Liquidacion Buenos Aires Pariacoto
Liquidacion Buenos Aires Pariacoto
Liquidacion Buenos Aires Pariacoto
II.- GARANTIAS
II.-1 RETENIDOS REMYPE 12,807.40
RETENCION POR FIEL CUMPLIMIENTO 12,807.40
RESUMEN DE SALDOS
CALENDARIO DE COMPROMISOS
MONTO
No. DESCRIPCION I.G.V.
(s/IGV)
1.00 CONTRACTUAL
TOTAL
(c/IGV)
151,127.27
0.00
0.00
151,127.27
0.00
0.00
0.00
0.00
0.00
0.00
151,127.27
CUADRO RESUMEN DE VALORIZACIONES TRAMITADAS
Obra: “RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA) SISTEMA DE AGUA
POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO ANCASH”
Pres. Contratado: 151,127.27 Nuevos Soles
Contratista: CONSORCIO ALPAMAYO
CONTRATO PRINCIPAL
01 Jun-21 73,386.90 0.00 73,386.90 13,209.64 86,596.54 0.00 86,596.54 E-001-175 Jul-21
02 Jul-21 54,687.06 0.00 54,687.06 9,843.67 64,530.73 0.00 64,530.73 E-001-178 Aug-21
TOTAL 151,127.27
ADICIONAL N° 01
01 0.00 0.00 0.00 #REF! #REF! 0.00 #REF!
02 0.00 0.00 0.00 #REF! #REF! 0.00 #REF!
03 0.00 0.00 0.00 #REF! #REF! 0.00 #REF!
0.00
ADELANTO DIRECTO
S/. S/. 0.00
0.00
S/. S/. 0.00
CUADRO RESUMEN DE VALORIZACIONES TRAMITADAS
LICITACION PUBLICA N° 002-2015-MDT/CE
Obra: “RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA) SISTEMA DE AGUA POTABLE EN LA
LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO ANCASH”
Pres. Contratado: 151,127.27 Nuevos Soles Fecha:
Contratista: CONSORCIO ALPAMAYO
CONTRATO PRINCIPAL
01 Jun-21 73,386.90 0.00 73,386.90 0.00 0.00 0.00 73,386.90 13,209.64 86,596.54 0.00 86,596.54 E-001-175 Jul-21
02 Jul-21 54,687.06 0.00 54,687.06 0.00 0.00 0.00 54,687.06 9,843.67 64,530.73 0.00 64,530.73 E-001-178 Aug-21
ADICIONAL N° 01
01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
128,073.95 0.00 128,073.95 0.00 0.00 0.00 128,073.95 23,053.31 151,127.27
0.00
ADELANTO DIRECTO ADELANTO PARA MATERIALES
S/. 0.00 S/. 0.00
0.00 0.00
S/. 0.00 S/. 0.00
EFECTIVO FECHA DE PAGO
CONCEPTO RECIBIDO Nº FACTURA
DE FACTURA
NETO
VALORIZACION Nº1 S/ 86,596.54 E-001-175 Jul-21
VALORIZACION Nº2 S/ 64,530.73 E-001-178 Aug-21
TOTAL S/ 151,127.27
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
RECALCULO DE LAS
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO
VALORIZACIONES
ANCASH”
02.01.05.03 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 1:2, e=2.0 m2 5.04 S/ 41.85 S/ 210.92 S/ 0.00 S/ 210.92 5.04 210.92 0.00 0.0000
5.04
02.01.06 FILTRO S/ 286.27 S/ 0.00 S/ 286.27
02.01.06.01 FILTRO PARA CAPTACION - GRAVA 3/4" A 1" m3 1.35 S/ 141.02 S/ 190.38 S/ 0.00 1.35 S/ 190.38 1.35 190.38 0.00 0.0000
02.01.06.02 FILTRO PARA CAPTACION - GRAVA 1 1/2" - 2" m3 0.68 S/ 141.02 S/ 95.89 S/ 0.00 0.68 S/ 95.89 0.68 95.89 0.00 0.0000
02.01.07 SUMINISTRO E INSTALACION DE ACCESORIOS S/ 921.05 S/ 0.00 S/ 921.05
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
RECALCULO DE LAS
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO
VALORIZACIONES
ANCASH”
02.01.09.01 PINTURA LATEX 2 MANOS, EN ESTRUCTURAS EXTERIORES m2 16.87 S/ 20.15 S/ 339.93 S/ 0.00 S/ 339.93 16.87 339.93 0.00 0.0000
16.87
02.01.10 VARIOS S/ 115.25 S/ 0.00 S/ 115.25
SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION
02.01.10.01 und 1.00 S/ 115.25 S/ 115.25 S/ 0.00 S/ 115.25 1.00 115.25 0.00 0.0000
DE F°G° 1.00
02.02 CERCO PERIMETRICO DE CAPTACION S/ 5,924.58 S/ 1,486.11 S/ 4,438.47
02.02.01 TRABAJOS PRELIMINARES S/ 129.83 S/ 76.61 S/ 53.22
02.02.01.01 LIMPIEZA DEL TERRENO MANUAL m2 33.90 S/ 0.69 S/ 23.39 33.90 S/ 23.39 33.90 23.39 0.00 0.0000
02.02.01.02 TRAZOS Y REPLANTEO INICIAL DE OBRA m2 33.90 S/ 1.57 S/ 53.22 33.90 S/ 53.22 33.90 53.22 0.00 0.0000
02.02.01.03 TRAZOS Y REPLANTEO FINAL DE OBRA m2 33.90 S/ 1.57 S/ 53.22 S/ 0.00 33.90 S/ 53.22 33.90 53.22 0.00 0.0000
02.02.02 MOVIMIENTO DE TIERRAS S/ 102.48 S/ 102.48 S/ 0.00
EXCAVACION MANUAL PARA ESTRUCTURA EN TERRENO
02.02.02.01 m3 1.04 S/ 54.02 S/ 56.18 S/ 56.18 1.04 56.18 0.00 0.0000
CONGLOMERADO 0.80m DE PROFUNDIDAD 1.04
NIVELACION COMPACTACION MANUAL DE TERRENO
02.02.02.02 m2 1.28 S/ 6.60 S/ 8.45 S/ 8.45 1.28 8.45 0.00 0.0000
CONGLOMERADO 1.28
02.02.02.03 RELLENO CON MATERIAL PROPIO m3 0.48 S/ 39.46 S/ 18.94 0.48 S/ 18.94 0.48 18.94 0.00 0.0000
ELIMINACION DE MATERIAL EXEDENTE EN CARRETILLA
02.02.02.04 m3 0.70 S/ 27.01 S/ 18.91 S/ 18.91 0.70 18.91 0.00 0.0000
(30M) 0.70
02.02.03 OBRAS DE CONCRETO SIMPLE S/ 370.22 S/ 370.22 S/ 0.00
02.02.03.01 CONCRETO F'C= 175 KG/CM2 EN DADOS DE POSTES m3 0.80 S/ 462.78 S/ 370.22 0.80 S/ 370.22 0.80 370.22 0.00 0.0000
02.02.04 VARIOS S/ 4,655.32 S/ 936.80 S/ 3,718.52
SUMINISTRO Y COLOCACION DE COLUMNAS DE TUBO DE F°
02.02.04.01 und 8.00 S/ 117.10 S/ 936.80 S/ 936.80 8.00 936.80 0.00 0.0000
G° DE 2" X 2.5MM 8.00
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
RECALCULO DE LAS
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO
VALORIZACIONES
ANCASH”
03.01.04.03.01 CONCRETO f´c = 210 kg/cm2 m3 0.15 S/ 507.73 S/ 76.16 0.15 S/ 76.16 0.15 76.16 0.00 0.0000
03.01.05.03 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 1:2, e=2.0 m2 6.66 S/ 41.85 S/ 278.72 S/ 0.00 S/ 278.72 6.66 278.72 0.00 0.0000
6.66
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
RECALCULO DE LAS
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO
VALORIZACIONES
ANCASH”
03.01.09.01 PINTURA LATEX 2 MANOS, EN ESTRUCTURAS EXTERIORES m2 18.43 S/ 20.15 S/ 371.36 S/ 0.00 S/ 371.36 18.43 371.36 0.00 0.0000
18.43
03.01.10 VARIOS S/ 115.25 S/ 0.00 S/ 115.25
SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION
03.01.10.01 und 1.00 S/ 115.25 S/ 115.25 S/ 0.00 S/ 115.25 1.00 115.25 0.00 0.0000
DE F°G° 1.00
03.02 CERCO PERIMETRICO DE CAPTACION S/ 5,924.58 S/ 1,486.11 S/ 4,438.47
03.02.01 TRABAJOS PRELIMINARES S/ 129.83 S/ 76.61 S/ 53.22
03.02.01.01 LIMPIEZA DEL TERRENO MANUAL m2 33.90 S/ 0.69 S/ 23.39 33.90 S/ 23.39 33.90 23.39 0.00 0.0000
03.02.01.02 TRAZOS Y REPLANTEO INICIAL DE OBRA m2 33.90 S/ 1.57 S/ 53.22 33.90 S/ 53.22 33.90 53.22 0.00 0.0000
03.02.01.03 TRAZOS Y REPLANTEO FINAL DE OBRA m2 33.90 S/ 1.57 S/ 53.22 S/ 0.00 33.90 S/ 53.22 33.90 53.22 0.00 0.0000
03.02.02 MOVIMIENTO DE TIERRAS S/ 102.48 S/ 102.48 S/ 0.00
EXCAVACION MANUAL PARA ESTRUCTURA EN TERRENO
03.02.02.01 m3 1.04 S/ 54.02 S/ 56.18 S/ 56.18 1.04 56.18 0.00 0.0000
CONGLOMERADO 0.80m DE PROFUNDIDAD 1.04
NIVELACION COMPACTACION MANUAL DE TERRENO
03.02.02.02 m2 1.28 S/ 6.60 S/ 8.45 S/ 8.45 1.28 8.45 0.00 0.0000
CONGLOMERADO 1.28
03.02.02.03 RELLENO CON MATERIAL PROPIO m3 0.48 S/ 39.46 S/ 18.94 0.48 S/ 18.94 0.48 18.94 0.00 0.0000
ELIMINACION DE MATERIAL EXEDENTE EN CARRETILLA
03.02.02.04 m3 0.70 S/ 27.01 S/ 18.91 S/ 18.91 0.70 18.91 0.00 0.0000
(30M) 0.70
03.02.03 OBRAS DE CONCRETO SIMPLE S/ 370.22 S/ 370.22 S/ 0.00
03.02.03.01 CONCRETO F'C= 175 KG/CM2 EN DADOS DE POSTES m3 0.80 S/ 462.78 S/ 370.22 0.80 S/ 370.22 0.80 370.22 0.00 0.0000
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
RECALCULO DE LAS
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO
VALORIZACIONES
ANCASH”
05.01.05.03 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 1:2, e=2.0 m2 3.52 S/ 41.85 S/ 147.31 S/ 0.00 S/ 147.31 3.52 147.31 0.00 0.0000
3.52
05.01.06 PINTURA S/ 110.42 S/ 0.00 S/ 110.42
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
RECALCULO DE LAS
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO
VALORIZACIONES
ANCASH”
05.01.06.01 PINTURA LATEX 2 MANOS, EN ESTRUCTURAS EXTERIORES m2 5.48 S/ 20.15 S/ 110.42 S/ 0.00 S/ 110.42 5.48 110.42 0.00 0.0000
5.48
05.01.07 SUMINISTRO E INSTALACION DE ACCESORIOS S/ 963.11 S/ 0.00 S/ 963.11
05.01.07.01 ACCESORIOS DE INGRESO glb 1.00 S/ 338.57 S/ 338.57 S/ 0.00 1.00 S/ 338.57 1.00 338.57 0.00 0.0000
05.01.07.02 ACCESORIOS DE LIMPIA Y REBOSE glb 1.00 S/ 384.26 S/ 384.26 S/ 0.00 1.00 S/ 384.26 1.00 384.26 0.00 0.0000
05.01.07.03 ACCESORIOS DE SALIDA glb 1.00 S/ 170.02 S/ 170.02 S/ 0.00 1.00 S/ 170.02 1.00 170.02 0.00 0.0000
SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION
05.01.07.04 und 1.00 S/ 70.26 S/ 70.26 S/ 0.00 S/ 70.26 1.00 70.26 0.00 0.0000
DE F°G° - CRP 06 1.00
05.01.08 CARPINTERIA METALICA S/ 850.70 S/ 0.00 S/ 850.70
TAPA METALICA 0.80x0.80 m, CON MECANISMO DE
05.01.08.01 und 1.00 S/ 452.13 S/ 452.13 S/ 0.00 S/ 452.13 1.00 452.13 0.00 0.0000
SEGURIDAD 1.00
TAPA METALICA 0.60x0.60 m, CON MECANISMO DE
05.01.08.02 und 1.00 S/ 398.57 S/ 398.57 S/ 0.00 S/ 398.57 1.00 398.57 0.00 0.0000
SEGURIDAD 1.00
06 MANTENIMIENTO DE RESERVORIO V=10M3 S/ 10,881.17 S/ 2,034.36 S/ 8,846.81
06.01 MANTENIMIENTO DE RESERVORIO EXISTENTE S/ 2,088.80 S/ 0.00 S/ 2,088.80
06.01.01 CAMBIO DE VALVULAS S/ 433.27 S/ 0.00 S/ 433.27
06.01.01.01 CAMBIO DE ACCESORIOS DE INGRESO glb 1.00 S/ 433.27 S/ 433.27 S/ 0.00 1.00 S/ 433.27 1.00 433.27 0.00 0.0000
06.01.02 CARPINTERIA METALICA S/ 797.14 S/ 0.00 S/ 797.14
TAPA METALICA 0.60x0.60 m, CON MECANISMO DE
06.01.02.01 und 2.00 S/ 398.57 S/ 797.14 S/ 0.00 S/ 797.14 2.00 797.14 0.00 0.0000
SEGURIDAD 2.00
06.01.03 PINTURA S/ 858.39 S/ 0.00 S/ 858.39
06.01.03.01 PINTURA LATEX 2 MANOS, EN ESTRUCTURAS EXTERIORES m2 42.60 S/ 20.15 S/ 858.39 S/ 0.00 S/ 858.39 42.60 858.39 0.00 0.0000
42.60
06.02 CONSTRUCCION DE CERCO PERIMETRICO S/ 8,792.37 S/ 2,034.36 S/ 6,758.01
06.02.01 TRABAJOS PRELIMINARES S/ 175.79 S/ 103.73 S/ 72.06
06.02.01.01 LIMPIEZA DEL TERRENO MANUAL m2 45.90 S/ 0.69 S/ 31.67 45.90 S/ 31.67 45.90 31.67 0.00 0.0000
06.02.01.02 TRAZOS Y REPLANTEO INICIAL DE OBRA m2 45.90 S/ 1.57 S/ 72.06 45.90 S/ 72.06 45.90 72.06 0.00 0.0000
06.02.01.03 TRAZOS Y REPLANTEO FINAL DE OBRA m2 45.90 S/ 1.57 S/ 72.06 S/ 0.00 45.90 S/ 72.06 45.90 72.06 0.00 0.0000
06.02.02 MOVIMIENTO DE TIERRAS S/ 138.10 S/ 138.10 S/ 0.00
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
RECALCULO DE LAS
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO
VALORIZACIONES
ANCASH”
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA) SISTEMA DE AGUA
POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO ANCASH”
Ir Ir
MONOMIO SIMB. IND. DESCRIPCION COEF. % Io Julio-20 Kr Kr
Julio-21 Agosto-21
1 GO 39 Indice Gen precios al Consumidor 0.395 100.00% 466.82 484.63 0.410 489.40 0.414
2 MO 47 Mano de Obra Inc. Leyes Sociales 0.247 100.00% 619.99 653.54 0.260 653.54 0.260
28
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA) SISTEMA DE AGUA
POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO ANCASH”
4 FO 21 Cemento Portland Tipo I 0.095 100.00% 423.68 423.68 0.095 423.68 0.095
5 MA 49 Maquinaria y Equipo Importado 0.082 100.00% 333.13 383.78 0.094 401.37 0.099
6 AC 02 Acero de Construccion Liso 0.065 100.00% 583.77 830.65 0.092 839.89 0.094
Fecha de
Presupuesto: ABRIL - 2016
ESTRUCTURAS
Ir
Io Ir Ir Ir
MONOMIO SIMB. IND. DESCRIPCION COEF. % Set- Kr Kr Kr Kr
Abr-16 Oct-2016 Nov-2016 Dic-2016
2016
1 A 03 ACERO DE CONSTRUCCION CORRUGAD 0.000 100.00% 442.80 466.04 0.000 464.71 0.000 468.62 0.000 470.17 0.000
2 AG 05 AGREGADO GRUESO 0.000 100.00% 441.35 437.98 0.000 436.38 0.000 435.35 0.000 437.61 0.000
3 C 21 CEMENTO PORTLAND TIPO MS 0.000 100.00% 462.57 459.93 0.000 462.57 0.000 462.57 0.000 462.57 0.000
4 H 38 HORMIGON 0.000 100.00% 419.96 418.16 0.000 422.28 0.000 423.64 0.000 420.19 0.000
5 MN 43 MADERA NACIONAL 0.000 100.00% 696.29 703.46 0.000 702.16 0.000 700.57 0.000 698.83 0.000
6 M 47 MANO DE OBRA 0.000 100.00% 544.12 562.24 0.000 562.24 0.000 562.24 0.000 562.24 0.000
7 48 EQUIPO NACIONAL 0.000 100.00% 364.31 368.68 0.000 368.83 0.000 369.67 0.000 369.41 0.000
EN
8 39 INDICE GENERAL DE PRECIOS AL CONS 0.000 100.00% 427.58 431.85 0.000 433.63 0.000 434.89 0.000 436.35 0.000
GGU
K= 0.000 K= 0.000 K= 0.000 K= 0.000
30
Fecha de
Presupuesto: ABRIL - 2016
ARQUITECTURA
Ir
Io Ir Ir Ir
MONOMIO SIMB. IND. DESCRIPCION COEF. % Set- Kr Kr Kr Kr
Abr-16 Oct-2016 Nov-2016 Dic-2016
2016
1 AAC 02 ACERO DE CONSTRUCCION LISO 0.000 100.00% 449.75 481.58 0.000 482.15 0.000 484.88 0.000 484.81 0.000
2 MN 43 MADERA NACIONAL 0.000 100.00% 696.29 703.46 0.000 702.16 0.000 700.57 0.000 698.83 0.000
3 P 54 PINTURA 0.000 100.00% 373.98 373.98 0.000 375.63 0.000 377.56 0.000 377.56 0.000
4 MO 47 MANO DE OBRA 0.000 100.00% 544.12 562.24 0.000 562.24 0.000 562.24 0.000 562.24 0.000
5 V 79 VIDRIO NACIONAL 0.000 100.00% 458.22 474.82 0.000 476.53 0.000 479.51 0.000 477.78 0.000
6 GGU 39 INDICE GENERAL DE PRECIOS AL CONS 0.000 100.00% 427.58 431.85 0.000 433.63 0.000 434.89 0.000 436.35 0.000
04 AGREGADO FINO 0.000 20.00% 530.51 527.05 0.000 530.96 0.000 527.62 0.000 527.57 0.000
7 ACP 21 CEMENTO PORTLAND TIPO MS 0.000 44.44% 462.57 459.93 0.000 462.57 0.000 462.57 0.000 462.57 0.000
51 PERFIL LIVIANO 0.000 35.56% 247.86 268.06 0.000 264.41 0.000 266.56 0.000 279.97 0.000
Fecha de
Presupuesto: ABRIL - 2016
INSTALACIONES SANITARIAS
Ir
Io Ir Ir Ir
MONOMIO SIMB. IND. DESCRIPCION COEF. % Set- Kr Kr Kr Kr
Abr-16 Oct-2016 Nov-2016 Dic-2016
2016
1 T 72 TUBERIA PVC 0.000 100.00% 409.29 415.68 0.000 415.95 0.000 416.93 0.000 416.46 0.000
2 V 78 VALVULA DE BRONCE NACIONAL 0.000 100.00% 479.96 489.98 0.000 490.27 0.000 491.50 0.000 491.00 0.000
3 MO 47 MANO DE OBRA 0.000 100.00% 544.12 562.24 0.000 562.24 0.000 562.24 0.000 562.24 0.000
4 GGU 39 INDICE GENERAL DE PRECIOS AL CONS 0.000 100.00% 427.58 431.85 0.000 433.63 0.000 434.89 0.000 436.35 0.000
Fecha de
Presupuesto: ABRIL - 2016
INSTALACIONES ELECTRICAS
Ir
Io Ir Ir Ir
MONOMIO SIMB. IND. DESCRIPCION COEF. % Set- Kr Kr Kr Kr
Abr-16 Oct-2016 Nov-2016 Dic-2016
2016
1 A 11 ARTEFACTO ALUMBRADO EXTERIOR 0.000 100.00% 240.07 246.14 0.000 246.36 0.000 247.33 0.000 246.86 0.000
2 C 18 CABLE TELEFÓNICO 0.000 100.00% 289.51 289.79 0.000 288.37 0.000 290.80 0.000 316.30 0.000
3 D 30 DÓLAR 0.000 100.00% 458.22 474.82 0.000 476.53 0.000 479.51 0.000 477.78 0.000
4 MO 47 MANO DE OBRA 0.000 100.00% 544.12 562.24 0.000 562.24 0.000 562.24 0.000 562.24 0.000
5 GGU 39 INDICE GENERAL DE PRECIOS AL CONS 0.000 100.00% 427.58 431.85 0.000 433.63 0.000 434.89 0.000 436.35 0.000
Fórmula:
VAL Avance K-1 Reajuste Reajuste
N° Ejecutado Ejecutado Reconocido
(2) (3) (2) x (3) (4)
1 73,386.90 0.073 5,357.24 5,357.24
73,386.90
2 54,687.06 0.084 4,593.71 4,593.71
128,073.95
9,950.95 9,950.95
SUBTOTAL S/ 9,950.95
IGV (18%) S/ 1,791.17
TOTAL REAJUSTE NETO S/ 11,742.12
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO
ANCASH”
02.01.05.03 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 1:2, e=2.0 m2 5.04 S/ 41.85 S/ 210.92
5.04 5.04 -
02.01.06 FILTRO S/ 286.27 0.00
02.01.06.01 FILTRO PARA CAPTACION - GRAVA 3/4" A 1" m3 1.35 S/ 141.02 S/ 190.38 1.35 1.35 -
02.01.06.02 FILTRO PARA CAPTACION - GRAVA 1 1/2" - 2" m3 0.68 S/ 141.02 S/ 95.89 0.68 0.68 -
02.01.07 SUMINISTRO E INSTALACION DE ACCESORIOS S/ 921.05 0.00
02.01.07.01 ACCESORIOS DE TUBERIAS DE CONDUCCION glb 1.00 S/ 583.75 S/ 583.75 1.00 1.00 -
02.01.07.02 ACCESORIOS DE TUBERIAS DE LIMPIA Y REBOSE glb 1.00 S/ 337.30 S/ 337.30 1.00 1.00 -
02.01.08 CARPINTERIA METALICA S/ 904.26 0.00
TAPA METALICA 0.80x0.80 m, CON MECANISMO DE
02.01.08.01 und 2.00 S/ 452.13 S/ 904.26
SEGURIDAD 2.00 2.00 -
02.01.09 PINTURA S/ 339.93 0.00
03.01.05.03 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 1:2, e=2.0 m2 6.66 S/ 41.85 S/ 278.72
6.66 6.66 -
03.01.06 FILTRO S/ 253.84 0.00
03.01.06.01 FILTRO PARA CAPTACION - GRAVA 3/4" A 1" m3 1.46 S/ 141.02 S/ 205.89 1.46 1.46 -
03.01.06.02 FILTRO PARA CAPTACION - GRAVA 1 1/2" - 2" m3 0.34 S/ 141.02 S/ 47.95 0.34 0.34 -
03.01.07 SUMINISTRO E INSTALACION DE ACCESORIOS S/ 921.05 0.00
03.01.07.01 ACCESORIOS DE TUBERIAS DE CONDUCCION glb 1.00 S/ 583.75 S/ 583.75 1.00 1.00 -
03.01.07.02 ACCESORIOS DE TUBERIAS DE LIMPIA Y REBOSE glb 1.00 S/ 337.30 S/ 337.30 1.00 1.00 -
03.01.08 CARPINTERIA METALICA S/ 904.26 0.00
TAPA METALICA 0.80x0.80 m, CON MECANISMO DE
03.01.08.01 und 2.00 S/ 452.13 S/ 904.26
SEGURIDAD 2.00 2.00 -
03.01.09 PINTURA S/ 371.36 0.00
05.01.05.03 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 1:2, e=2.0 m2 3.52 S/ 41.85 S/ 147.31
3.52 3.52 -
05.01.06 PINTURA S/ 110.42 0.00
02.01.03.04 ENCOFRADO Y DESENCOFRADO EN ZANJA DE CORONACION m2 9.60 S/ 51.39 S/ 493.34 S/ 0.00 S/ 493.34
9.60 9.60 493.34 0.00 0.00
02.01.03.05 CONCRETO f'c=140 kg/cm2 (I) P/ZANJA DE CORONACION m3 0.68 S/ 411.96 S/ 280.13 S/ 0.00 0.68 S/ 280.13 0.68 280.13 0.00 0.00
02.01.03.06 ENCOFRADO Y DESENCOFRADO P/LOSA DE TECHO m2 6.14 S/ 51.39 S/ 315.53 S/ 0.00 6.14 S/ 315.53 6.14 315.53 0.00 0.00
02.01.03.07 CONCRETO f'c=140 kg/cm2 (I) P/LOSA DE TECHO m3 0.72 S/ 411.96 S/ 296.61 S/ 0.00 0.72 S/ 296.61 0.72 296.61 0.00 0.00
02.01.03.08 DADO CONCRETO F'C=140 kg/cm2 (0.30 X 0.20 X 0.20M) und 1.00 S/ 44.95 S/ 44.95 S/ 0.00 1.00 S/ 44.95 1.00 44.95 0.00 0.00
PIEDRA ASENTADA PARA SALIDA DE LIMPIA Y REBOSE
02.01.03.09 m2 0.25 S/ 67.44 S/ 16.86 S/ 0.00 S/ 16.86
F'C=140 KG/CM2 + 30%PM 0.25 0.25 16.86 0.00 0.00
02.01.03.10 MATERIAL IMPERMEABLE (LECHADA DE CEMENTO) m2 0.29 S/ 34.97 S/ 10.14 S/ 0.00 0.29 S/ 10.14 0.29 10.14 0.00 0.00
CONCRETO F'C=140 KG/CM2 + 30%PM P/RELLENO (Proteccion
02.01.03.11 m3 2.22 S/ 371.95 S/ 825.73 S/ 0.00 S/ 825.73
de afloramiento) 2.22 2.22 825.73 0.00 0.00
02.01.04 OBRAS DE CONCRETO ARMADO S/ 3,087.46 S/ 1,613.51 S/ 1,473.95
02.01.04.01 PROTECCION DE AFLORAMIENTO S/ 1,165.07 S/ 0.00 S/ 1,165.07
02.01.04.01.01 MUROS REFORZADOS S/ 1,165.07 S/ 0.00 S/ 1,165.07
02.01.04.01.01.0 ACERO CORRUGADO fy= 4200 kg/cm2 GRADO 60 kg 32.20 S/ 5.25 S/ 169.05 S/ 0.00 32.20 S/ 169.05 32.20 169.05 0.00 0.00
02.01.04.01.01.0 ENCOFRADO Y DESENCOFRADO m2 11.28 S/ 51.39 S/ 579.68 S/ 0.00 11.28 S/ 579.68 11.28 579.68 0.00 0.00
02.01.04.01.01.0 CONCRETO f´c = 210 kg/cm2 m3 0.82 S/ 507.73 S/ 416.34 S/ 0.00 0.82 S/ 416.34 0.82 416.34 0.00 0.00
02.01.04.02 CAMARA HUMEDA S/ 1,381.22 S/ 1,182.70 S/ 198.52
02.01.04.02.01 LOSA DE FONDO S/ 230.05 S/ 230.05 S/ 0.00
02.01.04.02.01.0 ACERO CORRUGADO fy= 4200 kg/cm2 GRADO 60 kg 9.68 S/ 5.25 S/ 50.82 9.68 S/ 50.82 9.68 50.82 0.00 0.00
02.01.04.02.01.0 ENCOFRADO Y DESENCOFRADO m2 0.82 S/ 51.39 S/ 42.14 0.82 S/ 42.14 0.82 42.14 0.00 0.00
02.01.04.02.01.0 CONCRETO f´c = 210 kg/cm2 m3 0.27 S/ 507.73 S/ 137.09 0.27 S/ 137.09 0.27 137.09 0.00 0.00
02.01.04.02.02 MURO REFORZADO S/ 952.65 S/ 952.65 S/ 0.00
02.01.04.02.02.0 ACERO CORRUGADO fy= 4200 kg/cm2 GRADO 60 kg 38.27 S/ 5.25 S/ 200.92 38.27 S/ 200.92 38.27 200.92 0.00 0.00
02.01.04.02.02.0 ENCOFRADO Y DESENCOFRADO m2 8.70 S/ 51.39 S/ 447.09 8.70 S/ 447.09 8.70 447.09 0.00 0.00
02.01.04.02.02.0 CONCRETO f´c = 210 kg/cm2 m3 0.60 S/ 507.73 S/ 304.64 0.60 S/ 304.64 0.60 304.64 0.00 0.00
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN
BALANCE DE VALORIZADO Y
EL(LA) SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ,
COSTO TOTAL
DEPARTAMENTO ANCASH”
02.01.05.03 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 1:2, e=2.0 m2 5.04 S/ 41.85 S/ 210.92 S/ 0.00 S/ 210.92
5.04 5.04 210.92 0.00 0.00
02.01.06 FILTRO S/ 286.27 S/ 0.00 S/ 286.27
02.01.06.01 FILTRO PARA CAPTACION - GRAVA 3/4" A 1" m3 1.35 S/ 141.02 S/ 190.38 S/ 0.00 1.35 S/ 190.38 1.35 190.38 0.00 0.00
02.01.06.02 FILTRO PARA CAPTACION - GRAVA 1 1/2" - 2" m3 0.68 S/ 141.02 S/ 95.89 S/ 0.00 0.68 S/ 95.89 0.68 95.89 0.00 0.00
02.01.07 SUMINISTRO E INSTALACION DE ACCESORIOS S/ 921.05 S/ 0.00 S/ 921.05
02.01.07.01 ACCESORIOS DE TUBERIAS DE CONDUCCION glb 1.00 S/ 583.75 S/ 583.75 S/ 0.00 1.00 S/ 583.75 1.00 583.75 0.00 0.00
02.01.07.02 ACCESORIOS DE TUBERIAS DE LIMPIA Y REBOSE glb 1.00 S/ 337.30 S/ 337.30 S/ 0.00 1.00 S/ 337.30 1.00 337.30 0.00 0.00
02.01.08 CARPINTERIA METALICA S/ 904.26 S/ 0.00 S/ 904.26
TAPA METALICA 0.80x0.80 m, CON MECANISMO DE
02.01.08.01 und 2.00 S/ 452.13 S/ 904.26 S/ 0.00 S/ 904.26
SEGURIDAD 2.00 2.00 904.26 0.00 0.00
02.01.09 PINTURA S/ 339.93 S/ 0.00 S/ 339.93
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN
BALANCE DE VALORIZADO Y
EL(LA) SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ,
COSTO TOTAL
DEPARTAMENTO ANCASH”
02.01.09.01 PINTURA LATEX 2 MANOS, EN ESTRUCTURAS EXTERIORES m2 16.87 S/ 20.15 S/ 339.93 S/ 0.00 S/ 339.93
16.87 16.87 339.93 0.00 0.00
02.01.10 VARIOS S/ 115.25 S/ 0.00 S/ 115.25
SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION
02.01.10.01 und 1.00 S/ 115.25 S/ 115.25 S/ 0.00 S/ 115.25
DE F°G° 1.00 1.00 115.25 0.00 0.00
02.02 CERCO PERIMETRICO DE CAPTACION S/ 5,924.58 S/ 1,486.11 S/ 4,438.47
02.02.01 TRABAJOS PRELIMINARES S/ 129.83 S/ 76.61 S/ 53.22
02.02.01.01 LIMPIEZA DEL TERRENO MANUAL m2 33.90 S/ 0.69 S/ 23.39 33.90 S/ 23.39 33.90 23.39 0.00 0.00
02.02.01.02 TRAZOS Y REPLANTEO INICIAL DE OBRA m2 33.90 S/ 1.57 S/ 53.22 33.90 S/ 53.22 33.90 53.22 0.00 0.00
02.02.01.03 TRAZOS Y REPLANTEO FINAL DE OBRA m2 33.90 S/ 1.57 S/ 53.22 S/ 0.00 33.90 S/ 53.22 33.90 53.22 0.00 0.00
02.02.02 MOVIMIENTO DE TIERRAS S/ 102.48 S/ 102.48 S/ 0.00
EXCAVACION MANUAL PARA ESTRUCTURA EN TERRENO
02.02.02.01 m3 1.04 S/ 54.02 S/ 56.18 S/ 56.18
CONGLOMERADO 0.80m DE PROFUNDIDAD 1.04 1.04 56.18 0.00 0.00
NIVELACION COMPACTACION MANUAL DE TERRENO
02.02.02.02 m2 1.28 S/ 6.60 S/ 8.45 S/ 8.45
CONGLOMERADO 1.28 1.28 8.45 0.00 0.00
02.02.02.03 RELLENO CON MATERIAL PROPIO m3 0.48 S/ 39.46 S/ 18.94 0.48 S/ 18.94 0.48 18.94 0.00 0.00
02.02.02.04 ELIMINACION DE MATERIAL EXEDENTE EN CARRETILLA (30M) m3 0.70 S/ 27.01 S/ 18.91 S/ 18.91
0.70 0.70 18.91 0.00 0.00
02.02.03 OBRAS DE CONCRETO SIMPLE S/ 370.22 S/ 370.22 S/ 0.00
02.02.03.01 CONCRETO F'C= 175 KG/CM2 EN DADOS DE POSTES m3 0.80 S/ 462.78 S/ 370.22 0.80 S/ 370.22 0.80 370.22 0.00 0.00
02.02.04 VARIOS S/ 4,655.32 S/ 936.80 S/ 3,718.52
SUMINISTRO Y COLOCACION DE COLUMNAS DE TUBO DE F°
02.02.04.01 und 8.00 S/ 117.10 S/ 936.80 S/ 936.80
G° DE 2" X 2.5MM 8.00 8.00 936.80 0.00 0.00
SUMINISTRO E INSTALACION DE MALLA METÁLICA n°10
02.02.04.02 m2 30.91 S/ 98.09 S/ 3,031.96 S/ 0.00 S/ 3,031.96
COCADAS 2"x2" 30.91 30.91 3,031.96 0.00 0.00
02.02.04.03 SUMINISTRO E INSTALACION DE ALAMBRE DE PUAS m 69.90 S/ 2.61 S/ 182.44 S/ 0.00 69.90 S/ 182.44 69.90 182.44 0.00 0.00
PUERTA METALICA DE 1.20x2.20 m. UNA HOJA CON TUBO DE
02.02.04.04 und 1.00 S/ 504.12 S/ 504.12 S/ 0.00 S/ 504.12
2" Y MALLA ROMBO DE 1/2" X 1/2" N°12 1.00 1.00 504.12 0.00 0.00
02.02.05 PINTURA S/ 666.73 S/ 0.00 S/ 666.73
02.02.05.01 PINTADO DE PUERTA METALICA m2 1.95 S/ 20.29 S/ 39.57 S/ 0.00 1.95 S/ 39.57 1.95 39.57 0.00 0.00
02.02.05.02 PINTADO DE CERCO PERIMETRICO m2 30.91 S/ 20.29 S/ 627.16 S/ 0.00 30.91 S/ 627.16 30.91 627.16 0.00 0.00
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN
BALANCE DE VALORIZADO Y
EL(LA) SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ,
COSTO TOTAL
DEPARTAMENTO ANCASH”
03.01.03.04 ENCOFRADO Y DESENCOFRADO EN ZANJA DE CORONACION m2 9.60 S/ 51.39 S/ 493.34 S/ 0.00 S/ 493.34
9.60 9.60 493.34 0.00 0.00
03.01.03.05 CONCRETO f'c=140 kg/cm2 (I) P/ZANJA DE CORONACION m3 0.68 S/ 411.96 S/ 280.13 S/ 0.00 0.68 S/ 280.13 0.68 280.13 0.00 0.00
03.01.03.06 ENCOFRADO Y DESENCOFRADO P/LOSA DE TECHO m2 6.60 S/ 51.39 S/ 339.17 S/ 0.00 6.60 S/ 339.17 6.60 339.17 0.00 0.00
03.01.03.07 CONCRETO f'c=140 kg/cm2 (I) P/LOSA DE TECHO m3 0.78 S/ 411.96 S/ 321.33 S/ 0.00 0.78 S/ 321.33 0.78 321.33 0.00 0.00
03.01.03.08 DADO CONCRETO F'C=140 kg/cm2 (0.30 X 0.20 X 0.20M) und 1.00 S/ 44.95 S/ 44.95 S/ 0.00 1.00 S/ 44.95 1.00 44.95 0.00 0.00
PIEDRA ASENTADA PARA SALIDA DE LIMPIA Y REBOSE
03.01.03.09 m2 0.25 S/ 67.44 S/ 16.86 S/ 0.00 S/ 16.86
F'C=140 KG/CM2 + 30%PM 0.25 0.25 16.86 0.00 0.00
03.01.03.10 MATERIAL IMPERMEABLE (LECHADA DE CEMENTO) m2 0.29 S/ 34.97 S/ 10.14 S/ 0.00 0.29 S/ 10.14 0.29 10.14 0.00 0.00
CONCRETO F'C=140 KG/CM2 + 30%PM P/RELLENO (Proteccion
03.01.03.11 m3 2.22 S/ 371.95 S/ 825.73 S/ 0.00 S/ 825.73
de afloramiento) 2.22 2.22 825.73 0.00 0.00
03.01.04 OBRAS DE CONCRETO ARMADO S/ 3,288.72 S/ 1,739.25 S/ 1,549.47
03.01.04.01 PROTECCION DE AFLORAMIENTO S/ 1,165.07 S/ 0.00 S/ 1,165.07
03.01.04.01.01 MUROS REFORZADOS S/ 1,165.07 S/ 0.00 S/ 1,165.07
03.01.04.01.01.0 ACERO CORRUGADO fy= 4200 kg/cm2 GRADO 60 kg 32.20 S/ 5.25 S/ 169.05 S/ 0.00 32.20 S/ 169.05 32.20 169.05 0.00 0.00
03.01.04.01.01.0 ENCOFRADO Y DESENCOFRADO m2 11.28 S/ 51.39 S/ 579.68 S/ 0.00 11.28 S/ 579.68 11.28 579.68 0.00 0.00
03.01.04.01.01.0 CONCRETO f´c = 210 kg/cm2 m3 0.82 S/ 507.73 S/ 416.34 S/ 0.00 0.82 S/ 416.34 0.82 416.34 0.00 0.00
03.01.04.02 CAMARA HUMEDA S/ 1,595.90 S/ 1,321.86 S/ 274.04
03.01.04.02.01 LOSA DE FONDO S/ 294.72 S/ 294.72 S/ 0.00
03.01.04.02.01.0 ACERO CORRUGADO fy= 4200 kg/cm2 GRADO 60 kg 12.12 S/ 5.25 S/ 63.63 12.12 S/ 63.63 12.12 63.63 0.00 0.00
03.01.04.02.01.0 ENCOFRADO Y DESENCOFRADO m2 0.94 S/ 51.39 S/ 48.31 0.94 S/ 48.31 0.94 48.31 0.00 0.00
03.01.04.02.01.0 CONCRETO f´c = 210 kg/cm2 m3 0.36 S/ 507.73 S/ 182.78 0.36 S/ 182.78 0.36 182.78 0.00 0.00
03.01.04.02.02 MURO REFORZADO S/ 1,027.14 S/ 1,027.14 S/ 0.00
03.01.04.02.02.0 ACERO CORRUGADO fy= 4200 kg/cm2 GRADO 60 kg 38.27 S/ 5.25 S/ 200.92 38.27 S/ 200.92 38.27 200.92 0.00 0.00
03.01.04.02.02.0 ENCOFRADO Y DESENCOFRADO m2 8.47 S/ 51.39 S/ 435.27 8.47 S/ 435.27 8.47 435.27 0.00 0.00
03.01.04.02.02.0 CONCRETO f´c = 210 kg/cm2 m3 0.77 S/ 507.73 S/ 390.95 0.77 S/ 390.95 0.77 390.95 0.00 0.00
03.01.04.02.03 LOSA DE TECHO S/ 274.04 S/ 0.00 S/ 274.04
03.01.04.02.03.0 ACERO CORRUGADO fy= 4200 kg/cm2 GRADO 60 kg 9.12 S/ 5.25 S/ 47.88 S/ 0.00 9.12 S/ 47.88 9.12 47.88 0.00 0.00
03.01.04.02.03.0 ENCOFRADO Y DESENCOFRADO m2 2.82 S/ 51.39 S/ 144.92 S/ 0.00 2.82 S/ 144.92 2.82 144.92 0.00 0.00
03.01.04.02.03.0 CONCRETO f´c = 210 kg/cm2 m3 0.16 S/ 507.73 S/ 81.24 S/ 0.00 0.16 S/ 81.24 0.16 81.24 0.00 0.00
03.01.04.03 CAMARA SECA S/ 527.75 S/ 417.39 S/ 110.36
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN
BALANCE DE VALORIZADO Y
EL(LA) SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ,
COSTO TOTAL
DEPARTAMENTO ANCASH”
03.01.05.03 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 1:2, e=2.0 m2 6.66 S/ 41.85 S/ 278.72 S/ 0.00 S/ 278.72
6.66 6.66 278.72 0.00 0.00
03.01.06 FILTRO S/ 253.84 S/ 0.00 S/ 253.84
03.01.06.01 FILTRO PARA CAPTACION - GRAVA 3/4" A 1" m3 1.46 S/ 141.02 S/ 205.89 S/ 0.00 1.46 S/ 205.89 1.46 205.89 0.00 0.00
03.01.06.02 FILTRO PARA CAPTACION - GRAVA 1 1/2" - 2" m3 0.34 S/ 141.02 S/ 47.95 S/ 0.00 0.34 S/ 47.95 0.34 47.95 0.00 0.00
03.01.07 SUMINISTRO E INSTALACION DE ACCESORIOS S/ 921.05 S/ 0.00 S/ 921.05
03.01.07.01 ACCESORIOS DE TUBERIAS DE CONDUCCION glb 1.00 S/ 583.75 S/ 583.75 S/ 0.00 1.00 S/ 583.75 1.00 583.75 0.00 0.00
03.01.07.02 ACCESORIOS DE TUBERIAS DE LIMPIA Y REBOSE glb 1.00 S/ 337.30 S/ 337.30 S/ 0.00 1.00 S/ 337.30 1.00 337.30 0.00 0.00
03.01.08 CARPINTERIA METALICA S/ 904.26 S/ 0.00 S/ 904.26
TAPA METALICA 0.80x0.80 m, CON MECANISMO DE
03.01.08.01 und 2.00 S/ 452.13 S/ 904.26 S/ 0.00 S/ 904.26
SEGURIDAD 2.00 2.00 904.26 0.00 0.00
03.01.09 PINTURA S/ 371.36 S/ 0.00 S/ 371.36
03.01.09.01 PINTURA LATEX 2 MANOS, EN ESTRUCTURAS EXTERIORES m2 18.43 S/ 20.15 S/ 371.36 S/ 0.00 S/ 371.36
18.43 18.43 371.36 0.00 0.00
03.01.10 VARIOS S/ 115.25 S/ 0.00 S/ 115.25
SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION
03.01.10.01 und 1.00 S/ 115.25 S/ 115.25 S/ 0.00 S/ 115.25
DE F°G° 1.00 1.00 115.25 0.00 0.00
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN
BALANCE DE VALORIZADO Y
EL(LA) SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ,
COSTO TOTAL
DEPARTAMENTO ANCASH”
03.02.02.04 ELIMINACION DE MATERIAL EXEDENTE EN CARRETILLA (30M) m3 0.70 S/ 27.01 S/ 18.91 S/ 18.91
0.70 0.70 18.91 0.00 0.00
03.02.03 OBRAS DE CONCRETO SIMPLE S/ 370.22 S/ 370.22 S/ 0.00
03.02.03.01 CONCRETO F'C= 175 KG/CM2 EN DADOS DE POSTES m3 0.80 S/ 462.78 S/ 370.22 0.80 S/ 370.22 0.80 370.22 0.00 0.00
03.02.04 VARIOS S/ 4,655.32 S/ 936.80 S/ 3,718.52
SUMINISTRO Y COLOCACION DE COLUMNAS DE TUBO DE F°
03.02.04.01 und 8.00 S/ 117.10 S/ 936.80 S/ 936.80
G° DE 2" X 2.5MM 8.00 8.00 936.80 0.00 0.00
SUMINISTRO E INSTALACION DE MALLA METÁLICA n°10
03.02.04.02 m2 30.91 S/ 98.09 S/ 3,031.96 S/ 0.00 S/ 3,031.96
COCADAS 2"x2" 30.91 30.91 3,031.96 0.00 0.00
03.02.04.03 SUMINISTRO E INSTALACION DE ALAMBRE DE PUAS m 69.90 S/ 2.61 S/ 182.44 S/ 0.00 69.90 S/ 182.44 69.90 182.44 0.00 0.00
PUERTA METALICA DE 1.20x2.20 m. UNA HOJA CON TUBO DE
03.02.04.04 und 1.00 S/ 504.12 S/ 504.12 S/ 0.00 S/ 504.12
2" Y MALLA ROMBO DE 1/2" X 1/2" N°12 1.00 1.00 504.12 0.00 0.00
03.02.05 PINTURA S/ 666.73 S/ 0.00 S/ 666.73
03.02.05.01 PINTADO DE PUERTA METALICA m2 1.95 S/ 20.29 S/ 39.57 S/ 0.00 1.95 S/ 39.57 1.95 39.57 0.00 0.00
03.02.05.02 PINTADO DE CERCO PERIMETRICO m2 30.91 S/ 20.29 S/ 627.16 S/ 0.00 30.91 S/ 627.16 30.91 627.16 0.00 0.00
04 RENOVACION DE LINEA DE CONDUCCION S/ 1,826.00 S/ 1,826.00 S/ 0.00
04.01 TRABAJOS PRELIMINARES S/ 124.00 S/ 124.00 S/ 0.00
04.01.01 DESBROCE Y LIMPIEZA DE TERRENO EN ZONA BOSCOSA m 50.00 S/ 1.38 S/ 69.00 50.00 S/ 69.00 50.00 69.00 0.00 0.00
04.01.02 TRAZO Y REPLANTEO DE OBRAS LINEALES m 50.00 S/ 1.10 S/ 55.00 50.00 S/ 55.00 50.00 55.00 0.00 0.00
04.02 MOVIMIENTO DE TIERRAS S/ 1,230.50 S/ 1,230.50 S/ 0.00
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN
BALANCE DE VALORIZADO Y
EL(LA) SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ,
COSTO TOTAL
DEPARTAMENTO ANCASH”
05.01.02.04 ELIMINACION DE MATERIAL EXEDENTE EN CARRETILLA (30M) m3 2.26 S/ 27.01 S/ 61.04 S/ 0.00 S/ 61.04
2.26 2.26 61.04 0.00 0.00
05.01.03 OBRAS DE CONCRETO SIMPLE S/ 190.38 S/ 0.00 S/ 190.38
05.01.03.01 CONCRETO f´c = 100 kg/cm2, PARA SOLADOS m2 2.52 S/ 44.33 S/ 111.71 S/ 0.00 2.52 S/ 111.71 2.52 111.71 0.00 0.00
05.01.03.02 DADO CONCRETO F'C=140 kg/cm2 (0.30 X 0.20 X 0.20M) und 1.00 S/ 44.95 S/ 44.95 S/ 0.00 1.00 S/ 44.95 1.00 44.95 0.00 0.00
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN
BALANCE DE VALORIZADO Y
EL(LA) SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ,
COSTO TOTAL
DEPARTAMENTO ANCASH”
05.01.05.03 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 1:2, e=2.0 m2 3.52 S/ 41.85 S/ 147.31 S/ 0.00 S/ 147.31
3.52 3.52 147.31 0.00 0.00
05.01.06 PINTURA S/ 110.42 S/ 0.00 S/ 110.42
05.01.06.01 PINTURA LATEX 2 MANOS, EN ESTRUCTURAS EXTERIORES m2 5.48 S/ 20.15 S/ 110.42 S/ 0.00 S/ 110.42
5.48 5.48 110.42 0.00 0.00
05.01.07 SUMINISTRO E INSTALACION DE ACCESORIOS S/ 963.11 S/ 0.00 S/ 963.11
05.01.07.01 ACCESORIOS DE INGRESO glb 1.00 S/ 338.57 S/ 338.57 S/ 0.00 1.00 S/ 338.57 1.00 338.57 0.00 0.00
05.01.07.02 ACCESORIOS DE LIMPIA Y REBOSE glb 1.00 S/ 384.26 S/ 384.26 S/ 0.00 1.00 S/ 384.26 1.00 384.26 0.00 0.00
05.01.07.03 ACCESORIOS DE SALIDA glb 1.00 S/ 170.02 S/ 170.02 S/ 0.00 1.00 S/ 170.02 1.00 170.02 0.00 0.00
SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION
05.01.07.04 und 1.00 S/ 70.26 S/ 70.26 S/ 0.00 S/ 70.26
DE F°G° - CRP 06 1.00 1.00 70.26 0.00 0.00
05.01.08 CARPINTERIA METALICA S/ 850.70 S/ 0.00 S/ 850.70
TAPA METALICA 0.80x0.80 m, CON MECANISMO DE
05.01.08.01 und 1.00 S/ 452.13 S/ 452.13 S/ 0.00 S/ 452.13
SEGURIDAD 1.00 1.00 452.13 0.00 0.00
TAPA METALICA 0.60x0.60 m, CON MECANISMO DE
05.01.08.02 und 1.00 S/ 398.57 S/ 398.57 S/ 0.00 S/ 398.57
SEGURIDAD 1.00 1.00 398.57 0.00 0.00
06 MANTENIMIENTO DE RESERVORIO V=10M3 S/ 10,881.17 S/ 2,034.36 S/ 8,846.81
06.01 MANTENIMIENTO DE RESERVORIO EXISTENTE S/ 2,088.80 S/ 0.00 S/ 2,088.80
06.01.01 CAMBIO DE VALVULAS S/ 433.27 S/ 0.00 S/ 433.27
06.01.01.01 CAMBIO DE ACCESORIOS DE INGRESO glb 1.00 S/ 433.27 S/ 433.27 S/ 0.00 1.00 S/ 433.27 1.00 433.27 0.00 0.00
06.01.02 CARPINTERIA METALICA S/ 797.14 S/ 0.00 S/ 797.14
TAPA METALICA 0.60x0.60 m, CON MECANISMO DE
06.01.02.01 und 2.00 S/ 398.57 S/ 797.14 S/ 0.00 S/ 797.14
SEGURIDAD 2.00 2.00 797.14 0.00 0.00
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN
BALANCE DE VALORIZADO Y
EL(LA) SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ,
COSTO TOTAL
DEPARTAMENTO ANCASH”
06.01.03.01 PINTURA LATEX 2 MANOS, EN ESTRUCTURAS EXTERIORES m2 42.60 S/ 20.15 S/ 858.39 S/ 0.00 S/ 858.39
42.60 42.60 858.39 0.00 0.00
06.02 CONSTRUCCION DE CERCO PERIMETRICO S/ 8,792.37 S/ 2,034.36 S/ 6,758.01
06.02.01 TRABAJOS PRELIMINARES S/ 175.79 S/ 103.73 S/ 72.06
06.02.01.01 LIMPIEZA DEL TERRENO MANUAL m2 45.90 S/ 0.69 S/ 31.67 45.90 S/ 31.67 45.90 31.67 0.00 0.00
06.02.01.02 TRAZOS Y REPLANTEO INICIAL DE OBRA m2 45.90 S/ 1.57 S/ 72.06 45.90 S/ 72.06 45.90 72.06 0.00 0.00
06.02.01.03 TRAZOS Y REPLANTEO FINAL DE OBRA m2 45.90 S/ 1.57 S/ 72.06 S/ 0.00 45.90 S/ 72.06 45.90 72.06 0.00 0.00
06.02.02 MOVIMIENTO DE TIERRAS S/ 138.10 S/ 138.10 S/ 0.00
EXCAVACION MANUAL PARA ESTRUCTURA EN TERRENO
06.02.02.01 m3 1.41 S/ 54.02 S/ 76.17 S/ 76.17
CONGLOMERADO 0.80m DE PROFUNDIDAD 1.41 1.41 76.17 0.00 0.00
NIVELACION COMPACTACION MANUAL DE TERRENO
06.02.02.02 m2 1.76 S/ 6.60 S/ 11.62 S/ 11.62
CONGLOMERADO 1.76 1.76 11.62 0.00 0.00
06.02.02.03 RELLENO CON MATERIAL PROPIO m3 0.70 S/ 39.46 S/ 27.62 0.70 S/ 27.62 0.70 27.62 0.00 0.00
06.02.02.04 ELIMINACION DE MATERIAL EXEDENTE EN CARRETILLA (30M) m3 0.84 S/ 27.01 S/ 22.69 S/ 22.69
0.84 0.84 22.69 0.00 0.00
06.02.03 OBRAS DE CONCRETO SIMPLE S/ 504.43 S/ 504.43 S/ 0.00
06.02.03.01 CONCRETO F'C= 175 KG/CM2 EN DADOS DE POSTES m3 1.09 S/ 462.78 S/ 504.43 1.09 S/ 504.43 1.09 504.43 0.00 0.00
06.02.04 VARIOS S/ 6,917.55 S/ 1,288.10 S/ 5,629.45
SUMINISTRO Y COLOCACION DE COLUMNAS DE TUBO DE F°
06.02.04.01 und 11.00 S/ 117.10 S/ 1,288.10 S/ 1,288.10
G° DE 2" X 2.5MM 11.00 11.00 1,288.10 0.00 0.00
SUMINISTRO E INSTALACION DE MALLA METÁLICA n°10
06.02.04.02 m2 50.12 S/ 98.09 S/ 4,916.27 S/ 0.00 S/ 4,916.27
COCADAS 2"x2" 50.12 50.12 4,916.27 0.00 0.00
06.02.04.03 SUMINISTRO E INSTALACION DE ALAMBRE DE PUAS m 80.10 S/ 2.61 S/ 209.06 S/ 0.00 80.10 S/ 209.06 80.10 209.06 0.00 0.00
PUERTA METALICA DE 1.20x2.20 m. UNA HOJA CON TUBO DE
06.02.04.04 und 1.00 S/ 504.12 S/ 504.12 S/ 0.00 S/ 504.12
2" Y MALLA ROMBO DE 1/2" X 1/2" N°12 1.00 1.00 504.12 0.00 0.00
06.02.05 PINTURA S/ 1,056.50 S/ 0.00 S/ 1,056.50
06.02.05.01 PINTADO DE PUERTA METALICA m2 1.95 S/ 20.29 S/ 39.57 S/ 0.00 1.95 S/ 39.57 1.95 39.57 0.00 0.00
06.02.05.02 PINTADO DE CERCO PERIMETRICO m2 50.12 S/ 20.29 S/ 1,016.93 S/ 0.00 50.12 S/ 1,016.93 50.12 1,016.93 0.00 0.00
07 GESTION DE RIESGO S/ 21,373.32 S/ 21,373.32 S/ 0.00
07.01 CONSTRUCCION DE MURO DE CONTENCION S/ 21,373.32 S/ 21,373.32 S/ 0.00
07.01.01 TRABAJOS PRELIMINARES S/ 249.75 S/ 249.75 S/ 0.00
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN
BALANCE DE VALORIZADO Y
EL(LA) SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ,
COSTO TOTAL
DEPARTAMENTO ANCASH”
07.01.02.04 ELIMINACION DE MATERIAL EXEDENTE EN CARRETILLA (30M) m3 77.03 S/ 27.01 S/ 2,080.58 S/ 2,080.58
77.03 77.03 2,080.58 0.00 0.00
07.01.03 OBRAS DE CONCRETO SIMPLE S/ 11,633.04 S/ 11,633.04 S/ 0.00
07.01.03.01 CONCRETO f´c = 100 kg/cm2, PARA SOLADOS m2 25.00 S/ 44.33 S/ 1,108.25 25.00 S/ 1,108.25 25.00 1,108.25 0.00 0.00
07.01.03.02 MAMPOSTERIA DE PIEDRA f'c=140 kg/cm2 + 30%PM m3 32.81 S/ 320.78 S/ 10,524.79 32.81 S/ 10,524.79 32.81 10,524.79 0.00 0.00
08 SEGURIDAD Y SALUD EN EL TRABAJO S/ 2,203.22 S/ 2,203.22 S/ 0.00
08.01 SEGURIDAD EN OBRA S/ 2,203.22 S/ 2,203.22 S/ 0.00
08.01.01 EQUIPO DE PROTECCION PERSONAL glb 14.00 S/ 152.53 S/ 2,135.42 14.00 S/ 2,135.42 14.00 2,135.42 0.00 0.00
08.01.02 EQUIPO DE PROTECCION COLECTIVA glb 1.00 S/ 67.80 S/ 67.80 1.00 S/ 67.80 1.00 67.80 0.00 0.00
09 FLETE S/ 16,615.44 S/ 13,292.35 S/ 3,323.09
09.01 FLETE TERRESTRE glb 1.00 S/ 9,788.14 S/ 9,788.14 0.80 S/ 7,830.51 0.20 S/ 1,957.63 1.00 9,788.14 0.00 0.00
09.02 FLETE RURAL glb 1.00 S/ 6,827.30 S/ 6,827.30 0.80 S/ 5,461.84 0.20 S/ 1,365.46 1.00 6,827.30 0.00 0.00
COSTO DIRECTO S/. 95,335.47 54,627.61 40,707.86 95,335.47 0.00
GASTOS GENERALES #REF! #REF! #REF! #REF! #REF! #REF!
UTILIDAD 10.00% 9,533.55 5,462.76 4,070.79 9,533.55 0.00
SUB-TOTAL S/. #REF! #REF! #REF! #REF! #REF!
FACTOR DE RELACION 1.00000 #REF! #REF! #REF! #REF! #REF!
I.G.V. 18.00% #REF! #REF! #REF! #REF! #REF!
COSTO TOTAL S/. #REF! #REF! #REF! #REF! #REF!
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO BALANCE VALORIZADO Y COSTO TOTAL
ANCASH”
02.01.05.03 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 1:2, e=2.0 m2 5.04 S/ 41.85 S/ 210.92 S/ 0.00 S/ 210.92
5.04 5.04 210.92 0.00 0.00
02.01.06 FILTRO S/ 286.27 S/ 0.00 S/ 286.27
02.01.06.01 FILTRO PARA CAPTACION - GRAVA 3/4" A 1" m3 1.35 S/ 141.02 S/ 190.38 S/ 0.00 1.35 S/ 190.38 1.35 190.38 0.00 0.00
02.01.06.02 FILTRO PARA CAPTACION - GRAVA 1 1/2" - 2" m3 0.68 S/ 141.02 S/ 95.89 S/ 0.00 0.68 S/ 95.89 0.68 95.89 0.00 0.00
02.01.07 SUMINISTRO E INSTALACION DE ACCESORIOS S/ 921.05 S/ 0.00 S/ 921.05
02.01.07.01 ACCESORIOS DE TUBERIAS DE CONDUCCION glb 1.00 S/ 583.75 S/ 583.75 S/ 0.00 1.00 S/ 583.75 1.00 583.75 0.00 0.00
02.01.07.02 ACCESORIOS DE TUBERIAS DE LIMPIA Y REBOSE glb 1.00 S/ 337.30 S/ 337.30 S/ 0.00 1.00 S/ 337.30 1.00 337.30 0.00 0.00
02.01.08 CARPINTERIA METALICA S/ 904.26 S/ 0.00 S/ 904.26
TAPA METALICA 0.80x0.80 m, CON MECANISMO DE
02.01.08.01 und 2.00 S/ 452.13 S/ 904.26 S/ 0.00 S/ 904.26
SEGURIDAD 2.00 2.00 904.26 0.00 0.00
02.01.09 PINTURA S/ 339.93 S/ 0.00 S/ 339.93
02.01.09.01 PINTURA LATEX 2 MANOS, EN ESTRUCTURAS EXTERIORES m2 16.87 S/ 20.15 S/ 339.93 S/ 0.00 S/ 339.93
16.87 16.87 339.93 0.00 0.00
02.01.10 VARIOS S/ 115.25 S/ 0.00 S/ 115.25
SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION
02.01.10.01 und 1.00 S/ 115.25 S/ 115.25 S/ 0.00 S/ 115.25
DE F°G° 1.00 1.00 115.25 0.00 0.00
02.02 CERCO PERIMETRICO DE CAPTACION S/ 5,924.58 S/ 1,486.11 S/ 4,438.47
02.02.01 TRABAJOS PRELIMINARES S/ 129.83 S/ 76.61 S/ 53.22
02.02.01.01 LIMPIEZA DEL TERRENO MANUAL m2 33.90 S/ 0.69 S/ 23.39 33.90 S/ 23.39 33.90 23.39 0.00 0.00
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO BALANCE VALORIZADO Y COSTO TOTAL
ANCASH”
03.01.05.03 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 1:2, e=2.0 m2 6.66 S/ 41.85 S/ 278.72 S/ 0.00 S/ 278.72
6.66 6.66 278.72 0.00 0.00
03.01.06 FILTRO S/ 253.84 S/ 0.00 S/ 253.84
03.01.06.01 FILTRO PARA CAPTACION - GRAVA 3/4" A 1" m3 1.46 S/ 141.02 S/ 205.89 S/ 0.00 1.46 S/ 205.89 1.46 205.89 0.00 0.00
03.01.06.02 FILTRO PARA CAPTACION - GRAVA 1 1/2" - 2" m3 0.34 S/ 141.02 S/ 47.95 S/ 0.00 0.34 S/ 47.95 0.34 47.95 0.00 0.00
03.01.07 SUMINISTRO E INSTALACION DE ACCESORIOS S/ 921.05 S/ 0.00 S/ 921.05
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO BALANCE VALORIZADO Y COSTO TOTAL
ANCASH”
03.01.09.01 PINTURA LATEX 2 MANOS, EN ESTRUCTURAS EXTERIORES m2 18.43 S/ 20.15 S/ 371.36 S/ 0.00 S/ 371.36
18.43 18.43 371.36 0.00 0.00
03.01.10 VARIOS S/ 115.25 S/ 0.00 S/ 115.25
SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION
03.01.10.01 und 1.00 S/ 115.25 S/ 115.25 S/ 0.00 S/ 115.25
DE F°G° 1.00 1.00 115.25 0.00 0.00
03.02 CERCO PERIMETRICO DE CAPTACION S/ 5,924.58 S/ 1,486.11 S/ 4,438.47
03.02.01 TRABAJOS PRELIMINARES S/ 129.83 S/ 76.61 S/ 53.22
03.02.01.01 LIMPIEZA DEL TERRENO MANUAL m2 33.90 S/ 0.69 S/ 23.39 33.90 S/ 23.39 33.90 23.39 0.00 0.00
03.02.01.02 TRAZOS Y REPLANTEO INICIAL DE OBRA m2 33.90 S/ 1.57 S/ 53.22 33.90 S/ 53.22 33.90 53.22 0.00 0.00
03.02.01.03 TRAZOS Y REPLANTEO FINAL DE OBRA m2 33.90 S/ 1.57 S/ 53.22 S/ 0.00 33.90 S/ 53.22 33.90 53.22 0.00 0.00
03.02.02 MOVIMIENTO DE TIERRAS S/ 102.48 S/ 102.48 S/ 0.00
EXCAVACION MANUAL PARA ESTRUCTURA EN TERRENO
03.02.02.01 m3 1.04 S/ 54.02 S/ 56.18 S/ 56.18
CONGLOMERADO 0.80m DE PROFUNDIDAD 1.04 1.04 56.18 0.00 0.00
NIVELACION COMPACTACION MANUAL DE TERRENO
03.02.02.02 m2 1.28 S/ 6.60 S/ 8.45 S/ 8.45
CONGLOMERADO 1.28 1.28 8.45 0.00 0.00
03.02.02.03 RELLENO CON MATERIAL PROPIO m3 0.48 S/ 39.46 S/ 18.94 0.48 S/ 18.94 0.48 18.94 0.00 0.00
ELIMINACION DE MATERIAL EXEDENTE EN CARRETILLA
03.02.02.04 m3 0.70 S/ 27.01 S/ 18.91 S/ 18.91
(30M) 0.70 0.70 18.91 0.00 0.00
03.02.03 OBRAS DE CONCRETO SIMPLE S/ 370.22 S/ 370.22 S/ 0.00
03.02.03.01 CONCRETO F'C= 175 KG/CM2 EN DADOS DE POSTES m3 0.80 S/ 462.78 S/ 370.22 0.80 S/ 370.22 0.80 370.22 0.00 0.00
03.02.04 VARIOS S/ 4,655.32 S/ 936.80 S/ 3,718.52
SUMINISTRO Y COLOCACION DE COLUMNAS DE TUBO DE F°
03.02.04.01 und 8.00 S/ 117.10 S/ 936.80 S/ 936.80
G° DE 2" X 2.5MM 8.00 8.00 936.80 0.00 0.00
SUMINISTRO E INSTALACION DE MALLA METÁLICA n°10
03.02.04.02 m2 30.91 S/ 98.09 S/ 3,031.96 S/ 0.00 S/ 3,031.96
COCADAS 2"x2" 30.91 30.91 3,031.96 0.00 0.00
03.02.04.03 SUMINISTRO E INSTALACION DE ALAMBRE DE PUAS m 69.90 S/ 2.61 S/ 182.44 S/ 0.00 69.90 S/ 182.44 69.90 182.44 0.00 0.00
PUERTA METALICA DE 1.20x2.20 m. UNA HOJA CON TUBO DE
03.02.04.04 und 1.00 S/ 504.12 S/ 504.12 S/ 0.00 S/ 504.12
2" Y MALLA ROMBO DE 1/2" X 1/2" N°12 1.00 1.00 504.12 0.00 0.00
03.02.05 PINTURA S/ 666.73 S/ 0.00 S/ 666.73
03.02.05.01 PINTADO DE PUERTA METALICA m2 1.95 S/ 20.29 S/ 39.57 S/ 0.00 1.95 S/ 39.57 1.95 39.57 0.00 0.00
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO BALANCE VALORIZADO Y COSTO TOTAL
ANCASH”
05.01.05.03 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 1:2, e=2.0 m2 3.52 S/ 41.85 S/ 147.31 S/ 0.00 S/ 147.31
3.52 3.52 147.31 0.00 0.00
05.01.06 PINTURA S/ 110.42 S/ 0.00 S/ 110.42
05.01.06.01 PINTURA LATEX 2 MANOS, EN ESTRUCTURAS EXTERIORES m2 5.48 S/ 20.15 S/ 110.42 S/ 0.00 S/ 110.42
5.48 5.48 110.42 0.00 0.00
05.01.07 SUMINISTRO E INSTALACION DE ACCESORIOS S/ 963.11 S/ 0.00 S/ 963.11
05.01.07.01 ACCESORIOS DE INGRESO glb 1.00 S/ 338.57 S/ 338.57 S/ 0.00 1.00 S/ 338.57 1.00 338.57 0.00 0.00
05.01.07.02 ACCESORIOS DE LIMPIA Y REBOSE glb 1.00 S/ 384.26 S/ 384.26 S/ 0.00 1.00 S/ 384.26 1.00 384.26 0.00 0.00
05.01.07.03 ACCESORIOS DE SALIDA glb 1.00 S/ 170.02 S/ 170.02 S/ 0.00 1.00 S/ 170.02 1.00 170.02 0.00 0.00
SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION
05.01.07.04 und 1.00 S/ 70.26 S/ 70.26 S/ 0.00 S/ 70.26
DE F°G° - CRP 06 1.00 1.00 70.26 0.00 0.00
05.01.08 CARPINTERIA METALICA S/ 850.70 S/ 0.00 S/ 850.70
TAPA METALICA 0.80x0.80 m, CON MECANISMO DE
05.01.08.01 und 1.00 S/ 452.13 S/ 452.13 S/ 0.00 S/ 452.13
SEGURIDAD 1.00 1.00 452.13 0.00 0.00
TAPA METALICA 0.60x0.60 m, CON MECANISMO DE
05.01.08.02 und 1.00 S/ 398.57 S/ 398.57 S/ 0.00 S/ 398.57
SEGURIDAD 1.00 1.00 398.57 0.00 0.00
06 MANTENIMIENTO DE RESERVORIO V=10M3 S/ 10,881.17 S/ 2,034.36 S/ 8,846.81
06.01 MANTENIMIENTO DE RESERVORIO EXISTENTE S/ 2,088.80 S/ 0.00 S/ 2,088.80
06.01.01 CAMBIO DE VALVULAS S/ 433.27 S/ 0.00 S/ 433.27
06.01.01.01 CAMBIO DE ACCESORIOS DE INGRESO glb 1.00 S/ 433.27 S/ 433.27 S/ 0.00 1.00 S/ 433.27 1.00 433.27 0.00 0.00
06.01.02 CARPINTERIA METALICA S/ 797.14 S/ 0.00 S/ 797.14
TAPA METALICA 0.60x0.60 m, CON MECANISMO DE
06.01.02.01 und 2.00 S/ 398.57 S/ 797.14 S/ 0.00 S/ 797.14
SEGURIDAD 2.00 2.00 797.14 0.00 0.00
06.01.03 PINTURA S/ 858.39 S/ 0.00 S/ 858.39
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO BALANCE VALORIZADO Y COSTO TOTAL
ANCASH”
06.01.03.01 PINTURA LATEX 2 MANOS, EN ESTRUCTURAS EXTERIORES m2 42.60 S/ 20.15 S/ 858.39 S/ 0.00 S/ 858.39
42.60 42.60 858.39 0.00 0.00
06.02 CONSTRUCCION DE CERCO PERIMETRICO S/ 8,792.37 S/ 2,034.36 S/ 6,758.01
06.02.01 TRABAJOS PRELIMINARES S/ 175.79 S/ 103.73 S/ 72.06
06.02.01.01 LIMPIEZA DEL TERRENO MANUAL m2 45.90 S/ 0.69 S/ 31.67 45.90 S/ 31.67 45.90 31.67 0.00 0.00
06.02.01.02 TRAZOS Y REPLANTEO INICIAL DE OBRA m2 45.90 S/ 1.57 S/ 72.06 45.90 S/ 72.06 45.90 72.06 0.00 0.00
06.02.01.03 TRAZOS Y REPLANTEO FINAL DE OBRA m2 45.90 S/ 1.57 S/ 72.06 S/ 0.00 45.90 S/ 72.06 45.90 72.06 0.00 0.00
06.02.02 MOVIMIENTO DE TIERRAS S/ 138.10 S/ 138.10 S/ 0.00
EXCAVACION MANUAL PARA ESTRUCTURA EN TERRENO
06.02.02.01 m3 1.41 S/ 54.02 S/ 76.17 S/ 76.17
CONGLOMERADO 0.80m DE PROFUNDIDAD 1.41 1.41 76.17 0.00 0.00
NIVELACION COMPACTACION MANUAL DE TERRENO
06.02.02.02 m2 1.76 S/ 6.60 S/ 11.62 S/ 11.62
CONGLOMERADO 1.76 1.76 11.62 0.00 0.00
06.02.02.03 RELLENO CON MATERIAL PROPIO m3 0.70 S/ 39.46 S/ 27.62 0.70 S/ 27.62 0.70 27.62 0.00 0.00
ELIMINACION DE MATERIAL EXEDENTE EN CARRETILLA
06.02.02.04 m3 0.84 S/ 27.01 S/ 22.69 S/ 22.69
(30M) 0.84 0.84 22.69 0.00 0.00
06.02.03 OBRAS DE CONCRETO SIMPLE S/ 504.43 S/ 504.43 S/ 0.00
06.02.03.01 CONCRETO F'C= 175 KG/CM2 EN DADOS DE POSTES m3 1.09 S/ 462.78 S/ 504.43 1.09 S/ 504.43 1.09 504.43 0.00 0.00
06.02.04 VARIOS S/ 6,917.55 S/ 1,288.10 S/ 5,629.45
SUMINISTRO Y COLOCACION DE COLUMNAS DE TUBO DE F°
06.02.04.01 und 11.00 S/ 117.10 S/ 1,288.10 S/ 1,288.10
G° DE 2" X 2.5MM 11.00 11.00 1,288.10 0.00 0.00
SUMINISTRO E INSTALACION DE MALLA METÁLICA n°10
06.02.04.02 m2 50.12 S/ 98.09 S/ 4,916.27 S/ 0.00 S/ 4,916.27
COCADAS 2"x2" 50.12 50.12 4,916.27 0.00 0.00
06.02.04.03 SUMINISTRO E INSTALACION DE ALAMBRE DE PUAS m 80.10 S/ 2.61 S/ 209.06 S/ 0.00 80.10 S/ 209.06 80.10 209.06 0.00 0.00
PUERTA METALICA DE 1.20x2.20 m. UNA HOJA CON TUBO DE
06.02.04.04 und 1.00 S/ 504.12 S/ 504.12 S/ 0.00 S/ 504.12
2" Y MALLA ROMBO DE 1/2" X 1/2" N°12 1.00 1.00 504.12 0.00 0.00
06.02.05 PINTURA S/ 1,056.50 S/ 0.00 S/ 1,056.50
06.02.05.01 PINTADO DE PUERTA METALICA m2 1.95 S/ 20.29 S/ 39.57 S/ 0.00 1.95 S/ 39.57 1.95 39.57 0.00 0.00
06.02.05.02 PINTADO DE CERCO PERIMETRICO m2 50.12 S/ 20.29 S/ 1,016.93 S/ 0.00 50.12 S/ 1,016.93 50.12 1,016.93 0.00 0.00
07 GESTION DE RIESGO S/ 21,373.32 S/ 21,373.32 S/ 0.00
07.01 CONSTRUCCION DE MURO DE CONTENCION S/ 21,373.32 S/ 21,373.32 S/ 0.00
07.01.01 TRABAJOS PRELIMINARES S/ 249.75 S/ 249.75 S/ 0.00
07.01.01.01 LIMPIEZA DEL TERRENO MANUAL m2 25.00 S/ 0.69 S/ 17.25 25.00 S/ 17.25 25.00 17.25 0.00 0.00
07.01.01.02 TRAZO Y REPLANTEO INICAL m2 25.00 S/ 4.65 S/ 116.25 25.00 S/ 116.25 25.00 116.25 0.00 0.00
07.01.01.03 TRAZO Y REPLANTEO FINAL m2 25.00 S/ 4.65 S/ 116.25 25.00 S/ 116.25 25.00 116.25 0.00 0.00
07.01.02 MOVIMIENTO DE TIERRAS S/ 9,490.53 S/ 9,490.53 S/ 0.00
07.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 ### S/ 54.02 S/ 5,537.05 102.50 S/ 5,537.05 102.50 5,537.05 0.00 0.00
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN DE RESERVORIOS; EN EL(LA)
SISTEMA DE AGUA POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO BALANCE VALORIZADO Y COSTO TOTAL
ANCASH”
Fórmula: ESTRUCTURAS
VAL Avance K-1 Reajuste Reajuste
N° Ejecutado Ejecutado Reconocido
(2) (3) (2) x (3) (4)
1 0.00 #REF! #REF! #REF!
0.00
2 0.00 -1.000 0.00 0.00
0.00
3 0.00 -1.000 0.00 0.00
0.00
4 0.00 -1.000 0.00 0.00
0.00
5 0.00 -1.000 0.00 0.00
0.00
6 0.00 -1.000 0.00 0.00
0.00
#REF! #REF!
Fórmula: ARQUITECTURA
VAL Avance K-1 Reajuste Reajuste
N° Ejecutado Ejecutado Reconocido
(2) (3) (2) x (3) (4)
1 0.00 #REF! #REF! #REF!
0.00
2 0.00 #REF! #REF! #REF!
0.00
3 0.00 #REF! #REF! #REF!
0.00
4 0.00 #REF! #REF! #REF!
0.00
5 0.00 #REF! #REF! #REF!
0.00
6 0.00 #REF! #REF! #REF!
0.00
#REF! #REF!
RECALCULO DE REINTEGROS ADICIONAL N° 01 - MAYORES METRADOS
Fórmula: ESTRUCTURAS
VAL Avance K-1 Reajuste Reajuste
N° Ejecutado Ejecutado Reconocido
(2) (3) (2) x (3) (4)
1 0.00 -1.000 0.00 0.00
0.00
2 0.00 -1.000 0.00 0.00
0.00
3 0.00 -1.000 0.00 0.00
0.00
4 0.00 -1.000 0.00 0.00
0.00
5 0.00 -1.000 0.00 0.00
0.00
6 0.00 -1.000 0.00 0.00
0.00
0.00 0.00
Fórmula: ARQUITECTURA
VAL Avance K-1 Reajuste Reajuste
N° Ejecutado Ejecutado Reconocido
(2) (3) (2) x (3) (4)
1 0.00 -1.000 0.00 0.00
0.00
2 0.00 -1.000 0.00 0.00
0.00
3 0.00 -1.000 0.00 0.00
0.00
4 0.00 -1.000 0.00 0.00
0.00
5 0.00 -1.000 0.00 0.00
0.00
6 0.00 -1.000 0.00 0.00
0.00
0.00 0.00
RECALCULO DE REINTEGROS ADICIONAL N° 01 PARTIDAS NUEVAS
Obra:
“RENOVACIÓN DE CAPTACIÓN DE AGUA DE
MANANTIAL Y LÍNEA DE CONDUCCIÓN; REPARACIÓN
DE RESERVORIOS; EN EL(LA) SISTEMA DE AGUA
POTABLE EN LA LOCALIDAD BUENOS AIRES, DISTRITO
DE PARIACOTO, PROVINCIA HUARAZ, DEPARTAMENTO
ANCASH”
G.G.D. = G.G.V. x Fr Ip
x
PC x Io
G.G.D. = 129.940