Municipalidad Distrital de Poroy: Informe Técnico
Municipalidad Distrital de Poroy: Informe Técnico
Municipalidad Distrital de Poroy: Informe Técnico
INFORME TÉCNICO:
P á g i n a 1 | 19
1.1.5. UBICACIÓN.
LOCALIDAD : POROY-CUSCO-PERU
SECTOR : POROY
DISTRITO : POROY
PROVINCIA : CUSCO
DEPARTAMENTO : CUSCO
P á g i n a 2 | 19
A
PRESUPUESTO EXPEDIENTE TÉCNICO S/.
APROBADO 257,960.98
PRESUPUESTO EXPEDIENTE TÉCNICO S/. S/. -
-21.65%
MODIFICACIÓN N°01 202,120.48 55,840.50
S/. -
INCIDENCIA PERFIL Y EXPEDIENTE -21.65%
55,840.50
PRESUPUES AVANCE
AVANCES ANTERIOR AVANCE ACTUAL SALDO
TO ACUMULADO
ITE VALORIZACIO
M N Valorizado % Valorizado % Valorizado % Valorizado %
S/.
S/. S/. S/. S/.
PROGRAMADO S/ S/ S/ S/
1 0% 1.48% 1.48% 98.52%
(CD) 199,968.79 2,955.60 2,955.60 197,013.19
GASTOS S/ S/ S/ S/ S/
2 0% 24.21% 24.21% 75.79%
GENERALES 19,996.87 - 4,841.20 4,841.20 15,155.67
GASTOS DE S/ S/ S/ S/ S/
3 0% 0% 0.00% 100.00%
SUPERVISION 19,996.88 - - - 19,996.88
GASTOS DE S/ S/ S/ S/ S/
4 0% 0% 0.00% 100.00%
LIQUIDACION 9,998.44 - - - 9,998.44
GASTOS DE
S/ S/ S/ S/ S/
5 EXPEDIENTE 0% 0% 0.00% 100.00%
8,000.00 - - - 8,000.00
TECNICO
S/ S/ S/ S/
COSTO TOTAL 0% 26% S/ 7,796.80 26% 96.98%
257,960.98 - 7,796.80 250,164.18
El avance Financiero del proyecto al mes de OCTUBRE del 2021 acumulado es 1.88 %.
S/. 4,841.20 (CUATRO MIL OCHOCIENTOS CUARENTA Y UN CON VEINTE CON
20/100 Soles)
N EJECUTAD
DESCRIPCIÓN EXPEDIENTE % % SALDO %
° O
AVANCE S/. 100 1.88 S/.
1 S/. 4,841.20 98.12%
FINANCIERO 257,960.98 % % 253,199.78
RESIDENTES DE OBRA
INSPECTORES DE OBRA
PROYECTISTA:
1° NOMBRE DEL PROYECTISTA : ING. PEDRO GONZALES
HUARCAYA QUISPE
CIP - 60132
1.3. BASE LEGAL
1.3.1. NORMAS QUE REGULAN LA EJECUCIÓN DE LAS OBRAS PUBLICAS POR
ADMINISTRACIÓN DIRECTA
P á g i n a 7 | 19
La residencia afirma que los rendimientos son inferiores a los rendimientos presentados en
el expediente técnico, los cuales hacen que la ejecución de las diferentes actividades diarias
sea más duradera de lo debido.
AMPLIACI
ON DE
DESCRIPCION
PLAZO EN
DIAS
POR FALTA DE MANO DE OBRA 7
CAUSAL 01
CALIFICADA Y BAJO RENDIMIENTO
CAUSAL 02 PARTIDAS COMPLEMENTARIAS 8
TOTAL DE DIAS PARA LA AMPLIACION N°01 15
UN
ITEM DESCRIPCION Metrado Precio (S/.) Parcial (S/.)
D
01 REPARACION SISTEMA DE BOMBEO
01.01 TRABAJOS PRELIMINARES
S/.
01.01.01 CARTEL DE IDENTIFICACION DE OBRA und 1.00 S/. 333.98
333.98
S/.
01.01.02 TRAZO Y REPLANTEO m2 1200.00 S/. 1,596.00
1.33
P á g i n a 8 | 19
S/.
01.02.02 CAMA DE APOYO PARA TUBERIAS, e=10CM m 150.00 S/. 3,061.50
20.41
RELLENO CON MATERIAL PROPIO ZARANDEADO Y COMPACTADO S/.
01.02.03 m3 13.50 S/. 1,587.33
MANUAL 117.58
S/.
01.02.04 RELLENO CON MATERIAL PROPIO m3 67.50 S/. 1,995.30
29.56
S/.
01.02.05 INSTALACION DE TUBERÍA PVC SAP DE 2" m 150.00 S/. 2,455.50
16.37
S/.
01.02.06 PRUEBA HIDRÁULICA m 150.00 S/. 43.50
0.29
EXPLORACIÓN GEOFISICA Y PERFORACIÓN DE POZO DE S/.
01.02.07 glb 1.00 S/. 20,000.00
PRODUCCIÓN DE AGUAS 20,000.00
01.03 TUBERIA IMPULSION TRAMO 2 S/. -
S/.
01.03.02 CAMA DE APOYO PARA TUBERIAS, e=10CM m 250.00 S/. 5,102.50
20.41
RELLENO CON MATERIAL PROPIO ZARANDEADO Y COMPACTADO S/.
01.03.03 m3 22.50 S/. 2,645.55
MANUAL 117.58
S/.
01.03.04 RELLENO CON MATERIAL PROPIO m3 112.50 S/. 3,325.50
29.56
S/.
01.03.05 INSTALACION DE TUBERÍA PVC SAP DE 2" m 250.00 S/. 4,092.50
16.37
S/.
01.03.06 PRUEBA HIDRÁULICA m 250.00 S/. 72.50
0.29
EXPLORACIÓN GEOFISICA Y PERFORACIÓN DE POZO DE S/.
01.03.07 glb 1.00 S/. 20,000.00
PRODUCCIÓN DE AGUAS 20,000.00
01.04 OBRAS DE CONCRETO SIMPLE S/. -
S/.
01.04.01 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS HIDRÁULICAS m2 1.20 S/. 158.16
131.80
S/.
01.04.02 ENROCADO CON PIEDRA PESADA (ZAMPEADO); E=0.30 M A MANO m2 0.68 S/. 22.45
33.02
S/.
01.04.03 CONCRETO f'c=140 kg/cm2 PARA SOLADOS m3 0.68 S/. 228.95
336.69
S/.
01.04.04 CONCRETO C:H 1:10 + 30% P.M. PARA CIMIENTOS m3 1.00 S/. 195.78
195.78
S/.
01.04.05 SARDINEL DE CONCRETO SIMPLE F'C=175 KG/CM2 DE 20X40 CM. m 6.00 S/. 130.02
21.67
S/.
01.04.06 CURADO DE CONCRETO m2 1.20 S/. 0.26
0.22
01.05 CARPINTERÍA METÁLICA S/. -
S/.
01.05.01 COBERTURA DE ALUZINC 1.07m x 5.0m x 0.4mm m2 6.00 S/. 1,200.00
200.00
S/.
01.05.02 PUERTA METÁLICA DE 0.90 x 2.50 m INC. CERRADURA und 2.00 S/. 1,120.00
560.00
S/.
01.05.03 CERCO CON MALLA OLÍMPICA GALVANIZADA DE 2''x2'' m 12.00 S/. 5,760.00
480.00
01.06 PINTURA S/. -
S/.
01.06.01 PINTURA ANTICORROSIVA m2 36.00 S/. 184.68
5.13
02 CONSTRUCCION DE PLATAFORMA S/. -
02.01 TRABAJOS PRELIMINARES S/. -
S/.
02.01.01 TRAZO Y REPLANTEO m2 225.00 S/. 299.25
1.33
S/.
02.01.02 EXCAVACION P/BASE DE LOSA EN TERRENO NORMAL m3 8.10 S/. 157.95
19.50
S/.
02.01.03 ENROCADO CON PIEDRA PESADA (ZAMPEADO); E=0.30 M A MANO m2 8.10 S/. 267.46
33.02
02.02 OBRAS DE CONCRETO SIMPLE S/. -
P á g i n a 9 | 19
S/.
02.02.01 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 36.00 S/. 4,744.80
131.80
S/.
02.02.02 CONCRETO f'c=175 kg/cm2 PARA SOLADOS m3 7.20 S/. 3,501.58
486.33
S/.
02.02.03 CONCRETO C:H 1:10 + 30% P.M. PARA CIMIENTOS m3 4.00 S/. 783.12
195.78
S/.
02.02.04 SARDINEL DE CONCRETO SIMPLE F'C=175 KG/CM2 DE 20X40 CM. m 24.00 S/. 520.08
21.67
S/.
02.02.05 CURADO DE CONCRETO m2 24.00 S/. 5.28
0.22
02.03 OBRAS DE CONCRETO ARMADO S/. -
S/.
02.03.01 ENCOFRADO Y DESENCOFRADO DE LOSAS m2 36.00 S/. 4,744.80
131.80
S/.
02.03.02 JUNTAS ASFÁLTICAS m 7.00 S/. 61.60
8.80
S/.
02.03.03 CONCRETO f'c=175 kg/cm2 PARA LOSAS m3 8.10 S/. 3,274.51
404.26
S/.
02.03.04 ACERO fy=4200 kg/cm2 kg 50.00 S/. 567.00
11.34
S/.
02.03.05 CURADO DE CONCRETO m2 24.00 S/. 5.28
0.22
TARRAJEO IMPERMEABILIZADO C/MORTERO MEZCLA C:M 1:5, e=1.5 S/.
02.03.06 m2 72.00 S/. 1,402.56
cm 19.48
02.04 CARPINTERÍA METÁLICA S/. -
S/.
02.04.01 PUERTA METÁLICA DE 0.90 x 2.50 m INC. CERRADURA und 1.00 S/. 560.00
560.00
S/.
02.04.02 CERCO CON MALLA OLÍMPICA GALVANIZADA DE 2''x2'' m 23.00 S/. 11,040.00
480.00
02.05 PINTURA S/. -
S/.
02.05.01 PINTURA ANTICORROSIVA m2 72.00 S/. 369.36
5.13
03 ADQUISICION DE CISTERNA S/. -
03.01 TRABAJOS PRELIMINARES S/. -
S/.
03.01.01 TRANSPORTE DE MATERIAL DESMONTADO glb 1.00 S/. 216.93
216.93
03.02 INSTALACIÓN DE ACCESORIOS Y CISTERNA S/. -
S/.
03.02.01 INSTALACIÓN DE CISTERNA und 1.00 S/. 4,190.77
4,190.77
S/.
03.02.02 INSTALACIÓN SUMINISTROS DE CISTERNA glb 1.00 S/. 2,000.00
2,000.00
03.03 SISTEMA DE CLORACIÓN S/. -
S/.
03.03.01 ARMADURA DE ESTRUCTURA METÁLICA und 1.00 S/. 2,000.00
2,000.00
S/.
03.03.02 INSTALACIÓN DE TANQUE DE CLORACION glb 1.00 S/. 3,000.00
3,000.00
03.04 SEGURIDAD Y SALUD S/. -
S/.
03.04.01 EQUIPOS DE PROTECCIÓN COLECTIVA glb 1.00 S/. 1,100.00
1,100.00
S/.
03.04.02 EQUIPOS DE PROTECCIÓN INDIVIDUAL glb 1.00 S/. 2,600.00
2,600.00
S/.
03.04.03 IMPLEMENTACION SANITARIA DEL PROYECTO POR COVID-19 glb 1.00 S/. 691.00
691.00
04 RENOVACION DE RED DE DISTRIBUCION S/. -
04.01 TRABAJOS PRELIMINARES S/. -
S/.
04.01.01 TRAZO Y REPLANTEO m2 1800.00 S/. 2,394.00
1.33
Transporte de Agregados y Piedra con Volquete 5 m³ (D = 5 a 7 Km) -
S/.
04.01.02 Carguío a mano m3 10.00 S/. 209.00
20.90
Equipo
Transp. de Tuberia Hasta Ø 2" con Volquete 5 m³ (D = 5 a 7 Km) - Carguío a S/.
04.01.03 m 200.00 S/. 182.00
Mano 0.91
S/.
04.01.04 Transporte de Cemento con Bugui (Distancia de 0.100 a 200 m) bls 15.00 S/. 226.50
15.10
04.02 TUBERÍA EN LÍNEA DE DITRIBUCION TRAMO 01 S/. -
S/.
04.02.01 EXCAVACIÓN CAJA CANAL MATERIAL SUELTO A MANO m3 60.00 S/. 1,477.80
24.63
04.02.02 CAMA DE APOYO PARA TUBERIAS, e=10CM m 100.00 S/. S/. 2,041.00
P á g i n a 10 | 19
20.41
RELLENO CON MATERIAL PROPIO ZARANDEADO Y COMPACTADO S/.
04.02.03 m3 9.00 S/. 1,058.22
MANUAL 117.58
S/.
04.02.04 RELLENO CON MATERIAL PROPIO m3 45.00 S/. 1,330.20
29.56
S/.
04.02.05 INSTALACION DE TUBERÍA PVC SAP DE 2" m 100.00 S/. 1,637.00
16.37
S/.
04.02.06 PRUEBA HIDRÁULICA m 100.00 S/. 29.00
0.29
04.02.07 PILETA PÚBLICA S/. -
04.02.07.0 S/.
EXCAVACIÓN CAJA CANAL MATERIAL SUELTO A MANO m3 6.00 S/. 147.78
1 24.63
04.02.07.0 S/.
ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS HIDRÁULICAS m2 4.00 S/. 527.20
2 131.80
04.02.07.0 S/.
SOLADO DE CONCRETO MEZCLA C:H 1:12 DE 2" m2 5.00 S/. 88.55
3 17.71
04.02.07.0 S/.
CONCRETO f'c=175 kg/cm2 PARA OBRAS HIDRÁULICAS m3 4.00 S/. 1,617.04
4 404.26
04.02.07.0 S/.
CURADO DE CONCRETO m2 5.00 S/. 1.10
5 0.22
04.02.07.0 S/.
INSTALACION DE PILETA und 5.00 S/. 455.80
6 91.16
04.03 TUBERÍA EN LÍNEA DE DITRIBUCION TRAMO 02 S/. -
S/.
04.03.01 EXCAVACIÓN CAJA CANAL MATERIAL SUELTO A MANO m3 60.00 S/. 1,477.80
24.63
S/.
04.03.02 CAMA DE APOYO PARA TUBERIAS, e=10CM m 100.00 S/. 2,041.00
20.41
RELLENO CON MATERIAL PROPIO ZARANDEADO Y COMPACTADO S/.
04.03.03 m3 9.00 S/. 1,058.22
MANUAL 117.58
S/.
04.03.04 RELLENO CON MATERIAL PROPIO m3 45.00 S/. 1,330.20
29.56
S/.
04.03.05 INSTALACION DE TUBERÍA PVC SAP DE 2" m 100.00 S/. 1,637.00
16.37
04.03.06 PILETA PÚBLICA S/. -
04.03.06.0 S/.
EXCAVACIÓN CAJA CANAL MATERIAL SUELTO A MANO m3 6.00 S/. 147.78
1 24.63
04.03.06.0 S/.
ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS HIDRÁULICAS m2 4.00 S/. 527.20
2 131.80
04.03.06.0 S/.
SOLADO DE CONCRETO MEZCLA C:H 1:12 DE 2" m2 5.00 S/. 88.55
3 17.71
04.03.06.0 S/.
CONCRETO f'c=175 kg/cm2 PARA OBRAS HIDRÁULICAS m3 4.00 S/. 1,617.04
4 404.26
04.03.06.0 S/.
CURADO DE CONCRETO m2 4.00 S/. 0.88
5 0.22
04.03.06.0 S/.
INSTALACION DE PILETA und 5.00 S/. 455.80
6 91.16
TOTAL S/ 148,511.95
esto generando un incremento en el presupuesto motivo por el cual esta residencia solicita la
actualización de precios para poder continuar con las actividades programadas y cumplir con la
meta del proyecto.
Se realizará la actualización de precio por las incoherencias en su análisis de precios unitarios de las
partidas siguientes.
ACTUALIZACION DE PRECIOS
Item Descripción
Precio Precio Parcial
UND Metrado
Anterior Actual (S/.) Actual(S/.)
01 REPARACION SISTEMA DE BOMBEO
EXCAVACIÓN CAJA CANAL MATERIAL SUELTO A 24.63
01.02.01 m3 90.00 18.15 2216.70
MANO
EXCAVACIÓN CAJA CANAL MATERIAL SUELTO A 24.63
01.03.01 m3 150.00 18.15 3694.50
MANO
S/.
TOTAL
5,911.20
P á g i n a 12 | 19
Las causales del aumento a los costos indirectos del expediente técnico son debido a, la
ampliación de plazo y mayores metrados en la modificación N°01.
MODIFICACIO
APROBADO EXPEDIENT
N
SEGÚN E
DESCRIPCION PRESUPUESTA
EXPEDIENTE MODIFICAD
L COSTO
TECNICO O N°01
INDIRECTO
El incremento de los costos indirectos en el proyecto es a causa de las modificaciones que viene
teniendo el expediente primogénito debido a los adicionales (PARTIDAS
COMPLEMENTARIAS Y DEDUCTIVOS DE OBRA) como también a la actualización de
precios de la modificación N° 01 que se solicitará para continuar con el proyecto.
PRECIO
DESCRIPCION
MODIFICADO
CAUSAL S/. 195,612.79
POR DEDUCTIVOS DE OBRA C.D
01
CAUSAL S/. 148,511.95
POR PARTIDAS COMPLEMENTARIAS C.D
02
CAUSAL S/. 1,555.20
ACTUALIZACIÓN DE PRECIOS
03
CAUSAL (-) S/. 10,294.86
REDUCCION EN COSTOS INDIRECTOS
04
S/. 202,120.48
TOTAL PRESUPUESTO MODIFICADO
P á g i n a 13 | 19
Existe partidas que no van a ser ejecutadas a causa de no ser en gran parte compatible con las
necesidades y objetivos de la IOARR
a. Características
Son partidas que no son necesarias para la conclusión de metas, en algunos casos son partidas que son
reemplazadas por otras que se vinculan directamente.
b. Justificación
Se realizará la deducción de partidas no vinculantes que generaran una un atraso en tiempos y en
los procesos de construcción y metrados que fueron contemplados en la IOARR.
1 Activo 01 : Reparacion Sistema de Bombeo
1.1 RED BOMBEO N°1 - MEJORAMIENTO (01 UNID)
Electrobomba multietápica horizontal PENTAX U7 400/ 5T 4HP (NUEVO) und 1 3,905.62 3,905.62
1.2.2.0 Relleno cama de apoyo con suelo tamizado m3 15.34 S/ 67.77 S/ 1,039.59
2
1.2.3 Relleno cama protección suelo tamizado m3 30.67 S/ 71.25 S/ 2,185.24
1.2.4 Relleno con suelo granel m3 51.12 S/ 67.77 S/ 3,464.40
1.2.5 Retiro material excedente m3 31.95 S/ 14.27 S/ 455.93
1.3 Tuberías S/ 2,325.41
Suministro de Tuberias Tubo PVC SAP C 10 Ø 1/2" m 213 S/ 8.07 S/ 1,718.91
Accesorios de linea de Impulsion glb 1 S/ 500.00 S/ 500.00
1.4 Prueba hidráulica instalada insitu. m 213 S/ 0.50 S/ 106.50
3.6 RED BOMBEO N°2 - MEJORAMIENTO (01 UNID) S/ 3,390.62
3.6.1 Electrobomba multietápica VERTICAL PENTAX U5V 400/8T 4HP und 1 S/ 3,390.62 S/ 3,390.62
3.7 TUBERIA IMPULSION TRAMO 2 (306 m.l ) S/ 16,301.13
3.7.1 Trabajos preliminares
3.7.2 Trazo nivelacion y replanteo longitudinal. m 306 S/ 1.03 S/ 315.18
3.7.3 Movimiento de tierras
P á g i n a 14 | 19
P á g i n a 15 | 19
P á g i n a 16 | 19
6.2.4.9 Tee PVC SAP C10 D= 1/ 2" X 1 /2" und 3 S/ 4.53 S/ 13.59
6.2.4.0 Reducción PVC SAP C10 D= 1" - 3/4" und 2 S/ 4.77 S/ 9.54
6.2.4.1 Reducción PVC SAP C10 D= 3/4" - 1/2" und 2 S/ 3.93 S/ 7.86
6.2.4.2 Tee PVC SAP C10 D= 3/4 " X 1/2" und 1 S/ 5.85 S/ 5.85
6.2.4.3 Tee PVC SAP C10 D= 1" x 3/4 " und 2 S/ 5.97 S/ 11.94
6.2.4.4 Tee PVC SAP C10 D= 1 1/2" x 3/4 " und 6 S/ 12.15 S/ 72.90
6.2.4.5 Tee PVC SAP C10 D= 3/4" x 3/4 " und 1 S/ 5.97 S/ 5.97
6.3 CAMARA VALVULA CONTROL ( 02 UNID ) S/ 633.69
6.3.1 Obras preliminares S/ 0.66
6.3.1.1 Trazo nivelacion y replanteo en area m2 0.64 S/ 1.03 S/ 0.66
6.3.2 Movimiento de tierras con miscelaneos S/ 3.57
6.3.2.1 Excavación plataforma, fundación, muro int. m3 0.16 S/ 8.06 S/ 1.29
6.3.2.2 Retiro de suelo de excavación excedentes m3 0.16 S/ 14.27 S/ 2.28
6.3.3 Encofrado, desencofrado S/ 15.11
6.3.3.1 Encofrado de muros perimétricos m2 0.34 S/ 44.45 S/ 15.11
6.3.4 Estructura de concreto S/ 37.18
6.3.4.1 Muro perimétrico fc'= 175 Kg/cm2 m3 0.09 S/ 413.14 S/ 37.18
6.3.5 Tarrajeo S/ 46.51
6.3.5.1 Tarrajeo cara interna, externa visible m2 1.7 S/ 27.36 S/ 46.51
6.3.6 Tapas (instalaciones especiales) S/ 271.80
6.3.6.1 Tapa metálica 0.45m x 0.30m, e =1/ 16" und 2 S/ 135.90 S/ 271.80
6.3.7 Accesorios S/ 258.86
6.3.7.1 Codo PVC SAP C10 Ø 1 1/2" X 45º SP und 8 S/ 8.61 S/ 68.88
6.3.7.2 Adaptador PVC SAP C10 Ø 1 1/2" und 4 S/ 5.95 S/ 23.80
6.3.7.3 Unión universal PVC SAP C10 Ø 1 1/2 " und 4 S/ 16.06 S/ 64.24
6.3.7.4 Niple Re PVC SAP C10 Ø 1 1/2" x 2" und 4 S/ 6.22 S/ 24.88
6.3.7.5 Válvula esferica PVC SAP Ø 1 1/2 " und 2 S/ 25.05 S/ 50.10
6.3.7.6 Niple R mixto PVC SAP C10 Ø 1 1/2" x 4" und 4 S/ 6.74 S/ 26.96
6.4 CAMARA VALVULA DE AIRE ( 09 UNID ) S/ 2,245.83
6.4.1 Obras preliminares S/ 2.32
6.4.1.1 Trazo nivelacion y replanteo en area m2 2.25 S/ 1.03 S/ 2.32
6.4.2 Movimiento de tierras con miscelaneos S/ 10.88
6.4.2.1 Excavación plataforma, fundación, muro int. m3 1.35 S/ 8.06 S/ 10.88
6.4.3 Estructura de concreto S/ 291.31
6.4.3.1 Muro perimétrico, fc'= 140 Kg/cm2 m3 0.68 S/ 428.40 S/ 291.31
6.4.4 Encofrado, desencofrado S/ 100.01
6.4.4.1 Encofrado de muros perimétricos m2 2.25 S/ 44.45 S/ 100.01
6.4.5 Tarrajeo S/ 246.24
6.4.5.1 Tarrajeo cara interna, externa visible m2 9 S/ 27.36 S/ 246.24
6.4.6 Accesorios (instalaciones especiales) S/ 371.97
6.4.6.1 Válvula aire doble efecto, Ø 3/4" und 9 S/ 15.92 S/ 143.28
6.4.6.2 Niple Fº Gº, Ø 3/4" x 0.50m und 9 S/ 3.70 S/ 33.30
6.4.6.3 Unión PVC SAP C10, Ri, Ø 3/4" und 9 S/ 8.99 S/ 80.91
6.4.6.4 Válvula paso PVC SAP Ø 3/4" und 9 S/ 12.72 S/ 114.48
6.4.7 Tapas S/ 1,223.10
6.4.7.1 Tapa metálica 0. 45 x 0. 45, e =1/ 16" und 9 S/ 135.90 S/ 1,223.10
6.5 CAMARA VALVULA PURGA ( 2 UNID ) S/ 554.97
6.5.1 Obras preliminares S/ 0.66
6.5.1.0 Trazo nivelacion y replanteo en area m2 0.64 S/ 1.03 S/ 0.66
1
6.5.2 Movimiento de tierras con miscelaneos S/ 3.57
6.5.2.1 Excavación plataforma, fundación, muro int. m3 0.16 S/ 8.06 S/ 1.29
6.5.2.2 Retiro de suelo de excavación excedentes m3 0.16 S/ 14.27 S/ 2.28
6.5.3 Encofrado, desencofrado S/ 15.11
6.5.3.1 Encofrado de muros perimétricos m2 0.34 S/ 44.45 S/ 15.11
6.5.4 Estructura de concreto S/ 37.18
6.5.4.1 Muro perimétrico fc'= 175 Kg/cm2 m3 0.09 S/ 413.14 S/ 37.18
6.5.5 Tarrajeo S/ 46.51
P á g i n a 17 | 19
por ser necesaria para culminar al 100% las metas contempladas en el Expediente
Tecnico (IOARR): ” REPARACION DE SISTEMA DE BOMBEO; CONSTRUCCION DE
PLATAFORMA; ADQUISICION DE CISTERNA; RENOVACION DE RED DE
DISTRIBUCION; EN EL (LA). APV VILLA LAS ROCAS DISTRITO DE POROY,
PROVINCIA CUSCO, DEPARTAMENTO CUSCO”. CUI N° 2516437”.
1.5.2. RECOMENDACIONES
Se Solicita el registro de la MODIFICADO N° 01 por DEDUCTIVOSDE OBRA y
PARTIDAS COMPLEMENTARIAS DEL COSTO DIRECTO, GASTOS
GENERALES, de obra en el banco de proyectos.
Se solicita la aprobacion del Expediente de MODIFICADO N° 01 por las causales
descritas anteriormente.
P á g i n a 19 | 19