00% 2
FUGOLASTIC GARRAFA $1.00 * 0.525000 0.00% 2
PERDURA BULTO $125.00 * 0.800000 $100.00 31.83%
1 0.1
MATERIALES
AACE-0001 Canal de acero monten de 102 x 51 calibre 14
(3.30 kg. /cm2) 4″ x 2″
KG $30.00 * 0.330000 $9.90 1.76% 1
ACEL-006 Clavo con cabeza de 1 1/2″ kg $25.00 * 0.100000 $2.50 0.44%
ACEL-007 Clavo con cabeza de 2″ kg $25.00 * 0.100000 $2.50 0.44%
AACE-0019 Cuadrado de fierro de (25 mm) 1″ de espesor kg $30.00 * 0.540000 $16.20 2.88%
SOLD-002 (5.00 kg/cm2)
Soldadura 6013-3 (1/8″) verde. kg $70.00 * 0.043500 $3.05 0.54%
SPGC-088 Molde de poliuretano para concreto estampado pza $1,111.23 * 0.000600 $0.67 0.12%
SPGC-134 modelodepiedra
Molde chico para
poliuretano acom./river
concretorock 0.75 x
estampado pza $1,261.71 * 0.000100 $0.13 0.02%
0.75 mtspiedra
modelo rígido marca
chico SPG
acom./river rock 0.75
SPGC-019 Endurecedor color recinto presentacion de 27x cb $266.23 * 0.083375 $22.20 3.94%
0.75
kg mtsconcreto
para flexible marca SPG marca SPG
SPGC-015 Desmoldante enestampado
polvo SPG para concreto caj $544.04 * 0.011117 $6.05 1.07%
SPGC-312 estampado,
Sellador color25%
acrílico grisbidón
oscuro,
20 presentacion
lts marca SPGen bote $1,782.60 * 0.010005 $17.83 3.17%
caja de 10 kg, marca SPG
AACE-0255 Malla electrosoldada 66-1010 rollo de 100 mts M2 $16.76 * 1.050000 $17.60 3.13%
SUBTOTAL: MATERIALES $98.62 17.51%
MANO DE OBRA
CUADRILLA NO. 1 (1 OF. CARPINTERO + 1 JOR $1,567.50 * 0.020000 $31.35 5.57%
AYUDANTE) 1
CUADRILLA NO. 2 (1 OF. FIERRERO + 1 JOR $1,567.50 * 0.006667 $10.45 1.86%
AYUDANTE) 1
CUADRILLA NO. 3 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.066667 $104.50 18.56%
AYUDANTE) 1
CABO (%)mo $146.30 * 0.100000 $14.63 2.60%
LIMPIEZA (%)mo $146.30 * 0.050000 $7.32 1.30%
SUBTOTAL: MANO DE OBRA $168.25 29.88%
EQUIPO Y HERRAMIENTA
EQUIPO DE SEGURIDAD (%)mo $146.30 * 0.020000 $2.93 0.52%
HERRAMIENTA MENOR (%)mo $146.30 * 0.030000 $4.39 0.78%
AMAIN-010 Soldadora marca Lincoln modelo SAE 300 cap. hora $147.11 * 0.020880 $3.07 0.55%
300 Amp.
SUBTOTAL: EQUIPO Y HERRAMIENTA $10.39 1.84%
BASICO
CONCRETO FC=250KG/CM2 M3 $1,590.00 * 0.157500 $250.43 44.47% 1
SERVICIO DE BOMBEO M3 $225.00 * 0.157500 $35.44 6.29%
50 0.02
150 0.006666667
15 0.066666667
MATERIALES
ADOCRETO M2 $248.00 * 1.050000 $260.40 52.90% 1
POLVO DE PIEDRA M3 $350.00 * 0.073500 $25.73 5.23% 1
AGUA M3 $125.00 * 0.050000 $6.25 1.27%
1 1 1.05 1.05
1 0.07 1.05 0.0735
1 0.05
MATERIALES
ADOCRETO M2 $243.00 * 1.050000 $255.15 70.65% 1
POLVO DE PIEDRA M3 $350.00 * 0.046200 $16.17 4.48% 1
AGUA M3 $125.00 * 0.050000 $6.25 1.73%
1 1 1.05 1.05
1 0.07 1.05 0.0735
1 0.05
MATERIALES
ADOPASTO M2 $205.00 * 1.050000 $215.25 61.70% 1
POLVO DE PIEDRA M3 $350.00 * 0.073500 $25.73 7.37% 1
AGUA M3 $125.00 * 0.050000 $6.25 1.79%
1 1 1.05 1.05
1 0.07 1.05 0.0735
1 0.05
MATERIALES
CINCEL PUNTA P/MARTILLO NEUMATICO PZA $1,300.00 * 0.004910 $6.38 8.51%
MASCARILLA CON FILTRO PZA $4.00 * 1.000000 $4.00 5.33%
EXTENCION 100MTS PZA $3,500.00 * 0.000333 $1.17 1.56%
0.00%
SUBTOTAL: MATERIALES $11.55 15.40%
MANO DE OBRA 0.00%
CUADRILLA NO. 10 ( 2 AYUDANTE) JOR $2,375.12 / 50.000000 $47.50 63.33% 0.02
CABO (%)mo $47.50 * 0.100000 $4.75 6.33%
ACARREOS HORIZONTALES (%)mo $47.50 * 0.020000 $0.95 1.27%
CUADRILLA DE LIMPIEZA (%)mo $47.50 * 0.050000 $2.38 3.17%
7957.796295
MATERIALES
CINCEL PUNTA P/MARTILLO NEUMATICO PZA $1,300.00 * 0.004910 $6.38 4.39%
MASCARILLA CON FILTRO PZA $4.00 * 1.000000 $4.00 2.75%
EXTENCION 100MTS PZA $3,500.00 * 0.000333 $1.17 0.80%
0.00%
SUBTOTAL: MATERIALES $11.55 7.94%
MANO DE OBRA 0.00%
CUADRILLA NO. 01 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.066667 $104.50 71.86%
AYUDANTE) 15
CABO (%)mo $104.50 * 0.100000 $10.45 7.19%
ACARREOS HORIZONTALES (%)mo $104.50 * 0.020000 $2.09 1.44%
CUADRILLA DE LIMPIEZA (%)mo $104.50 * 0.050000 $5.23 3.59%
15429.94268
10215.7262
MATERIALES
CINCEL PUNTA P/MARTILLO NEUMATICO PZA $1,300.00 * 0.010000 $13.00 13.53%
MASCARILLA CON FILTRO PZA $4.00 * 1.000000 $4.00 4.16%
EXTENCION 100MTS PZA $3,500.00 * 0.000333 $1.17 1.21%
0.00%
SUBTOTAL: MATERIALES $18.17 18.90%
MANO DE OBRA 0.00%
CUADRILLA NO. 4 (1 OF. CARPINTERO + 2 JOR $2,375.12 / 40.000000 $59.38 61.78%
AYUDANTE) 0.025
CABO (%)mo $59.38 * 0.100000 $5.94 6.18%
ACARREOS HORIZONTALES (%)mo $59.38 * 0.020000 $1.19 1.24%
CUADRILLA DE LIMPIEZA (%)mo $59.38 * 0.050000 $2.97 3.09%
10197.06732
MATERIALES
CINCEL PUNTA P/MARTILLO NEUMATICO PZA $1,300.00 * 0.010000 $13.00 10.71%
MASCARILLA CON FILTRO PZA $4.00 * 1.000000 $4.00 3.30%
EXTENCION 100MTS PZA $3,500.00 * 0.000333 $1.17 0.96%
0.00%
0.00%
SUBTOTAL: MATERIALES $18.17 14.97%
MANO DE OBRA 0.00%
CUADRILLA NO. 4 (1 OF. CARPINTERO + 2 JOR $2,375.12 / 30.000000 $79.17 65.24%
AYUDANTE)
CABO (%)mo $79.17 * 0.100000 $7.92 6.52%
ACARREOS HORIZONTALES (%)mo $79.17 * 0.020000 $1.58 1.30%
CUADRILLA DE LIMPIEZA (%)mo $79.17 * 0.050000 $3.96 3.26%
MATERIALES
CINCEL PUNTA P/MARTILLO NEUMATICO PZA $1,300.00 * 0.015000 $19.50 3.25%
DIESEL P/COMPRESOR LTS $21.00 * 0.750000 $15.75 2.62%
MASCARILLA CON FILTRO PZA $4.00 * 2.000000 $8.00 1.33%
PINTURA EN AEROSOL PZA $45.00 0.010000 $0.45 0.07%
0.00%
SUBTOTAL: MATERIALES $43.70 7.28%
MANO DE OBRA 0.00%
CUADRILLA NO. 4 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.200000 $341.92 56.93%
AYUDANTE)
CABO (%)mo $341.92 * 0.100000 $34.19 5.69%
ACARREOS HORIZONTALES (%)mo $341.92 * 0.020000 $6.84 1.14%
CUADRILLA DE LIMPIEZA (%)mo $341.92 * 0.020000 $6.84 1.14%
MATERIALES
CINCEL PUNTA P/MARTILLO NEUMATICO PZA $1,300.00 * 0.050000 $65.00 5.73%
DIESEL P/COMPRESOR LTS $21.00 * 5.000000 $105.00 9.26%
MASCARILLA CON FILTRO PZA $4.00 * 2.000000 $8.00 0.71%
POLIETILENO NEGRO M2 $4.70 * 3.000000 $14.10 1.24%
PINTURA EN AEROSOL PZA $45.00 0.010000 $0.45 0.04%
0.00%
SUBTOTAL: MATERIALES $192.55 16.97%
MANO DE OBRA 0.00%
CUADRILLA NO. 4 (1 OF. ALBAÑIL + 1 JOR $1,709.62 * 0.250000 $427.41 37.67%
AYUDANTE)
CABO (%)mo $427.41 * 0.100000 $42.74 3.77%
ACARREOS HORIZONTALES (%)mo $427.41 * 0.020000 $8.55 0.75%
CUADRILLA DE LIMPIEZA (%)mo $427.41 * 0.020000 $8.55 0.75%
$ 214,192.71
MATERIALES
Varilla #2 (1/4") kg $15.20 1.050000 $15.96 60.44%
Alambre recocido cal 16 PZA $20.00 * 0.035000 $0.70 2.65%
MATERIALES
VARILLA #2, 3, 4, 5, 6, 8, 10 Y 12 KG $13.40 * 1.050000 $14.07 58.66%
Alambre recocido cal 16 PZA $20.00 * 0.035000 $0.70 2.92%
MATERIALES
CONECTORES MECANICOS ROSCADOS PZA $230.00 * 0.018519 0.00%
VARILLA #10 Y 12 KG $13.40 * 1.050000 $14.07 50.38%
MATERIALES
MALLA ELECTROSOLDADA 6X6-10/10 M2 $1,475.00 0.010000 $14.75 59.32%
Alambre recocido cal 16 PZA $20.00 * 0.035000 $0.70 2.82%
MATERIALES
CONECTORES MECANICOS ROSCADOS PZA $230.00 * 1.000000 $230.00 95.55%
MANO DE OBRA
CUADRILLA NO. 1 (1 OF. FIERRERO + 1 JOR $1,709.62 * 0.005000 $8.55 65.44%
AYUDANTE)
CABO (%)mo $8.55 * 0.100000 $0.85 6.54%
ACARREOS HORIZONTALES (%)mo $9.40 * 0.050000 $0.47 3.60%
CUADRILLA DE LIMPIEZA (%)mo $9.40 * 0.050000 $0.47 3.60%
MATERIALES
DISCO DE CORTE PZA $118.10 * 0.050000 $5.91 2.03%
GAFAS DE SEGURIDAD PZA $133.62 * 0.010000 $1.34 0.46%
GUANTES DE CARNAZA PAR $73.27 * 0.040000 $2.93 1.01%
TAPONES AUDITIVOS PAR $11.20 * 0.500000 $5.60 1.92%
MATERIALES
DISCO DE CORTE PZA $118.10 * 0.050000 $5.91 5.22%
GAFAS DE SEGURIDAD PZA $133.62 * 0.010000 $1.34 1.18%
GUANTES DE CARNAZA PAR $73.27 * 0.040000 $2.93 2.59%
TAPONES AUDITIVOS PAR $11.20 * 0.500000 $5.60 4.95%
MATERIALES
TRIPLAY TIPO COMÚN 1.22x2.44 MTS PZA $385.00 * 0.042088 $16.20 9.36%
(16mm) 0.336700337
POLIN DE 3AR PZA $30.00 * 0.083333 $2.50 1.44% 1
BARROTE DE PINO DE 3RA PZA $30.00 * 0.083333 $2.50 1.44% 1
CHAFLAN DE PINO PZA $7.00 * 2.000000 $14.00 8.08% 1
DESMOLDANTE LTS $21.00 * 0.220000 $4.62 2.67%
CLAVO DE 2" A 4" ESTANDAR KG $20.00 * 0.250000 $5.00 2.89%
ALAMBRE RECOCIDO CAL. 16. KG $17.50 * 0.200000 $3.50 2.02%
0.00%
SUBTOTAL: MATERIALES $48.32 27.90%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.025000 $42.74 24.68%
AYUDANTE) habilitado 40
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.040000 $68.38 39.49%
AYUDANTE) cimbra y decimbra 25
ACARREOS HORIZONTALES (%)mo $111.13 * 0.020000 $2.22 1.28%
CUADRILLA DE LIMPIEZA (%)mo $111.13 * 0.050000 $5.56 3.21%
8 0.042087542
12 0.083333333
12 0.083333333
0.5 2
1 0.025
1 0.04
MATERIALES
TRIPLAY TIPO COMÚN 1.22x2.44 MTS PZA $385.00 * 0.168350 $64.81 27.24%
(16mm) 0.336700337
POLIN DE 3AR PZA $30.00 * 0.468750 $14.06 5.91%
BARROTE DE PINO DE 3RA PZA $30.00 * 0.468750 $14.06 5.91%
CHAFLAN DE PINO PZA $7.00 * 1.000000 $7.00 2.94%
DESMOLDANTE LTS $21.00 * 0.220000 $4.62 1.94%
CLAVO DE 2" A 4" ESTANDAR KG $20.00 * 0.250000 $5.00 2.10%
ALAMBRE RECOCIDO CAL. 16. KG $17.50 * 0.200000 $3.50 1.47%
0.00%
SUBTOTAL: MATERIALES $113.06 47.52%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.025000 $42.74 17.97%
AYUDANTE) habilitado 40
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.040000 $68.38 28.74%
AYUDANTE) cimbra y decimbra 25
ACARREOS HORIZONTALES (%)mo $111.13 * 0.020000 $2.22 0.93%
CUADRILLA DE LIMPIEZA (%)mo $111.13 * 0.050000 $5.56 2.34%
2 0.168350168
1 0.025
1 0.04
MATERIALES
TRIPLAY TIPO FENOLICO A DOS CARAS DE PZA $1,100.00 * 0.168350 $185.19 35.74%
1.22x2.44 MTS (19mm) 1
POLIN DE 3AR PZA $30.00 * 0.468750 $14.06 2.71%
BARROTE DE PINO DE 3RA PZA $30.00 * 0.468750 $14.06 2.71%
CHAFLAN DE PINO PZA $7.00 * 1.000000 $7.00 1.35%
DESMOLDANTE LTS $21.00 * 0.220000 $4.62 0.89%
CLAVO DE 2" A 4" ESTANDAR KG $20.00 * 0.250000 $5.00 0.97%
ALAMBRE RECOCIDO CAL. 16. KG $17.50 * 0.200000 $3.50 0.68%
0.00%
SUBTOTAL: MATERIALES $233.43 45.06%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.040000 $68.38 13.20%
AYUDANTE) habilitado 25
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.100000 $170.96 33.00%
AYUDANTE) cimbra y decimbra 10
CABO (%)mo $239.35 * 0.100000 $23.93 4.62%
ACARREOS HORIZONTALES (%)mo $239.35 * 0.020000 $4.79 0.92%
CUADRILLA DE LIMPIEZA (%)mo $239.35 * 0.050000 $11.97 2.31%
1 0.04
1 0.1
MATERIALES
TRIPLAY TIPO FENOLICO A DOS CARAS DE PZA $1,100.00 * 0.168350 $185.19 6.92%
1.22x2.44 MTS (19mm) CIMBRA
POLIN DE 3AR PZA $30.00 * 0.320000 $9.60 0.36%
DESMOLDANTE LTS $21.00 * 0.440000 $9.24 0.35% POLIN
CLAVO DE 2" A 4" ESTANDAR KG $20.00 * 0.250000 $5.00 0.19%
SILLETAS PZA $1.00 * 8.000000 $8.00 0.30%
MOÑOS PZA $1.00 * 4.000000 $4.00 0.15%
ALAMBRE RECOCIDO CAL. 16. KG $17.50 * 0.400000 $7.00 0.26%
ALAMBRON 1/4" KG $15.00 * 0.250000 $3.75 0.14%
VARILLA #4 KG $11.90 * 55.000000 $654.50 24.45%
0.00%
0.00%
SUBTOTAL: MATERIALES $886.28 33.11%
MANO DE OBRA 0.00%
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.200000 $341.92 12.77%
AYUDANTE)
CUADRILLA NO. 1 (1 OF. FIERRERO + 1 JOR $1,709.62 * 0.280000 $478.69 17.88%
AYUDANTE)
CABO (%)mo $820.62 * 0.100000 $82.06 3.07%
ELEVACIONES (%)mo $820.62 * 0.050000 $41.03 1.53%
ACARREOS HORIZONTALES (%)mo $820.62 * 0.020000 $16.41 0.61%
CUADRILLA DE LIMPIEZA (%)mo $820.62 * 0.020000 $16.41 0.61%
4 USOS
2 0.673400673 0.168350168
10 USOS
8 3.2 0.32
MATERIALES
TRIPLAY TIPO FENOLICO A DOS CARAS DE PZA $1,100.00 * 0.168350 $185.19 6.40%
1.22x2.44 MTS (19mm) CIMBRA
POLIN DE 3AR PZA $30.00 * 0.320000 $9.60 0.33%
DESMOLDANTE LTS $21.00 * 0.440000 $9.24 0.32% POLIN
CLAVO DE 2" A 4" ESTANDAR KG $20.00 * 0.250000 $5.00 0.17%
SILLETAS PZA $3.00 * 8.000000 $24.00 0.83%
MOÑOS PZA $25.00 * 4.000000 $100.00 3.45%
ALAMBRE RECOCIDO CAL. 16. KG $17.50 * 0.400000 $7.00 0.24%
ALAMBRON 1/4" KG $15.00 * 0.250000 $3.75 0.13%
VARILLA #4 KG $11.90 * 55.000000 $654.50 22.61%
0.00%
0.00%
SUBTOTAL: MATERIALES $998.28 34.48%
MANO DE OBRA 0.00%
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.200000 $341.92 11.81%
AYUDANTE)
CUADRILLA NO. 1 (1 OF. FIERRERO + 1 JOR $1,709.62 * 0.280000 $478.69 16.54%
AYUDANTE)
CABO (%)mo $820.62 * 0.100000 $82.06 2.83%
ELEVACIONES (%)mo $820.62 * 0.050000 $41.03 1.42%
ACARREOS HORIZONTALES (%)mo $820.62 * 0.020000 $16.41 0.57%
CUADRILLA DE LIMPIEZA (%)mo $820.62 * 0.020000 $16.41 0.57%
4 USOS
2 0.673400673 0.168350168
10 USOS
8 3.2 0.32
MATERIALES
TRIPLAY TIPO FENOLICO A DOS CARAS DE PZA $1,050.00 * 0.056117 $58.92 14.50%
1.22x2.44 MTS (16mm) CIMBRA
POLIN DE 3AR PZA $30.00 * 0.266667 $8.00 1.97%
DESMOLDANTE LTS $21.00 * 0.250000 $5.25 1.29% POLIN
CLAVO DE 2" A 4" ESTANDAR KG $20.00 * 0.250000 $5.00 1.23%
SILLETAS PZA $2.00 * 8.000000 $16.00 3.94%
MOÑOS PZA $16.83 * 3.000000 $50.48 12.42%
ALAMBRE RECOCIDO CAL. 16. KG $17.50 * 0.400000 $7.00 1.72%
0.00%
SUBTOTAL: MATERIALES $150.66 37.07%
MANO DE OBRA 0.00%
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.125000 $213.70 52.58%
AYUDANTE)
CABO (%)mo $213.70 * 0.100000 $21.37 5.26%
ACARREOS HORIZONTALES (%)mo $213.70 * 0.020000 $4.27 1.05%
CUADRILLA DE LIMPIEZA (%)mo $213.70 * 0.020000 $4.27 1.05%
4 USOS
1 0.336700337 0.056116723
10 USOS
4 1.6 0.266666667
1682.758621
16.82758621
MATERIALES
CEMENTO GRIS SACO 50 KG TON $3,380.00 * 0.257500 $870.35 52.60% 50
GRAVA DE 3/4" M3 $305.00 * 0.684950 $208.91 12.63% 19
POLVO DE PIEDRA M3 $295.00 * 0.587100 $173.19 10.47% 19
AGUA M3 $100.00 * 0.264195 $26.42 1.60% 19
0.00%
0.00%
SUBTOTAL: MATERIALES $1278.87 77.30%
MANO DE OBRA 0.00%
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 5 JOR $4,371.61 * 0.062500 $273.23 16.51%
AYUDANTE) 16
CABO (%)mo $273.23 * 0.100000 $27.32 1.65%
ACARREOS HORIZONTALES (%)mo $273.23 * 0.050000 $13.66 0.83%
CUADRILLA DE LIMPIEZA (%)mo $273.23 * 0.020000 $5.46 0.33%
5 1.03 0.2575
35 1.03 0.68495
30 1.03 0.5871
13.5 1.03 0.264195
1 0.0625
MATERIALES
CEMENTO GRIS SACO 50 KG TON $3,380.00 * 0.309000 $1044.42 57.39% 50
GRAVA DE 3/4" M3 $305.00 * 0.675165 $205.93 11.32% 19
POLVO DE PIEDRA M3 $295.00 * 0.567530 $167.42 9.20% 19
AGUA M3 $100.00 * 0.264195 $26.42 1.45% 19
0.00%
0.00%
SUBTOTAL: MATERIALES $1444.19 79.36%
MANO DE OBRA 0.00%
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 5 JOR $4,371.61 * 0.062500 $273.23 15.01%
AYUDANTE) 234.375
CABO (%)mo $273.23 * 0.100000 $27.32 1.50%
ACARREOS HORIZONTALES (%)mo $273.23 * 0.050000 $13.66 0.75%
CUADRILLA DE LIMPIEZA (%)mo $273.23 * 0.020000 $5.46 0.30%
6 1.03 0.309
34.5 1.03 0.675165
29 1.03 0.56753
13.5 1.03 0.264195
MATERIALES
CEMENTO GRIS SACO 50 KG TON $3,380.00 * 0.360500 $1218.49 61.25% 50
GRAVA DE 3/4" M3 $305.00 * 0.675165 $205.93 10.35% 19
POLVO DE PIEDRA M3 $295.00 * 0.557745 $164.53 8.27% 19
AGUA M3 $100.00 * 0.248539 $24.85 1.25% 19
0.00%
0.00%
SUBTOTAL: MATERIALES $1613.80 81.12%
MANO DE OBRA 0.00%
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 5 JOR $4,371.61 * 0.062500 $273.23 13.73%
AYUDANTE)
CABO (%)mo $273.23 * 0.100000 $27.32 1.37%
ACARREOS HORIZONTALES (%)mo $273.23 * 0.050000 $13.66 0.69%
CUADRILLA DE LIMPIEZA (%)mo $273.23 * 0.020000 $5.46 0.27%
7 1.03 0.3605
34.5 1.03 0.675165
28.5 1.03 0.557745
12.7 1.03 0.248539
MATERIALES
CEMENTO GRIS SACO 50 KG TON $3,380.00 * 0.412000 $1392.56 64.47% 50
GRAVA DE 3/4" M3 $305.00 * 0.665380 $202.94 9.39% 19
POLVO DE PIEDRA M3 $295.00 * 0.557745 $164.53 7.62% 19
AGUA M3 $100.00 * 0.244625 $24.46 1.13% 19
0.00%
0.00%
SUBTOTAL: MATERIALES $1784.50 82.61%
MANO DE OBRA 0.00%
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 5 JOR $4,371.61 * 0.062500 $273.23 12.65%
AYUDANTE)
CABO (%)mo $273.23 * 0.100000 $27.32 1.26%
ACARREOS HORIZONTALES (%)mo $273.23 * 0.050000 $13.66 0.63%
CUADRILLA DE LIMPIEZA (%)mo $273.23 * 0.020000 $5.46 0.25%
8 1.03 0.412
34 1.03 0.66538
28.5 1.03 0.557745
12.5 1.03 0.244625
MATERIALES
CEMENTO GRIS SACO 50 KG TON $3,380.00 * 0.437750 $1479.60 66.34% 50
GRAVA DE 3/4" M3 $305.00 * 0.645810 $196.97 8.83% 19
POLVO DE PIEDRA M3 $295.00 * 0.534261 $157.61 7.07% 19
AGUA M3 $100.00 * 0.205485 $20.55 0.92% 19
0.00%
0.00%
SUBTOTAL: MATERIALES $1854.72 83.16%
MANO DE OBRA 0.00%
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 5 JOR $4,371.61 * 0.062500 $273.23 12.25%
AYUDANTE)
CABO (%)mo $273.23 * 0.100000 $27.32 1.23%
ACARREOS HORIZONTALES (%)mo $273.23 * 0.050000 $13.66 0.61%
CUADRILLA DE LIMPIEZA (%)mo $273.23 * 0.020000 $5.46 0.25%
MATERIALES
0.00%
SUBTOTAL: MATERIALES $1326.15 100.00%
(CD) Costo directo $1,326.15 100.00%
(CI) INDIRECTOS 10.0000% $132.62
SUBTOTAL1 $1,458.77
(CF) FINANCIAMIENTO 0.0000% $0.00
SUBTOTAL2 $1,458.77
(CU) UTILIDAD 8.0000% $106.09
PRECIO UNITARIO (CD+CI+CF+CU+IVA MATERIALES) $1,564.86
16% IVA MATERIALES
TOTAL $1,564.86
MATERIALES
0.00%
SUBTOTAL: MATERIALES $1652.70 100.00%
(CD) Costo directo $1,652.70 100.00%
(CI) INDIRECTOS 10.0000% $165.27
SUBTOTAL1 $1,817.97
(CF) FINANCIAMIENTO 0.0000% $0.00
SUBTOTAL2 $1,817.97
(CU) UTILIDAD 8.0000% $132.22
PRECIO UNITARIO (CD+CI+CF+CU+IVA MATERIALES) $1,950.19
16% IVA MATERIALES
TOTAL $1,950.19
MATERIALES
0.00%
SUBTOTAL: MATERIALES $1657.95 100.00%
(CD) Costo directo $1,657.95 100.00%
(CI) INDIRECTOS 10.0000% $165.80
SUBTOTAL1 $1,823.75
(CF) FINANCIAMIENTO 0.0000% $0.00
SUBTOTAL2 $1,823.75
(CU) UTILIDAD 8.0000% $132.64
PRECIO UNITARIO (CD+CI+CF+CU+IVA MATERIALES) $1,956.38
16% IVA MATERIALES
TOTAL $1,956.38
MATERIALES
0.00%
SUBTOTAL: MATERIALES $1669.50 100.00%
(CD) Costo directo $1,669.50 100.00%
(CI) INDIRECTOS 10.0000% $166.95
SUBTOTAL1 $1,836.45
(CF) FINANCIAMIENTO 0.0000% $0.00
SUBTOTAL2 $1,836.45
(CU) UTILIDAD 8.0000% $133.56
PRECIO UNITARIO (CD+CI+CF+CU+IVA MATERIALES) $1,970.01
16% IVA MATERIALES
TOTAL $1,970.01
MATERIALES
0.00%
SUBTOTAL: MATERIALES $1779.75 100.00%
(CD) Costo directo $1,779.75 100.00%
(CI) INDIRECTOS 10.0000% $177.98
SUBTOTAL1 $1,957.73
(CF) FINANCIAMIENTO 0.0000% $0.00
SUBTOTAL2 $1,957.73
(CU) UTILIDAD 8.0000% $142.38
PRECIO UNITARIO (CD+CI+CF+CU+IVA MATERIALES) $2,100.11
16% IVA MATERIALES
TOTAL $2,100.11
MATERIALES
0.00%
SUBTOTAL: MATERIALES $1879.50 100.00%
(CD) Costo directo $1,879.50 100.00%
(CI) INDIRECTOS 10.0000% $187.95
SUBTOTAL1 $2,067.45
(CF) FINANCIAMIENTO 0.0000% $0.00
SUBTOTAL2 $2,067.45
(CU) UTILIDAD 8.0000% $150.36
PRECIO UNITARIO (CD+CI+CF+CU+IVA MATERIALES) $2,217.81
16% IVA MATERIALES
TOTAL $2,217.81
SIMUNISTRO DE CONCRETO ESTRUCTURAL f'c= 350 kg/cm2 rev. 18, MASA VOLUMETRICA 2,200 KG/CM2 bombeable resistencia normal a
28 días de edad, RESISTENTE A LOS SULFATOS, RELACION AGUA-CEMENTO 0.45 (PILAS) , INCLUYE: SUMINISTRO, DE MATERIAL.
MATERIALES
0.00%
SUBTOTAL: MATERIALES $2322.60 100.00%
(CD) Costo directo $2,322.60 100.00%
(CI) INDIRECTOS 10.0000% $232.26
SUBTOTAL1 $2,554.86
(CF) FINANCIAMIENTO 0.0000% $0.00
SUBTOTAL2 $2,554.86
(CU) UTILIDAD 8.0000% $185.81
PRECIO UNITARIO (CD+CI+CF+CU+IVA MATERIALES) $2,740.67
16% IVA MATERIALES
TOTAL $2,740.67
MATERIALES
SERVICIO DE BOMBEO M3 $225.00 * 1.050000 $236.25 100.00%
0.00%
SUBTOTAL: MATERIALES $236.25 100.00%
(CD) Costo directo $236.25 100.00%
(CI) INDIRECTOS 10.0000% $23.63
SUBTOTAL1 $259.88
(CF) FINANCIAMIENTO 0.0000% $0.00
SUBTOTAL2 $259.88
(CU) UTILIDAD 8.0000% $18.90
PRECIO UNITARIO (CD+CI+CF+CU+IVA MATERIALES) $278.78
16% IVA MATERIALES
TOTAL $278.78
MATERIALES
SERVICIO DE BOMBEO M3 $325.00 * 1.050000 $341.25 100.00%
0.00%
SUBTOTAL: MATERIALES $341.25 100.00%
(CD) Costo directo $341.25 100.00%
(CI) INDIRECTOS 10.0000% $34.13
SUBTOTAL1 $375.38
(CF) FINANCIAMIENTO 0.0000% $0.00
SUBTOTAL2 $375.38
(CU) UTILIDAD 8.0000% $27.30
PRECIO UNITARIO (CD+CI+CF+CU+IVA MATERIALES) $402.68
16% IVA MATERIALES
TOTAL $402.68
MANO DE OBRA
CUADRILLA NO. 6 (1 OF. ALBAÑIL + 5 JOR $4,371.61 / 25.000000 $174.86 82.74%
AYUDANTE)
CABO (%)mo $174.86 * 0.100000 $17.49 8.27%
CUADRILLA DE LIMPIEZA (%)mo $174.86 * 0.020000 $3.50 1.65%
MATERIALES
HILTI RE-500 PZA $1,387.00 * 0.200000 $277.40 80.37%
APLICADOR PZA $5,000.00 * 0.001000 $5.00 1.45%
BROCA DE 3/4" A 1 1/2" PZA $3,500.00 * 0.003330 $11.66 3.38%
0.00%
SUBTOTAL: MATERIALES $294.06 85.19%
MANO DE OBRA
CUADRILLA NO. 3 (1 OF. ALBAÑIL + 1 JOR $1,709.62 * 0.020000 $34.19 9.91%
AYUDANTE)
CABO (%)mo $34.19 * 0.100000 $3.42 0.99%
CUADRILLA DE LIMPIEZA (%)mo $37.61 * 0.050000 $1.88 0.54%
$1,102,569.02
MATERIALES
SIKA ANCHORFIX 3001 PZA $1,340.08 * 0.012048 $16.15 15.25%
PISTOLA PARA APLICACION MANUAL PZA $1,815.30 * 0.001000 $1.82 1.71%
VARILLA DEL #3 KG $11.90 * 1.000000 $11.90 11.24%
BROCA DE 3/8" A 1" PZA $215.00 * 0.020000 $4.30 4.06%
0.00%
SUBTOTAL: MATERIALES $34.16 32.27%
MANO DE OBRA
CUADRILLA NO. 3 (1 OF. ALBAÑIL + 1 JOR $1,709.62 * 0.030000 $51.29 48.45%
AYUDANTE)
CABO (%)mo $51.29 * 0.100000 $5.13 4.84%
CUADRILLA DE LIMPIEZA (%)mo $56.42 * 0.050000 $2.82 2.66%
MATERIALES
SIKA ANCHORFIX 3001 PZA $1,999.00 * 0.027027 $54.03 35.11%
PISTOLA PARA APLICACION MANUAL PZA $3,850.00 * 0.001000 $3.85 2.50%
VARILLA DEL #3 KG $20.00 * 1.000000 $20.00 13.00%
BROCA DE 3/8" A 1" PZA $215.00 * 0.020000 $4.30 2.79%
0.00%
SUBTOTAL: MATERIALES $82.18 53.40%
MANO DE OBRA
CUADRILLA NO. 3 (1 OF. ALBAÑIL + 1 JOR $1,709.62 * 0.030000 $51.29 33.33%
AYUDANTE)
CABO (%)mo $51.29 * 0.100000 $5.13 3.33%
CUADRILLA DE LIMPIEZA (%)mo $56.42 * 0.050000 $2.82 1.83%
MATERIALES
BLOCK 10X20X40CM PZA $7.10 * 12.500000 $88.75 36.89%
$0.00 0.00%
$0.00 0.00%
0.00%
SUBTOTAL: MATERIALES $88.75 36.89%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.066667 $113.97 47.38%
AYUDANTE) 15
CABO (%)mo $113.97 * 0.100000 $11.40 4.74%
ELEVACIONES (%)mo $125.37 * 0.050000 0.00% 3
ACARREOS HORIZONTALES (%)mo $125.37 * 0.020000 $2.51 1.04% 5
CUADRILLA DE LIMPIEZA (%)mo $125.37 * 0.020000 $2.51 1.04% 0.008
1 0.066666667
1.05
0.0084
MATERIALES
BLOCK 12X20X40CM PZA $7.25 * 12.500000 $90.63 36.22%
$0.00 0.00%
$0.00 0.00%
0.00%
SUBTOTAL: MATERIALES $90.63 36.22%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.068966 $117.90 47.13%
AYUDANTE) 14.5
CABO (%)mo $117.90 * 0.100000 $11.79 4.71%
ELEVACIONES (%)mo $129.70 * 0.050000 0.00%
ACARREOS HORIZONTALES (%)mo $129.70 * 0.020000 $2.59 1.04%
CUADRILLA DE LIMPIEZA (%)mo $129.70 * 0.020000 $2.59 1.04%
1 0.068965517
1.05
0.01008
1.05
0.0084
MATERIALES
BLOCK 15X20X40CM PZA $7.30 * 12.500000 $91.25 31.96%
$0.00 0.00%
$0.00 0.00%
0.00%
SUBTOTAL: MATERIALES $91.25 31.96%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.080000 $136.77 47.91%
AYUDANTE) 12.5
CABO (%)mo $136.77 * 0.100000 $13.68 4.79%
ELEVACIONES (%)mo $150.45 * 0.050000 $7.52 2.63%
ACARREOS HORIZONTALES (%)mo $150.45 * 0.020000 $3.01 1.05%
CUADRILLA DE LIMPIEZA (%)mo $150.45 * 0.020000 $3.01 1.05%
1 0.08
1.05
0.0126
1.05
0.0084
MATERIALES
BLOCK 20X20X40CM PZA $13.63 * 12.500000 $170.38 45.85%
$0.00 0.00%
$0.00 0.00%
0.00%
SUBTOTAL: MATERIALES $170.38 45.85%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,567.50 * 0.086613 $135.77 36.54%
AYUDANTE) 11.5456
CABO (%)mo $135.77 * 0.100000 $13.58 3.65%
ELEVACIONES (%)mo $149.34 * 0.050000 $7.47 2.01%
ACARREOS HORIZONTALES (%)mo $149.34 * 0.020000 $2.99 0.80%
CUADRILLA DE LIMPIEZA (%)mo $149.34 * 0.020000 $2.99 0.80%
1 0.086613082
1.05
0.0168
1.05
0.0084
MATERIALES
CELOTEX DE 12.5MM PZA $350.00 * 0.070000 $24.50 32.35% 0.2
0.00%
SUBTOTAL: MATERIALES $24.50 32.35%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.025000 $42.74 56.43%
AYUDANTE) 40
CABO (%)mo $42.74 * 0.100000 $4.27 5.64%
ELEVACIONES (%)mo $47.01 * 0.050000 0.00%
ACARREOS HORIZONTALES (%)mo $47.01 * 0.020000 $0.94 1.24%
CUADRILLA DE LIMPIEZA (%)mo $47.01 * 0.020000 $0.94 1.24%
1.2 0.24
1 0.025
MATERIALES
MASILLA FINA PERDURA SACO 40 KG BULTO $94.73 * 0.166667 $15.79 8.66% 6
AGUA M3 $80.00 * 0.005000 $0.40 0.22%
SELLADOR 5x1 LTS $50.00 * 0.041667 $2.08 1.14%
RODILLO PZA $80.00 * 0.005000 $0.40 0.22%
SUBTOTAL: MATERIALES $18.67 10.24%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.066667 $104.50 57.30%
AYUDANTE) 15
CABO (%)mo $104.50 * 0.100000 $10.45 5.73%
ELEVACIONES (%)mo $114.95 * 0.050000 0.00%
ACARREOS HORIZONTALES (%)mo $114.95 * 0.050000 $5.75 3.15%
CUADRILLA DE LIMPIEZA (%)mo $114.95 * 0.020000 $2.30 1.26%
1 0.166666667
1 0.066666667
MATERIALES
MASILLA FINA PERDURA SACO 40 KG BULTO $94.73 * 0.166667 $15.79 7.30% 6
AGUA M3 $80.00 * 0.005000 $0.40 0.19%
SELLADOR 5x1 LTS $50.00 * 0.041667 $2.08 0.96%
RODILLO PZA $80.00 * 0.005000 $0.40 0.19%
SUBTOTAL: MATERIALES $18.67 8.64%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.083333 $130.63 60.42%
AYUDANTE) 12
CABO (%)mo $130.63 * 0.100000 $13.06 6.04%
ELEVACIONES (%)mo $143.69 * 0.050000 0.00%
ACARREOS HORIZONTALES (%)mo $143.69 * 0.050000 $7.18 3.32%
CUADRILLA DE LIMPIEZA (%)mo $143.69 * 0.020000 $2.87 1.33%
1 0.166666667
1 0.083333333
MATERIALES
MASILLA FINA PERDURA SACO 40 KG BULTO $94.73 * 0.166667 $15.79 17.95%
AGUA M3 $80.00 * 0.005000 $0.40 0.45%
SELLADOR 5x1 LTS $50.00 * 0.020833 $1.04 1.18%
RODILLO PZA $80.00 * 0.005000 $0.40 0.45%
SUBTOTAL: MATERIALES $17.63 20.04%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 1 JOR $1,709.62 * 0.033333 $56.99 64.79%
AYUDANTE)
CABO (%)mo $56.99 * 0.100000 $5.70 6.48%
CUADRILLA DE LIMPIEZA (%)mo $62.69 * 0.020000 $1.25 1.43%
MATERIALES
RECUBRIMIENTO DCORATIVO CUB $838.65 * 0.052632 $44.14 20.41%
TEXTURIZADO (MAPLACEMENT CUB. 19
TS)
MATERIALES
Alambre Galvanizado #14 kg $40.69 * 0.800000 $32.55 6.26%
Clavo hilti pza $2.50 2.500000 $6.25 1.20%
Panel Glass Liner 61.5X61.5 cms pza $68.04 * 3.050000 $207.52 39.89%
DONN DX TEE principal blanco 3.66 m x 1 1/2" ml $121.99 0.346000 $42.21 8.11%
DONN DX TEE conectora blanco 1.22 m x 1" ml $35.37 1.500000 $53.06 10.20%
DONN DX TEE conectora blanco 0.61 m x 1" ml $17.69 1.500000 $26.54 5.10%
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.126347 $198.05 12.29%
AYUDANTE) COLADORES
CABO (%)mo $198.05 * 0.100000 $19.80 1.23%
ACARREOS HORIZONTALES (%)mo $198.05 * 0.050000 $9.90 0.61%
ANDAMIOS (%)mo $198.05 * 0.050000 $9.90 0.61%
TOTAL $1,901.26
0.12635
MATERIALES
AGUA M3 $80.00 * 0.005000 $0.40 0.29%
SELLADOR 5x1 LTS $50.00 * 0.020833 $1.04 0.77%
RODILLO PZA $80.00 * 0.005000 $0.40 0.29%
SUBTOTAL: MATERIALES $1.84 1.36%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 1 JOR $1,709.62 * 0.050000 $85.48 62.97%
AYUDANTE)
CABO (%)mo $85.48 * 0.100000 $8.55 6.30%
CUADRILLA DE LIMPIEZA (%)mo $94.03 * 0.020000 $1.88 1.39%
MATERIALES
AGUA M3 $80.00 * 0.005000 $0.40 0.24%
SELLADOR 5x1 LTS $50.00 * 0.020833 $1.04 0.63%
RODILLO PZA $80.00 * 0.005000 $0.40 0.24%
SUBTOTAL: MATERIALES $1.84 1.11%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 1 JOR $1,709.62 * 0.055556 $94.98 57.07%
AYUDANTE)
CABO (%)mo $94.98 * 0.100000 $9.50 5.71%
CUADRILLA DE LIMPIEZA (%)mo $104.48 * 0.020000 $2.09 1.26%
MATERIALES
MASILLA FINA PERDURA SACO 40 KG BULTO $94.73 * 0.025000 $2.37 3.59% 0.125
AGUA M3 $80.00 * 0.005000 $0.40 0.61%
SELLADOR 5x1 LTS $50.00 * 0.008333 $0.42 0.63% 0.041667
RODILLO PZA $80.00 * 0.005000 $0.40 0.61%
PERFIL TUBULAR PZA $250.00 * 0.016667 $4.17 6.31% 0.333333333
SUBTOTAL: MATERIALES $7.75 11.74%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.025000 $39.19 59.35%
AYUDANTE) 40
CABO (%)mo $39.19 * 0.100000 $3.92 5.94%
ELEVACIONES (%)mo $43.11 * 0.050000 $2.16 3.26%
ACARREOS HORIZONTALES (%)mo $43.11 * 0.050000 $2.16 3.26%
CUADRILLA DE LIMPIEZA (%)mo $43.11 * 0.020000 $0.86 1.31%
5 0.025
5 0.0083334
20 0.016666667
1 0.025
MATERIALES
MASILLA FINA PERDURA SACO 40 KG BULTO $94.73 * 0.041667 $3.95 3.89% 0.125
AGUA M3 $80.00 * 0.005000 $0.40 0.39%
SELLADOR 5x1 LTS $50.00 * 0.008333 $0.42 0.41% 0.041667
RODILLO PZA $80.00 * 0.005000 $0.40 0.39%
PERFIL TUBULAR PZA $250.00 * 0.016667 $4.17 4.10% 0.333333333
SUBTOTAL: MATERIALES $9.33 9.19%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.033333 $52.25 51.46%
AYUDANTE) 30
CABO (%)mo $52.25 * 0.100000 $5.23 5.15%
ELEVACIONES (%)mo $57.48 * 0.050000 $2.87 2.83%
ACARREOS HORIZONTALES (%)mo $57.48 * 0.050000 $2.87 2.83%
CUADRILLA DE LIMPIEZA (%)mo $57.48 * 0.020000 $1.15 1.13%
SUBTOTAL: MANO DE OBRA $64.37 63.40%
AUXILIAR MORTERO 1:4
MORTERO 1:1:4 M3 $1,803.66 * 0.004725 $8.52 8.39%
SUBTOTAL: AUXILIAR MORTERO 1:4 $8.52 8.39%
EQUIPO Y HERRAMIENTA
EQUIPO DE SEGURIDAD (%)mo $64.37 * 0.020000 $1.29 1.27%
HERRAMIENTA MENOR (%)mo $64.37 * 0.030000 $1.93 1.90%
ANDAMIOS (%)mo $64.37 * 0.250000 $16.09 15.85%
SUBTOTAL: EQUIPO Y HERRAMIENTA $19.31 19.02%
(CD) Costo directo $101.54 100.00%
(CI) INDIRECTOS 10.0000% $10.15
SUBTOTAL1 $111.69
(CF) FINANCIAMIENTO 0.0000% $0.00
SUBTOTAL2 $111.69
(CU) UTILIDAD 8.0000% $8.12
PRECIO UNITARIO (CD+CI+CF+CU+IVA MATERIALES) $119.81
16% IVA MATERIALES
TOTAL $119.81
0.3
3 0.041666667
5 0.0083334
20 0.016666667
1 0.033333333
MATERIALES
MASILLA FINA PERDURA SACO 40 KG BULTO $94.73 * 0.031250 $2.96 8.78% 0.125
AGUA M3 $80.00 * 0.005000 $0.40 1.19%
SELLADOR 5x1 LTS $50.00 * 0.010417 $0.52 1.54% 0.041667
RODILLO PZA $80.00 * 0.005000 $0.40 1.19%
SUBTOTAL: MATERIALES $4.28 12.70%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.012500 $19.59 58.11%
AYUDANTE) 80
CABO (%)mo $19.59 * 0.100000 $1.96 5.81%
ELEVACIONES (%)mo $21.55 * 0.050000 0.00%
ACARREOS HORIZONTALES (%)mo $21.55 * 0.050000 $1.08 3.20%
CUADRILLA DE LIMPIEZA (%)mo $21.55 * 0.020000 $0.43 1.28%
4 0.03125
4 0.01041675
1 0.0125
1 0.015 1.05 0
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.033333 $52.25 77.70%
AYUDANTE) 30
CABO (%)mo $52.25 * 0.100000 $5.23 7.77%
ELEVACIONES (%)mo $57.48 * 0.050000 0.00%
ACARREOS HORIZONTALES (%)mo $57.48 * 0.050000 $2.87 4.27%
CUADRILLA DE LIMPIEZA (%)mo $57.48 * 0.020000 $1.15 1.71%
1 0.033333333
MATERIALES
PERFATRIM FLEXIBLE CORNER TAPE DE 2" ML $7.60 * 2.200000 $16.72 15.84%
30.50 M.
CINTA DE REFUERZO PERFACINTA ROLLO ML $0.51 * 1.100000 $0.56 0.53%
75 MTS
REDIMIX COMPUESTO MULTIUSOS 25KG KG $6.23 * 1.500000 $9.35 8.85%
SUBTOTAL: MATERIALES $26.63 25.23%
MANO DE OBRA
CUADRILLA NO. 102 (1 OF. JOR $1,709.62 * 0.016129 $27.57 26.13%
TABLAROQUERO + 1 AYUDANTE) 62
OF. CALEFATERO JOR $1,044.12 * 0.033333 $34.80 32.98% 30
CABO (%)mo $62.38 * 0.100000 $6.24 5.91%
ELEVACIONES (%)mo $33.81 * 0.050000 $1.69 1.60%
ACARREOS HORIZONTALES (%)mo $33.81 * 0.050000 $1.69 1.60%
CUADRILLA DE LIMPIEZA (%)mo $33.81 * 0.020000 $0.68 0.64%
1 0.016129032
1 0.033333333
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 1 JOR $1,709.62 * 0.020000 $34.19 74.52%
AYUDANTE) 50
CABO (%)mo $34.19 * 0.100000 $3.42 7.45%
ELEVACIONES (%)mo $37.61 * 0.050000 0.00%
ACARREOS HORIZONTALES (%)mo $37.61 * 0.050000 $1.88 4.10%
CUADRILLA DE LIMPIEZA (%)mo $37.61 * 0.020000 $0.75 1.64%
1 0.02
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.020000 $31.35 44.60%
AYUDANTE) 50
CABO (%)mo $31.35 * 0.100000 $3.14 4.46%
ELEVACIONES (%)mo $34.49 * 0.050000 $1.72 2.45%
ACARREOS HORIZONTALES (%)mo $34.49 * 0.050000 $1.72 2.45%
CUADRILLA DE LIMPIEZA (%)mo $34.49 * 0.020000 $0.69 0.98%
TOTAL $82.95
1 0.02
MATERIALES
PIEDRA MAYA M2 $230.00 * 1.100000 $253.00 47.91%
AGUA M3 $160.00 * 0.050000 $8.00 1.51%
SASCAB M3 $320.00 * 0.050000 $16.00 3.03%
1 0.119360434
7.55 3 22.65
1359.87638
1,034.08
MATERIALES
MARTELINA DE RODILLOS PZA $6,724.13 * 0.002000 $13.45 25.42% 6724.137931
TOTAL $62.43
1 0.016666667
7.55 3 22.65
1359.87638
1,034.08
MATERIALES
PIEDRA MAYA M2 $230.00 * 1.100000 $253.00 45.93%
AGUA M3 $160.00 * 0.050000 $8.00 1.45%
SASCAB M3 $320.00 * 0.050000 $16.00 2.90%
1 0.098359467
1 0.0125
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. COLOCADOR + 1 JOR $1,709.62 * 0.250000 $427.41 63.12%
AYUDANTE) 4
CABO (%)mo $427.41 * 0.100000 $42.74 6.31%
ELEVACIONES (%)mo $470.15 * 0.050000 $23.51 3.47%
ACARREOS HORIZONTALES (%)mo $470.15 * 0.050000 $23.51 3.47%
CUADRILLA DE LIMPIEZA (%)mo $470.15 * 0.020000 $9.40 1.39%
1 0.25
1 0.033333333
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. COLOCADOR + 1 JOR $1,576.50 * 0.250000 $394.13 58.20%
AYUDANTE) 4
CABO (%)mo $394.13 * 0.100000 $39.41 5.82%
ELEVACIONES (%)mo $433.54 * 0.050000 $21.68 3.20%
ACARREOS HORIZONTALES (%)mo $433.54 * 0.050000 $21.68 3.20%
CUADRILLA DE LIMPIEZA (%)mo $433.54 * 0.020000 $8.67 1.28%
TOTAL $799.02
1 0.25
1 0.033333333
MATERIALES
ADHESIVO FLEXIBLE GRIS BULTO $380.00 * 0.800000 $304.00 36.60%
CLAVO GALVANIZADO DE 2" KG $40.00 * 0.140000 $5.60 0.67%
ALAMBRE GALVANIZADO KG $90.00 * 0.050000 $4.50 0.54%
SUBTOTAL: MATERIALES $314.10 37.82%
MANO DE OBRA 5.882352941
CUADRILLA NO. 2 (1 OF. COLOCADOR + 1 JOR $1,709.62 * 0.146971 $251.27 30.25%
AYUDANTE) 0.147058824 4
CABO (%)mo $251.27 * 0.100000 $25.13 3.03%
ELEVACIONES (%)mo $276.39 * 0.050000 $13.82 1.66%
ACARREOS HORIZONTALES (%)mo $276.39 * 0.050000 $13.82 1.66%
CUADRILLA DE LIMPIEZA (%)mo $276.39 * 0.020000 $5.53 0.67%
1 0.25
1 0.033333333
MATERIALES
PSP BULTO $160.00 * 1.000000 $160.00 5.82%
COPA DE DESBASTE 120 EN 4" PZA $320.00 * 0.100000 $32.00 1.16%
COPA DE DESBASTE 60 EN 4" PZA $320.00 * 0.166700 $53.34 1.94%
COPA CHALAT 4" PZA $320.00 * 0.166700 $53.34 1.94%
ACIDO LTS $20.00 * 0.200000 $4.00 0.15%
DISCO ESSY CUT DE DIAMANTE 4" PZA $450.00 * 0.100000 $45.00 1.64%
SUBTOTAL: MATERIALES $347.69 12.65%
MANO DE OBRA
CUADRILLA NO. 1 (1 OF. HABILITADOR + 1 JOR $1,709.62 * 0.666667 $1139.75 41.47%
AYUDANTE)
CUADRILLA NO. 2 (1 OF. COLOCADOR + 1 JOR $1,709.62 * 0.333333 $569.87 20.74%
AYUDANTE)
CABO (%)mo $1,709.62 * 0.100000 $170.96 6.22%
ELEVACIONES (%)mo $1,709.62 * 0.050000 $85.48 3.11%
ACARREOS HORIZONTALES (%)mo $1,709.62 * 0.050000 $85.48 3.11%
CUADRILLA DE LIMPIEZA (%)mo $1,709.62 * 0.020000 $34.19 1.24%
TOTAL $3,243.02
Página 138 de 1
MATERIALES
POSTE EXTENSION PARA PINTURA 4 - 8 PZA $366.37 * 0.002000 $0.73 2.00%
FELPA POLIESTIRENO DE 22.86 CMS PZA $30.17 * 0.005000 $0.15 0.41%
MANERAL PARA RODILLO 23 CMS PZA $56.03 * 0.002000 $0.11 0.31%
BROCHA DE 4 " PZA $52.58 * 0.002000 $0.11 0.29%
PLATICO CAL 600 M2 $6.26 * 0.020000 $0.13 0.34%
SUBTOTAL: MATERIALES $1.23 3.35%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. PINTOR + 1 JOR $1,567.50 * 0.016667 $26.13 71.32%
AYUDANTE)
CABO (%)mo $26.13 * 0.100000 $2.61 7.13%
ELEVACIONES (%)mo $28.74 * 0.050000 $1.44 3.92%
ACARREOS HORIZONTALES (%)mo $28.74 * 0.050000 $1.44 3.92%
CUADRILLA DE LIMPIEZA (%)mo $28.74 * 0.020000 $0.57 1.57%
MATERIALES
PINTURA VINILCA MCA. SHERWIN LT $55.26 * 0.250000 $13.82 16.79%
WILLIANS
SELLADOR VINILICO (CUBETA DE 19 LTS) LT $49.46 * 0.041660 $2.06 2.50%
POSTE EXTENSION PARA PINTURA 4 - 8 PZA $366.37 * 0.002000 $0.73 0.89%
FELPA POLIESTIRENO DE 22.86 CMS PZA $30.17 * 0.005000 $0.15 0.18%
MANERAL PARA RODILLO 23 CMS PZA $56.03 * 0.002000 $0.11 0.14%
BROCHA DE 4 " PZA $52.58 * 0.002000 $0.11 0.13%
PLATICO CAL 600 M2 $6.26 * 0.020000 $0.13 0.15%
SUBTOTAL: MATERIALES $17.10 20.78%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. PINTOR + 1 JOR $1,567.50 * 0.025000 $39.19 47.63%
AYUDANTE) 40.00
CABO (%)mo $39.19 * 0.100000 $3.92 4.76%
ELEVACIONES (%)mo $43.11 * 0.050000 $2.16 2.62%
ACARREOS HORIZONTALES (%)mo $43.11 * 0.050000 $2.16 2.62%
CUADRILLA DE LIMPIEZA (%)mo $43.11 * 0.020000 $0.86 1.05%
MATERIALES
CEMENTO GRIS SACO DE 50KG TON $3,380.00 * 0.360500 $1218.49 67.56% 350
ARENA M3 $250.00 * 1.150000 $287.50 15.94%
AGUA M3 $80.00 * 0.185000 $14.80 0.82%
0.00%
SUBTOTAL: MATERIALES $1520.79 84.32%
MANO DE OBRA
CUADRILLA NO. 7 (1 OF. ALBAÑIL + 3 JOR $2,375.12 * 0.083000 $197.13 10.93%
AYUDANTE)
CABO (%)mo $197.13 * 0.100000 $19.71 1.09%
ACARREOS HORIZONTALES (%)mo $216.85 * 0.050000 $10.84 0.60%
CUADRILLA DE LIMPIEZA (%)mo $216.85 * 0.020000 $4.34 0.24%
0.3605
MATERIALES
CEMENTO GRIS SACO DE 50KG TON $4,180.00 * 0.360000 $1504.80 61.06% 350
ARENA M3 $350.00 * 1.150000 $402.50 16.33%
AGUA M3 $30.00 * 0.260000 $7.80 0.32%
0.00%
SUBTOTAL: MATERIALES $1915.10 77.71%
MANO DE OBRA
CUADRILLA NO. 7 (1 OF. ALBAÑIL + 3 JOR $2,375.12 * 0.166667 $395.85 16.06%
AYUDANTE)
CABO (%)mo $395.85 * 0.100000 $39.59 1.61%
ACARREOS HORIZONTALES (%)mo $435.44 * 0.050000 $21.77 0.88%
CUADRILLA DE LIMPIEZA (%)mo $435.44 * 0.020000 $8.71 0.35%
0.3605
MATERIALES
CASETON DE POLIESTIRENO M3 $650.00 * 0.070000 $45.50 12.40%
MADERA TIPO TRIPLAY 1.22X2.44MTS PZA $385.00 * 0.250000 $96.25 26.23%
CLAVO 2" A 4" ESTANDAR PZA $20.00 * 0.200000 $4.00 1.09%
ALAMBRE RECOCIDO CAL. 16. KG $17.50 * 0.400000 $7.00 1.91%
POLIN DE 3AR PZA $30.00 * 0.200000 $6.00 1.64%
FESTERBOND LTS $119.10 * 0.250000 $29.78 8.11%
DESMOLDANTE LTS $21.00 * 0.220000 $4.62 1.26%
0.00%
SUBTOTAL: MATERIALES $193.15 52.63%
MANO DE OBRA
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.050000 $85.48 23.29%
AYUDANTE)
CUADRILLA NO. 3 (1 OF. ALBAÑIL + 1 JOR $1,709.62 * 0.033333 $56.99 15.53%
AYUDANTE)
CABO (%)mo $142.47 * 0.100000 $14.25 3.88%
ACARREOS HORIZONTALES (%)mo $142.47 * 0.020000 $2.85 0.78%
CUADRILLA DE LIMPIEZA (%)mo $142.47 * 0.050000 $7.12 1.94%
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.000000 $0.00 0.00%
AYUDANTE) COLADORES
ACARREOS HORIZONTALES (%)mo $0.00 * 0.050000 $0.00 0.00%
ANDAMIOS (%)mo $0.00 * 0.050000 $0.00 0.00%
TOTAL $266.72
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.014832 $23.25 27.72%
AYUDANTE) COLADORES 67.42
CABO (%)mo $23.25 * 0.100000 $2.32 2.77%
ACARREOS HORIZONTALES (%)mo $23.25 * 0.050000 $1.16 1.39%
ANDAMIOS (%)mo $23.25 * 0.050000 $1.16 1.39%
TOTAL $98.99
0.01483
1 1 1.03 0.0222
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.022248 $34.87 29.36%
AYUDANTE) COLADORES
CABO (%)mo $34.87 * 0.100000 $3.49 2.94%
ACARREOS HORIZONTALES (%)mo $34.87 * 0.050000 $1.74 1.47%
ANDAMIOS (%)mo $34.87 * 0.050000 $1.74 1.47%
TOTAL $140.16
0.063
0.02225
44.9479
1 1 1.03 0.0334
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.015450 $24.22 11.67%
AYUDANTE) COLADORES
CABO (%)mo $24.22 * 0.100000 $2.42 1.17%
ACARREOS HORIZONTALES (%)mo $24.22 * 0.050000 $1.21 0.58%
ANDAMIOS (%)mo $24.22 * 0.050000 $1.21 0.58%
TOTAL $244.93
0.01545
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.020600 $32.29 12.59%
AYUDANTE) COLADORES
CABO (%)mo $32.29 * 0.100000 $3.23 1.26%
ACARREOS HORIZONTALES (%)mo $32.29 * 0.050000 $1.61 0.63%
ANDAMIOS (%)mo $32.29 * 0.050000 $1.61 0.63%
TOTAL $302.72
0.0206
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.041200 $64.58 11.82%
AYUDANTE) COLADORES
CABO (%)mo $64.58 * 0.100000 $6.46 1.18%
ACARREOS HORIZONTALES (%)mo $64.58 * 0.050000 $3.23 0.59%
ANDAMIOS (%)mo $64.58 * 0.050000 $3.23 0.59%
TOTAL $644.85
0.0412
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.027467 $43.05 12.52%
AYUDANTE) COLADORES
CABO (%)mo $43.05 * 0.100000 $4.31 1.25%
ACARREOS HORIZONTALES (%)mo $43.05 * 0.050000 $2.15 0.63%
ANDAMIOS (%)mo $43.05 * 0.050000 $2.15 0.63%
TOTAL $405.69
0.02747
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.061800 $96.87 10.80%
AYUDANTE) COLADORES
CABO (%)mo $96.87 * 0.100000 $9.69 1.08%
ACARREOS HORIZONTALES (%)mo $96.87 * 0.050000 $4.84 0.54%
ANDAMIOS (%)mo $96.87 * 0.050000 $4.84 0.54%
TOTAL $1,076.58
0.0618
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.085833 $134.54 11.91%
AYUDANTE) COLADORES
CABO (%)mo $134.54 * 0.100000 $13.45 1.19%
ACARREOS HORIZONTALES (%)mo $134.54 * 0.050000 $6.73 0.60%
ANDAMIOS (%)mo $134.54 * 0.050000 $6.73 0.60%
TOTAL $1,333.09
0.08583
1 1 1.03 0.1288
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.030900 $48.44 12.63%
AYUDANTE) COLADORES
CABO (%)mo $48.44 * 0.100000 $4.84 1.26%
ACARREOS HORIZONTALES (%)mo $48.44 * 0.050000 $2.42 0.63%
ANDAMIOS (%)mo $48.44 * 0.050000 $2.42 0.63%
TOTAL $452.61
0.0309
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.054933 $86.11 12.74%
AYUDANTE) COLADORES
CABO (%)mo $86.11 * 0.100000 $8.61 1.27%
ACARREOS HORIZONTALES (%)mo $86.11 * 0.050000 $4.31 0.64%
ANDAMIOS (%)mo $86.11 * 0.050000 $4.31 0.64%
TOTAL $797.27
0.05493
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.085833 $134.54 14.59%
AYUDANTE) COLADORES
CABO (%)mo $134.54 * 0.100000 $13.45 1.46%
ACARREOS HORIZONTALES (%)mo $134.54 * 0.050000 $6.73 0.73%
ANDAMIOS (%)mo $134.54 * 0.050000 $6.73 0.73%
TOTAL $1,088.42
0.08583
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.089267 $139.93 12.72%
AYUDANTE) COLADORES
CABO (%)mo $139.93 * 0.100000 $13.99 1.27%
ACARREOS HORIZONTALES (%)mo $139.93 * 0.050000 $7.00 0.64%
ANDAMIOS (%)mo $139.93 * 0.050000 $7.00 0.64%
TOTAL $1,297.91
0.08927
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.096133 $150.69 13.08%
AYUDANTE) COLADORES
CABO (%)mo $150.69 * 0.100000 $15.07 1.31%
ACARREOS HORIZONTALES (%)mo $150.69 * 0.050000 $7.53 0.65%
ANDAMIOS (%)mo $150.69 * 0.050000 $7.53 0.65%
TOTAL $1,359.14
0.09613
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.030900 $48.44 11.43%
AYUDANTE) COLADORES
CABO (%)mo $48.44 * 0.100000 $4.84 1.14%
ACARREOS HORIZONTALES (%)mo $48.44 * 0.050000 $2.42 0.57%
ANDAMIOS (%)mo $48.44 * 0.050000 $2.42 0.57%
TOTAL $500.02
0.0309
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.068667 $107.64 14.18%
AYUDANTE) COLADORES
CABO (%)mo $107.64 * 0.100000 $10.76 1.42%
ACARREOS HORIZONTALES (%)mo $107.64 * 0.050000 $5.38 0.71%
ANDAMIOS (%)mo $107.64 * 0.050000 $5.38 0.71%
TOTAL $895.48
0.06867
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.030900 $48.44 12.70%
AYUDANTE) COLADORES
CABO (%)mo $48.44 * 0.100000 $4.84 1.27%
ACARREOS HORIZONTALES (%)mo $48.44 * 0.050000 $2.42 0.64%
ANDAMIOS (%)mo $48.44 * 0.050000 $2.42 0.64%
TOTAL $449.91
0.0309
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.126347 $198.05 12.29%
AYUDANTE) COLADORES
CABO (%)mo $198.05 * 0.100000 $19.80 1.23%
ACARREOS HORIZONTALES (%)mo $198.05 * 0.050000 $9.90 0.61%
ANDAMIOS (%)mo $198.05 * 0.050000 $9.90 0.61%
TOTAL $1,901.26
0.12635
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.082400 $131.84 13.13%
AYUDANTE) COLADORES
CABO (%)mo $131.84 * 0.100000 $13.18 1.31%
ACARREOS HORIZONTALES (%)mo $131.84 * 0.050000 $6.59 0.66%
ANDAMIOS (%)mo $131.84 * 0.050000 $6.59 0.66%
TOTAL $1,185.13
0.0824
1 0 0.996 0 0
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.082400 $131.84 12.36%
AYUDANTE) COLADORES
CABO (%)mo $131.84 * 0.100000 $13.18 1.24%
ACARREOS HORIZONTALES (%)mo $131.84 * 0.050000 $6.59 0.62%
ANDAMIOS (%)mo $131.84 * 0.050000 $6.59 0.62%
TOTAL $1,258.58
0.0824
1 4 2.25 9 9.45
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.041200 $65.92 10.53%
AYUDANTE) COLADORES
CABO (%)mo $65.92 * 0.100000 $6.59 1.05%
ACARREOS HORIZONTALES (%)mo $65.92 * 0.050000 $3.30 0.53%
ANDAMIOS (%)mo $65.92 * 0.050000 $3.30 0.53%
TOTAL $738.83
0.0412
1 1 1.03 0.0618
1 1 1.03 1.1639
1 0 2.25 0 0
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.038453 $61.52 10.23%
AYUDANTE) COLADORES
CABO (%)mo $61.52 * 0.100000 $6.15 1.02%
ACARREOS HORIZONTALES (%)mo $61.52 * 0.050000 $3.08 0.51%
ANDAMIOS (%)mo $61.52 * 0.050000 $3.08 0.51%
TOTAL $709.66
0.03845
1 1 1.03 0.0577
1 1 1.03 1.1124
1 0 2.25 0 0
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.049715 $79.54 11.68%
AYUDANTE) COLADORES
CABO (%)mo $79.54 * 0.100000 $7.95 1.17%
ACARREOS HORIZONTALES (%)mo $79.54 * 0.050000 $3.98 0.58%
ANDAMIOS (%)mo $79.54 * 0.050000 $3.98 0.58%
TOTAL $803.63
0.04971
1 1 1.03 0.0746
1 1 1.03 1.03
1 0 2.25 0 0
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.096133 $153.81 12.96%
AYUDANTE) COLADORES
CABO (%)mo $153.81 * 0.100000 $15.38 1.30%
ACARREOS HORIZONTALES (%)mo $153.81 * 0.050000 $7.69 0.65%
ANDAMIOS (%)mo $153.81 * 0.050000 $7.69 0.65%
TOTAL $1,400.25
0.09613
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.061800 $98.88 13.20%
AYUDANTE) COLADORES
CABO (%)mo $98.88 * 0.100000 $9.89 1.32%
ACARREOS HORIZONTALES (%)mo $98.88 * 0.050000 $4.94 0.66%
ANDAMIOS (%)mo $98.88 * 0.050000 $4.94 0.66%
TOTAL $883.62
0.0618
1 0 1.56 0 0
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.212180 $339.49 12.46%
AYUDANTE) COLADORES
CABO (%)mo $339.49 * 0.100000 $33.95 1.25%
ACARREOS HORIZONTALES (%)mo $339.49 * 0.050000 $16.97 0.62%
ANDAMIOS (%)mo $339.49 * 0.050000 $16.97 0.62%
TOTAL $3,214.70
0.21218
1 1 1.03 0.3183
1 0 1.56 0 0
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.151067 $241.71 12.47%
AYUDANTE) COLADORES
CABO (%)mo $241.71 * 0.100000 $24.17 1.25%
ACARREOS HORIZONTALES (%)mo $241.71 * 0.050000 $12.09 0.62%
ANDAMIOS (%)mo $241.71 * 0.050000 $12.09 0.62%
TOTAL $2,286.70
0.15107
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.192267 $307.62 12.01%
AYUDANTE) COLADORES
CABO (%)mo $307.62 * 0.100000 $30.76 1.20%
ACARREOS HORIZONTALES (%)mo $307.62 * 0.050000 $15.38 0.60%
ANDAMIOS (%)mo $307.62 * 0.050000 $15.38 0.60%
TOTAL $3,022.71
0.19227
1 0 1.56 0 0
1 12 2.25 27 28.35
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.116733 $186.77 12.15%
AYUDANTE) COLADORES
CABO (%)mo $186.77 * 0.100000 $18.68 1.22%
ACARREOS HORIZONTALES (%)mo $186.77 * 0.050000 $9.34 0.61%
ANDAMIOS (%)mo $186.77 * 0.050000 $9.34 0.61%
TOTAL $1,813.40
0.11673
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.075533 $120.85 12.55%
AYUDANTE) COLADORES
CABO (%)mo $120.85 * 0.100000 $12.09 1.26%
ACARREOS HORIZONTALES (%)mo $120.85 * 0.050000 $6.04 0.63%
ANDAMIOS (%)mo $120.85 * 0.050000 $6.04 0.63%
TOTAL $1,136.08
0.07553
1 0 1.56 0 0
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.103000 $164.80 13.71%
AYUDANTE) COLADORES
CABO (%)mo $164.80 * 0.100000 $16.48 1.37%
ACARREOS HORIZONTALES (%)mo $164.80 * 0.050000 $8.24 0.69%
ANDAMIOS (%)mo $164.80 * 0.050000 $8.24 0.69%
TOTAL $1,418.45
0.103
1 0 1.56 0 0
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.077250 $123.60 12.01%
AYUDANTE) COLADORES
CABO (%)mo $123.60 * 0.100000 $12.36 1.20%
ACARREOS HORIZONTALES (%)mo $123.60 * 0.050000 $6.18 0.60%
ANDAMIOS (%)mo $123.60 * 0.050000 $6.18 0.60%
TOTAL $1,214.16
0.07725
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.109867 $175.79 13.19%
AYUDANTE) COLADORES
CABO (%)mo $175.79 * 0.100000 $17.58 1.32%
ACARREOS HORIZONTALES (%)mo $175.79 * 0.050000 $8.79 0.66%
ANDAMIOS (%)mo $175.79 * 0.050000 $8.79 0.66%
TOTAL $1,572.33
0.10987
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.030900 $49.44 13.47%
AYUDANTE) COLADORES
CABO (%)mo $49.44 * 0.100000 $4.94 1.35%
ACARREOS HORIZONTALES (%)mo $49.44 * 0.050000 $2.47 0.67%
ANDAMIOS (%)mo $49.44 * 0.050000 $2.47 0.67%
TOTAL $432.95
0.0309
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.027467 $43.95 15.51%
AYUDANTE) COLADORES
CABO (%)mo $43.95 * 0.100000 $4.39 1.55%
ACARREOS HORIZONTALES (%)mo $43.95 * 0.050000 $2.20 0.78%
ANDAMIOS (%)mo $43.95 * 0.050000 $2.20 0.78%
TOTAL $334.32
0.02747
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.041200 $65.92 15.73%
AYUDANTE) COLADORES
CABO (%)mo $65.92 * 0.100000 $6.59 1.57%
ACARREOS HORIZONTALES (%)mo $65.92 * 0.050000 $3.30 0.79%
ANDAMIOS (%)mo $65.92 * 0.050000 $3.30 0.79%
TOTAL $494.53
0.0412
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.054933 $87.89 15.01%
AYUDANTE) COLADORES
CABO (%)mo $87.89 * 0.100000 $8.79 1.50%
ACARREOS HORIZONTALES (%)mo $87.89 * 0.050000 $4.39 0.75%
ANDAMIOS (%)mo $87.89 * 0.050000 $4.39 0.75%
TOTAL $691.02
0.05493
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.020600 $32.96 13.32%
AYUDANTE) COLADORES
CABO (%)mo $32.96 * 0.100000 $3.30 1.33%
ACARREOS HORIZONTALES (%)mo $32.96 * 0.050000 $1.65 0.67%
ANDAMIOS (%)mo $32.96 * 0.050000 $1.65 0.67%
TOTAL $291.91
0.0206
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.020600 $32.96 10.95%
AYUDANTE) COLADORES
CABO (%)mo $32.96 * 0.100000 $3.30 1.10%
ACARREOS HORIZONTALES (%)mo $32.96 * 0.050000 $1.65 0.55%
ANDAMIOS (%)mo $32.96 * 0.050000 $1.65 0.55%
TOTAL $355.16
0.0206
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.041200 $65.92 15.00%
AYUDANTE) COLADORES
CABO (%)mo $65.92 * 0.100000 $6.59 1.50%
ACARREOS HORIZONTALES (%)mo $65.92 * 0.050000 $3.30 0.75%
ANDAMIOS (%)mo $65.92 * 0.050000 $3.30 0.75%
TOTAL $518.41
0.0412
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.041200 $65.92 14.31%
AYUDANTE) COLADORES
TOTAL $543.70
0.0412
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.027467 $43.05 14.91%
AYUDANTE) COLADORES
ACARREOS HORIZONTALES (%)mo $43.05 * 0.050000 $2.15 0.75%
ANDAMIOS (%)mo $43.05 * 0.050000 $2.15 0.75%
TOTAL $340.84
0.02747
2726.72
1626.72
2200
528
7081.44
1770.36
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.054933 $87.89 15.03%
AYUDANTE) COLADORES
ACARREOS HORIZONTALES (%)mo $87.89 * 0.050000 $4.39 0.75%
ANDAMIOS (%)mo $87.89 * 0.050000 $4.39 0.75%
TOTAL $689.86
0.05493
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.082400 $131.84 20.09%
AYUDANTE) COLADORES
ACARREOS HORIZONTALES (%)mo $131.84 * 0.050000 $6.59 1.00%
ANDAMIOS (%)mo $131.84 * 0.050000 $6.59 1.00%
1660.46
830.23
0.0824
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.054933 $87.89 15.65%
AYUDANTE) COLADORES
ACARREOS HORIZONTALES (%)mo $87.89 * 0.050000 $4.39 0.78%
ANDAMIOS (%)mo $87.89 * 0.050000 $4.39 0.78%
1660.46
830.23
0.05493
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.027467 $43.05 12.87%
AYUDANTE) COLADORES
ACARREOS HORIZONTALES (%)mo $43.05 * 0.050000 $2.15 0.64%
ANDAMIOS (%)mo $43.05 * 0.050000 $2.15 0.64%
TOTAL $394.87
1819.84
0.02747
3158.92
1626.72
2200
528
7513.64
1878.41
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.027467 $43.05 14.11%
AYUDANTE) COLADORES
ACARREOS HORIZONTALES (%)mo $43.05 * 0.050000 $2.15 0.71%
ANDAMIOS (%)mo $43.05 * 0.050000 $2.15 0.71%
TOTAL $360.05
1819.84
0.02747
2880.42
1626.72
2200
528
7235.14
1808.79
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.027467 $43.95 14.02%
AYUDANTE) COLADORES
ACARREOS HORIZONTALES (%)mo $43.95 * 0.050000 $2.20 0.70%
ANDAMIOS (%)mo $43.95 * 0.050000 $2.20 0.70%
TOTAL $369.87
0.02747
2958.93
1626.72
2200
528
7313.65
1828.41
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.041200 $65.92 15.17%
AYUDANTE) COLADORES
TOTAL $512.74
0.0412
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.020600 $32.96 12.82%
AYUDANTE) COLADORES
CABO (%)mo $32.96 * 0.100000 $3.30 1.28%
ACARREOS HORIZONTALES (%)mo $32.96 * 0.050000 $1.65 0.64%
ANDAMIOS (%)mo $32.96 * 0.050000 $1.65 0.64%
TOTAL $303.32
0.0206
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.099910 $159.86 13.34%
AYUDANTE) COLADORES
CABO (%)mo $159.86 * 0.100000 $15.99 1.33%
ACARREOS HORIZONTALES (%)mo $159.86 * 0.050000 $7.99 0.67%
ANDAMIOS (%)mo $159.86 * 0.050000 $7.99 0.67%
TOTAL $1,414.52
0.09991
1 1 1.03 0.1499
DEMOLICIONES
DEMOLICIÓN DE PLANTILLA DE CONCRETO FC=100KG/CM2 5
CM DE ESPESOR POR MEDIO DE ROMPERDORA ELECTRICA
DE 20GK, INCLUYE: MANO DE OBRA, ACARREOS A 50 MTS
DENTRO DE LA OBRA, HERRAMIENTA MENOR, EQUIPO, M2 $ 114.18
LIMPIEZA Y TODO LO NECESARIO PARA SU CORRECTA
EJECUCIÓN.
ESTRUCTURA
ACEROS
HABILITADO Y ARMADO DE ACERO DE REFUERZO DEL N°2
(1/4”) FY=4200KG/CM2, INCLUYE: HABILITADO, COLOCADO,
MANO DE OBRA, MATERIAL, ACARREOS, ELEVACIÓN,
CORTES, GANCHOS, TRASLAPES, HERRAMIENTA MENOR, KG $ 31.16
EQUIPO, LIMPIEZA Y TODO LO NECESARIO PARA SU
CORRECTA EJECUCIÓN.
HABILITADO Y ARMADO DE ACERO DE REFUERZO DEL N°3, 4,
5, 6, 8 FY=4200KG/CM2, INCLUYE: HABILITADO, COLOCADO,
MANO DE OBRA, MATERIAL, ACARREOS, ELEVACIÓN,
CORTES, GANCHOS, TRASLAPES, HERRAMIENTA MENOR, KG $ 28.30
EQUIPO, LIMPIEZA Y TODO LO NECESARIO PARA SU
CORRECTA EJECUCIÓN.
CONCRETOS PREMEZCLADOS
CONCRETO f'c= 100 kg/cm2 rev. 14, BOMBEABLE resistencia
normal a 28 días INCLUYE: SUMINISTRO DE MATERIAL. M3 $ 1,564.86
xxxxxx
CIMBRA
CIMBRA ACABADO COMUN DE 16MM EN CASTILLOS,
CADENAS, CERRAMIENTOS, INCLUYE: CIMBRA Y DESCIMBRA,
MANO DE OBRA, ACARREOS, HERRAMIENTA MENOR, M2 $ 205.73
EQUIPO, LIMPIEZA Y TODO LO NECESARIO PARA SU
CORRECTA EJECUCIÓN.
ALBAÑILERIA
MUROS
ALBERCAS
ALBERCA O2
ESPEJO DE AGUA 06
ESPEJO DE AGUA 01
$ 260.94
5.45 3.97 21.6365
Página 272 de 1
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.061800 $96.87 8.18%
AYUDANTE) COLADORES
ACARREOS HORIZONTALES (%)mo $96.87 * 0.050000 $4.84 0.41%
ANDAMIOS (%)mo $96.87 * 0.050000 $4.84 0.41%
6
SUBTOTAL: AUXILIAR $1070.99 90.46%
(CD) Costo directo $1,183.94 100.00%
(CI) INDIRECTOS 10.0000% $118.39
SUBTOTAL1 $1,302.34
(CF) FINANCIAMIENTO 0.0000% $0.00
SUBTOTAL2 $1,302.34
(CU) UTILIDAD 8.0000% $94.72
PRECIO UNITARIO (CD+CI+CF+CU+IVA MATERIALES) $1,397.05
TOTAL $1,397.05
0.0618
0.0927
0.3 1 1.03 0.0618
0.2 1 1.03 0.0309
11176.4
1626.72
2200
528
15531.1
3882.78
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.041200 $65.92 10.59%
AYUDANTE) COLADORES
CABO (%)mo $65.92 * 0.100000 $6.59 1.06%
ACARREOS HORIZONTALES (%)mo $65.92 * 0.050000 $3.30 0.53%
ANDAMIOS (%)mo $65.92 * 0.050000 $3.30 0.53%
TOTAL $734.68
0.0412
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.274667 $439.46 16.35%
AYUDANTE) COLADORES
CABO (%)mo $439.46 * 0.100000 $43.95 1.63%
ACARREOS HORIZONTALES (%)mo $439.46 * 0.050000 $21.97 0.82%
ANDAMIOS (%)mo $439.46 * 0.050000 $21.97 0.82%
TOTAL $3,171.88
0.27467
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.012360 $19.78 2.54%
AYUDANTE) COLADORES
CABO (%)mo $19.78 * 0.100000 $1.98 0.25%
ACARREOS HORIZONTALES (%)mo $19.78 * 0.050000 $0.99 0.13%
ANDAMIOS (%)mo $19.78 * 0.050000 $0.99 0.13%
TOTAL $917.20
0.01236
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.137333 $219.73 13.35%
AYUDANTE) COLADORES
CABO (%)mo $219.73 * 0.100000 $21.97 1.33%
ACARREOS HORIZONTALES (%)mo $219.73 * 0.050000 $10.99 0.67%
ANDAMIOS (%)mo $219.73 * 0.050000 $10.99 0.67%
TOTAL $1,942.92
0.13733
1 1 1.03 0.206
1 1 1.03 2.06
13.2384
1 2 0.996 1.992 2.0916
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.144200 $230.72 13.45%
AYUDANTE) COLADORES
CABO (%)mo $230.72 * 0.100000 $23.07 1.35%
ACARREOS HORIZONTALES (%)mo $230.72 * 0.050000 $11.54 0.67%
ANDAMIOS (%)mo $230.72 * 0.050000 $11.54 0.67%
TOTAL $2,023.51
0.1442
11.592
1 3 0.996 2.988 3.1374
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.185400 $290.61 16.47%
AYUDANTE) COLADORES
CABO (%)mo $290.61 * 0.100000 $29.06 1.65%
ACARREOS HORIZONTALES (%)mo $290.61 * 0.050000 $14.53 0.82%
ANDAMIOS (%)mo $290.61 * 0.050000 $14.53 0.82%
TOTAL $2,082.45
0.1854
9.0048
1 8 1.56 12.48 13.104
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.030900 $49.44 15.35%
AYUDANTE) COLADORES
ACARREOS HORIZONTALES (%)mo $49.44 * 0.050000 $2.47 0.77%
ANDAMIOS (%)mo $49.44 * 0.050000 $2.47 0.77%
TOTAL $380.05
0.0309
3040.4
1626.72
2200
528
7395.12
1848.78
MATERIALES
SIKADUR 32 KG $585.34 * 0.500000 $292.67 89.71% 585.3448276
BROCHA DE 4" PZA $62.06 * 0.050000 $3.10 0.95%
0.00% 62.06896552
SUBTOTAL: MATERIALES $295.77 90.66%
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.016667 $26.13 8.01%
AYUDANTE) COLADORES
ACARREOS HORIZONTALES (%)mo $26.13 * 0.050000 $1.31 0.40%
ANDAMIOS (%)mo $26.13 * 0.050000 $1.31 0.40%
TOTAL $391.48
#REF!
3131.85
1626.72
2200
528
7486.57
1871.64
MATERIALES
BOVEDILLA DE POLIESTIRENO PZA $82.81 * 1.500000 $124.22 14.92%
1.23X0.63X0.15CM 0.7503
VIGUETA 12-5 ML $57.00 * 2.500000 $142.50 17.12%
POLIN PZA $61.00 * 1.000000 $61.00 7.33%
MALLA ELECTROSOLDADA 6-6 10-10 ROLLO $1,475.00 * 0.010500 $15.49 1.86% 0.0105
ALAMBRE RECOCIDO KG $16.90 * 0.250000 $4.23 0.51%
CLAVO DE 2" P/CONCRETO KG $40.00 * 0.050000 $2.00 0.24%
0.00%
SUBTOTAL: MATERIALES $349.43 41.97%
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. CARPINTERO + 1 JOR $1,599.99 * 0.100000 $160.00 19.22%
AYUDANTE) $ 55,199.66
CUADRILLA NO. 6 (1 OF. FIERRERO + 1 JOR $1,599.99 * 0.006667 $10.67 1.28%
AYUDANTE)
CABO (%)mo $170.67 * 0.100000 $17.07 2.05%
ACARREOS HORIZONTALES (%)mo $170.67 * 0.100000 $17.07 2.05%
ANDAMIOS (%)mo $170.67 * 0.050000 $8.53 1.02%
1.332800213 1.399440224
1 1
0.0715
0.0715
2 1 2
MATERIALES
LAMINA ZINTRO R100 PZA $270.49 * 1.200000 $324.59 38.87%
POLIN PZA $61.00 * 0.250000 $15.25 1.83%
DISCO DE CORTE PZA $45.00 * 0.010000 $0.45 0.05%
MALLA ELECTROSOLDADA 6-6 10-10 ROLLO $1,475.00 * 0.010500 $15.49 1.85%
ALAMBRE RECOCIDO KG $16.90 * 0.250000 $4.23 0.51%
CLAVO DE 2" P/CONCRETO KG $40.00 * 0.050000 $2.00 0.24%
0.00%
SUBTOTAL: MATERIALES $362.00 43.35%
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. HERRERO + 1 JOR $1,599.99 * 0.066667 $106.67 12.77%
AYUDANTE)
CUADRILLA NO. 6 (1 OF. FIERRERO + 1 JOR $1,599.99 * 0.006667 $10.67 1.28%
AYUDANTE)
CUADRILLA NO. 7 (1 OF. CARPINTERO + 1 JOR $1,599.99 * 0.025000 $40.00 4.79%
AYUDANTE)
CABO (%)mo $146.67 * 0.100000 $14.67 1.76%
ACARREOS HORIZONTALES (%)mo $146.67 * 0.100000 $14.67 1.76%
ANDAMIOS (%)mo $146.67 * 0.050000 $7.33 0.88%
TOTAL $985.43
MATERIALES
BOVEDILLA DE CONCRETO 15 X 25 X 56 CM PZA $26.63 * 8.000000 $213.04 22.68%
0.7503
VIGUETA 12-5 ML $66.00 * 2.500000 $165.00 17.57%
POLIN PZA $61.00 * 1.000000 $61.00 6.49%
MALLA ELECTROSOLDADA 6-6 10-10 ROLLO $1,475.00 * 0.010500 $15.49 1.65% 0.0105
ALAMBRE RECOCIDO KG $16.90 * 0.250000 $4.23 0.45%
CLAVO DE 2" P/CONCRETO KG $40.00 * 0.050000 $2.00 0.21%
0.00%
SUBTOTAL: MATERIALES $460.75 49.05%
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.100000 $156.75 16.69%
AYUDANTE) $ 54,078.75
CUADRILLA NO. 6 (1 OF. FIERRERO + 1 JOR $1,567.50 * 0.006667 $10.45 1.11%
AYUDANTE) $ 150.00
CABO (%)mo $167.20 * 0.100000 $16.72 1.78%
ACARREOS HORIZONTALES (%)mo $167.20 * 0.100000 $16.72 1.78%
ANDAMIOS (%)mo $167.20 * 0.050000 $8.36 0.89%
1.332800213 1.399440224
1 1
0.0715
0.0715
2 1 2
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.020600 $32.96 12.97%
AYUDANTE) COLADORES
ACARREOS HORIZONTALES (%)mo $32.96 * 0.050000 $1.65 0.65%
ANDAMIOS (%)mo $32.96 * 0.050000 $1.65 0.65%
TOTAL $299.82
0.0206
1 0 0.996 0 0
2398.6
1626.72
2200
528
6753.32
1688.33
MATERIALES
SIKA ANCHORFIX 301 (600ML) PZA $1,340.08 * 0.055550 $74.44 14.95%
0.00%
SUBTOTAL: MATERIALES $74.44 14.95%
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.066669 $106.67 21.42%
AYUDANTE)
ACARREOS HORIZONTALES (%)mo $106.67 * 0.050000 $5.33 1.07%
ANDAMIOS (%)mo $106.67 * 0.050000 $5.33 1.07%
TOTAL $597.57
MATERIALES
GRAUT CONSTRUCTOR SACO DE 22KG BULTO $320.00 * 0.860000 $275.20 75.77%
AGUA M3 $80.00 * 0.005000 $0.40 0.11%
0.00%
SUBTOTAL: MATERIALES $275.60 75.88%
MANO DE OBRA
CUADRILLA NO. 3 (1 OF. ALBAÑIL + 1 JOR $1,709.62 * 0.040000 $68.38 18.83%
AYUDANTE)
CABO (%)mo $68.38 * 0.100000 $6.84 1.88%
ELEVACIONES (%)mo $68.38 * 0.050000 $3.42 0.94%
ACARREOS HORIZONTALES (%)mo $68.38 * 0.020000 $1.37 0.38%
CUADRILLA DE LIMPIEZA (%)mo $68.38 * 0.050000 $3.42 0.94%
TOTAL $428.58
MATERIALES
GRAUT CONSTRUCTOR SACO DE 22KG BULTO $320.00 * 0.500000 $160.00 57.13%
AGUA M3 $80.00 * 0.005000 $0.40 0.14%
TRIPLAY DE 19MM PZA $385.00 * 0.050000 $19.25 6.87% 0.101010101
SUBTOTAL: MATERIALES $179.65 64.15%
MANO DE OBRA
CUADRILLA NO. 3 (1 OF. ALBAÑIL + 1 JOR $1,567.50 * 0.050000 $78.38 27.99%
AYUDANTE) 20
CABO (%)mo $78.38 * 0.100000 $7.84 2.80%
ELEVACIONES (%)mo $78.38 * 0.050000 $3.92 1.40%
ACARREOS HORIZONTALES (%)mo $78.38 * 0.020000 $1.57 0.56%
CUADRILLA DE LIMPIEZA (%)mo $78.38 * 0.050000 $3.92 1.40%
TOTAL $330.46
MATERIALES
DECK DE CUMARU CALIDAD SELECTA DE M2 $760.50 * 1.100000 $836.55 51.55%
19 MM X 140MM DE ANCHO LARGOS DE 3 A
9 PIES.
0.673400673
TORNIBROCA 1 1/4" PZA $2.50 * 48.000000 $120.00 7.39% 0.673400673
RESANADOR PARA MADERA RESISTOL PZA $1.00 * 48.000000 $48.00 2.96%
875 DE 115 ML
RESISTOL 850 BLANCO 500 GR PZA $72.41 * 0.010000 $0.72 0.04% 14
DUELA DE MADERA DE CUMARU PARA M2 $650.00 * 0.300000 $195.00 12.02%
BASTIDOR 0.6
0.00% 14
SUBTOTAL: MATERIALES $1200.27 73.96% 0.6
MANO DE OBRA 14
CUADRILLA NO. 2 (1 OF. CARPINTERO + 1 JOR $1,709.62 * 0.200000 $341.92 21.07%
AYUDANTE) 0.6 5
CABO (%)mo $341.92 * 0.100000 $34.19 2.11% 14
ACARREOS HORIZONTALES (%)mo $376.12 * 0.020000 $7.52 0.46% 0.6
CUADRILLA DE LIMPIEZA (%)mo $376.12 * 0.050000 $18.81 1.16% 14
0.6
SUBTOTAL: MANO DE OBRA $402.44 24.80%
EQUIPO Y HERRAMIENTA
EQUIPO DE SEGURIDAD (%)mo $402.44 * 0.020000 $8.05 0.50%
HERRAMIENTA MENOR (%)mo $402.44 * 0.030000 $12.07 0.74%
0.3
2 1.5
0.125
0.5
4 0.168350168
4 0.168350168
1 0.2
MATERIALES
SIKA ANCHORFIX 301 (600ML) PZA $1,340.08 / 0.375000 $502.53 9.72%
VARILLA DEL #4 KG $14.60 14.356800 $209.61 4.06%
0.00%
SUBTOTAL: MATERIALES $712.14 13.78%
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.500000 $800.00 15.48%
AYUDANTE)
1 AYUDANTE JOR $675.00 * 0.500000 $337.50 6.53%
ACARREOS HORIZONTALES (%)mo $1,137.50 * 0.100000 $113.75 2.20%
ANDAMIOS (%)mo $1,137.50 * 0.050000 $56.87 1.10%
TOTAL $6,202.53
1 1
0.36225
0.36225
2 1 1.03 1.648
TOTAL $5,587.11
1 1
1 1 1.05 0.42
0.44625
0.44625
2 1 1.03 2.06
$ 592,731.75
1 1
0.280875
0.280875
2 1 1.03 1.442
TOTAL $2,639.49
1 1 1
0.2625
0.2625
$ 1,517,731.60
BASICOS
TRAZO Y NIVELACION CON EQUIPO
TOPOGRAFICO M2 $12.06 * 1.000000 $12.06 1.19%
TOTAL $1,191.84
1 1 1
0.1575
0.1575
$ 685,316.11
TOTAL $1,507.00
1 1 1
0.1575
0.1575
$ 866,536.79
MATERIALES
ANDAMIO TUBULAR CON MARCOS Y PT $27.50 * 2.000000 $55.00 4.18%
CRUCETAS
0.00%
SUBTOTAL: MATERIALES $55.00 4.18%
MANO DE OBRA
CUADRILLA NO. 5 (1 OF. CARPINTERO + 1 JOR $1,599.99 * 0.083333 $133.33 10.14%
AYUDANTE)
CUADRILLA NO. 5 (1 OF. ALBAÑIL + 1 JOR $1,599.99 * 0.050000 0.00%
AYUDANTE)
CABO (%)mo $133.33 * 0.100000 $13.33 1.01%
ACARREOS HORIZONTALES (%)mo $146.67 * 0.100000 $14.67 1.12%
ANDAMIOS (%)mo $146.67 * 0.050000 $7.33 0.56%
TOTAL $1,551.07
1 1
0.105
0.105
2 1 2
MATERIALES
ALAMBRE RECOCIDO CAL. 16 KG $16.90 * 0.092949 $1.57 0.12%
DUELA DE PINO 3RA 3/4" X 3.5" X 8.25´ PZA $32.00 * 0.265000 $8.48 0.67%
BARROTE DE 1 1/2" X 3 1/2" X 8.25´ PT $16.05 * 1.310000 $21.03 1.66%
CLAVO DE 2" A 5" KG $40.00 * 0.011000 $0.44 0.03%
SOLDADURA 7018-3 (1/8") KG $70.90 * 0.212162 $15.04 1.19%
LAMINA LOSACERO SECC. 4 DE 0.95 X 6.10 M2 $270.49 * 1.000000 $270.49 21.37%
CAL. 22 PERALTE DE 6.35 CM (8 KG/CM2)
TOTAL $1,493.34
1 1
0.063
0.063
2 1 2
4000
FACTOR FACTOR
Sn= SALARIO SALARIO SALARIO
CODIGO MANO DE OBRA DESCRIPCION DE LA CATEGORIA
NOMINAL INTEGRADO REAL
Sn en Veces el
ON DE LA CATEGORIA
salario del DF
2.975707 $ 605.00
2.975707 $ 605.00
CIALIZADO 2.975707 $ 605.00
4.734080 $ 962.50
4.734080 $ 962.50
TERO DE O. NEGRA 4.734080 $ 962.50
4.734080 $ 962.50
4.734080 $ 962.50
MAQUINARIA MENOR 4.734080 $ 962.50
5.410377 $ 1,100.00
5.680896 $ 1,155.00
5.680896 $ 1,155.00
MAQUINARIA PESADA 6.086674 $ 1,237.50
6.762971 $ 1,375.00
0.000000 $ -
Página 327 de 1
TOTAL $2,302.61
1 1
0.21
0.21
2 1 2
TOTAL $4,090.10
1 1
1 1 1.05 0.42
0.44625
0.44625
2 1 1.03 2.06
TOTAL $2,295.48
1 1
0.280875
0.280875
2 1 1.03 1.442
TOTAL $2,907.18
1 1
0.280875
0.280875
2 1 1.03 1.442
TOTAL $3,314.85
1 1
0.32025
0.32025
2 1 1.03 1.442
TOTAL $1,233.91
1 0.25
0.118125
0.118125
2 1 1.03 0.824
TOTAL $523.61
1 0
1 0.45 1.35 0
1 0.05 1.05 0
0.063
0.063
2 1 1.03 0.618
TOTAL $2,878.70
1 0.5
1 1 1.05 0.44961
0.44961
0.44961
1 1 1.03 2.2042
TOTAL $2,976.79
1 1
0.5376
0.5376
4 1 3.2
TOTAL $1,447.30
1 1 1
0.126
0.126
1 1 1 1.03 1.03
TOTAL $718.82
1 1.56 1.56
0.0945
0.0945
0.6
2.4
7.2
3
10.2
TOTAL $2,397.69
1 1
0.1575
0.1575
2 1 2
TOTAL $2,331.09
1 1
0.23625
0.23625
2 1 1.03 1.442
TOTAL $3,900.22
1 1
1 1 1.35 1.485
1 1 1.05 0.486045
0.51492
0.51492
2 1 1.03 2.06
TOTAL $3,046.78
1 1
0.21
0.21
2 1 2
TOTAL $1,674.39
1 1 1
0.2625
0.2625
$ 962,790.99
Habilitado y armado
de fierro de refuerzo
Concepto Unidad Rendimiento Inverso
Habilitado y armado ton 0.170 ton / Jor 5.882 Jor / ton
de fierro de refuerzo
en cimentación
Habilitado y armado ton 0.160 ton / Jor 6.250 Jor / ton
de fierro de refuerzo
en estructura
Habilitado y armado ton 0.130 ton / Jor 7.692 Jor / ton
de alambrón de 1/4" y
5/16"
Cimbrar y descimbrar,
acabado no aparente
Hechura de cimbra
Concepto Unidad Rendimiento Inverso
En cimientos m2 17.000 m2 / Jor 0.059 Jor / m2
En columnas m2 8.500 m2 / Jor 0.118 Jor / m2
rectangulares
En columnas circulares m2 4.000 m2 / Jor 0.250 Jor / m2
En trabes m2 10.000 m2 / Jor 0.100 Jor / m2
En losas m2 10.000 m2 / Jor 0.100 Jor / m2
Losas Reticuladas
Concepto Unidad Rendimiento Inverso
Colocación block de caja 100.000 caja / Jor 0.010 Jor / caja
200 x 400 x 400 mm
Colocación de block caja 40.000 caja / Jor 0.025 Jor / caja
hasta 350 x 600 x
600mm
Entrepiso reticular caja 40.000 caja / Jor 0.025 Jor / caja
celulado línea menor
Entre piso reticular caja 30.000 caja / Jor 0.033 Jor / caja
celulado lónea mayor
Muros de tabique
común o ligero, no
aparente
Concepto Unidad Rendimiento Inverso
Muro de tabique de m2 11.000 m2 / Jor 0.091 Jor / m2
70mm de espesor
Muro de tabique de m2 10.000 m2 / Jor 0.100 Jor / m2
140mm de espesor
Muro de tabique de m2 8.000 m2 / Jor 0.125 Jor / m2
210mm de espesor
Muro de tabique de m2 6.000 m2 / Jor 0.167 Jor / m2
280mm de espesor
Sobreprecio par cara m2 40.000 m2 / Jor 0.025 Jor / m2
aparente
Muro de block
extruído
Concepto Unidad Rendimiento Inverso
Muro de block m2 4.500 m2 / Jor 0.222 Jor / m2
extruído de 50 x 100 x
150 mm en 100mm de
espesor
Castilos y cadenas
Concepto Unidad Rendimiento Inverso
Castillo centro de m 30.000 m / Jor 0.033 Jor / m
block: 1 v. 3/8"
(9.5mm)
Castillos y cadenas de m 10.000 m / Jor 0.100 Jor / m
150mm x 150mm con
4var. De 3/8" (9.5mm)
Recubrimientos
Concepto Unidad Rendimiento Inverso
Repellados de mezcla m2 19.000 m2 / Jor 0.053 Jor / m2
Pisos
Concepto Unidad Rendimiento Inverso
Firmes de concreto m2 10.000 m2 / Jor 0.100 Jor / m2
para pisos, espesor de
80 a 100 mm
Acabado escobillado m2 35.000 m2 / Jor 0.029 Jor / m2
integral sobre firmes
Martelinados
Concepto Unidad Rendimiento Inverso
Martelinado fino m2 4.000 m2 / Jor 0.250 Jor / m2
sobre pisos
Materlinado fino m2 2.000 m2 / Jor 0.500 Jor / m2
sobre columnas
Martelinado fino m2 3.000 m2 / Jor 0.333 Jor / m2
sobre muros
Martelinado fino m2 2.000 m2 / Jor 0.500 Jor / m2
sobre trabes y losas
Azoteas
Concepto Unidad Rendimiento Inverso
Relleno de tezontle en m3 2.000 m3 / Jor 0.500 Jor / m3
azoteas
Entortado sobre casco m2 20.000 m2 / Jor 0.050 Jor / m2
Varios
Concepto Unidad Rendimiento Inverso
Hechura de tarimas de pza 19.000 pza / Jor 0.053 Jor / pza
500 x 1000 mm
Muro de block vidrio m2 3.500 m2 / Jor 0.286 Jor / m2
de 100 x 200 x 200mm
incluyendo refuerzo
en juntas
Registros de 400 x 600 pza 2.000 pza / Jor 0.500 Jor / pza
mm con profundidad
promedio de 1250mm