MINISTERIO DE CULTURA
PRESUPUESTO SEDE ADMINISTRATIVA
CANTIDAD TIEMPO TIEMPO
CARGO / OFICIO DEDICACIÓN SALARIO VALORPARCIAL ($)
(Personas) (Meses) (1) (1x2x3x4)=(5)
(2) (3) (4)
PERSONAL PROFESIONAL
DIRECTOR INTERVENTORIA 1 6 30% $ 4,500,000.00 $ 8,100,000.00
RESIDENTE DE INTERVENTORIA 1 6 100% $ 2,500,000.00 $ 15,000,000.00
INSPECTOR DE OBRA 1 6 30% $ 1,800,000.00 $ 3,240,000.00
RESIDENTE EN HSQ 1 6 30% $ 1,800,000.00 $ 3,240,000.00
ESPECIALISTA HIDROSANITARIO Y AMBIENTAL 1 6 15% $ 4,700,000.00 $ 4,230,000.00
ESPECIALISTA EN GEOTECNIA 1 6 15% $ 4,700,000.00 $ 4,230,000.00
ESPECIALISTA ELECTRICO 1 6 15% $ 4,700,000.00 $ 4,230,000.00
ESPECIALISTA EN ESTRUCTURAS 1 6 15% $ 4,700,000.00 $ 4,230,000.00
PERSONAL TÉCNICO Y ADMINISTRATIVO
CONTADOR 1 6 25% $ 1,800,000.00 $ 2,700,000.00
ABOGADO 1 6 20% $ 2,000,000.00 $ 2,400,000.00
SECRETARIA 1 6 100% $ 877,803.00 $ 5,266,818.00
SUBTOTAL COSTOS DE PERSONAL $ 56,866,818.00
FACTOR MULTIPLICADOR F.M. (1) 1.20
TOTAL COSTOS DE PERSONAL = SUMATORIA (5) x F.M. = (A) $ 68,240,182.00
GASTOS OPERACIONALES
CANTIDAD/MESES COSTO VALOR PARCIAL ($)
CONCEPTO UNIDAD (-8-) ($) (6x7)=(9)
(7) (6)
Oficina/Campamento en la zona del proyecto (incluye dotacion y servicios) MES 6 $ 650,000.00 $ 3,900,000.00
Transporte MES 6 $ 450,000.00 $ 2,700,000.00
Laboratorios
Toma de densidades (cono y arena) CANTD 10 $ 100,000.00 $ 1,000,000.00
Toma de cilindros CANTD 35 $ 100,000.00 $ 3,500,000.00
Papeleria y Planimetria MES 6 $ 500,000.00 $ 3,000,000.00
Comunicaciones MES 6 $ 500,000.00 $ 3,000,000.00
TOTAL GASTOS Y COSTOS OPERACIONALES DE INTERVENTORIA = SUMATORIA (9) = (B) $ 17,100,000.00
COSTO TOTAL = (A) + (B) $ 85,340,182.00
IVA 19 % 19.00% $ 16,214,635.00
VALOR TOTAL DE INTERVENTORIA $ 101,554,817.00