IE. 2026 SIMON BOLIVAR - INSTALACION DE CERCO PERIMETRICO
DESCRIPCION
ESTRUCTURA
CERCO PERIMETRICO
SUMINISTRO E INSTALACION CERCO TIPO PLACA LISO O TEXTURADO DE 2.50m DE ALTURA EFECTIVA Y 0.7m DE PROFUN
SUMINISTRO DE MATERIALES PARA CERCO PERIMETRICO TIPO PLACA
PLACAS DE 2.00x0.5x0.05M DE ESPESOR,REFORZADA CON CANASTILLA DE ACERO DE 4.7 mm
POSTES DE 0.14x 0.14x 3.20mts.CONCRETO F'C=210kg/cm2 REFORZADOS CON MALLA DE ACERO DE 8 mm, ESTRIBOS DE 4
POSTE DE 2.5M LIBRES CEMENTO TIPO 1 F'C 210 KG/CM2 0.14X0.14X3.20M
INSTALACION DE CERCO 2.5M 0.4X0.4X0.7 (POSTES)
INSTALACION DE CERCO 2.5M Concreto f`c= 145 kg/cm2
UNIDAD CANTIDAD P.UNITARIO P.PARCIAL TOTAL

-------
------- S/ 33,003.20
S/ 20,571.20
ML 259 S/ 46.80 S/ 12,121.20
UND 126 S/ 65.00 S/ 8,190.00
UND 4 S/ 65.00 S/ 260.00
S/ 12,432.00
ML 259 S/ 48.00 S/ 12,432.00

costo directo S/ 33,003.20


subtotal S/ 33,003.20
igv S/ 5,940.58
costo de ejecución de obr S/ 38,943.78
Obras Preliminares

PARTIDA 1.1.1.1
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
CLAVOS CON CABEZA PROMEDIO
AGUA
CEMENTO PORTLAND PUZOLANICO TIPO IP (42.5KG)
BANER
HORMIGON (PUESTO EN OBRA)
MADERA TORNILLO

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.1.1.2
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
ALAMBRE NEGRO N°8
ALAMBRE NEGRO RECOCIDO N°16
CLAVOS PARA MADERA CON CABEZA DE 3"
CERRADURA TIPO PARCHE DE 2 GOLPES
HORMIGON (PUESTO EN OBRA)
MADERA TORNILLO TRATADA
TRIPLEY DE 4"X8"X4MM
CALAMINA GALVANIZADA DE 1.83X0.83
BISAGRA DE ALUMINIO 3 1/2" X 3 1/2"
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.1.1.3
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
SERVICIO DE ALQUILER DE SERVICIOS HIGIENICOS PORTATILES

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.1.2.1
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.1.2.2
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
CLAVOS PARA MADERA CON CABEZA DE 3"
YESO BOLSA 28KG
MADERA TORNILLO
CORDEL

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS
TEODOLITO
HERRAMIENTAS 3% M.OBRA
MIRAS

PARTIDA 1.1.3.1
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
CASCO DE SEGURIDAD
LENTES DE SEGURIDAD
MASCARILLA DESECHABLE CONTRA POLVO
GUANTES DE CUERO
UNIFORME PARA OBRERO
AGUA PARA INGERIR

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.1.3.2
ESPECIFICACIONES

CUADRILLA
RENDIMIENTO

DESCRIPCION
MATERIALES
SOGA DE NYLON 1/2"
MALLA DE SEÑALIZACION (ROLLO)

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.1.3.3
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
CINTA DE SEÑALIZACION COLOR ROJO (200M)
CONO DE SEÑALIZACION NARANJA DE 28" DE ALTURA

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.1.3.4
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
CAMILLA RIGIDA DE MADERA
EXTINTOR DE POLVO QUIMICO SECO (PQS)
BOTIQUIN PARA LA OBRA (IMPLEMENTADO)
SUBCONTRATO SCTR

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.1.3.5
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
EXAMEN MEDICO PRE-OCUPACIONAL/AMD. Y OBREROS

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.1.3.6
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
SC PREVENCION DE SEGURIDAD

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS
HERRAMIENTAS 3% M.OBRA

PARTIDA 1.2.1.1.1
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
CERCO PERIMETRICO TIPO PLACA ALTURA 2.50M/CEMENTO TIPO 1 F'C 210 KG/CM2

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.2.1.1.2
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
POSTE DE 2.5M LIBRES CEMENTO TIPO 1 F'C 210 KG/CM2 0.14X0.14X3.20M
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.2.1.2.1
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
INSTALACION DE CERCO 2.5M CONCRETO CICLOPEO 1:8 + 30%PG CEMENTO TIPO 1 0.4X0.4X

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA
PARTIDA 1.2.1.3.1
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
TRANSPORTE DE MATERIALES

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.3.1.1
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
PLAN DE MONITOREO ARQUEOLOGICO
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.4.1.1
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS
CAMINO CISTERNA AGUA 4X2 122HP 1500 GAL
HERRAMIENTAS 3% M.OBRA

PARTIDA 1.4.2.1
ESPECIFICACIONES
CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
BOLSA DE PLASTICO GRANDE PARA RESIDUOS (PQT DE 100)
TACHOS RECOLECTORES DE PLASTICO GRANDE

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.4.3.1
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.5.1
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO

DESCRIPCION
MATERIALES
ENSAYO PARA DETERMINAR LA RESISTENCIA A COMPRESIÓN DE UNA PROBETA CILÍNDRICA

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA

PARTIDA 1.6.1
ESPECIFICACIONES

CUADRILLA

RENDIMIENTO
DESCRIPCION
MATERIALES
ALQUILER DE OFICINAS

MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPER. EQ. MED

EQUIPO Y HERRAMIENTAS

HERRAMIENTAS 3% M.OBRA
CARTEL DE OBRA 3.60 X 2.40 UNIDAD

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0.1 2 0 1 0
4 UND/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 619.92
KG 0.1100 S/. 4.00 S/. 0.44
M3 0.0500 S/. 4.50 S/. 0.23
KG 0.7000 S/. 22.00 S/. 15.40
UND 1.0000 S/. 400.00 S/. 400.00
M3 0.2100 S/. 35.00 S/. 7.35
P2 39.3000 S/. 5.00 S/. 196.50

S/. 133.29
HH 0.2000 S/. 27.46 S/. 5.49
HH 4.0000 S/. 23.34 S/. 93.36
HH 0.0000 S/. 18.43 S/. 0.00
HH 2.0000 S/. 17.22 S/. 34.44
HH 0.0000 S/. 23.34 S/. 0.00

S/. 4.00

0.03 S/. 133.29 S/. 4.00


TOTAL S/. 757.21

CASETA DE ALMACEN Y GUARDIANIA M2

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0.1 1 0 1 0
30 M2/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 72.64
KG 0.2000 S/. 3.50 S/. 0.70
KG 0.0800 S/. 4.50 S/. 0.36
KG 0.2100 S/. 4.00 S/. 0.84
UND 0.0062 S/. 70.00 S/. 0.43
M3 0.1100 S/. 35.00 S/. 3.85
P2 3.6000 S/. 6.10 S/. 21.96
PLN 0.9000 S/. 30.00 S/. 27.00
PLN 0.7000 S/. 25.00 S/. 17.50
PZA 0.0150 S/. 4.00 S/. 0.06
S/. 11.55
HH 0.0267 S/. 27.46 S/. 0.73
HH 0.2667 S/. 23.34 S/. 6.22
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.2667 S/. 17.22 S/. 4.59
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.35

0.03 S/. 11.55 S/. 0.35


TOTAL S/. 84.54

MODULO DE SERVICIOS HIGIENICOS PORTATILES UNIDAD

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
1 M2/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 500.00
MES 1.0000 S/. 500.00 S/. 500.00

S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 500.00

LIMPIEZA DE TERRENO MANUAL M2


CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV
0 0 0 1 0
100 M2/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 0.00

S/. 1.38
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0800 S/. 17.22 S/. 1.38
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.04

0.03 S/. 1.38 S/. 0.04


TOTAL S/. 1.42

TRAZO Y REPLANTEO PRELIMINAR C/EQUIPO M2

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 2 1
200 M2/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 0.00
0.0500 S/. 4.00
0.0550 S/. 17.50
0.0200 S/. 8.50
0.1900 S/. 0.15

S/. 2.31
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0800 S/. 17.22 S/. 1.38
HH 0.0400 S/. 23.34 S/. 0.93

S/. 0.07

0.03 S/. 2.31 S/. 0.07


TOTAL S/. 2.38

EQUIPOS DE PROTECCION PERSONAL PQT

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
1 PQT/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 230.04
UND 4.0000 S/. 3.81 S/. 15.24
UND 4.0000 S/. 3.30 S/. 13.20
UND 4.0000 S/. 3.00 S/. 12.00
PAR 4.0000 S/. 6.70 S/. 26.80
JGO 4.0000 S/. 15.70 S/. 62.80
UND 5.0000 S/. 20.00 S/. 100.00

S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 230.04

EQUIPOS DE PROTECCION COLECTIVA PQT

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
1 PQT/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 75.90
UND 5.0000 S/. 6.20 S/. 31.00
UND 1.0000 S/. 44.90 S/. 44.90

S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 75.90

SEÑALIZACION TEMPORAL DE SEGURIDAD PQT

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
1 PQT/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 119.34
UND 1.0000 S/. 29.50 S/. 29.50
UND 4.0000 S/. 22.46 S/. 89.84

S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 119.34

RECURSOS PARA RESPUESTA ANTE EMERGENCIA GLB

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
1 GLB/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 1,100.00
UND 1.0000 S/. 300.00 S/. 300.00
UND 1.0000 S/. 350.00 S/. 350.00
UND 1.0000 S/. 100.00 S/. 100.00
UND 1.0000 S/. 350.00 S/. 350.00

S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 1,100.00

EXAMEN MEDICO PRE-OCUPACIONAL POR PERSONA UND

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
1 UND/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 200.00
UND 1.0000 S/. 200.00 S/. 200.00

S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 200.00

CAPACITACION EN SEGURIDAD Y SALUD MES

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
1 UND/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 1,500.00
UND 1.0000 S/. 1,500.00 S/. 1,500.00

S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00
0.03 S/. 0.00 S/. 0.00
TOTAL S/. 1,500.00

PLACA ALTURA 2.50M/CEMENTO TIPO 1 F'C 210 KG/CM2 ML

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
10 GLB/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 46.80
UND 1.0000 S/. 46.80 S/. 46.80

S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 46.80

POSTE DE 2.5M LIBRES CEMENTO TIPO 1 F'C 210 KG/CM2 0.14X0.14X3.20M UND

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
10 UND/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 65.00
UND 1.0000 S/. 65.00 S/. 65.00
S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 65.00

INSTALACION DE CERCO 2.5M CONCRETO CICLOPEO 1:8 + 30%PG CEMENTO TIPO 1 0.4X0.4X ML

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
10 ML/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 52.00
UND 1.0000 S/. 52.00 S/. 52.00

S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 52.00
TRANSPORTE DE MATERIALES GLB

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
10 GLB/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 1,500.00
UND 1.0000 S/. 1,500.00 S/. 1,500.00

S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 1,500.00

MONITOREO E INFORME FINAL DEL PLAN DE MONITOREO ARQUEOLOGICO GLB

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
10 GLB/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 1,240.70
UND 1.0000 S/. 1,240.70 S/. 1,240.70
S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 1,240.70

RIEGO DEL AREA PARA EVITAR EL POLVO GLB

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 1 0
0.3 GLB/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 0.00
S/. 0.00

S/. 459.20
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 26.6667 S/. 17.22 S/. 459.20
HH 0.0000 S/. 23.34 S/. 0.00

S/. 380.44
HM 3.3333 S/. 110.00 S/. 366.67
0.03 S/. 459.20 S/. 13.78
TOTAL S/. 839.64

CONTENEDOR DE PLASTICO PARA RESIDUOS UND


CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV
0 0 0 0 0
1 UND/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 147.18
PQT 1.0000 S/. 48.64 S/. 48.64
UND 1.0000 S/. 98.54 S/. 98.54

S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 147.18

LIMPIEZA Y RESTAURACION DE AREAS OCUPADAS EN CONSTRUCCIONES P. M2

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 1 0
100 M2/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 0.00

S/. 1.38
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0800 S/. 17.22 S/. 1.38
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.04

0.03 S/. 1.38 S/. 0.04


TOTAL S/. 1.42

ENSAYO PARA DETERMINAR LA RESISTENCIA A COMPRESION DE CONCRETO DE LAS PLACAS UND

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
1 UND/DIA

UNID CANT P. UNIT. PARCIAL TOTAL


S/. 513.84
1 6.0000 S/. 85.64 S/. 513.84

S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 513.84

ALQUILER DE OFICINAS PARA AUTORIZACION DE EJECUCION UND

CAPATAZ OPERARIO OFICIAL PEON OPER EQ LIV


0 0 0 0 0
1 UND/DIA
UNID CANT P. UNIT. PARCIAL TOTAL
S/. 2,047.00
1 1.0000 S/. 2,047.00 S/. 2,047.00

S/. 0.00
HH 0.0000 S/. 27.46 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00
HH 0.0000 S/. 18.43 S/. 0.00
HH 0.0000 S/. 17.22 S/. 0.00
HH 0.0000 S/. 23.34 S/. 0.00

S/. 0.00

0.03 S/. 0.00 S/. 0.00


TOTAL S/. 2,047.00
Actividad

PLACAS DE 2.00x0.5x0.05M DE ESPESOR,REFORZADA CON CANASTILLA DE ACERO DE 4.7 mm

POSTES DE 0.14x 0.14x 3.20mts.CONCRETO F'C=210kg/cm2 REFORZADOS CON MALLA DE ACERO

INSTALACION DE CERCO 2.5M Concreto f`c= 145 kg/cm2


Lunes Martes Miércoles Jueves
(Partida) Dia 1 Dia 2 Dia 3 Dia 4
S/ 12,121.20
1.1.1.1.1
S/ 8,450.00
1.1.1.1.2
S/ 1,130.18 S/ 1,130.18 S/ 1,130.18
1.1.1.2.1
S/ 20,571.20 S/ 1,130.18 S/ 1,130.18 S/ 1,130.18

Dia 1 Dia 2 Dia 3 Dia 4


Curva S S/ 20,571.20 S/ 21,701.38 S/ 22,831.56 S/ 23,961.75
S/ 20,571.20 S/ 21,701.38 S/ 22,831.56 S/ 23,961.75
valorizacion bruta
amortizacion 20% 20.00%
valorizacion neta

tiempo S/ 6,600.64
0

Tiempo Monto Total


Dia 0 0
Dia 1 S/ 20,571.20
Dia 2 S/ 21,701.38
Dia 3 S/ 22,831.56 curva s
Dia 4 S/ 23,961.75
35000
Dia 5 S/ 25,091.93
Dia 6 S/ 26,222.11 30000
Dia 7 S/ 26,787.20
25000
Dia 8 S/ 27,352.29
Dia 9 S/ 28,482.47 20000
Dia 10 S/ 29,612.65
15000
Dia 11 S/ 30,742.84
Dia 12 S/ 31,873.02 10000
Dia 13 S/ 33,003.20
5000

0
Di a Di a Di a Di a Di a Di a Di a D
0 1 2 3 4 5 6 7
Viernes Sábado Domingo Lunes Martes Miércoles Jueves Viernes
Dia 5 Dia 6 Dia 7 Dia 8 Dia 9 Dia 10 Dia 11 Dia 12

S/ 1,130.18 S/ 1,130.18 S/ 1,130.18 S/ 1,130.18 S/ 1,130.18 S/ 1,130.18 S/ 1,130.18

S/ 1,130.18 S/ 1,130.18 S/ 1,130.18 S/ 1,130.18 S/ 1,130.18 S/ 1,130.18 S/ 1,130.18

Dia 5 Dia 6 Dia 7 Dia 8 Dia 9 Dia 10 Dia 11 Dia 12


S/ 25,091.93 S/ 26,222.11 S/ 26,787.20 S/ 27,352.29 S/ 28,482.47 S/ 29,612.65 S/ 30,742.84 S/ 31,873.02
S/ 25,091.93 S/ 26,222.11 S/ 26,787.20 S/ 27,352.29 S/ 28,482.47 S/ 29,612.65 S/ 30,742.84 S/ 31,873.02
semana 1 S/ 26,222.11 semana 2 S/ 6,781.09
S/ 5,244.42 S/ 1,356.22
S/ 20,977.69 S/ 5,424.87

Acumulado Acumulado
S/ 27,578.33 S/ 33,003.20

curva s

Di a Di a Di a Di a Di a Di a Di a Di a Di a Di a Di a Di a Di a
1 2 3 4 5 6 7 8 9 10 11 12 13
Sábado Total
Dia 13
S/ 12,121.20

S/ 8,450.00

S/ 1,130.18 S/ 12,432.00

S/ 1,130.18 S/ 33,003.20 S/ 33,003.20

Dia 13
S/ 33,003.20 Adelanto para materiales S/ 6,600.64
S/ 33,003.20