Presupuesto

Cliente ARMONHY INMOBILIARIA SAC


DEL 15 DE NOVIEMBRE AL 27 DE NOVIEMBRE
Lugar EDIFICIO MULTIFAMILIAR "ELESPURU"
Contratista Medrano Ingenieria y Construccion sac RESUMEN DE LIQUIDACION

PRESUPUESTO VAL. ACUM. ANTERIOR VAL. ACTUAL VAL. ACUM. ACTUAL SALDO POR VAL.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
ITEM DESCRIPCION UND % % % %
(S/.) (S/.) (S/.) (S/.) (S/.)

1.00 ARQUTECTURA glb 245,435.05 96.77% 237,508.69 3.23% 7,926.36 100.00% 245,435.05 0.00% 0.00

COSTO DIRECTO (S/.) 245,435.05 96.77% 237,508.69 3.20% 7,926.36 100.00% 245,435.05 0.00% 0.00

IGV 18% 44,178.31 S/. 42,751.56 S/. 1,426.74 S/. 44,178.31 S/. 0.00
TOTAL VALORIZACION (S/.) 289,613.36 S/. 280,260.25 S/. 9,353.10 S/. 289,613.36 S/. 0.00
AMORTIZACION POR ADELANTO 35.00% 101,364.68 98,091.09 3,273.59 101,364.68 0.00
TOTAL A FACTURAR(S/.) 188,248.68 S/. 182,169.17 S/. 6,079.52 S/. 188,248.68 S/. 0.00
FONDO DE GARANTIA 5.00% (S/.) 5.00% 14,480.67 S/. 14,013.01 S/. 467.66 S/. 14,480.67 S/. 0.00
TOTAL NETO (S/.) 173,768.02 S/. 168,156.15 S/. 5,611.86 S/. 173,768.02 S/. 0.00

Nota : Los temas tributarios de detracción, etc se realizará de acuerdo a normas vigentes.

ADICIONALES DE OBRA

ITEM DESCRIPCIÓN UND METRADO P.U. TOTAL


S/. S/.

1.00 ARQUTECTURA S/ 15,776.74

1.01 DIVISIONES DE INTERIORES

1.01.01 INSTALACION DE LADRILLO KING BLOCK


SUMINISTRO E INSTALACION DE
1.01.01.01 M2 5.85 89.75 525.04
TABIQUES P-9
SUMINISTRO E INSTALACION DE
1.01.01.02 M2 17.64 96.30 1,698.25
TABIQUES P-12
SUMINISTRO E INSTALACION DE
1.01.01.03 M2 17.04 105.40 1,795.81
TABIQUES P-14
1.01.01.04 ANCLAJE DE MUROS M2 2,122.81 4.50 9,552.65

1.01.01.05 EPOXICO EN MUROS UND 9.00 245.00 2,205.00

COSTO DIRECTO S/. 15,776.74

Gastos Generales 0.03 S/. 473.30

Utilidad 0.03 S/. 473.30

Sub Total S/. 16,723.34

IGV 0.18 3,010.20

TOTAL S/. 19,733.54