Con Comentarios
Con Comentarios
Con Comentarios
Documentum Location: Docbases \ fls_prod_doc \ Documents \ Instruction \ Ball mill \ 726 \ Erection Instruction
Scope: This document identifies procedures essential towards the successful installation
and operation of the designated equipment. The check list is to be completed,
signed and dated by the erection supervisor. A copy is to be maintained in the
field site records and a copy is to be sent to FLSmidth c/o the designated project
manager.
NOTE
This check list is not a replacement for the installation and operation documents provided with
the project instruction manuals (references) which are to be read and understood prior to the
commencement of erection work and operation of the equipment.
las cuñas de la placa base
verificar la ubicación y estén correctamente
elevación de los pilares de ubicadas, niveladas y
cimentación y la ubicación y enlechadas de acuerdo con
70008612 proyección de los pernos de el manual de 3 instrucciones
todas las instrucciones han anclaje del contrato. mida la
sido leídas y entendidas nivelación de la parte
superior de la suela.
registrar lecturas. figura 1
7.
polos del motor instalados,
Shell, heads, trunnions assembled in cradles. Critical bolts tightened
verificaciones de to initial pre-load. Joint tightness verified. cáscara, cabezas, muñones
descentramiento del rotor y ensamblados en cunas.
8.
mediciones preliminares Lift pad assemblies are: inspected, cleaned, lubricated and installed. crítica, pernos apretados a
entrehierro confirmadas, la precarga inicial.
estanqueidad conjunta
9.
registradas y aprobadas Temporary or permanent lube sy system is installed and operation
el proveedor del motor verificada
confirmed. Mill is lowered in th
the bearings. Trunnion and bearing
housing clearances are uniform. los conjuntos de plataforma
de elevación son:
inspeccionados, limpiados,
10. Critical bolts tightened to final pr
pre-load. Joint tightness verified. lubricados e instalados
requerido antes de la12. Thrust pads are assembled with the specified axial and radial utilizando galgas de
rotación del molino: clearances according to the contract instruction manual. espesores, se mide el
elevación hidrostática, contacto entre los dos
molino vacío, revestimientos
13. Motor poles installed, rotor run-out checks and preliminary air gap muñones y las ocho
y polos del motor no measurements confirmed, recorded and approved by motor supplier. almohadillas de elevación
instalados. con indicadores de acuerdo con el manual
de carátula, verifique que la de instrucciones del
14.
elevación sea mayor que
Required before mill rotation
rotation: Hydrostatic lift, mill empty, liners contrato. las holguras en
0.003 o 0.075. nota: con and motor poles not installed. With dial indicators, verify lift is seis ubicaciones por
sistema de lubricación greater than 0.003" or 0.075 mm. Note: With temporary lube system, almohadilla no superan los
temporal, la elevación acceptable lift is +/- 0.001" or 0.025 mm. 0,03 mm
aceptable es de 0,001 o
0,025 mm
70008612 4
los revestimientos del molino y los polos del motor pueden instalarse
ahora rotando el molino con el sistema de lubricación permanente o con
un sistema de lubricación temporal. los elementos restantes de la lista de
verificación se deben realizar solo con el sistema de lubricación
permanente después: de completar el montaje del molino
NOTE:
NOTE
The mill liners and motor poles may be installed now by rotating the mill with the
conpermanent
el sistema de lubricación
lube system or with a temporary lube system. The remaining check list items areentofuncionamiento,
be made only
with the permanent lube system after erection of the mill is complete. refiriéndose a los
manómetros conectados a
15. With the lube system operating, referring to the pressure gauges las líneas de suministro de
connected to the bearing supply lines; verify the central recess pressure los cojinetes, verifique que la
presión del receso central de
of each pad, is within +/- 5% of the average pressure per bearing. Record cada pastilla esté dentro de
results in table, figure 6. 0,05 de la presión promedio
por cojinete. registrar los
16. With the lube system operating, utilizing temporary pressure gauges resultados en la tabla. figura
connected to pressure ports on each of the four corner pockets, measure 6
the corner pocket pressures, one pad at a time. Confirm the pressures are con el sistema de
between 1 MPa and 1.7 MPa lower than the central recess pressure. lubricación en
funcionamiento, utilizando
17. With the lube system operating, using feeler gauges, measure the manómetros temporales
operating clearances between the lift pads and the trunnion at six conectados a los puertos de
locations per pad and the thrust pads at three locations per pad as shown presión en cada uno de los
in Figure 3. Verify the lift pad clearance is greater than 0.006" or 0.15 cuatro bolsillos de las
esquinas, mida las
mm and the thrust pad clearance is greater than 0.013" or 0.35 mm. presiones de los bolsillos de
Record results in table, figure 5. las esquinas, una
almohadilla a la vez.
18. Main bearing seal assemblies are lubricated
icated and positioned with a slight confirme que las presiones
gap between the rubber and trunnion; +/- 0.005"; 0.15 mm. estén entre 1 mpa y 1,7 mpa
por debajo de la presión del
19. Verify the mill is insulated from ground. Measure the resistance of each hueco central
lift pad assembly from the top center of the pad to bottom of hydraulic
jack base is greater than 1 k . Complete Form 3. con el sistema de
lubricación en
20. Verify flange joints are tight from outside mill. funcionamiento, utilizando
galgas de espesores, mida
las holguras operativas
21. Required for “no load” operation:: Hydrostatic lift, mill empty, liners
entre las almohadillas de
and motor poles installed. With dial iindicators,
ndicators, verify lift is greater than elevación y el muñón en
0.003" or 0.075 mm. Complete Form 1 and 2. seis lugares por almohadilla
y las almohadillas de
requerido para la operación empuje en tres ubicaciones
"sin carga": elevación por almohadilla, como se
hidrostática, molino vacío, los conjuntos de sellos del muestra en la figura 3.
revestimientos y polos del cojinete principal están verifique que la holgura de
Verifique que el molino esté
motor instalados. con lubricados y colocados con la almohadilla de elevación
aislado de tierra. mida la
indicadores de carátula, un pequeño espacio entre la sea superior a 0,006 o 0,15
resistencia de cada conjunto
verifique que la elevación goma y el muñón mm y la holgura de la
de almohadilla de elevación
sea mayor que 0.003 o almohadilla de empuje es
desde el centro superior de
0.075. completar formulario superior a 0,013 o 0,35 mm.
la almohadilla hasta la parte
1y2 registre los resultados en la
inferior de la base del gato
hidráulico es mayor que 1 k. tabla figura 5
Verifique que las juntas de formulario completo 3
brida estén apretadas desde
el exterior del molino
70008612 5
6. “Partial load operation, 50% of full load grinding charge and ore
feed rate”: Oil film across trunnion is uniform, RTD temperature
gradient is within tolerance, seal contact is not tight, no vibration, no
unusual sounds. Complete Form 1 and 2.
8. Verify preliminary “partial load” motor air gap. Record, obtain motor
supplier approval.
10. “Full load operation, 100% of full load grinding charge and ore
feed rate”: Verify pressure distribution of lift pads in steady state
operation. Re-align the bearing pads if necessary to obtain a pad
pressure distribution, with load, within +/- 10% of the average
pressure per bearing.
11. “Full load operation, 100% of full load grinding charge and ore
feed rate”: Verify the hydrostatic lift of the mill loaded. With dial
indicators, verify lift is greater than 0.003" or 0.075 mm. Complete
Form 1 and 2.
12. “Full load operation, 100% of full load grinding charge and ore
feed rate”: Oil film across trunnion is uniform, RTD temperature
gradient is within tolerance, seal contact is not tight, no vibration, no
unusual sounds. Complete Form 1.
70008612 6
13. Verify the pad pressure distribution, with full load, is within +/- 5%
of the average pressure per bearing when mill stopped and +/- 10% of
the average pressure per bearing when the mill is in steady state
operation. Adjust bearings if necessary prior to operating the mill.
14. Re-check final “full load” motor air gap, record, obtain motor supplier
approval.
15. After 30 days of full load operation, verify critical fastener elongation,
registro de entrega de
100% of the bolts. documentos
Sign/date: _____________________
agujero de lechada
70008612 7
LATERAL SCRE W
SHEAR PLATES
LEVEL SCRE W
muelle aspero perno de
cimentacion
tornillo de nivel
paquete de cuñas
registro de lecturas de
FIGURE 1 medición de nivel en cuatro
ubicaciones igualmente
especificadas.
Axial: L5 L6 L7 L8
muñón flotante
Floating Trunnion:
Lateral: L1 L2 L3 L4
Axial: L5 L6 L7 L8
Signed/Date: _________________________
70008612 8
L1 _______________ L2 ______________
Signed/Date: ___________________
70008612 9
cojinete de empuje
FIGURE 3
FORM 1
operacion sin carga
Center RTD
Inboard RTD
Center RTD
Outboard RTD
Inboard RTD
Center RTD
Outboard RTD
Signed/Date: ___________________
70008612 14
elevación hidrostática
Form 2 los indicadores de carátula
2 y 4 deben estar en línea
Hydrostatic Lift con las almohadillas de los
cojinetes internos
Dial Indicators 2 and 4 to be in line with inner bearing pads.
vacio
extremo de aliimentacion
Discharge End
Discharge End
Discharge End
medicion de aislamiento
rodamientos flotantes
Form 3
Insulation Measurements
Pad A5
Pad A6
Pad A7
Pad A8
cojinete fijo
Fixed Bearings
Pad A1
Pad A2
Pad A3
Pad A4
Pad B1
Pad B2
Pad B3
Pad B4
Sign/Date: _____________________