Obra: MEJORAMIENTO DE LA TRANSITABILIDAD EN LAS CALLES DEL A.H. EL BOSQUE, DISTRITO DE PAIJAN - ASCOPE - LA LIBERTAD
02 OBRAS PRELIMINARES
03.02.01 CORTE EN TERRENO NATURAL PARA VEREDAS, RAMPAS Y SARDINELES S/ 11,629.36 S/ 11,629.36
03.02.02 PERFILADO Y COMPACTADO EN ZONA DE CORTE S/ 15,864.62 S/ 3,966.15 S/ 19,830.77
03.02.03 BASE DE HORMIGÓN, E=0.10 m. PARA VEREDAS S/ 17,472.88 S/ 7,488.38 S/ 24,961.25
03.02.04 ELIM.MAT.CARGUIO C/MAQ. VOLQUETE 15 M3 S/ 5,013.15 S/ 5,013.15
03.03.01 CONCRETO f'c=175 kg/cm2 PARA VEREDAS, INCLUYE BRUÑADO S/ 10,024.23 S/ 40,096.94 S/ 50,121.17
03.03.02 VEREDA: ENCOFRADO Y DESENCOFRADO S/ 3,162.38 S/ 7,378.88 S/ 10,541.26
03.03.03 CONCRETO f'c=175 kg/cm2 PARA SARDINELES S/ 586.97 S/ 2,347.86 S/ 2,934.83
03.03.04 SARDINELES: ENCOFRADO Y DESENCOFRADO S/ 1,246.03 S/ 2,907.39 S/ 4,153.42
03.03.05 CONCRETO f'c=175 kg/cm2 PARA RAMPAS S/ 357.89 S/ 1,431.55 S/ 1,789.44
03.03.06 RAMPAS: ENCOFRADO Y DESENCOFRADO S/ 171.40 S/ 399.93 S/ 571.33
03.04 VARIOS
04 PAVIMENTACION
04.02.01 CORTE DE MATERIAL SUELTO CON EQUIPO A NIVEL DE SUBRASANTE S/ 7,085.91 S/ 7,085.91
MES 1 MES 2 MES 3
Item Descripción TOTAL (S/.)
30 DIAS 30 DIAS 15 DIAS
04.02.02 CONFORMACIÓN DE SUBRASANTE EN TERRENO NATURAL C/ EQUIPO S/ 5,926.47 S/ 5,926.47
04.02.03 ELIM.MAT.CARGUIO C/MAQ. VOLQUETE 15 M3 S/ 16,226.71 S/ 16,226.71
04.03 PAVIMENTOS
04.03.01 SUB - BASE MATERIAL GRANULAR (HORMIGON) E=0.25 M COMPACTADO S/ 32,606.36 S/ 32,606.36
04.03.02 BASE DE MATERIAL GRANULAR (AFIRMADO) E=0.15 M COMPACTADO S/ 21,858.98 S/ 9,368.13 S/ 31,227.11
04.03.03 CAMA DE ARENA E= 40MM S/ 15,865.70 S/ 10,577.13 S/ 26,442.83
04.03.04 SUMINISTRO Y COLOCACION DE ADOQUINES TIPO II S/ 89,246.17 S/ 59,497.45 S/ 148,743.62
05 SEÑALIZACION
06 IMPACTO AMBIENTAL
06.01 RIEGO DE ZONA DE TRABAJO PARA MITIGAR IMPACTOS S/ 473.85 S/ 473.85 S/ 236.93 S/ 1,184.63
GASTOS GENERALES (8%) S/. 11,460.49 S/. 24,108.34 S/. 8,516.28 S/. 44,085.11
UTILIDADES (6%) S/. 7,640.33 S/. 16,072.23 S/. 5,677.52 S/. 29,390.07
===========
SUB TOTAL S/. 146,439.59 S/. 308,051.01 S/. 108,819.07 S/. 563,309.70
IGV 18% S/. 26,359.13 S/. 55,449.18 S/. 19,587.43 S/. 101,395.75
===========
TOTAL PRESUPUESTADO S/. 172,798.72 S/. 363,500.19 S/. 128,406.51 S/. 664,705.45