CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

MES 01 MES 02 MES 03


ITEM DESCRIPCIÓN UND METRADO PRECIO UNITARIO PARCIAL 20 - 31 01 - 22
06 - 31 AGOSTO
OCTUBRE NOVIEMBRE
01 OBRAS PRELIMINARES S/. 22,105.19 S/. 13,671.86 S/. 3,040.00 S/. 5,393.33
CARTEL DE IDENTIFICACION DE LA
01.01 und 1.00 S/. 1,540.25 S/. 1,540.25 S/. 1,540.25
OBRA DE 2.40 x 4.80m
CAMPAMENTO PROVISIONAL 2.00 S/. 500.00 S/. 1,000.00 S/. 500.00 S/. 240.00 S/. 260.00
01.02 mes
DE OBRA

MOVILIZACION Y DESMOVILIZACION 1.00 S/. 14,000.00 S/. 14,000.00 S/. 6,066.67 S/. 2,800.00 S/. 5,133.33
01.03 DE EQUIPO Y MAQUINARIA glb

TRAZO NIVELACION Y km 6.96 S/. 799.56 S/. 5,564.94 S/. 5,564.94


01.04
REPLANTEO
02 SEGURIDAD Y SALUD S/. 6,666.76 S/. 2,708.79 S/. 1,396.93 S/. 2,561.02

ELABORACION, IMPLEMENTACION Y
02.01 ADMINISTRACION DEL PLAN DE S/. 6,666.76 S/. 2,708.79 S/. 1,396.93 S/. 2,561.02
SEGURIDAD Y SALUD EN EL TRABAJO

EQUIPOS DE PROTECCION glb 1.00 S/. 2,200.80 S/. 2,200.80 S/. 888.04 S/. 463.33 S/. 849.43
02.01.01 PERSONAL
EQUIPOS DE PROTECCION
02.01.02 COLECTIVA glb 1.00 S/. 847.52 S/. 847.52 S/. 341.98 S/. 178.43 S/. 327.11

SEÑALIZACION TEMPORAL DE glb 1.00 S/. 627.12 S/. 627.12 S/. 271.75 S/. 125.42 S/. 229.94
02.01.03 SEGURIDAD
CAPACITACION DE SEGURIDAD Y glb 1.00 S/. 2,991.32 S/. 2,991.32 S/. 1,207.02 S/. 629.75 S/. 1,154.54
02.01.04 SALUD
03 EXPLANACIONES S/. 334,825.39 S/. 63,162.88 S/. 84,170.34 S/. 187,492.18
03.01 DESBROCE Y LIMPIEZA ha 1.02 S/. 1,331.25 S/. 1,357.88 S/. 1,357.88
CORTE DE MATERIAL SUELTO CON m3 50,053.34 S/. 2.84 S/. 142,151.49 S/. 61,805.00 S/. 37,083.00 S/. 43,263.50
03.02 MAQUINARIA
CORTE ROSA SUELTA (PER. Y DISP.) 2,202.45 S/. 15.60 S/. 34,358.22 S/. 34,358.22
03.03 CON MQUINARIA m3

CORTE ROCA FIJA (PERF. Y DISP.) m3 5,672.49 S/. 27.67 S/. 156,957.80 S/. 47,087.34 S/. 109,870.46
03.04 CON MAQUINARIA
04 IMPACTO AMBIENTAL S/. 7,622.44 S/. 7,622.44
RESTAURACION DEL PATIO DE m2 500.00 S/. 0.48 S/. 240.00 S/. 240.00
04.01 MAQUINAS Y CAMPAMENTO

ACONDICIONAMIENTO DE DEPOSITO m3 6,500.00 S/. 0.60 S/. 3,900.00 S/. 3,900.00


04.02 DE MATERIAL EXCEDENTE

04.03 REVEGETACION ha 1.00 S/. 3,482.44 S/. 3,482.44 S/. 3,482.44


PLAN PARA LA VIGILANCIA,
05 PREVENCION Y CONTROL DE COVID - S/. 4,175.50 S/. 1,809.38 S/. 835.10 S/. 1,531.02
19 EN EL TRABAJO
PLAN PARA LA EMERGENCIA glb 1.00 S/. 4,175.50 S/. 4,175.50 S/. 1,809.38 S/. 835.10 S/. 1,531.02
05.01 SANITARIA COVID - 19
06 FLETE S/. 2,585.58 S/. 1,120.42 S/. 517.12 S/. 948.05
06.01 FLETE TERRESTRE glb 1.00 S/. 2,585.58 S/. 2,585.58 S/. 1,120.42 S/. 517.12 S/. 948.05

COSTO DIRECTO S/377,980.86 S/82,473.33 S/89,959.49 S/205,548.04


GASTOS GENERALES S/45,673.15 S/9,965.63 S/10,870.22 S/24,837.31
UTILIDAD S/26,454.57 S/5,772.24 S/6,296.19 S/14,386.14
SUB TOTAL S/450,108.58 S/98,211.20 S/107,125.90 S/244,771.49
IGV (18%) S/81,019.55 S/17,678.02 S/19,282.66 S/44,058.87
TOTAL PRESUPUESTO S/531,128.13 S/115,889.22 S/126,408.56 S/288,830.35

% PROGRAMADO 21.82% 23.80% 54.38%


% PROGRAMADO ACUM. 21.82% 45.62% 100.00%