Resumen Ejecutivo
Resumen Ejecutivo
Resumen Ejecutivo
INDICE
1 OBJETIVOS ............................................................................................................................. 3
2 CARACTERISTICAS GENERALES DE LA LOCALIDAD ................................................................ 4
3 INFORMACION SOCIOECONOMICA....................................................................................... 5
4 PROYECCION DE LA POBLACION Y LA DEMANDA ................................................................. 7
4.1DEMANDA DE AGUA POTABLE ..................................................................................... 9
4.2DEMANDA DE ALCANTARILLADO ............................................................................... 12
5 DEFICIT POR COMPONENTES DE LOS SITEMAS DE TRANSITIBILDAD.................................. 13
6 DESCRIPCION DE LAS OBRAS PROYECTADAS ...................................................................... 15
6.1COMPONENTE DE AGUA POTABLE ............................................................................ 15
6.1.1REDES DE DISTRIBUCIÓN DE AGUA ..................................................................... 15
6.1.2CONEXIONES DOMICILIARIAS DE AGUA POTABLE .............................................. 15
6.2COMPONENTE ALCANTARILLADO .............................................................................. 16
6.2.1RED COLECTORA DE ALCANTARILLADO .............................................................. 16
6.2.2CONEXIONES DOMICILIARIAS DE ALCANTARILLADO .......................................... 17
7 RESUMEN DE LA EVALUACION DE VULNERABILIDAD ......................................................... 18
7.1PELIGROS DE CARÁCTER CLIMATICO ......................................................................... 18
7.2PELIGROS DE CARÁCTER GEOTECNICO-SISMICO ....................................................... 19
7.3PELIGROS DE CARÁCTER GEOLOGICO-SISMICO ......................................................... 19
7.4VULNERABILIDAD EN EL PROYECTO ........................................................................... 19
8 RESUMEN DE LA EVALUACION DE IMPACTO AMBIENTAL .................................................. 21
9 MEMORIA DE CÁLCULO DE LOS DISEÑOS PROYECTADOS ................................................. 28
9.1REDES DE AGUA POTABLE .......................................................................................... 28
9.2REDES DE ALCANTARILLADO ...................................................................................... 47
10 ESTRUCTURAS DE COSTOS DE OBRA ...................................Error! Bookmark not defined.
11 ESTUDIO TOPOGRAFICO.................................................................................................. 58
11.1INTRODUCCION ........................................................................................................ 58
11.2ALCANCE DE LOS SERVICIOS..................................................................................... 58
11.3RECOPILACIÓN DE INFORMACION ........................................................................... 59
11.4METODOLOGIA DE TRABAJO.................................................................................... 59
11.5TRABAJOS EJECUTADOS ........................................................................................... 61
RESUMEN EJECUTIVO
Página | 1
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
11.6Nivelación ................................................................................................................. 64
12 METRADO BASE ............................................................................................................... 67
12.1METRADO BASE DE AGUA POTABLE ........................................................................ 67
12.2METRADO BASE DE ALCANTARILLADO .................................................................... 69
13 CRONOGRAMA DE OBRA ....................................................Error! Bookmark not defined.
14 ESTUDIO DE SUELOS ........................................................................................................ 72
14.1DESCRIPCION Y OBJETIVO ........................................................................................ 72
14.2CARACTERISTICAS DEL PROYECTO ........................................................................... 72
14.3CARACTERISTICAS GEOLOGICAS Y GEOMORFOLOGICAS ......................................... 73
14.4EXCAVACION DE CALICATAS .................................................................................... 74
14.5MUESTREO DE SUELOS............................................................................................. 75
14.6AGRESIVIDAD DEL SUELO ......................................................................................... 77
14.7CONCLUSIONES Y RECOMENDACIONES ................................................................... 77
15 PANEL FOTOGRAFICO...................................................................................................... 79
RESUMEN EJECUTIVO
Página | 2
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
1 OBJETIVOS
1.1 OBJETIVO GENERAL
El objetivo o propósito principal del proyecto es: “Adecuada prestación de Servicio de Agua
Potable y Alcantarillado den la Zona del Proyecto”.
PROBLEMA CENTRAL OBJETIVO CENTRAL
“Inadecuada Prestación del Servicio de “Adecuada prestación de Servicio de
Agua Potable y Alcantarillado en el Sector Agua Potable y Alcantarillado en el Sector
Nor-Este Periférico de la Ciudad de Nor- Este Periférico de la Ciudad de
Huaral” Huaral.
RESUMEN EJECUTIVO
Página | 3
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Distrito de Huaral
RESUMEN EJECUTIVO
Página | 4
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
El distrito de Huaral tiene una extensión de 640.76 m según fuente del INEI. Siendo el
Área del sector Nor Este periférico 0.461 km2.
3 INFORMACION SOCIOECONOMICA
Evolución de la Población
La tasa de crecimiento poblacional entre los periodos ínter censales (1972-81 y 1981-93) (1993-2007),
del distrito de Huaral fueron 2.2 y 1.9 respectivamente.
Concentración de la Población
Huaral tiene una densidad de ocupación de 45 hab/Km2 según fuentes del INEI – Censo del año 2007-,
siendo uno de los distritos con menor extensión territorial, en las cuales se ubican gran cantidad de
terrenos eriazos, lo cual trajo consigo la masiva ocupación de los asentamientos Humanos de acuerdo a
datos de la Municipalidad Distrital tiene una densidad poblacional por lote de 4.71 hab/lote.
La población censada para el distrito de Huaral, según el INEI – 2007, es de 88,558.00 habitantes. De la
cual, 89.2 % y 10.8% habitan en la zona urbana y rural respectivamente.
RESUMEN EJECUTIVO
Página | 5
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CRECIMIENTO DE LA POBLACION.
De acuerdo a las estimaciones, la tendencia de la tasa media de crecimiento en la Provincia Huaral es de
1.93% y 1.82% en el distrito de Huaral.
RESUMEN EJECUTIVO
Página | 6
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
PROYECCION DE SUB-SECTOR
ITEMS Base Con Proy
RESUMEN EJECUTIVO
Página | 7
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 8
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CONEXIONES
NÚMERO
TASA TOTAL DE POBLACIÓN CONEXIONES CONEXIONES CONEXIONES CONEXIONES CONEXIONES TOTAL
AÑO CRECIMIENTO POBLACIÓN VIVIENDAS COBERTURA
SERVIDA DOMÉSTICAS COMERCIALES INDUSTRIALES ESTATALES MULTIFAMILIARES CONEXIONES
ANUAL
Dóm Multifam. C/M S/M Total C/M S/M Total C/M S/M Total C/M S/M Total C/M S/M Total C/M S/M Total
Base 2012 2.46 8,345 499 325 79.26% 6,614 254 245 499 10 9 19 4 4 8 1 0 1 162 163 325 431 421 852
0 2013 2.41 8,546 511 333 79.26% 6,773 258 253 511 10 9 19 4 4 8 1 0 1 168 165 333 441 431 872
1 2014 2.37 8,752 523 341 100.00% 8,752 523 0 523 20 0 20 9 0 9 1 0 1 341 0 341 894 0 894
2 2015 2.32 8,963 536 349 100.00% 8,963 536 0 536 20 0 20 9 0 9 1 0 1 349 0 349 915 0 915
3 2016 2.28 9,179 549 357 100.00% 9,179 549 0 549 21 0 21 9 0 9 1 0 1 357 0 357 937 0 937
4 2017 2.24 9,400 562 366 100.00% 9,400 562 0 562 21 0 21 10 0 10 1 0 1 366 0 366 960 0 960
5 2018 2.21 9,627 576 375 100.00% 9,627 576 0 576 22 0 22 10 0 10 1 0 1 375 0 375 984 0 984
6 2019 2.17 9,859 590 384 100.00% 9,859 590 0 590 22 0 22 10 0 10 1 0 1 384 0 384 1,006 0 1,006
7 2020 2.14 10,096 604 393 100.00% 10,096 604 0 604 23 0 23 11 0 11 1 0 1 393 0 393 1,032 0 1,032
8 2021 2.10 10,340 618 403 100.00% 10,340 618 0 618 24 0 24 11 0 11 1 0 1 403 0 403 1,057 0 1,057
9 2022 2.07 10,589 633 412 100.00% 10,589 633 0 633 24 0 24 12 0 12 1 0 1 412 0 412 1,083 0 1,083
10 2023 2.03 10,844 648 422 100.00% 10,844 648 0 648 25 0 25 12 0 12 1 0 1 422 0 422 1,109 0 1,109
11 2024 2.00 11,106 664 433 100.00% 11,106 664 0 664 25 0 25 12 0 12 1 0 1 433 0 433 1,135 0 1,135
12 2025 1.97 11,373 680 443 100.00% 11,373 680 0 680 26 0 26 13 0 13 1 0 1 443 0 443 1,163 0 1,163
13 2026 1.94 11,647 696 454 100.00% 11,647 696 0 696 27 0 27 13 0 13 1 0 1 454 0 454 1,191 0 1,191
14 2027 1.91 11,928 713 465 100.00% 11,928 713 0 713 27 0 27 14 0 14 1 0 1 465 0 465 1,220 0 1,220
15 2028 1.88 12,216 730 476 100.00% 12,216 730 0 730 28 0 28 14 0 14 1 0 1 476 0 476 1,249 0 1,249
16 2029 1.85 12,510 748 487 100.00% 12,510 748 0 748 28 0 28 15 0 15 1 0 1 487 0 487 1,279 0 1,279
17 2030 1.83 12,812 766 499 100.00% 12,812 766 0 766 29 0 29 15 0 15 2 0 2 499 0 499 1,311 0 1,311
18 2031 1.80 13,120 785 511 100.00% 13,120 785 0 785 30 0 30 16 0 16 2 0 2 511 0 511 1,344 0 1,344
19 2032 1.77 13,437 803 523 100.00% 13,437 803 0 803 31 0 31 17 0 17 2 0 2 523 0 523 1,377 0 1,377
20 2033 1.75 13,760 823 536 100.00% 13,760 823 0 823 31 0 31 17 0 17 2 0 2 536 0 536 1,409 0 1,409
RESUMEN EJECUTIVO
Página | 9
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Base 2012 373,800 33,683 7,700 4,250 173,034 592,467 1,184,934 13.71 432,501 17.83 24.69
0 2013 382,996 33,683 7,700 4,250 176,878 605,507 1,211,015 14.02 442,020 18.22 25.23
1 2014 366,340 28,667 6,930 4,250 145,091 551,277 1,110,555 12.76 402,432 16.59 22.97
2 2015 375,170 28,667 6,930 4,250 148,587 563,604 1,127,207 13.05 411,431 16.96 23.48
3 2016 384,212 30,100 6,930 4,250 152,169 577,660 1,155,320 13.37 421,692 17.38 24.07
4 2017 393,472 30,100 7,700 4,250 155,836 591,358 1,182,716 13.69 431,691 17.80 24.64
5 2018 402,955 31,533 7,700 4,250 159,592 606,030 1,212,061 14.03 442,402 18.24 25.25
6 2019 412,667 31,533 7,700 4,250 163,438 619,588 1,239,177 14.34 452,300 18.65 25.82
7 2020 422,613 32,967 8,470 4,250 167,377 635,677 1,271,354 14.71 464,044 19.13 26.49
8 2021 432,798 34,400 8,470 4,250 171,411 651,330 1,302,660 15.08 475,471 19.60 27.14
9 2022 443,229 34,400 9,240 4,250 175,543 666,662 1,333,324 15.43 486,663 20.06 27.78
10 2023 453,912 35,833 9,240 4,250 179,774 683,009 1,366,018 15.81 498,596 20.55 28.46
11 2024 464,852 35,833 9,240 4,250 184,106 698,282 1,396,563 16.16 509,746 21.01 29.10
12 2025 476,055 37,267 10,010 4,250 188,544 716,126 1,432,251 16.58 522,772 21.55 29.84
13 2026 487,529 38,700 10,010 4,250 193,088 733,577 1,467,154 16.98 535,511 22.08 30.57
14 2027 499,279 38,700 10,780 4,250 197,742 750,751 1,501,501 17.38 548,048 22.59 31.28
15 2028 511,313 40,133 10,780 4,250 202,507 768,983 1,537,967 17.80 561,358 23.14 32.04
16 2029 523,636 40,133 11,550 4,250 207,388 786,957 1,573,915 18.22 574,479 23.68 32.79
17 2030 536,256 41,567 11,550 8,500 212,386 810,259 1,620,519 18.76 591,489 24.38 33.76
18 2031 549,181 43,000 12,320 8,500 217,505 830,506 1,661,012 19.22 606,270 24.99 34.60
19 2032 562,417 44,433 13,090 8,500 222,748 851,188 1,702,376 19.70 621,367 25.61 35.47
20 2033 575,972 44,433 13,090 8,500 228,116 870,111 1,740,223 20.14 635,181 26.18 36.25
RESUMEN EJECUTIVO
Página | 10
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
2012 432,501 13.71 17.83 24.69 277 108 0 385 217 -168
2013 442,020 14.02 18.22 25.23 283 110 50 443 217 -226
2014 402,432 12.76 16.59 22.97 258 100 50 408 217 -191
2015 411,431 13.05 16.96 23.48 264 103 50 417 217 -200
2016 421,692 13.37 17.38 24.07 270 105 50 425 217 -208
2017 431,691 13.69 17.80 24.64 277 108 50 435 217 -218
2018 442,402 14.03 18.24 25.25 284 110 50 444 217 -227
2019 452,300 14.34 18.65 25.82 290 113 50 453 217 -236
2020 464,044 14.71 19.13 26.49 297 116 50 463 217 -246
2021 475,471 15.08 19.60 27.14 305 119 50 474 217 -257
2022 486,663 15.43 20.06 27.78 312 121 50 483 217 -266
2023 498,596 15.81 20.55 28.46 320 124 50 494 217 -277
2024 509,746 16.16 21.01 29.10 327 127 50 504 217 -287
2025 522,772 16.58 21.55 29.84 335 130 50 515 217 -298
2026 535,511 16.98 22.08 30.57 343 134 50 527 217 -310
2027 548,048 17.38 22.59 31.28 351 137 50 538 217 -321
2028 561,358 17.80 23.14 32.04 360 140 50 550 217 -333
2029 574,479 18.22 23.68 32.79 368 143 50 561 217 -344
2030 591,489 18.76 24.38 33.76 379 147 50 576 217 -359
2031 606,270 19.22 24.99 34.60 389 151 50 590 217 -373
2032 621,367 19.70 25.61 35.47 398 155 50 603 217 -386
2033 635,181 20.14 26.18 36.25 407 158 50 615 217 -398
RESUMEN EJECUTIVO
Página | 11
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 12
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
20
CAUDAL lt/sg.
15 Demanda
Proyectada
10 Oferta Actual
0
1 3 5 7 9 11 13 15 17 19
RESUMEN EJECUTIVO
Página | 13
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
40.00
30.00
20.00
10.00
0.00
1 2 3 4 5 6 7 8 9 1011121314151617181920
RESUMEN EJECUTIVO
Página | 14
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
El Sistema de Agua Potable será mixto. El Cerro San Cristóbal ubicado en la zona Noreste del
área del proyecto utilizará un sistema condominial, abasteciéndose por gravedad a partir del
Reservorio apoyado de 30m3 ubicado en la parte superior del mismo. El resto del área del
proyecto se abastecerá convencionalmente por gravedad a partir del reservorio de 1900m3
ubicado fuera del área del proyecto.
RESUMEN EJECUTIVO
Página | 15
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
La configuración topográfica del área de estudio que se desarrolla en solo un área de drenaje,
lo que facilita la evacuación de los desagües íntegramente por gravedad y con los diámetros
mínimos reglamentarios. El Sistema consistirá en un sistema mixto, utilizando el método
convencional y condominial en el área del Cerro San Cristóbal.
RESUMEN EJECUTIVO
Página | 16
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Se instalaran 142 buzones nuevos, de los cuales 121 serán rehabilitados y 21 buzones
proyectados.
RESUMEN EJECUTIVO
Página | 17
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
El área de influencia del proyecto presenta una sismicidad alta, debido a su ubicación. Por lo
que las fichas de vulnerabilidad se refieren a la ocurrencia de dicho fenómeno natural.
Asimismo, un alto riesgo de inundación por el desborde los canales de riego que circulan por la
ciudad.
Por otro lado, la costumbre de arrojar desechos y basura, a los canales de riego por
parte de los transeúntes y vecinos del lugar, ocasionan la estrangulación del cauce y/o la
contaminación del agua, provocando en el primer caso desbordes, y en el segundo caso
los canales se convierten en focos infecciosos de contaminación.
Nivel freático
RESUMEN EJECUTIVO
Página | 18
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Debido al peligro sísmico alto que se ubica la zona de estudio, ha sido necesario realizar
una evaluación entre el tipo de suelo y la capacidad de soporte de éste, ya que el tipo de
suelo determina el comportamiento futuro causado por los esfuerzos y deformaciones
que puedan originarse por el peso de una estructura. Sin embargo no solo del suelo
depende la capacidad portante sino también de las características geométricas del
cimiento y de la profundidad a que se encuentren los materiales aptos para apoyar.
Es el caso que como consecuencia de la fuerte meteorización que han soportado las
rocas de estos pequeños cerros y lomadas en el transcurso de los miles de años, se ha
generado una importante cobertura de suelo (suelo coluvial), donde se han cimentado
las viviendas existentes, la mayoría de ellas de naturaleza precaria. Por lo observado en
el terreno y sin haber hecho un estudio particular (corresponde a otra actividad), es muy
probable que ninguna de las cimentaciones de estas viviendas de expansión urbana,
hayan penetrado en roca fija.
Las zonas más vulnerables son aquellas donde se ubica infraestructura de servicios que
es importante para la ciudad, como son los reservorios, subestaciones eléctricas, y
aquella infraestructura de servicios de emergencia, como son los centros de atención de
RESUMEN EJECUTIVO
Página | 19
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Debido a que las tuberías de agua trabajan a presión durante eventos severos, éstas son
muy susceptibles a tener daño en suelos poco competentes, por lo que el análisis de
daño de este estudio se basa en el número de roturas que se producirían en la red en
estas condiciones. Por otro lado, las tuberías de desagüe, por trabajar como si fueran
canales, su análisis de daño se basa en la separación de sus juntas.
Debido a este evento las tuberías de distribución de agua pueden tener ciertos daños
como roturas o fisuras, a la vez cabe rescatar que estás fluyen con fuerte presión que si
se ocasiona un daño dentro del sistema de conexión ocasionaría un desastre.
RESUMEN EJECUTIVO
Página | 20
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 21
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 22
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Luego de identificar las acciones del proyecto que pueden generar alteraciones al
entorno y los factores potencialmente afectados por la construcción, operación,
mantenimiento y cierre del Proyecto, procedemos a determinar las posibles implicancias
ambientales derivadas de la ejecución del proyecto.
RESUMEN EJECUTIVO
Página | 23
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Para la descripción de los principales impactos hemos considerado las diferentes fases
desde la construcción, operación, cierre y el post-cierre de las plantas.
a) Etapa de Planificación
En esta etapa solo se dan actividades de inspección de campo que producirán impactos
no significativos ambientales, por ello las actividades no se tomarán en cuenta para la
valorización de impactos ambientales.
- Residuos sólidos
Debido a las instalaciones construidas, en el periodo de duración de la obra se puede
causar impactos de contaminación en las zonas aledañas del área del proyecto debido a
los deshechos acumulados por los trabajadores durante su permanencia en las
instalaciones.
en cuanto a los escombros que se generaran por las excavaciones se puede presentar
una alteración del paisaje, flora y fauna.
RESUMEN EJECUTIVO
Página | 24
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
El ruido es una variable importante en esta actividad debido al constante tránsito y uso
de maquinaria pesada.
- Demolición de estructuras
En la actividad de demolición se tendrá un impacto negativo y de baja significancia en
cuanto a la calidad del aire y suelo, debido a las partículas de polvo y desmonte que se
generen. Adicionalmente, en esta actividad se generarán ruidos molestos a
consecuencia de los trabajos que se realizan, por lo cual se considera esto como de
baja significancia.
- Revegetación
La revegetación es la culminación de la etapa de cierre y post-cierre, ya que con esta
actividad se pretende volver a las condiciones originales del medio en donde se situará
el proyecto. Esta actividad se cataloga como un impacto positivo alto, considerando las
condiciones que se produjeron en la construcción y operación.
RESUMEN EJECUTIVO
Página | 25
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 26
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Durante las diferentes fases del Proyecto (Fase de Construcción, Fase de Operación y
Mantenimiento, Fase de Cierre y Abandono) se generarán impactos positivos y
negativos.
FASE DE CONSTRUCCIÓN
El aire es uno de los componentes más afectados dentro del ambiente, este recurso es
utilizado para el traslado de los microorganismos que se adhieren al material particulado
PM10. Esto sucederá durante la fase de construcción debido principalmente al
movimiento de tierras, el traslado de maquinarias y emisión de gases de las
maquinarias. Asimismo, de no tomarse las medidas de mitigación necesarias, se
deteriorarán las áreas verdes, la morfología del terreno y el paisaje. La salud e higiene
de la población se verá impactada negativamente.
Es importante considerar que el aspecto socio económico dentro de esta fase tiene un
impacto positivo reflejado en el aumento de los ingresos en la población como resultado
de la generación de puestos de trabajo directos, por la misma ejecución de la obra, e
indirectos, por la prestación de servicios colaterales.
El cómo revertir esta situación, para cada punto descrito dentro de la fase constructiva,
se encuentra establecido en el Plan de Manejo Ambiental.
El paisaje tiene un impacto negativo importante debido a que durante esta fase se
deben movilizar equipos y maquinarias que alterarán el paisaje verde predominante.
Para eliminar o minimizar los impactos negativos de cada elemento descrito se han
establecido medidas correspondientes.
Las obras que aquí se ejecuten permitirán generar oportunidades de trabajo para los
pobladores del lugar y favorecer su calidad de vida. El valor del suelo podría verse
impactado positivamente si es que se posibilita un uso alternativo apropiado del mismo.
RESUMEN EJECUTIVO
Página | 27
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 28
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 29
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 30
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 31
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO DE TUBERIAS
Gradiente
Longitud Nudo Nudo Diámetro Caudal Velocidad
Label Material C Hidráulico
(m) Inicial Final (mm) (l/s) (m/s)
(m/km)
Tub-1 0.57 J-215 J-216 63 PVC 140 0.1522 0.06 1.349
Tub-2 1.46 J-217 J-218 63 PVC 140 0.2515 0.09 0.256
Tub-3 2.07 J-153 J-117 110 PVC 140 -9.0968 1.11 12.658
Tub-4 2.36 J-53 J-50 90 PVC 130 -1.3966 0.26 1.212
Tub-5 2.39 J-219 J-220 63 PVC 140 0.0338 0.01 0
Tub-6 2.45 J-221 J-222 63 PVC 140 -0.1501 0.06 0.099
Tub-7 2.74 J-90 J-54 90 PVC 130 -1.5419 0.28 1.452
Tub-8 2.87 J-1 J-2 110 PVC 140 3.8109 0.47 2.525
Tub-9 3.17 J-223 J-219 63 PVC 140 -0.0338 0.01 0.006
Tub-10 3.2 J-3 J-4 90 PVC 140 -0.5976 0.11 0.215
Tub-11 3.29 J-5 J-6 110 PVC 140 -0.3383 0.04 0.028
Tub-12 3.56 J-154 J-155 90 PVC 130 6.8484 1.25 22.888
Tub-13 3.71 J-24 J-192 110 PVC 130 -2.9172 0.36 1.765
Tub-14 4.14 J-224 J-225 63 PVC 140 0.5559 0.21 1.083
Tub-15 5.29 J-226 J-227 63 PVC 140 -0.1015 0.04 0.046
Tub-16 4.45 J-158 J-89 90 PVC 130 -2.0301 0.37 2.406
Tub-17 4.82 J-143 J-1 90 PVC 130 3.9462 0.72 8.244
Tub-18 5.22 J-213 Reserv 110 PVC 140 -2.7235 0.33 1.355
Tub-19 6.01 J-93 J-94 160 PVC 140 2.9479 0.17 0.254
Tub-20 6.42 J-228 J-229 63 PVC 140 0.0507 0.02 0.012
Tub-21 6.79 J-95 J-94 110 PVC 140 -15.2138 1.86 32.811
Tub-22 84.94 J-35 J-36 63 PVC 140 -0.5202 0.19 0.956
Tub-23 86.66 J-37 J-38 63 PVC 140 -0.5591 0.21 1.093
Tub-24 84.71 J-39 J-40 90 PVC 140 -1.6404 0.3 1.414
RESUMEN EJECUTIVO
Página | 32
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO DE TUBERIAS
Gradiente
Longitud Nudo Nudo Diámetro Caudal Velocidad
Label Material C Hidráulico
(m) Inicial Final (mm) (l/s) (m/s)
(m/km)
Tub-25 94.61 J-7 J-8 90 PVC 140 -1.5772 0.29 1.315
Tub-26 7.19 J-159 J-160 110 PVC 140 -6.6133 0.81 7.014
Tub-27 7.3 J-161 J-162 110 PVC 140 -1.8443 0.23 0.657
Tub-28 7.33 J-41 J-42 90 PVC 140 3.4473 0.63 5.594
Tub-29 7.5 J-145 J-165 110 PVC 140 9.0968 1.11 12.658
Tub-30 7.68 J-43 J-44 90 PVC 140 0.4229 0.08 0.114
Tub-31 10.56 J-8 J-6 110 PVC 140 -3.4148 0.42 2.062
Tub-32 7.9 J-34 J-45 90 PVC 140 5.6869 1.04 14.139
Tub-33 9.58 J-81 J-15 90 PVC 130 -3.7557 0.69 7.521
Tub-34 9.61 J-195 J-196 110 PVC 130 -3.0812 0.38 1.956
Tub-35 9.61 J-77 J-92 110 PVC 140 -7.7761 0.95 9.467
Tub-36 9.79 J-46 J-47 90 PVC 140 -0.1519 0.03 0.017
Tub-37 9.91 J-197 J-209 110 PVC 140 -17.7632 2.17 43.716
Tub-38 10.27 J-167 J-31 90 PVC 130 -3.1953 0.58 5.577
Tub-39 10.63 J-230 J-231 63 PVC 140 0.3247 0.12 0.399
Tub-40 10.3 J-9 J-10 110 PVC 140 -3.6132 0.44 2.289
Tub-41 10.42 J-225 J-227 63 PVC 140 0.4714 0.18 0.797
Tub-42 10.92 J-48 J-49 90 PVC 140 -2.7118 0.5 3.587
Tub-43 11.13 J-209 R-2 200 PVC 140 -51.693 1.91 17.207
Tub-44 11.3 J-232 J-233 63 PVC 140 -0.6204 0.23 1.325
Tub-45 11.53 J-11 J-12 110 PVC 140 -4.476 0.55 3.404
Tub-46 11.58 J-72 J-168 110 PVC 140 -10.692 1.31 17.073
Tub-47 11.74 J-52 J-169 90 PVC 130 -0.4902 0.09 0.173
Tub-48 11.88 J-4 J-189 90 PVC 130 -0.602 0.11 0.254
Tub-49 16.8 J-234 J-213 63 PVC 140 -1.5203 0.57 6.968
Tub-50 13.22 J-170 J-155 90 PVC 130 -7.5824 1.39 27.631
Tub-51 13.66 J-233 J-235 63 PVC 140 0.0507 0.02 0.014
Tub-52 13.81 J-50 J-51 90 PVC 140 -1.3966 0.26 1.049
Tub-53 14.5 J-47 J-52 90 PVC 140 -0.4902 0.09 0.151
Tub-54 15.08 J-59 J-38 90 PVC 130 1.8376 0.34 2.002
Tub-55 16.03 J-234 J-215 63 PVC 140 0.7476 0.28 1.872
Tub-56 16.66 J-96 J-97 110 PVC 140 3.61 0.44 2.286
Tub-57 16.58 J-53 J-54 90 PVC 140 1.5419 0.28 1.26
Tub-58 17.19 J-237 J-238 63 PVC 140 0.0507 0.02 0.012
Tub-59 17.52 J-219 J-232 63 PVC 140 -0.0677 0.03 0.022
Tub-60 17.33 J-199 J-200 110 PVC 130 2.5714 0.31 1.399
Tub-61 17.48 J-65 J-41 110 PVC 130 -6.5816 0.81 7.974
Tub-62 17.56 J-224 J-239 63 PVC 140 0.5458 0.2 1.045
Tub-63 17.93 J-236 J-226 63 PVC 140 -0.0169 0.01 0.001
Tub-64 18.58 J-239 J-218 63 PVC 140 0.2429 0.09 0.233
Tub-65 20.52 J-240 J-230 63 PVC 140 -0.0507 0.02 0.013
Tub-66 20.11 J-241 J-242 63 PVC 140 0.1522 0.06 0.099
Tub-67 20.35 J-243 J-225 63 PVC 140 -0.0846 0.03 0.033
Tub-68 21.38 J-231 J-244 63 PVC 140 0.0169 0.01 0.002
Tub-69 22.51 J-241 J-245 63 PVC 140 0.1899 0.07 0.148
Tub-70 22.43 J-95 J-60 200 PVC 140 -36.7862 1.36 9.165
Tub-71 28.82 J-237 J-246 63 PVC 140 0.0507 0.02 0.012
Tub-72 24.32 J-55 J-56 90 PVC 140 0.0236 0 0.001
Tub-73 24.46 J-237 J-247 63 PVC 140 -0.1691 0.06 0.119
Tub-74 24.67 J-11 J-13 110 PVC 140 2.0479 0.25 0.8
RESUMEN EJECUTIVO
Página | 33
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO DE TUBERIAS
Gradiente
Longitud Nudo Nudo Diámetro Caudal Velocidad
Label Material C Hidráulico
(m) Inicial Final (mm) (l/s) (m/s)
(m/km)
Tub-75 24.89 J-57 J-58 90 PVC 140 0.1626 0.03 0.019
Tub-76 26.55 J-233 J-234 63 PVC 140 -0.7388 0.28 1.831
Tub-77 26.52 J-248 J-217 63 PVC 140 -0.0507 0.02 0.013
Tub-78 27.31 J-227 J-217 63 PVC 140 0.3022 0.11 0.349
Tub-79 26.89 J-86 J-46 90 PVC 130 -0.1519 0.03 0.019
Tub-80 27.12 J-169 J-43 90 PVC 130 0.4229 0.08 0.132
Tub-81 27.25 J-44 J-55 90 PVC 140 0.1758 0.03 0.023
Tub-82 28.84 J-184 J-187 90 PVC 130 -0.3899 0.07 0.114
Tub-83 29.87 J-245 J-249 63 PVC 140 0.1222 0.05 0.065
Tub-84 30.06 J-59 J-8 90 PVC 140 -1.8376 0.34 1.745
Tub-85 30.08 J-60 J-61 110 PVC 140 -10.4552 1.28 16.38
Tub-86 31.09 J-62 J-63 90 PVC 140 -0.1353 0.02 0.014
Tub-87 32.64 J-218 J-241 63 PVC 140 0.4098 0.15 0.614
Tub-88 32.82 J-64 J-65 90 PVC 140 -0.1353 0.02 0.014
Tub-89 33.15 J-83 J-172 90 PVC 130 0.2908 0.05 0.066
Tub-90 33.51 J-168 J-77 110 PVC 140 -12.3086 1.51 22.161
Tub-91 33.74 J-201 J-4 90 PVC 130 -0.0044 0 0
Tub-92 50.05 J-213 J-224 63 PVC 140 1.2032 0.45 4.519
Tub-93 43.57 J-239 J-228 63 PVC 140 0.269 0.1 0.282
Tub-94 34.77 J-187 J-24 90 PVC 130 -0.9143 0.17 0.549
Tub-95 35.71 J-173 J-174 90 PVC 130 0.3383 0.06 0.088
Tub-96 36.4 J-9 J-11 110 PVC 140 -2.2758 0.28 0.973
Tub-97 36.52 J-176 J-53 90 PVC 130 0.1453 0.03 0.018
Tub-98 36.94 J-177 J-178 90 PVC 130 -0.4741 0.09 0.163
Tub-99 36.97 J-132 J-139 110 PVC 130 -3.7739 0.46 2.846
Tub-100 37.34 J-66 J-55 90 PVC 140 -0.1015 0.02 0.008
Tub-101 37.69 J-177 J-86 90 PVC 130 0.3388 0.06 0.087
Tub-110 37.87 J-15 J-167 90 PVC 130 -0.4328 0.08 0.138
Tub-103 38.64 J-14 J-15 90 PVC 140 3.323 0.61 5.228
Tub-104 39.47 J-250 J-226 63 PVC 140 -0.0846 0.03 0.033
Tub-105 39.09 J-165 J-163 110 PVC 140 9.0968 1.11 12.658
Tub-106 39.12 J-63 J-65 110 PVC 130 -6.3955 0.78 7.562
Tub-107 40.45 J-97 J-179 90 PVC 130 3.61 0.66 6.991
Tub-108 40.73 J-78 J-80 110 PVC 130 -6.929 0.85 8.771
Tub-109 40.93 J-67 J-45 90 PVC 140 -3.3706 0.62 5.367
Tub-110 41.21 J-68 J-69 90 PVC 140 -2.5883 0.47 3.291
Tub-111 41.43 J-242 J-251 63 PVC 140 0.0507 0.02 0.013
Tub-112 41.44 J-155 J-87 90 PVC 130 -0.9708 0.18 0.614
Tub-113 41.6 J-70 J-42 90 PVC 140 -3.4473 0.63 5.595
Tub-114 42.88 J-222 J-247 63 PVC 140 -0.2346 0.09 0.219
Tub-115 42.11 J-88 J-161 90 PVC 130 -1.3857 0.25 1.187
Tub-116 42.22 J-154 J-63 110 PVC 130 -6.1587 0.75 7.051
Tub-117 42.49 J-22 J-14 90 PVC 130 3.323 0.61 5.996
Tub-118 42.55 J-117 J-163 110 PVC 140 -9.0968 1.11 12.658
Tub-119 54.94 J-29 J-98 110 PVC 140 3.4414 0.42 2.092
Tub-120 43.06 J-202 J-203 110 PVC 130 -1.015 0.12 0.25
Tub-121 43.08 J-18 J-19 90 PVC 140 -0.0526 0.01 0.003
Tub-122 43.16 J-31 J-159 90 PVC 130 1.8211 0.33 1.969
Tub-123 43.71 J-71 J-48 90 PVC 140 1.9898 0.36 2.022
Tub-124 43.23 J-150 J-145 110 PVC 140 9.5812 1.17 13.935
RESUMEN EJECUTIVO
Página | 34
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO DE TUBERIAS
Gradiente
Longitud Nudo Nudo Diámetro Caudal Velocidad
Label Material C Hidráulico
(m) Inicial Final (mm) (l/s) (m/s)
(m/km)
Tub-125 43.37 J-89 J-154 90 PVC 130 0.9266 0.17 0.563
Tub-126 44.52 J-228 J-221 63 PVC 140 0.1675 0.06 0.117
Tub-127 44.48 J-20 J-18 90 PVC 140 1.0036 0.18 0.569
Tub-128 45.52 J-40 J-88 90 PVC 130 0.5723 0.1 0.231
Tub-129 46.11 J-12 J-139 110 PVC 130 -4.476 0.55 3.904
Tub-130 46.4 J-252 J-216 63 PVC 140 -0.0677 0.03 0.022
Tub-131 46.46 J-61 J-72 110 PVC 140 -10.692 1.31 17.074
Tub-132 46.5 J-21 J-20 90 PVC 140 2.1784 0.4 2.392
Tub-133 48.21 J-215 J-230 63 PVC 140 0.46 0.17 0.762
Tub-134 47.9 J-2 J-22 110 PVC 140 -1.3239 0.16 0.357
Tub-135 47.93 J-23 J-24 110 PVC 140 -2.0029 0.25 0.768
Tub-136 47.82 J-73 J-74 90 PVC 140 -0.1353 0.02 0.014
Tub-137 47.92 J-10 J-132 110 PVC 130 -3.6132 0.44 2.626
Tub-138 48.8 J-202 J-204 110 PVC 130 1.015 0.12 0.25
Tub-139 48.78 J-180 J-181 90 PVC 130 2.0301 0.37 2.407
Tub-140 48.8 J-26 J-27 90 PVC 140 2.4785 0.45 3.037
Tub-141 48.96 J-205 J-3 90 PVC 130 -0.4961 0.09 0.177
Tub-142 49.04 J-87 J-81 90 PVC 130 -1.7833 0.33 1.894
Tub-143 49.04 J-36 J-40 90 PVC 130 1.5115 0.28 1.394
Tub-144 49.56 J-38 J-36 90 PVC 130 1.7916 0.33 1.91
Tub-145 74.44 J-75 J-71 90 PVC 140 0.3896 0.07 0.099
Tub-146 50.42 J-17 J-28 90 PVC 140 1.502 0.27 1.201
Tub-147 49.97 J-13 J-150 110 PVC 140 10.8168 1.32 17.445
Tub-148 50.24 J-104 J-110 110 PVC 130 -4.259 0.52 3.561
Tub-149 52.23 J-76 J-44 90 PVC 140 -0.1287 0.02 0.013
Tub-150 52.09 J-27 J-21 90 PVC 140 2.9429 0.54 4.174
Tub-151 52.72 J-153 J-143 90 PVC 130 2.4159 0.44 3.323
Tub-152 52.93 J-48 J-77 90 PVC 140 4.5832 0.84 9.482
Tub-153 52.87 J-169 J-158 90 PVC 130 -1.0315 0.19 0.687
Tub-154 53.01 J-143 J-144 63 PVC 130 -1.5642 0.58 8.427
Tub-155 53.64 J-185 J-184 90 PVC 130 -1.4554 0.27 1.3
Tub-156 54.14 J-196 J-206 110 PVC 130 -1.0737 0.13 0.277
Tub-157 54.29 J-98 J-99 110 PVC 140 5.3037 0.65 4.661
Tub-158 58.61 J-231 J-253 63 PVC 140 0.2063 0.08 0.172
Tub-159 53.39 J-16 J-208 200 PVC 130 13 0.48 1.531
Tub-160 56.37 J-249 J-221 63 PVC 140 -0.233 0.09 0.216
Tub-161 56.75 J-26 J-17 110 PVC 140 -6.3669 0.78 6.537
Tub-162 56.77 J-196 J-104 110 PVC 130 -2.0075 0.25 0.884
Tub-163 56.84 J-189 J-185 90 PVC 130 -0.9366 0.17 0.574
Tub-164 56.89 J-67 J-78 90 PVC 140 3.286 0.6 5.12
Tub-165 56.45 J-253 J-254 63 PVC 140 0.0371 0.01 0.007
Tub-166 637 J-99 J-93 110 PVC 140 4.6853 0.57 3.704
Tub-167 58.51 J-203 J-207 110 PVC 130 0.812 0.1 0.166
Tub-168 58.74 J-21 J-79 63 PVC 130 0.0507 0.02 0.015
Tub-169 58.85 J-175 J-25 110 PVC 140 -0.9634 0.12 0.198
Tub-170 59.12 J-167 J-49 90 PVC 130 2.7118 0.5 4.115
Tub-171 60.4 J-41 J-78 110 PVC 130 -10.1473 1.24 17.778
Tub-172 61.11 J-100 J-99 110 PVC 140 -0.3478 0.04 0.03
Tub-173 61.98 J-110 J-103 110 PVC 130 -7.0236 0.86 8.994
Tub-174 62.34 J-92 J-159 110 PVC 140 -8.299 1.02 10.679
RESUMEN EJECUTIVO
Página | 35
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO DE TUBERIAS
Gradiente
Longitud Nudo Nudo Diametro Caudal Velocidad
Label Material C Hidraulico
(m) Inicial Final (mm) (l/s) (m/s)
(m/km)
Tub-175 62.36 J-45 J-80 90 PVC 140 2.2148 0.41 2.466
Tub-176 63.64 J-29 J-30 110 PVC 140 -0.9644 0.12 0.199
Tub-177 68.31 J-27 J-28 63 PVC 130 -1.3836 0.52 6.713
Tub-178 69.34 J-71 J-81 90 PVC 140 -1.8032 0.33 1.685
Tub-179 90.73 J-139 J-147 110 PVC 130 -8.4867 1.04 12.769
Tub-180 71.2 J-5 J-148 63 PVC 130 0.3383 0.13 0.495
Tub-181 71.62 J-183 J-176 110 PVC 130 -5.4239 0.66 5.573
Tub-182 71.93 J-82 J-83 90 PVC 140 -1.4546 0.27 1.132
Tub-183 72.3 J-84 J-47 90 PVC 140 -0.2538 0.05 0.045
Tub-184 72.86 J-172 J-182 90 PVC 130 -3.056 0.56 5.135
Tub-185 73.7 J-203 J-205 110 PVC 130 -1.8271 0.22 0.743
Tub-186 74.84 J-183 J-83 90 PVC 130 1.9823 0.36 2.303
Tub-187 87.09 J-205 J-32 110 PVC 130 -1.5001 0.18 0.515
Tub-188 98.42 J-149 J-150 63 PVC 130 -1.2357 0.46 5.446
Tub-189 77.42 J-85 J-86 90 PVC 140 -0.2707 0.05 0.05
Tub-190 77.53 J-184 J-82 90 PVC 130 -1.2685 0.23 1.008
Tub-191 78.04 J-185 J-58 90 PVC 130 0.0573 0.01 0.003
Tub-192 78.05 J-74 J-197 160 PVC 140 -17.7463 1.03 7.026
Tub-193 81.81 J-75 J-87 90 PVC 140 -0.5757 0.11 0.203
Tub-194 85.94 J-31 J-2 110 PVC 140 -5.1348 0.63 4.389
Tub-195 99.23 J-34 J-88 90 PVC 140 -2.439 0.45 2.948
Tub-196 86.97 J-105 J-106 200 PVC 140 -26.331 0.98 4.933
Tub-197 90.39 J-160 J-153 110 PVC 140 -6.6133 0.81 7.013
Tub-198 90.78 J-91 J-173 90 PVC 140 0.4383 0.08 0.123
Tub-199 91.29 J-89 J-70 90 PVC 140 -3.1597 0.58 4.761
Tub-200 92.6 J-178 J-158 90 PVC 130 -0.711 0.13 0.345
Tub-201 93.25 J-80 J-162 110 PVC 130 -5.929 0.73 6.572
Tub-202 97.92 J-93 J-96 160 PVC 140 1.213 0.07 0.049
Tub-203 124.05 J-182 J-90 90 PVC 130 -1.5165 0.28 1.403
Tub-204 104.3 J-182 J-176 90 PVC 130 -1.7932 0.33 1.913
Tub-205 155.19 J-96 J-100 110 PVC 140 -2.7861 0.34 1.415
Tub-206 110.45 J-6 J-26 110 PVC 140 -3.7531 0.46 2.456
Tub-207 112.11 J-100 J-101 110 PVC 140 -2.6583 0.33 1.297
Tub-208 110.96 J-176 J-170 110 PVC 130 -7.5824 0.93 10.364
Tub-209 111.01 J-187 J-188 90 PVC 130 0.3722 0.07 0.104
Tub-210 111.8 J-88 J-18 90 PVC 140 -0.8531 0.16 0.421
Tub-211 111.83 J-40 J-20 90 PVC 140 -0.9888 0.18 0.554
Tub-212 112.17 J-36 J-21 63 PVC 130 -0.4769 0.18 0.934
Tub-213 112.23 J-101 J-195 110 PVC 130 -2.9966 0.37 1.857
Tub-214 112.33 J-161 J-19 90 PVC 130 0.171 0.03 0.025
Tub-215 114.78 J-38 J-27 63 PVC 130 -0.7161 0.27 1.982
Tub-216 115.67 J-147 J-13 110 PVC 140 8.8705 1.09 12.081
Tub-217 116.89 J-74 J-147 160 PVC 140 17.5433 1.01 6.878
Tub-218 99.09 J-189 J-259 90 PVC 130 0.0808 0.01 0.006
Tub-219 118.74 J-68 J-190 90 PVC 130 0.0846 0.02 0.007
Tub-220 112.05 J-32 J-23 110 PVC 140 -1.5799 0.19 0.495
Tub-221 138.83 J-51 J-168 90 PVC 130 -1.3966 0.26 1.204
Tub-222 132.39 J-91 J-92 110 PVC 140 -0.5229 0.06 0.064
Tub-223 164.89 J-249 J-255 63 PVC 140 0.2369 0.09 0.223
Tub-224 150.02 J-107 J-95 200 PVC 140 -52 1.93 17.397
RESUMEN EJECUTIVO
Página | 36
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO DE TUBERIAS
Gradiente
Longitud Nudo Nudo Diámetro Caudal Velocidad
Label Material C Hidráulico
(m) Inicial Final (mm) (l/s) (m/s)
(m/km)
Tub-225 168.88 J-94 J-30 160 PVC 140 -12.2659 0.71 3.545
Tub-226 151.27 J-180 J-68 90 PVC 130 -2.2162 0.41 2.832
Tub-227 152.92 J-192 J-183 110 PVC 130 -3.1033 0.38 1.981
Tub-228 174.14 J-110 J-29 110 PVC 140 2.6969 0.33 1.332
Tub-229 178.04 J-30 J-103 160 PVC 140 -13.7209 0.79 4.363
Tub-230 200.55 J-98 J-104 110 PVC 140 -2.0992 0.26 0.837
Tub-231 246.32 J-60 J-105 200 PVC 140 -26.331 0.98 4.933
Tub-232 234.32 J-209 J-199 200 PVC 140 31.3076 1.16 6.798
Tub-233 31.88 J-34 J-39 90 PVC 130 -3.2479 0.59 5.748
Tub-234 50.46 J-39 J-35 90 PVC 130 -1.8951 0.35 2.119
Tub-235 47.91 J-35 J-37 90 PVC 130 -1.6795 0.31 1.694
Tub-236 45.32 J-37 J-7 90 PVC 130 -1.3741 0.25 1.169
Tub-237 84.75 J-80 J-256 90 PVC 130 1.0795 0.2 0.747
Tub-238 123.86 J-22 J-256 90 PVC 130 -4.9176 0.9 12.392
Tub-239 91.92 J-256 J-25 90 PVC 130 -4.655 0.85 11.194
Tub-240 62.25 J-90 J-258 90 PVC 130 0.0254 0 0.001
Tub-241 43.64 J-259 J-69 90 PVC 130 0.9643 0.18 0.606
Tub-242 43.73 J-57 J-261 90 PVC 130 -1.4606 0.27 1.308
Tub-243 62.34 J-69 J-261 90 PVC 130 -1.7763 0.33 1.88
Tub-244 29.27 J-261 J-172 90 PVC 130 -3.2623 0.6 5.795
Tub-245 46.67 J-185 J-32 110 PVC 130 0.0894 0.01 0.003
Tub-246 21.1 J-263 J-132 110 PVC 130 -0.0254 0 0.001
Tub-247 47.7 J-9 J-25 110 PVC 140 5.7029 0.7 5.331
Tub-248 63.5 J-175 J-264 110 PVC 140 -6.9876 0.86 7.766
Tub-249 176.3 J-264 J-199 110 PVC 140 -7.0129 0.86 7.818
Tub-250 29.47 J-162 J-265 110 PVC 140 -7.7733 0.95 9.461
Tub-251 6.55 J-265 J-175 110 PVC 140 -7.7987 0.95 9.518
Tub-252 6.27 J-199 J-266 200 PVC 140 21.2664 0.79 3.322
Tub-253 58.9 J-247 J-254 63 PVC 130 -0.4714 0.18 0.914
Tub-254 19.84 J-254 J-232 63 PVC 130 -0.4681 0.17 0.902
Tub-255 1.96 J-268 J-17 110 PVC 140 7.9197 0.97 9.789
Tub-256 24.34 J-268 J-273 110 PVC 140 -7.945 0.97 9.852
Tub-257 17.31 J-273 J-274 110 PVC 140 -7.9704 0.98 9.91
Tub-258 269.74 J-266 J-274 200 PVC 140 21.2664 0.79 3.321
Tub-259 5.03 J-274 J-16 200 PVC 130 13.2707 0.49 1.591
Tub-260 61.63 J-57 J-259 90 PVC 130 0.9089 0.17 0.544
Tub-261 24.82 R-13 J-206 110 PVC 130 1.2597 0.15 0.373
Tub-262 43.2 J-103 J-280 160 PVC 140 -20.8629 1.21 9.481
Tub-263 10.64 J-281 R-8 200 PVC 140 -47.194 1.75 14.537
Tub-264 4.58 J-280 J-281 160 PVC 140 -20.8629 1.21 9.481
Tub-265 81.38 J-173 J-283 90 PVC 140 0.1 0.02 0.008
Tub-266 9.26 J-106 J-284 200 PVC 140 -26.331 0.98 4.934
Tub-267 31.56 J-284 J-281 200 PVC 140 -26.331 0.98 4.933
Tub-268 49.04 J-145 J-285 63 PVC 130 0.4844 0.18 0.961
Tub-269 41.19 J-285 J-146 63 PVC 130 2.224 0.83 16.17
Tub-270 12.69 J-285 J-149 63 PVC 140 -1.7396 0.65 8.944
Tub-271 15.57 J-146 J-144 63 PVC 140 1.9364 0.72 10.907
Tub-272 45.56 J-256 J-149 63 PVC 130 0.7915 0.3 2.387
A partir de los Cálculos desarrollados como propósito MEJORAR EL SISTEMA DE AGUA
POTABLE DEL SECTOR NOR ESTE PERIFERICO, se ha podido constatar que en pro de sostener
un adecuado nivel de presiones en la malla de dicho sector, es necesario INSTALAR OCHO (08)
VALVULAS PARA EL AISLAMIENTO DEL SECTOR.
RESUMEN EJECUTIVO
Página | 37
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Además, se requiere que en el punto de Empalme Nº 1 ubicado en la Av. Benjamin Doig Lossio
(cruce con Av. Jorge Chávez) tenga como mínimo una presión de 12 m.c.a. en el Horario de
Máximo Consumo; en el Empalme Nº 2 ubicado en la Av. Mariscal Cáceres (Cruce con Av.
Jorge Chávez), 11 m.c.a; y por último, en el Empalme Nº 3 ubicado en la Av. Los Naturales
(Cruce con Av. Circunvalación Norte), 11 m.c.a.
Por ello se presenta el cálculo hidráulico para el óptimo desarrollo del sistema proyectado.
CALCULO EN NUDOS
Línea
Elevación Demanda Presión
Label Hidráulica
(m) (l/s) (mH2O)
(m)
J-1 177.15 0.1353 189.74 12.57
J-2 177.13 0 189.73 12.584
J-3 168.75 0.1015 186.75 17.963
J-4 168.8 0 186.75 17.921
J-5 178.09 0 192.19 14.067
J-6 178.2 0 192.19 13.962
J-7 176.58 0.203 192.04 15.431
J-8 178.05 0 192.16 14.085
J-9 180 0.1861 192.57 12.545
J-10 180.14 0 192.59 12.424
J-11 180 0.1522 192.61 12.58
J-12 180.14 0 192.64 12.478
J-13 180 0.1015 192.59 12.56
J-14 176.65 0 189.5 12.818
J-15 176.5 0 189.29 12.769
J-16 180.9 0.2707 193.25 12.328
J-17 180.58 0.0507 192.83 12.228
J-18 181.11 0.203 191.96 10.827
J-19 181.49 0.1184 191.96 10.439
J-20 180.5 0.1861 191.98 11.457
J-21 180.17 0.2369 192.09 11.896
J-22 176.89 0.2707 189.75 12.834
J-23 170.2 0.4229 186.84 16.615
J-24 170.84 0 186.88 16.011
J-25 180.33 0.0846 192.32 11.962
J-26 179.96 0.1353 192.46 12.474
J-27 179.94 0.203 192.31 12.34
J-28 180.99 0.1184 192.77 11.755
J-29 174.86 0.2199 186.89 12.006
J-30 175.81 0.4906 186.91 11.074
J-31 176.23 0.1184 189.36 13.098
J-32 168.5 0.1692 186.79 18.252
J-34 178.33 0 191.62 13.263
J-35 177.56 0.3045 191.91 14.312
J-36 178.51 0.2369 191.99 13.445
J-37 177 0.2538 191.99 14.957
J-38 178.12 0.203 192.08 13.935
J-39 177.92 0.2876 191.8 13.846
J-40 178.97 0.2876 191.92 12.918
J-41 176.9 0.1184 189.92 12.996
J-42 176.77 0 189.88 13.086
RESUMEN EJECUTIVO
Página | 38
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO EN NUDOS
Línea
Elevación Demanda Presión
Label Hidráulica
(m) (l/s) (mH2O)
(m)
J-97 173.59 0 186.27 12.652
J-98 173.91 0.2369 186.78 12.842
J-99 173.35 0.2707 186.52 13.151
J-100 172.44 0.2199 186.52 14.053
J-101 173.94 0.3383 186.67 12.705
J-110 176.2 0.0677 187.12 10.908
J-103 177.3 0.1184 187.68 10.361
J-104 175.5 0.1522 186.95 11.418
J-105 176.7 0 187.5 10.785
J-106 177.31 0 187.93 10.599
J-107 171.66 52 1907 11.788
J-117 177.39 0 189.98 12.565
J-132 181.07 0.1353 192.72 11.631
J-139 181 0.2369 192.82 11.801
J-143 177.14 0.0338 189.78 12.618
J-144 178.1 0.3722 190.23 12.109
J-145 178.62 0 191.11 12.471
J-146 178.29 0.2876 190.4 12.081
J-147 181.59 0.1861 193.98 12.364
J-148 178.09 0.3383 192.15 14.032
J-149 178.76 0.2876 191.18 12.397
J-150 179.2 0 191.71 12.486
J-153 177.36 0.0677 189.96 12.572
J-154 175.16 0.2369 189.19 13.993
J-155 175.13 0.2369 189.1 13.948
J-158 174.92 0.2876 189.2 14.253
J-159 176.1 0.1353 189.27 13.145
J-160 176.18 0 189.32 13.112
J-161 179.85 0.2876 191.96 12.084
J-162 179.94 0 191.96 12.001
J-163 177.98 0 190.52 12.513
J-165 178.53 0 191.02 12.461
J-167 176.02 0.0507 189.3 13.251
J-168 175 0.2199 187.77 12.748
J-169 174.86 0.1184 189.16 14.277
J-170 175 0 188.74 13.712
J-172 172.21 0.0846 187.02 14.775
J-173 176.95 0 188.59 11.611
J-174 177.41 0.3383 188.58 11.154
J-175 180.13 0.1522 192.3 12.153
J-176 173.85 0.2199 187.59 13.71
J-177 173.11 0.1353 189.16 16.021
J-178 173.88 0.2369 189.17 15.258
J-179 175.59 3.61 185.98 10.369
J-180 168.54 0.1861 186.16 17.593
J-181 167.54 2.0301 186.05 18.47
J-182 174 0.2538 187.39 13.363
J-183 173.08 0.3383 187.19 14.084
J-184 170.01 0.203 186.86 16.813
J-185 169.58 0.3722 186.79 17.178
J-187 170.44 0.1522 186.86 16.393
J-188 171.93 0.3722 186.85 14.886
J-189 169.11 0.2538 186.76 17.606
J-190 170.37 0.0846 186.59 16.189
RESUMEN EJECUTIVO
Página | 39
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO EN NUDOS
Línea
Elevación Demanda Presión
Label Hidráulica
(m) (l/s) (mH2O)
(m)
J-192 170.89 0.1861 186.89 15.963
J-195 174.5 0.0846 186.88 12.352
J-196 174.82 0 186.9 12.052
J-197 184.74 0.0169 195.34 10.571
J-199 183.9 0.4568 194.18 10.255
J-200 183.9 2.5714 194.15 10.231
J-201 168.47 0.0044 186.75 18.248
J-202 167.9 0 186.68 18.74
J-203 167.9 0 186.69 18.751
J-204 167.9 1.015 186.67 18.728
J-205 167.9 0.1692 186.74 18.805
J-206 174.83 0.1861 186.91 12.053
J-207 167.9 0.812 186.68 18.741
J-208 180.96 13 193.17 12.184
J-209 184.99 2.6222 195.77 10.752
J-213 194.97 0 195.78 0.816
J-215 194.01 0.1353 195.64 1.619
J-216 193.98 0.0846 195.64 1.651
J-217 178.5 0 195.53 17.001
J-218 178.71 0.0846 195.53 16.792
J-219 179.23 0 195.6 16.343
J-220 178.61 0.0338 195.6 16.958
J-221 176.29 0.0846 195.52 19.189
J-222 176.17 0.0846 195.52 19.309
J-223 180.25 0.0338 195.6 15.32
J-224 182.89 0.1015 195.56 12.638
J-225 180.53 0 195.55 14.992
J-226 176.77 0 195.54 18.737
J-227 177.5 0.0677 195.54 18.008
J-228 186.26 0.0507 195.53 9.252
J-229 187.01 0.0507 195.53 8.494
J-230 174.39 0.0846 195.6 21.169
J-231 172.42 0.1015 195.59 23.124
J-232 179.03 0.0846 195.6 16.535
J-233 183.16 0.0677 195.62 12.432
J-234 195.13 0.0338 195.67 0.539
J-235 184.11 0.0507 195.62 11.487
J-236 178.92 0.0169 195.54 16.586
J-237 179.71 0.0677 195.53 15.784
J-238 179.34 0.0507 195.53 16.157
J-239 184.45 0.0338 195.54 11.065
J-240 174.8 0.0507 195.6 20.759
J-241 180.33 0.0677 195.51 15.156
J-242 183.83 0.1015 195.51 11.658
J-243 181.16 0.0846 195.55 14.365
J-244 172.5 0.0169 195.59 23.048
J-245 179.06 0.0677 195.51 16.415
J-246 187.62 0.0507 195.53 7.891
J-247 176.09 0.0677 195.53 19.406
J-248 171.37 0.0507 195.53 24.118
J-249 176.59 0.1184 195.51 18.876
J-250 170.69 0.0846 195.54 24.799
J-251 176.86 0.0507 195.51 18.609
J-252 173.47 0.0677 195.63 22.121
RESUMEN EJECUTIVO
Página | 40
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO EN NUDOS
Línea
Elevación Demanda Presión
Label Hidráulica
(m) (l/s) (mH2O)
(m)
J-253 173.77 0.1692 195.58 21.775
J-254 175.79 0.0338 195.58 19.755
J-255 170.69 0.2369 195.47 24.732
J-256 178.54 0.0254 191.29 12.716
J-258 175.37 0.0254 187.56 12.169
J-259 170.33 0.0254 186.76 16.39
J-261 172.21 0.0254 186.85 14.609
J-263 181.19 0.0254 192.72 11.507
J-264 181.07 0.0254 192.8 11.699
J-265 180.03 0.0254 2004 12.182
J-266 183.94 0 194.15 10.194
J-268 180.57 0.0254 192.85 12.251
J-273 180.86 0.0254 193.09 12.201
J-274 180.99 0.0254 193.26 12.244
J-280 177 0 188.09 11.067
J-281 177.17 0 188.14 10.944
J-283 177.69 0.1 188.59 10.875
J-284 177.13 0 187.98 10.829
J-285 178.82 0 191.06 12.224
CALCULO DE TUBERIAS
Gradiente
Longitud Nudo Nudo Diámetro Caudal Velocidad
Label Material PVC Hidráulico
(m) Inicial Final (mm) (l/s) (m/s)
(m/km)
Tub-1 0.57 J-215 J-216 63 PVC 140 0.1522 0.06 1.349
Tub-2 1.46 J-217 J-218 63 PVC 140 0.2515 0.09 0.256
Tub-3 2.07 J-153 J-117 110 PVC 140 -9.0968 1.11 12.658
Tub-4 2.36 J-53 J-50 90 PVC 130 -1.3966 0.26 1.204
Tub-5 2.39 J-219 J-220 63 PVC 140 0.0338 0.01 0
Tub-6 2.45 J-221 J-222 63 PVC 140 -0.1501 0.06 0.099
Tub-7 2.74 J-90 J-54 90 PVC 130 -1.5419 0.28 1.445
Tub-8 2.87 J-1 J-2 110 PVC 140 3.8109 0.47 2.525
Tub-9 3.17 J-223 J-219 63 PVC 140 -0.0338 0.01 0.006
Tub-10 3.2 J-3 J-4 90 PVC 140 -0.5976 0.11 0.221
Tub-11 3.29 J-5 J-6 110 PVC 140 -0.3383 0.04 0.028
Tub-12 3.56 J-154 J-155 90 PVC 130 6.8484 1.25 22.882
Tub-13 3.71 J-24 J-192 110 PVC 130 -2.9172 0.36 1.765
Tub-14 4.14 J-224 J-225 63 PVC 140 0.5559 0.21 1.083
Tub-15 5.29 J-226 J-227 63 PVC 140 -0.1015 0.04 0.046
Tub-16 4.45 J-158 J-89 90 PVC 130 -2.0301 0.37 2.406
Tub-17 4.82 J-143 J-1 90 PVC 130 3.9463 0.72 8.244
Tub-18 5.22 J-213 Reserv 110 PVC 140 -2.7235 0.33 1.355
Tub-19 6.01 J-93 J-94 160 PVC 140 2.9479 0.17 0.254
Tub-20 6.42 J-228 J-229 63 PVC 140 0.0507 0.02 0.012
Tub-21 6.79 J-95 J-94 110 PVC 140 -15.2138 1.86 32.811
Tub-22 84.94 J-35 J-36 63 PVC 140 -0.5202 0.19 0.956
Tub-23 86.66 J-37 J-38 63 PVC 140 -0.5591 0.21 1.093
Tub-24 84.71 J-39 J-40 90 PVC 140 -1.6404 0.3 1.414
RESUMEN EJECUTIVO
Página | 41
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO DE TUBERIAS
Gradiente
Longitud Nudo Nudo Diámetro Caudal Velocidad
Label Material PVC Hidráulico
(m) Inicial Final (mm) (l/s) (m/s)
(m/km)
Tub-25 94.61 J-7 J-8 90 PVC 140 -1.5772 0.29 1.315
Tub-26 7.19 J-159 J-160 110 PVC 140 -6.6133 0.81 7.014
Tub-27 7.3 J-161 J-162 110 PVC 140 -1.8443 0.23 0.66
Tub-28 7.33 J-41 J-42 90 PVC 140 3.4473 0.63 5.597
Tub-29 7.5 J-145 J-165 110 PVC 140 9.0968 1.11 12.658
Tub-30 7.68 J-43 J-44 90 PVC 140 0.4229 0.08 0.116
Tub-31 10.56 J-8 J-6 110 PVC 140 -3.4148 0.42 2.062
Tub-32 7.9 J-34 J-45 90 PVC 140 5.6869 1.04 14.139
Tub-33 9.58 J-81 J-15 90 PVC 130 -3.7557 0.69 7.523
Tub-34 9.61 J-195 J-196 110 PVC 130 -3.0812 0.38 1.956
Tub-35 9.61 J-77 J-92 110 PVC 140 -7.7761 0.95 9.467
Tub-36 9.79 J-46 J-47 90 PVC 140 -0.1519 0.03 0.017
Tub-37 9.91 J-197 J-209 110 PVC 140 -17.7632 2.17 43.716
Tub-38 10.27 J-167 J-31 90 PVC 130 -3.1953 0.58 5.577
Tub-39 10.63 J-230 J-231 63 PVC 140 0.3247 0.12 0.399
Tub-40 10.3 J-9 J-10 110 PVC 140 -3.6132 0.44 2.289
Tub-41 10.42 J-225 J-227 63 PVC 140 0.4714 0.18 0.797
Tub-42 10.92 J-48 J-49 90 PVC 140 -2.7118 0.5 3.587
Tub-43 11.13 J-209 R-2 200 PVC 140 -51.693 1.91 17.207
Tub-44 11.3 J-232 J-233 63 PVC 140 -0.6204 0.23 1.325
Tub-45 11.53 J-11 J-12 110 PVC 140 -4.476 0.55 3.404
Tub-46 11.58 J-72 J-168 110 PVC 140 -10.6921 1.31 17.075
Tub-47 11.74 J-52 J-169 90 PVC 130 -0.4902 0.09 0.173
Tub-48 11.88 J-4 J-189 90 PVC 130 -0.602 0.11 0.252
Tub-49 16.8 J-234 J-213 63 PVC 140 -1.5203 0.57 6.968
Tub-50 13.22 J-170 J-155 90 PVC 130 -7.5824 1.39 27.632
Tub-51 13.66 J-233 J-235 63 PVC 140 0.0507 0.02 0.014
Tub-52 13.81 J-50 J-51 90 PVC 140 -1.3966 0.26 1.049
Tub-53 14.5 J-47 J-52 90 PVC 140 -0.4902 0.09 0.151
Tub-54 15.08 J-59 J-38 90 PVC 130 1.8376 0.34 2.003
Tub-55 16.03 J-234 J-215 63 PVC 140 0.7476 0.28 1.872
Tub-56 16.66 J-96 J-97 110 PVC 140 3.61 0.44 2.286
Tub-57 16.58 J-53 J-54 90 PVC 140 1.5419 0.28 1.261
Tub-58 17.19 J-237 J-238 63 PVC 140 0.0507 0.02 0.012
Tub-59 17.52 J-219 J-232 63 PVC 140 -0.0677 0.03 0.022
Tub-60 17.33 J-199 J-200 110 PVC 130 2.5714 0.31 1.399
Tub-61 17.48 J-65 J-41 110 PVC 130 -6.5816 0.81 7.974
Tub-62 17.56 J-224 J-239 63 PVC 140 0.5458 0.2 1.045
Tub-63 17.93 J-236 J-226 63 PVC 140 -0.0169 0.01 0.001
Tub-64 18.58 J-239 J-218 63 PVC 140 0.2429 0.09 0.233
Tub-65 20.52 J-240 J-230 63 PVC 140 -0.0507 0.02 0.013
Tub-66 20.11 J-241 J-242 63 PVC 140 0.1522 0.06 0.099
Tub-67 20.35 J-243 J-225 63 PVC 140 -0.0846 0.03 0.033
Tub-68 21.38 J-231 J-244 63 PVC 140 0.0169 0.01 0.002
Tub-69 22.51 J-241 J-245 63 PVC 140 0.1899 0.07 0.148
Tub-70 22.43 J-95 J-60 200 PVC 140 -36.7862 1.36 9.165
Tub-71 28.82 J-237 J-246 63 PVC 140 0.0507 0.02 0.012
Tub-72 24.32 J-55 J-56 90 PVC 140 0.0236 0 0
Tub-73 24.46 J-237 J-247 63 PVC 140 -0.1691 0.06 0.119
Tub-74 24.67 J-11 J-13 110 PVC 140 2.0479 0.25 0.799
Tub-75 24.89 J-57 J-58 90 PVC 140 0.1626 0.03 0.019
Tub-76 26.55 J-233 J-234 63 PVC 140 -0.7388 0.28 1.831
Tub-77 26.52 J-248 J-217 63 PVC 140 -0.0507 0.02 0.013
Tub-78 27.31 J-227 J-217 63 PVC 140 0.3022 0.11 0.349
RESUMEN EJECUTIVO
Página | 42
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO DE TUBERIAS
Gradiente
Longitud Nudo Nudo Diámetro Caudal Velocidad
Label Material PVC Hidráulico
(m) Inicial Final (mm) (l/s) (m/s)
(m/km)
Tub-79 26.89 J-86 J-46 90 PVC 130 -0.1519 0.03 0.02
Tub-80 27.12 J-169 J-43 90 PVC 130 0.4229 0.08 0.132
Tub-81 27.25 J-44 J-55 90 PVC 140 0.1758 0.03 0.023
Tub-82 28.84 J-184 J-187 90 PVC 130 -0.3899 0.07 0.114
Tub-83 29.87 J-245 J-249 63 PVC 140 0.1222 0.05 0.065
Tub-84 30.06 J-59 J-8 90 PVC 140 -1.8376 0.34 1.745
Tub-85 30.08 J-60 J-61 110 PVC 140 -10.4552 1.28 16.38
Tub-86 31.09 J-62 J-63 90 PVC 140 -0.1353 0.02 0.014
Tub-87 32.64 J-218 J-241 63 PVC 140 0.4098 0.15 0.614
Tub-88 32.82 J-64 J-65 90 PVC 140 -0.1353 0.02 0.014
Tub-89 33.15 J-83 J-172 90 PVC 130 0.2908 0.05 0.066
Tub-90 33.51 J-168 J-77 110 PVC 140 -12.3086 1.51 22.16
Tub-91 33.74 J-201 J-4 90 PVC 130 -0.0044 0 0
Tub-92 50.05 J-213 J-224 63 PVC 140 1.2032 0.45 4.519
Tub-93 43.57 J-239 J-228 63 PVC 140 0.269 0.1 0.282
Tub-94 34.77 J-187 J-24 90 PVC 130 -0.9143 0.17 0.549
Tub-95 35.71 J-173 J-174 90 PVC 130 0.3383 0.06 0.087
Tub-96 36.4 J-9 J-11 110 PVC 140 -2.2758 0.28 0.972
Tub-97 36.52 J-176 J-53 90 PVC 130 0.1453 0.03 0.018
Tub-98 36.94 J-177 J-178 90 PVC 130 -0.4741 0.09 0.163
Tub-99 36.97 J-132 J-139 110 PVC 130 -3.7739 0.46 2.847
Tub-100 37.34 J-66 J-55 90 PVC 140 -0.1015 0.02 0.008
Tub-101 37.69 J-177 J-86 90 PVC 130 0.3388 0.06 0.087
Tub-110 37.87 J-15 J-167 90 PVC 130 -0.4328 0.08 0.138
Tub-103 38.64 J-14 J-15 90 PVC 140 3.323 0.61 5.227
Tub-104 39.47 J-250 J-226 63 PVC 140 -0.0846 0.03 0.033
Tub-105 39.09 J-165 J-163 110 PVC 140 9.0968 1.11 12.658
Tub-106 39.12 J-63 J-65 110 PVC 130 -6.3955 0.78 7.562
Tub-107 40.45 J-97 J-179 90 PVC 130 3.61 0.66 6.991
Tub-108 40.73 J-78 J-80 110 PVC 130 -6.929 0.85 8.771
Tub-109 40.93 J-67 J-45 90 PVC 140 -3.3706 0.62 5.367
Tub-110 41.21 J-68 J-69 90 PVC 140 -2.5883 0.47 3.291
Tub-111 41.43 J-242 J-251 63 PVC 140 0.0507 0.02 0.013
Tub-112 41.44 J-155 J-87 90 PVC 130 -0.9708 0.18 0.614
Tub-113 41.6 J-70 J-42 90 PVC 140 -3.4473 0.63 5.595
Tub-114 42.88 J-222 J-247 63 PVC 140 -0.2346 0.09 0.219
Tub-115 42.11 J-88 J-161 90 PVC 130 -1.3857 0.25 1.187
Tub-116 42.22 J-154 J-63 110 PVC 130 -6.1587 0.75 7.051
Tub-117 42.49 J-22 J-14 90 PVC 130 3.323 0.61 5.996
Tub-118 42.55 J-117 J-163 110 PVC 140 -9.0968 1.11 12.658
Tub-119 54.94 J-29 J-98 110 PVC 140 3.4414 0.42 2.092
Tub-120 43.06 J-202 J-203 110 PVC 130 -1.015 0.12 0.25
Tub-121 43.08 J-18 J-19 90 PVC 140 -0.0526 0.01 0.003
Tub-122 43.16 J-31 J-159 90 PVC 130 1.8211 0.33 1.969
Tub-123 43.71 J-71 J-48 90 PVC 140 1.9898 0.36 2.022
Tub-124 43.23 J-150 J-145 110 PVC 140 9.5812 1.17 13.935
Tub-125 43.37 J-89 J-154 90 PVC 130 0.9266 0.17 0.563
Tub-126 44.52 J-228 J-221 63 PVC 140 0.1675 0.06 0.117
Tub-127 44.48 J-20 J-18 90 PVC 140 1.0036 0.18 0.569
Tub-128 45.52 J-40 J-88 90 PVC 130 0.5723 0.1 0.231
Tub-129 46.11 J-12 J-139 110 PVC 130 -4.476 0.55 3.905
Tub-130 46.4 J-252 J-216 63 PVC 140 -0.0677 0.03 0.022
Tub-131 46.46 J-61 J-72 110 PVC 140 -10.6921 1.31 17.074
Tub-132 46.5 J-21 J-20 90 PVC 140 2.1784 0.4 2.391
RESUMEN EJECUTIVO
Página | 43
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO DE TUBERIAS
Gradiente
Longitud Nudo Nudo Diámetro Caudal Velocidad
Label Material PVC Hidráulico
(m) Inicial Final (mm) (l/s) (m/s)
(m/km)
Tub-133 48.21 J-215 J-230 63 PVC 140 0.46 0.17 0.762
Tub-134 47.9 J-2 J-22 110 PVC 140 -1.3239 0.16 0.357
Tub-135 47.93 J-23 J-24 110 PVC 140 -2.0029 0.25 0.768
Tub-136 47.82 J-73 J-74 90 PVC 140 -0.1353 0.02 0.014
Tub-137 47.92 J-10 J-132 110 PVC 130 -3.6132 0.44 2.626
Tub-138 48.8 J-202 J-204 110 PVC 130 1.015 0.12 0.25
Tub-139 48.78 J-180 J-181 90 PVC 130 2.0301 0.37 2.407
Tub-140 48.8 J-26 J-27 90 PVC 140 2.4785 0.45 3.037
Tub-141 48.96 J-205 J-3 90 PVC 130 -0.4961 0.09 0.177
Tub-142 49.04 J-87 J-81 90 PVC 130 -1.7833 0.33 1.893
Tub-143 49.04 J-36 J-40 90 PVC 130 1.5115 0.28 1.394
Tub-144 49.56 J-38 J-36 90 PVC 130 1.7916 0.33 1.91
Tub-145 74.44 J-75 J-71 90 PVC 140 0.3896 0.07 0.099
Tub-146 50.42 J-17 J-28 90 PVC 140 1.502 0.27 1.201
Tub-147 49.97 J-13 J-150 110 PVC 140 10.8169 1.32 17.445
Tub-148 50.24 J-104 J-110 110 PVC 130 -4.259 0.52 3.561
Tub-149 52.23 J-76 J-44 90 PVC 140 -0.1287 0.02 0.012
Tub-150 52.09 J-27 J-21 90 PVC 140 2.943 0.54 4.174
Tub-151 52.72 J-153 J-143 90 PVC 130 2.4159 0.44 3.323
Tub-152 52.93 J-48 J-77 90 PVC 140 4.5832 0.84 9.482
Tub-153 52.87 J-169 J-158 90 PVC 130 -1.0315 0.19 0.687
Tub-154 53.01 J-143 J-144 63 PVC 130 -1.5642 0.58 8.427
Tub-155 53.64 J-185 J-184 90 PVC 130 -1.4554 0.27 1.3
Tub-156 54.14 J-196 J-206 110 PVC 130 -1.0736 0.13 0.277
Tub-157 54.29 J-98 J-99 110 PVC 140 5.3037 0.65 4.661
Tub-158 58.61 J-231 J-253 63 PVC 140 0.2063 0.08 0.172
Tub-159 53.39 J-16 J-208 200 PVC 130 13 0.48 1.531
Tub-160 56.37 J-249 J-221 63 PVC 140 -0.233 0.09 0.216
Tub-161 56.75 J-26 J-17 110 PVC 140 -6.3669 0.78 6.537
Tub-162 56.77 J-196 J-104 110 PVC 130 -2.0075 0.25 0.884
Tub-163 56.84 J-189 J-185 90 PVC 130 -0.9366 0.17 0.575
Tub-164 56.89 J-67 J-78 90 PVC 140 3.286 0.6 5.12
Tub-165 56.45 J-253 J-254 63 PVC 140 0.0371 0.01 0.007
Tub-166 637 J-99 J-93 110 PVC 140 4.6853 0.57 3.704
Tub-167 58.51 J-203 J-207 110 PVC 130 0.812 0.1 0.165
Tub-168 58.74 J-21 J-79 63 PVC 130 0.0507 0.02 0.015
Tub-169 58.85 J-175 J-25 110 PVC 140 -0.9634 0.12 0.198
Tub-170 59.12 J-167 J-49 90 PVC 130 2.7118 0.5 4.115
Tub-171 60.4 J-41 J-78 110 PVC 130 -10.1473 1.24 17.778
Tub-172 61.11 J-100 J-99 110 PVC 140 -0.3478 0.04 0.03
Tub-173 61.98 J-110 J-103 110 PVC 130 -7.0236 0.86 8.994
Tub-174 62.34 J-92 J-159 110 PVC 140 -8.299 1.02 10.68
Tub-175 62.36 J-45 J-80 90 PVC 140 2.2148 0.41 2.466
Tub-176 63.64 J-29 J-30 110 PVC 140 -0.9644 0.12 0.199
Tub-177 68.31 J-27 J-28 63 PVC 130 -1.3836 0.52 6.713
Tub-178 69.34 J-71 J-81 90 PVC 140 -1.8032 0.33 1.685
Tub-179 90.73 J-139 J-147 110 PVC 130 -8.4867 1.04 12.769
Tub-180 71.2 J-5 J-148 63 PVC 130 0.3383 0.13 0.494
Tub-181 71.62 J-183 J-176 110 PVC 130 -5.4239 0.66 5.573
Tub-182 71.93 J-82 J-83 90 PVC 140 -1.4546 0.27 1.132
Tub-183 72.3 J-84 J-47 90 PVC 140 -0.2538 0.05 0.045
Tub-184 72.86 J-172 J-182 90 PVC 130 -3.056 0.56 5.135
Tub-185 73.7 J-203 J-205 110 PVC 130 -1.8271 0.22 0.743
Tub-186 74.84 J-183 J-83 90 PVC 130 1.9823 0.36 2.303
RESUMEN EJECUTIVO
Página | 44
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO DE TUBERIAS
Gradiente
Longitud Nudo Nudo Diámetro Caudal Velocidad
Label Material PVC Hidráulico
(m) Inicial Final (mm) (l/s) (m/s)
(m/km)
Tub-187 87.09 J-205 J-32 110 PVC 130 -1.5001 0.18 0.516
Tub-188 98.42 J-149 J-150 63 PVC 130 -1.2357 0.46 5.445
Tub-189 77.42 J-85 J-86 90 PVC 140 -0.2707 0.05 0.05
Tub-190 77.53 J-184 J-82 90 PVC 130 -1.2685 0.23 1.008
Tub-191 78.04 J-185 J-58 90 PVC 130 0.0573 0.01 0.003
Tub-192 78.05 J-74 J-197 160 PVC 140 -17.7463 1.03 7.026
Tub-193 81.81 J-75 J-87 90 PVC 140 -0.5757 0.11 0.203
Tub-194 85.94 J-31 J-2 110 PVC 140 -5.1348 0.63 4.389
Tub-195 99.23 J-34 J-88 90 PVC 140 -2.439 0.45 2.948
Tub-196 86.97 J-105 J-106 200 PVC 140 -26.331 0.98 4.933
Tub-197 90.39 J-160 J-153 110 PVC 140 -6.6133 0.81 7.013
Tub-198 90.78 J-91 J-173 90 PVC 140 0.4383 0.08 0.123
Tub-199 91.29 J-89 J-70 90 PVC 140 -3.1597 0.58 4.762
Tub-200 92.6 J-178 J-158 90 PVC 130 -0.711 0.13 0.345
Tub-201 93.25 J-80 J-162 110 PVC 130 -5.929 0.73 6.572
Tub-202 97.92 J-93 J-96 160 PVC 140 1.213 0.07 0.049
Tub-203 124.05 J-182 J-90 90 PVC 130 -1.5165 0.28 1.403
Tub-204 104.3 J-182 J-176 90 PVC 130 -1.7932 0.33 1.913
Tub-205 155.19 J-96 J-100 110 PVC 140 -2.7861 0.34 1.415
Tub-206 110.45 J-6 J-26 110 PVC 140 -3.7531 0.46 2.456
Tub-207 112.11 J-100 J-101 110 PVC 140 -2.6583 0.33 1.297
Tub-208 110.96 J-176 J-170 110 PVC 130 -7.5824 0.93 10.364
Tub-209 111.01 J-187 J-188 90 PVC 130 0.3722 0.07 0.104
Tub-210 111.8 J-88 J-18 90 PVC 140 -0.8531 0.16 0.421
Tub-211 111.83 J-40 J-20 90 PVC 140 -0.9888 0.18 0.554
Tub-212 112.17 J-36 J-21 63 PVC 130 -0.4769 0.18 0.934
Tub-213 112.23 J-101 J-195 110 PVC 130 -2.9966 0.37 1.857
Tub-214 112.33 J-161 J-19 90 PVC 130 0.171 0.03 0.025
Tub-215 114.78 J-38 J-27 63 PVC 130 -0.7161 0.27 1.982
Tub-216 115.67 J-147 J-13 110 PVC 140 8.8705 1.09 12.081
Tub-217 116.89 J-74 J-147 160 PVC 140 17.5433 1.01 6.878
Tub-218 99.09 J-189 J-259 90 PVC 130 0.0808 0.01 0.006
Tub-219 118.74 J-68 J-190 90 PVC 130 0.0846 0.02 0.007
Tub-220 112.05 J-32 J-23 110 PVC 140 -1.5799 0.19 0.495
Tub-221 138.83 J-51 J-168 90 PVC 130 -1.3966 0.26 1.204
Tub-222 132.39 J-91 J-92 110 PVC 140 -0.5229 0.06 0.064
Tub-223 164.89 J-249 J-255 63 PVC 140 0.2369 0.09 0.223
Tub-224 150.02 J-107 J-95 200 PVC 140 -52 1.93 17.397
Tub-225 168.88 J-94 J-30 160 PVC 140 -12.2659 0.71 3.545
Tub-226 151.27 J-180 J-68 90 PVC 130 -2.2162 0.41 2.832
Tub-227 152.92 J-192 J-183 110 PVC 130 -3.1033 0.38 1.981
Tub-228 174.14 J-110 J-29 110 PVC 140 2.6969 0.33 1.332
Tub-229 178.04 J-30 J-103 160 PVC 140 -13.7209 0.79 4.363
Tub-230 200.55 J-98 J-104 110 PVC 140 -2.0992 0.26 0.837
Tub-231 246.32 J-60 J-105 200 PVC 140 -26.331 0.98 4.933
Tub-232 234.32 J-209 J-199 200 PVC 140 31.3076 1.16 6.798
Tub-233 31.88 J-34 J-39 90 PVC 130 -3.2479 0.59 5.748
Tub-234 50.46 J-39 J-35 90 PVC 130 -1.8951 0.35 2.119
Tub-235 47.91 J-35 J-37 90 PVC 130 -1.6795 0.31 1.694
Tub-236 45.32 J-37 J-7 90 PVC 130 -1.3741 0.25 1.169
Tub-237 84.75 J-80 J-256 90 PVC 130 1.0795 0.2 0.747
Tub-238 123.86 J-22 J-256 90 PVC 130 -4.9176 0.9 12.392
Tub-239 91.92 J-256 J-25 90 PVC 130 -4.655 0.85 11.194
Tub-240 62.25 J-90 J-258 90 PVC 130 0.0254 0 0.001
RESUMEN EJECUTIVO
Página | 45
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO DE TUBERIAS
Gradiente
Longitud Nudo Nudo Diámetro Caudal Velocidad
Label Material PVC Hidráulico
(m) Inicial Final (mm) (l/s) (m/s)
(m/km)
Tub-241 43.64 J-259 J-69 90 PVC 130 0.9643 0.18 0.607
Tub-242 43.73 J-57 J-261 90 PVC 130 -1.4606 0.27 1.309
Tub-243 62.34 J-69 J-261 90 PVC 130 -1.7763 0.33 1.88
Tub-244 29.27 J-261 J-172 90 PVC 130 -3.2623 0.6 5.795
Tub-245 46.67 J-185 J-32 110 PVC 130 0.0894 0.01 0.003
Tub-246 21.1 J-263 J-132 110 PVC 130 -0.0254 0 0
Tub-247 47.7 J-9 J-25 110 PVC 140 5.7029 0.7 5.331
Tub-248 63.5 J-175 J-264 110 PVC 140 -6.9876 0.86 7.766
Tub-249 176.3 J-264 J-199 110 PVC 140 -7.0129 0.86 7.818
Tub-250 29.47 J-162 J-265 110 PVC 140 -7.7734 0.95 9.461
Tub-251 6.55 J-265 J-175 110 PVC 140 -7.7987 0.95 9.518
Tub-252 6.27 J-199 J-266 200 PVC 140 21.2665 0.79 3.322
Tub-253 58.9 J-247 J-254 63 PVC 130 -0.4714 0.18 0.914
Tub-254 19.84 J-254 J-232 63 PVC 130 -0.4681 0.17 0.902
Tub-255 1.96 J-268 J-17 110 PVC 140 7.9197 0.97 9.789
Tub-256 24.34 J-268 J-273 110 PVC 140 -7.945 0.97 9.852
Tub-257 17.31 J-273 J-274 110 PVC 140 -7.9704 0.98 9.91
Tub-258 269.74 J-266 J-274 200 PVC 140 21.2665 0.79 3.321
Tub-259 5.03 J-274 J-16 200 PVC 130 13.2707 0.49 1.591
Tub-260 61.63 J-57 J-259 90 PVC 130 0.9089 0.17 0.543
Tub-261 24.82 R-13 J-206 110 PVC 130 1.2597 0.15 0.373
Tub-262 43.2 J-103 J-280 160 PVC 140 -20.8629 1.21 9.481
Tub-263 10.64 J-281 R-8 200 PVC 140 -47.1939 1.75 14.537
Tub-264 4.58 J-280 J-281 160 PVC 140 -20.8629 1.21 9.481
Tub-265 81.38 J-173 J-283 90 PVC 140 0.1 0.02 0.008
Tub-266 9.26 J-106 J-284 200 PVC 140 -26.331 0.98 4.934
Tub-267 31.56 J-284 J-281 200 PVC 140 -26.331 0.98 4.933
Tub-268 49.04 J-145 J-285 63 PVC 130 0.4844 0.18 0.961
Tub-269 41.19 J-285 J-146 63 PVC 130 2.224 0.83 16.17
Tub-270 12.69 J-285 J-149 63 PVC 140 -1.7396 0.65 8.945
Tub-271 15.57 J-146 J-144 63 PVC 140 1.9364 0.72 10.908
Tub-272 45.56 J-256 J-149 63 PVC 130 0.7915 0.3 2.387
Se recomienda a partir de ello, que con la finalidad de complementar el proyecto de la referencia y de mejorar las presiones en
el Sistema, se programen de acuerdo a las posibilidades y alcances que la EPS se permita, el mejoramiento de la Troncal
principales que tiene como punto de partida la PTAP Huando.
RESUMEN EJECUTIVO
Página | 46
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO DE BUZONES
Cota Cota Prof. Caudal Diámetro
Label
Terreno (m) Fondo (m) (m) Total (L/s) (mm)
1 185.5 183.5 2.00 2.4371 1,200.00
1 185.5 184.3 1.20 1.5771 1,200.00
2 185.34 183.84 1.50 1.6543 1,200.00
3 184.72 183.32 1.40 1.7314 1,200.00
4 184.5 182.85 1.65 1.8085 1,200.00
5 184 182.3 1.70 1.8856 1,200.00
6 182.92 181.77 1.15 1.9628 1,200.00
7 182.5 181.1 1.40 2.0399 1,200.00
8 181.91 180.61 1.30 2.117 1,200.00
9 181.5 180.2 1.30 2.1941 1,200.00
10 181 179.5 1.50 2.2713 1,200.00
11 185.78 183.28 2.50 2.5143 1,200.00
12 185 182.75 2.25 2.5914 1,200.00
13 184.88 182.18 2.70 11.9785 1,200.00
14 184.7 182.05 2.65 12.0556 1,200.00
15 184.5 181.9 2.60 12.1328 1,200.00
16 183.57 181.59 1.98 13.427 1,200.00
17 182.7 180.71 1.99 13.9041 1,200.00
18 181.7 180 1.70 18.0684 1,200.00
19 180.84 179.15 1.69 18.1455 1,200.00
20 180 178.3 1.70 24.9168 1,200.00
21 177.41 175.53 1.88 24.5082 1,200.00
22 176.79 174.86 1.93 24.5853 1,200.00
23 176.15 174.15 2.00 27.971 1,200.00
24 175.69 173.39 2.30 4.1223 1,200.00
25 175 172.87 2.13 5.7766 1,200.00
25 175 173.8 1.20 1.5771 1,200.00
26 175 172.3 2.70 5.8537 1,200.00
27 173.84 171.99 1.85 18.2436 1,200.00
28 173.61 172.41 1.20 1.5771 1,200.00
28 173.61 171.63 1.98 18.3207 1,200.00
29 173.18 171.09 2.09 18.3979 1,200.00
30 172.58 170.37 2.21 18.475 1,200.00
31 171.73 169.38 2.35 28.4062 1,200.00
32 183.92 182.72 1.20 1.5771 1,200.00
33 182 180.8 1.20 1.5771 1,200.00
33 182 180.8 1.20 1.5771 1,200.00
34 181.17 179.97 1.20 1.5771 1,200.00
35 181.04 179.69 1.35 1.6543 1,200.00
35 181.04 179.72 1.32 1.5771 1,200.00
36 180.98 179.18 1.80 3.3085 1,200.00
37 180.71 179.01 1.70 3.3856 1,200.00
38 180.3 179.1 1.20 1.5771 1,200.00
39 180 178.69 1.31 3.2314 1,200.00
40 180 178.42 1.58 6.6941 1,200.00
41 177.28 175.72 1.56 1.5771 1,200.00
41 177.28 176.08 1.20 1.5771 1,200.00
42 176.77 175.17 1.60 1.6543 1,200.00
43 176.43 175.13 1.30 1.5771 1,200.00
44 176.21 174.51 1.70 3.3085 1,200.00
45 176.18 174.58 1.60 3.2571 1,200.00
46 176 174.18 1.82 3.3343 1,200.00
47 175.03 173.73 1.30 1.5771 1,200.00
RESUMEN EJECUTIVO
Página | 47
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO DE BUZONES
Cota Caudal
Cota Prof. Diámetro
Label Terreno Total
Fondo (m) (m) (mm)
(m) (L/s)
48 177.35 175.49 1.86 11.9271 1,200.00
49 176.85 174.99 1.86 12.0043 1,200.00
50 176.19 174.29 1.90 12.0814 1,200.00
51 175.87 173.85 2.02 12.1585 1,200.00
51 175.87 173.85 2.02 1.5771 1,200.00
52 175 173.25 1.75 12.2356 1,200.00
53 174.5 172.7 1.80 12.3128 1,200.00
54 176.19 174.99 1.20 1.5771 1,200.00
55 175.83 174.16 1.67 1.6543 1,200.00
56 175.41 173.36 2.05 1.7314 1,200.00
57 174.91 172.74 2.17 3.3856 1,200.00
58 174.51 172.19 2.32 3.4628 1,200.00
59 175.47 174.27 1.20 1.5771 1,200.00
60 175.12 173.46 1.66 1.6543 1,200.00
61 174.52 172.59 1.93 1.7314 1,200.00
62 173.94 171.89 2.05 1.8085 1,200.00
63 173.91 171.64 2.27 5.3484 1,200.00
64 177.53 175.93 1.60 3.6941 1,200.00
65 173.36 171.26 2.10 7.0027 1,200.00
66 173.29 171.59 1.70 2.6971 1,200.00
67 172.44 170.74 1.70 9.7769 1,200.00
68 171.87 170.17 1.70 9.854 1,200.00
69 178.31 177.11 1.20 1.5771 1,200.00
70 177.72 176.46 1.26 1.6543 1,200.00
71 177 175.6 1.40 3.3085 1,200.00
72 176.84 175.35 1.49 3.3856 1,200.00
73 176.5 175 1.50 3.4628 1,200.00
74 175.5 174.1 1.40 1.5771 1,200.00
75 176.83 175.63 1.20 1.5771 1,200.00
75 176.83 175.63 1.20 1.5771 1,200.00
76 176.71 175.44 1.27 1.6543 1,200.00
77 176.25 174.87 1.38 1.7314 1,200.00
78 175.97 174.28 1.69 1.8085 1,200.00
79 175.47 173.47 2.00 3.4628 1,200.00
80 174.12 172.63 1.49 3.5399 1,200.00
81 173.27 171.73 1.54 3.617 1,200.00
82 172.12 170.72 1.40 3.6941 1,200.00
83 176.07 174.51 1.56 1.6543 1,200.00
84 174.63 173.23 1.40 1.7314 1,200.00
85 171.84 170.28 1.56 1.8085 1,200.00
86 171.19 169.67 1.52 1.8856 1,200.00
87 170.5 169.15 1.35 1.9628 1,200.00
88 175 173.24 1.76 1.6543 1,200.00
89 175.16 172.73 2.43 1.7314 1,200.00
90 174.84 172.24 2.60 1.8085 1,200.00
91 173.84 171.73 2.11 1.8856 1,200.00
91 173.84 172.64 1.20 1.5771 1,200.00
92 173.13 171.93 1.20 1.5771 1,200.00
92 173.13 170.89 2.24 1.9628 1,200.00
93 172.62 170.26 2.36 2.0399 1,200.00
94 175.44 174.04 1.40 1.5771 1,200.00
95 175.01 173.26 1.75 1.6543 1,200.00
96 174.74 172.27 2.47 1.7314 1,200.00
97 173.82 171.9 1.92 1.8085 1,200.00
98 173.79 172.19 1.60 1.6543 1,200.00
RESUMEN EJECUTIVO
Página | 48
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Cota Caudal
Cota Prof. Diámetro
Label Terreno Total
Fondo (m) (m) (mm)
(m) (L/s)
99 174 171.5 2.50 3.5399 1,200.00
100 172.77 171.03 1.74 3.617 1,200.00
101 172.18 169.65 2.53 5.734 1,200.00
110 172.24 169.45 2.79 7.3883 1,200.00
103 172.07 170.77 1.30 1.5771 1,200.00
104 170.3 168.74 1.56 3.2314 1,200.00
105 170.87 169.41 1.46 1.5771 1,200.00
105 170.87 169 1.87 7.4654 1,200.00
106 180.36 179.16 1.20 1.5771 1,200.00
107 182.01 180.51 1.50 1.5771 1,200.00
108 181.19 179.59 1.60 1.6543 1,200.00
109 180.15 178.43 1.72 3.3085 1,200.00
110 181.52 179.96 1.56 1.5771 1,200.00
111 180.6 178.99 1.61 1.6543 1,200.00
112 179.92 178.12 1.80 5.0399 1,200.00
112 179.92 178.72 1.20 1.5771 1,200.00
113 180.46 178.9 1.56 1.5771 1,200.00
114 179.45 178.25 1.20 1.5771 1,200.00
114 179.45 177.6 1.85 6.6941 1,200.00
115 180.5 179.1 1.40 1.5771 1,200.00
116 180 178.3 1.70 1.6543 1,200.00
117 179.01 177.05 1.96 8.4255 1,200.00
118 178.5 176.5 2.00 4.8127 1,200.00
119 179.45 177.99 1.46 1.6543 1,200.00
120 178.92 177.39 1.53 1.7314 1,200.00
121 178.95 177.44 1.51 1.6543 1,200.00
122 178.39 176.79 1.60 3.4628 1,200.00
123 178.29 177.09 1.20 2.0771 1,200.00
123 178.29 176.69 1.60 3.5399 1,200.00
124 177.89 176.33 1.56 3.617 1,200.00
125 177.26 176.54 0.72 2.1543 1,200.00
126 178.72 177.16 1.56 1.5771 1,200.00
127 177.7 175.94 1.76 3.8085 1,200.00
128 176.96 175.66 1.30 1.5771 1,200.00
129 176.5 175.03 1.47 1.6543 1,200.00
130 176.14 175.34 0.80 1.5771 1,200.00
131 176.61 174.83 1.78 1.6543 1,200.00
132 175.76 175.06 0.70 1.5771 1,200.00
133 176.18 174.55 1.63 1.6543 1,200.00
134 174.44 173.69 0.75 1.5771 1,200.00
135 173.15 172.48 0.67 3.0771 1,200.00
136 173.5 172.19 1.31 3.1543 1,200.00
137 173.99 171.89 2.10 3.2314 1,200.00
138 173.53 171.93 1.60 1.5771 1,200.00
139 173 171 2.00 1.6543 1,200.00
140 172.13 169.63 2.50 1.7314 1,200.00
141 172.01 168.81 3.20 21.6685 1,200.00
142 170.92 168.62 2.30 22.2156 1,200.00
142 170.92 169.72 1.20 2.5771 1,200.00
143 172.15 170.95 1.20 1.5771 1,200.00
144 171.02 169.41 1.61 1.6543 1,200.00
145 170.42 168.38 2.04 23.947 1,200.00
146 172.16 170.96 1.20 1.5771 1,200.00
147 171.5 169.9 1.60 1.6543 1,200.00
148 170.63 168.93 1.70 1.7314 1,200.00
RESUMEN EJECUTIVO
Página | 49
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 50
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
CALCULO EN TUBERIAS
Caudal Velocidad Tensión
Buzón CF Buzón CF Diámetro Caudal Longitud Pendiente Tirante
Label Material Recolectado Promedio Tractiva
Inicial Inicial(m) Final Final(m) (mm) Total (L/s) (m) (m/m) "Y"(%)
(L/s) (m/s) (Pascals)
Tub-1 131 174.83 OF-7 174.7 PVC 200 0.1543 1.6543 6.71 0.019 0.691 3.12 15.7
Tub-2 10 179.5 OF-1 179.37 PVC 200 0.7713 2.2713 7.92 0.016 0.717 3.153 18.7
Tub-3 BE-29 171.48 OF-3 171.34 PVC 200 0.1543 1.6543 8.23 0.017 0.66 2.82 15.9
Tub-4 133 174.55 OF-8 174.4 PVC 200 0.1543 1.6543 8.23 0.018 0.679 2.966 15.8
Tub-5 13 182.18 14 182.05 PVC 200 0.3085 11.9785 8.53 0.015 1.126 6.083 49.3
Tub-6 BE-26 173.44 OF-10 173.18 PVC 200 0.1543 1.6543 8.53 0.03 0.812 4.422 15
Tub-7 127 175.94 OF-13 175.84 PVC 200 0.3085 3.8085 8.84 0.011 0.732 2.965 25.2
Tub-8 118 176.5 OF-11 176.4 PVC 200 1.0027 4.8127 10.36 0.01 0.741 2.892 29
Tub-9 BE-25 174.18 OF-6 174.03 PVC 200 0.2314 1.7314 10.97 0.014 0.62 2.426 16.6
Tub-10 137 171.89 OF-9 171.8 PVC 200 0.2314 3.2314 10.97 0.008 0.624 2.143 24.1
Tub-11 BE-31 168.23 OF-5 168.1 PVC 200 0.3085 3.3085 11.28 0.012 0.707 2.829 23.5
Tub-12 122 176.79 123 176.69 PVC 200 0.4628 3.4628 11.89 0.008 0.639 2.258 25.9
Tub-13 BE-13 168.75 BE-14 168.7 PVC 200 1.5426 7.5426 11.89 0.004 0.621 1.807 41.1
Tub-14 64 175.93 OF-12 175.8 PVC 200 0.6941 3.6941 13.11 0.01 0.694 2.636 25.2
Tub-15 36 179.18 37 179.01 PVC 200 0.3085 3.3085 13.11 0.013 0.737 3.110 25.3
Tub-16 82 170.72 BP-01 169.52 PVC 200 0.6941 3.6941 14.94 0.08 1.453 13.439 20.4
Tub-17 73 175 OF-2 174.87 PVC 200 0.4628 3.4628 15.24 0.009 0.642 2.284 24.9
Tub-18 134 173.69 BE-26 173.44 PVC 200 0.0771 1.5771 15.54 0.016 0.64 2.638 17.4
Tub-19 BE-36 166.57 OF-15 166.42 PVC 200 0.5399 4.5399 17.37 0.009 0.698 2.591 28.6
Tub-20 BE-16 167.48 BE-17 167.32 PVC 200 2.2367 9.7367 18.59 0.009 0.864 3.548 47.6
Tub-21 34 179.97 35 179.69 PVC 200 0.0771 1.5771 18.59 0.015 0.625 2.505 17.4
Tub-22 75 175.63 83 174.51 PVC 200 0.0771 1.5771 18.59 0.06 1.014 7.348 17.4
Tub-23 47 173.73 25 172.87 PVC 200 0.0771 1.5771 17.07 0.05 0.952 6.4 24.3
Tub-24 62 171.89 63 171.64 PVC 200 0.3085 1.8085 20.12 0.012 0.608 2.297 25.3
Tub-25 83 174.51 84 173.23 PVC 200 0.1543 1.6543 20.12 0.064 1.048 7.834 17.8
Tub-26 86 169.67 87 169.15 PVC 200 0.3856 1.8856 20.12 0.026 0.796 4.133 19
Tub-27 14 182.05 15 181.9 PVC 200 0.3856 12.0556 21.95 0.007 0.838 3.204 50.7
Tub-28 101 169.65 110 169.45 PVC 200 1.234 5.734 23.77 0.008 0.74 2.802 35.7
Tub-29 96 172.27 97 171.9 PVC 200 0.2314 1.7314 25.6 0.014 0.632 2.533 18.2
Tub-30 58 172.19 63 171.64 PVC 200 0.4628 3.4628 26.82 0.021 0.877 4.529 28.9
Tub-31 97 171.9 99 171.5 PVC 200 0.3085 1.8085 27.13 0.015 0.645 2.624 22.2
RESUMEN EJECUTIVO
Página | 51
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 52
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 53
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Caudal Tensión
Buzón CF Buzón CF Diámetro Caudal Longitud Pendiente Velocidad Tirante
Label Material Recolectado Tractiva
Inicial Inicial(m) Final Final(m) (mm) Total (L/s) (m) (m/m) Promedio (m/s) "Y"(%)
(L/s) (Pascals)
Tub-98 124 176.33 64 175.93 PVC 200 0.617 3.617 50.9 0.008 0.633 2.18 26.4
Tub-99 117 177.05 118 176.5 PVC 200 0.9255 8.4255 50.9 0.011 0.901 4.013 38.3
Tub-100 104 168.74 BE-31 168.23 PVC 200 0.2314 3.2314 51.21 0.01 0.667 2.498 25
Tub-101 15 181.9 16 181.59 PVC 200 0.4628 12.1328 51.21 0.006 0.802 2.91 51.8
Tub-110 147 169.9 148 168.93 PVC 200 0.1543 1.6543 51.51 0.019 0.683 3.054 17.8
Tub-103 148 168.93 149 168.04 PVC 200 0.2314 1.7314 51.82 0.017 0.67 2.903 44
Tub-104 50 174.29 51 173.85 PVC 200 0.2314 12.0814 51.82 0.008 0.909 3.823 49.2
Tub-105 18 180 19 179.15 PVC 200 0.8484 18.0684 53.04 0.016 1.277 7.453 60.8
Tub-106 53 172.7 27 171.99 PVC 200 0.4628 12.3128 53.04 0.013 1.082 5.55 51.4
Tub-107 61 172.59 62 171.89 PVC 200 0.2314 1.7314 53.34 0.013 0.611 2.351 18.2
Tub-108 98 172.19 99 171.5 PVC 200 0.1543 1.6543 53.34 0.013 0.6 2.278 21.8
Tub-109 106 179.16 109 178.43 PVC 200 0.0771 1.5771 53.64 0.014 0.601 2.321 21.2
Tub-110 94 174.04 95 173.26 PVC 200 0.0771 1.5771 53.95 0.014 0.613 2.437 17.4
Tub-111 154 168.05 155 167.3 PVC 200 0.2314 2.7314 54.25 0.014 0.714 2.993 23
Tub-112 111 178.99 112 178.12 PVC 200 0.1543 1.6543 54.56 0.016 0.648 2.673 24.4
Tub-113 115 179.1 116 178.3 PVC 200 0.0771 1.5771 54.56 0.015 0.62 2.452 17.4
Tub-114 110 179.96 111 178.99 PVC 200 0.0771 1.5771 54.56 0.018 0.661 2.854 17.4
Tub-115 116 178.3 117 177.05 PVC 200 0.1543 1.6543 54.56 0.023 0.734 3.548 29.2
Tub-116 144 169.41 145 168.38 PVC 200 0.1543 1.6543 54.86 0.019 0.682 3.047 41.7
Tub-117 20 178.3 BE-04 177.49 PVC 200 1.6968 24.9168 55.17 0.015 1.63 7.095 71.6
Tub-118 139 171 140 169.63 PVC 200 0.1543 1.6543 55.47 0.025 0.754 3.76 17.8
Tub-119 113 178.9 114 177.6 PVC 200 0.0771 1.5771 55.47 0.023 0.73 3.533 26.7
Tub-120 51 173.85 52 173.25 PVC 200 0.3085 12.1585 55.47 0.011 0.997 4.655 49.4
Tub-121 138 171.93 139 171 PVC 200 0.0771 1.5771 55.78 0.017 0.649 2.708 17.4
Tub-122 93 170.26 101 169.65 PVC 200 0.5399 2.0399 56.08 0.011 0.601 2.184 26.5
Tub-123 92 170.89 93 170.26 PVC 200 0.4628 1.9628 56.08 0.011 0.601 2.201 19.4
Tub-124 125 176.54 127 175.94 PVC 200 0.1543 2.1543 57 0.011 0.604 2.182 23.6
Tub-125 70 176.46 71 175.6 PVC 200 0.1543 1.6543 57.3 0.015 0.631 2.559 21.4
Tub-126 16 181.59 17 180.71 PVC 200 0.617 13.427 57.91 0.015 1.159 6.361 52.4
Tub-127 17 180.71 18 180 PVC 200 0.6941 13.9041 58.83 0.012 1.075 5.359 56.8
Tub-128 78 174.28 79 173.47 PVC 200 0.3085 1.8085 58.83 0.014 0.63 2.488 22.1
Tub-129 55 174.16 56 173.36 PVC 200 0.1543 1.6543 59.13 0.014 0.61 2.358 17.8
Tub-130 67 170.74 68 170.17 PVC 200 1.1569 9.7769 59.13 0.01 0.902 3.89 44.1
RESUMEN EJECUTIVO
Página | 54
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Caudal Tensión
Buzón CF Buzón CF Diámetro Caudal Longitud Pendiente Velocidad Tirante
Label Material Recolectado Tractiva
Inicial Inicial(m) Final Final(m) (mm) Total (L/s) (m) (m/m) Promedio (m/s) "Y"(%)
(L/s) (Pascals)
Tub-131 48 175.49 49 174.99 PVC 200 0.0771 11.9271 59.44 0.008 0.903 3.775 48.9
Tub-132 129 175.03 BE-25 174.18 PVC 200 0.1543 1.6543 59.74 0.014 0.621 2.452 17.8
Tub-133 59 174.27 60 173.46 PVC 200 0.0771 1.5771 59.74 0.014 0.601 2.314 17.4
Tub-134 54 174.99 55 174.16 PVC 200 0.0771 1.5771 60.96 0.014 0.602 2.322 17.4
Tub-135 153 168.95 154 168.05 PVC 200 0.1543 2.6543 61.57 0.015 0.723 3.084 22.6
Tub-136 49 174.99 50 174.29 PVC 200 0.1543 12.0043 61.87 0.011 1.01 4.802 49.1
Tub-137 33 180.8 36 179.18 PVC 200 0.0771 1.5771 62.79 0.026 0.755 3.805 21.2
Tub-138 110 169.45 105 169 PVC 200 1.3883 7.3883 63.09 0.007 0.748 2.731 38.1
Tub-139 19 179.15 20 178.3 PVC 200 0.9255 18.1455 63.4 0.013 1.195 6.457 66.2
Tub-140 BE-14 168.7 BE-15 168.12 PVC 200 1.6197 7.6197 64.31 0.009 0.821 3.335 38.7
Tub-141 65 171.26 67 170.74 PVC 200 1.0027 7.0027 64.31 0.008 0.771 2.953 40.5
Tub-142 107 180.51 108 179.59 PVC 200 0.0771 1.5771 64.62 0.014 0.61 2.407 17.4
Tub-143 108 179.59 109 178.43 PVC 200 0.1543 1.6543 64.62 0.018 0.675 2.933 21.4
Tub-144 9 180.2 10 179.5 PVC 200 0.6941 2.1941 65.23 0.011 0.611 2.233 20.6
Tub-145 BE-15 168.12 BE-16 167.48 PVC 200 1.6968 7.6968 65.84 0.01 0.846 3.554 41.4
Tub-146 60 173.46 61 172.59 PVC 200 0.1543 1.6543 66.75 0.013 0.602 2.291 17.8
Tub-147 143 170.95 144 169.41 PVC 200 0.0771 1.5771 66.75 0.023 0.725 3.491 17.4
Tub-148 95 173.26 96 172.27 PVC 200 0.1543 1.6543 67.06 0.015 0.628 2.525 17.8
Tub-149 68 170.17 31 169.38 PVC 200 1.234 9.854 70.41 0.011 0.955 4.405 55.5
Tub-150 91 171.73 92 170.89 PVC 200 0.3856 1.8856 71.32 0.012 0.604 2.245 19
Tub-151 46 174.18 24 173.39 PVC 200 0.1543 3.3343 75.29 0.01 0.685 2.638 25.8
Tub-152 BE-05 176.87 21 175.53 PVC 200 1.8511 24.3511 85.34 0.016 1.662 7.43 60.6
Tub-153 151 167.23 152 167.12 PVC 250 1.0798 26.1398 10.06 0.011 1.213 6.274 59.8
Tub-154 BE-34 166.95 OF-14 166.9 PVC 250 1.234 26.294 12.8 0.004 0.816 2.68 60.7
Tub-155 145 168.38 149 168.04 PVC 250 0.617 23.947 29.57 0.011 1.209 6.315 54.2
Tub-156 26 172.3 27 171.99 PVC 250 2.8537 5.8537 34.44 0.009 0.745 2.886 33.9
Tub-157 152 167.12 BE-34 166.95 PVC 250 1.1569 26.2169 39.62 0.004 0.847 2.902 65.4
Tub-158 142 168.62 145 168.38 PVC 250 0.3856 22.2156 40.54 0.006 0.925 3.585 52.5
Tub-159 141 168.81 142 168.62 PVC 250 0.3085 21.6685 41.15 0.005 0.837 2.898 54
Tub-160 24 173.39 25 172.87 PVC 250 2.6223 4.1223 41.76 0.012 0.755 3.184 23.1
Tub-161 21 175.53 22 174.86 PVC 250 1.9282 24.5082 48.16 0.014 1.305 7.426 53.2
Tub-162 22 174.86 23 174.15 PVC 250 2.0053 24.5853 48.16 0.015 1.334 7.79 55.1
Tub-163 149 168.04 150 167.7 PVC 250 0.9255 25.7555 53.04 0.006 0.988 4.036 55.3
RESUMEN EJECUTIVO
Página | 55
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Caudal Tensión
Buzón CF Buzón CF Diámetro Caudal Longitud Pendiente Velocidad Tirante
Label Material Recolectado Tractiva
Inicial Inicial(m) Final Final(m) (mm) Total (L/s) (m) (m/m) Promedio (m/s) "Y"(%)
(L/s) (Pascals)
Tub-164 25 172.87 26 172.3 PVC 250 2.7766 5.7766 55.78 0.01 0.778 3.166 25.2
Tub-165 150 167.7 151 167.23 PVC 250 1.0027 4.4427 57 0.008 0.667 2.387 38.5
Tub-166 23 174.15 24 173.39 PVC 250 2.391 27.971 71.32 0.011 1.222 6.302 53.7
Tub-167 BP-01 166.86 OF-4 166.76 PVC 315 8.0984 42.0684 14.02 0.007 1.164 5.3 51.2
Tub-168 27 171.99 28 171.63 PVC 315 3.3936 18.2436 24.69 0.015 1.201 6.644 33.8
Tub-169 29 171.09 30 170.37 PVC 315 3.5479 18.3979 36.58 0.02 1.34 8.437 33.9
Tub-170 28 171.63 29 171.09 PVC 315 3.4707 18.3207 45.72 0.012 1.116 5.639 33.8
Tub-171 31 169.38 BP-01 166.86 PVC 315 4.9362 28.4062 59.13 0.043 1.999 18.652 47.3
Tub-172 30 170.37 31 169.38 PVC 315 3.625 18.475 64.01 0.015 1.231 6.996 38.2
Tub-173 51 173.85 57 172.74 PVC 200 0.0771 1.5771 65.23 0.017 0.785 2.449 21.3
Tub-174 1 183.5 11 183.28 PVC 200 0.0771 2.4371 39.32 0.006 0.603 1.254 21.6
Tub-175 92 171.93 BE-29 171.48 PVC 200 0.0771 1.5771 24.69 0.018 0.804 2.582 17.4
Tub-176 105 169.41 104 168.74 PVC 200 0.0771 1.5771 49.68 0.013 0.722 2.046 21
Tub-177 142 169.72 153 168.95 PVC 200 0.0771 2.5771 45.11 0.017 0.907 3.063 22.3
Tub-178 114 178.25 121 177.44 PVC 200 0.0771 1.5771 45.72 0.018 0.66 2.847 17.4
Tub-179 112 178.72 119 177.99 PVC 200 0.0771 1.5771 46.02 0.016 0.634 2.615 17.4
Tub-180 152 167.12 BE-36 166.57 PVC 200 0.0771 1.5771 49.99 0.011 0.672 1.748 23.4
Tub-181 123 177.09 125 176.54 PVC 200 0.0771 2.0771 47.24 0.012 0.744 2.066 20
Tub-182 41 176.08 71 175.6 PVC 200 0.0771 1.5771 58.22 0.008 0.606 1.4 21.2
Tub-183 91 172.64 98 172.19 PVC 200 0.0771 1.5771 53.34 0.008 0.61 1.426 17.4
Tub-184 25 173.8 88 173.24 PVC 200 0.0771 1.5771 62.48 0.009 0.627 1.489 17.4
Tub-185 35 179.72 39 178.69 PVC 200 0.0771 1.5771 53.95 0.019 0.815 2.682 21
Tub-186 33 180.8 18 180 PVC 200 0.0771 1.5771 35.36 0.023 0.864 3.059 39
Tub-187 28 172.41 65 171.26 PVC 200 0.0771 1.5771 62.48 0.018 0.804 2.607 27.1
Tub-188 75 175.63 76 175.44 PVC 200 0.0771 1.5771 11.58 0.016 0.774 2.38 17.4
RESUMEN EJECUTIVO
Página | 56
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
04.00.00 FLETE
04.01.00 FLETE TERRESTRE 17,100.00
806,270.93
IGV. 18%
RESUMEN EJECUTIVO
Página | 57
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
11 ESTUDIO TOPOGRAFICO
11.1 INTRODUCCION
El presente informe forma parte de los Estudios Definitivos del Proyecto denominado
“CONSTRUCCION Y REHABILITACION DEL SISTEMA DE AGUA POTABLE Y
ALCANTARILLADO DEL SECTOR NOR ESTE PERIFERICO, CIUDAD DE HUARAL,
PROVINCIA DE HUARAL-REGION LIMA”.
Este Informe presenta información definitiva de los Servicios de Campo, gabinete y está
referido a los Servicios Topográficos, ejecutados en Huaral, como parte integrante de los
estudios definitivos del proyecto anteriormente citado.
Los trabajos que integran este Informe reflejan la obtención de la información de toda el área
urbana, y zonas colindantes por donde se trazaron las rutas de las obras líneas, necesaria para
las obras a proyectarse y es resultado de los trabajos desarrollados en forma sistemática tanto
en campo como en gabinete.
Es importante mencionar que los levantamientos topográficos se efectuaron basándose en una
poligonal de apoyo electrónica cerrada con medida directa utilizando la estación total y nivel de
ingeniero como equipo de precisión, cuyos puntos de vértices han sido ubicados y
monumentados teniendo como base los puntos de los vértices “V-A”, “V-B”, “V-C”, “V-D”,“V-E”,
“V-F”,“V-G”, “V-H”, “V-I”,“V-J”, establecidos con un GPS Navegador de +/- 2 m de precisión,
cuyos valores fueron dados con el elipsoide WGS84.
Toda la base topográfica ha sido “amarrada” al elipsoide WGS84.
Estos trabajos comprenden el levantamiento de las fajas de los colectores secundarios y sus
redes secundarias así como buzones y conexiones domiciliarias.
Levantamiento Planimétrico de Vías de Acceso
RESUMEN EJECUTIVO
Página | 58
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
En función a la importancia de los Estudios a ejecutarse como son los Diseños Definitivos para
la Instalación del sistema de Agua Potable y Alcantarillado, y para el cumplir con los
requerimientos establecidos en los Términos de Referencia, se han empleado equipos
electrónicos de alta precisión como son las Estaciones Totales, GPS Navegador y Nivel de
Ingeniero, en los que se ha almacenado información codificada que luego es convertida en
datos que se suministran a programas de cómputo para la elaboración de planos vectorizados
en formatos CAD (CIVIL 3D y LAND).
Se ha realizado el control geodésico estableciendo puntos base como vértices de la poligonal
cerrada.
Para el caso de la poligonal de control se realizó con los equipos de Estación Total, Nivel de
Ingeniero automático y un Tribach básicamente para poder obtener valores de posición y
niveles de error mínimos. Para ello, se tomaron lecturas de distancia repetida y en modo fino
del instrumento lo que significa que en un intervalo de tiempo de 2,5 segundos por visada,
utilizando de este tiempo el promedio de lecturas computarizadas, cada una de esas medidas
con rayos infrarrojos de onda corta, dan una cantidad considerable de precisión al desnivel
resultante, el cual se resulta principalmente de los puntos fijos de la posición del Tribach
utilizado. Además, se realizaron los ajustes por temperatura y presión en el momento de la
colección de datos.
La metodología resumida fue la siguiente:
Se ejecutó una poligonal con medida directa, utilizándose para ello Estación Total Topconde
aproximación 7” con colector interno de información, cada medida se realizo en modo fino, en
series de ocho visadas cada una, de las cuales el software de cálculo tomó el promedio final,
de esta manera se reduce al mínimo el error del operador.
RESUMEN EJECUTIVO
Página | 59
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Nivelación Geométrica
NivelaciónDiferencial
Descripción
Segundo Orden
Tolerancia 6 mm (N) ^ ½
N = Distancia en Km.
Apoyados en la poligonal de control, se procedió a realizar los levantamientos de obras
lineales, no lineales y áreas de calles.
Levantamientos Topográficos
Para los trabajos de levantamiento topográfico de las obras lineales, no lineales y calles se
siguió el siguiente procedimiento:
Apoyados en los vértices de las Poligonales de Control, se levantaron en campo todos los
detalles planimétricos compatibles con la escala de presentación de los servicios, tales como:
vivienda, veredas, canales, postes, etc. Para ello se hizo uso de una Estación Total y un nivel
automático; los cuales se apoyaron en una red de poligonal cerrada ajustada y calculada
previamente con un equipo de Estación Total.
Toda la información obtenida se ha procesado empleando programas, con un software de
cálculo en el caso de la Estación Total (indicado en el equipo de software utilizado)
Los puntos de coordenadas y con el empleo de los programas indicados, se procedieron a
modelar las superficies topográficas para finalmente obtener las curvas de nivel.
Estos trazos que generan los planos, han sido procesados en dibujos Vectorizados en Auto
CAD LAND y CIVL 3D. Los archivos están en unidades métricas. Los puntos son incluidos
RESUMEN EJECUTIVO
Página | 60
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
como bloques en la capa Puntos Topográficos y controlada en tres tipos de información básica
(número de punto, descripción y elevación).
El levantamiento Planimétrico se ejecutó con los siguientes límites de precisión.
Levantamiento Topográfico
Escala
Descripción
1:500 1:1000
Tipo de
Ítem Descripción Unidad Cantidad
Levantamiento
NIVELACION
Unidad
1 BM IGN Geométrica 1
2 Geométrica Unidad
BM AUXILIAR 09
3 Geométrica Unidad 10
VERTICES POLIGONAL
Geométrica
4 LONGITUD NIVELADA ml. 3843
RESUMEN EJECUTIVO
Página | 61
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Para el caso de la poligonal de control se realizó con los equipos de Estación Total, Nivel de
Ingeniero automático y un Tribach básicamente para poder obtener valores de posición y
niveles de error mínimos. Para ello, se tomaron lecturas de distancia repetida y en modo fino
del instrumento lo que significa que en un intervalo de tiempo de 2,5 segundos por visada,
utilizando de este tiempo el promedio de lecturas computarizadas, cada una de esas medidas
con rayos infrarrojos de onda corta, el cual se resulta principalmente de los puntos fijos de la
posición del Tribach utilizado. Además, se realizaron los ajustes por temperatura y presión en
el momento de la colección de datos.
Para la compensación del cálculo de coordenadas, se utilizaron formulas de cálculo conocidas
que ajusta las poligonales por el método de compensaciones lineales, el cual es un método
preciso de cierre lineal y angular. La posibilidad de utilizar equipos digitales en topografía evita
necesidad de hacer los cálculos manualmente.
Se ha establecido puntos geodésicos estratégicamente para fijar bases de posición para la
poligonal calculada, por el área y posición de la zona de estudio se colocado 3 puntos GPS
para establecer las base geodesias.
Hemos hecho las mediciones y cálculos de la poligonal cerrada para el cual se calculó el
azimut apoyados de los vértices “V-A” y “V-B”, cuya base se tomo con el GPS navegador con
lecturas durante 50 minutos en intervalos de 10 minutos por vertice, cuyo valor es de 134° 14’
40” estos vértices forman una base de apoyo a la poligonal cerrada lo cual nos dará una
posición con un error milimétrico de la posición de la poligonal de apoyo.
Los trabajos de campo de la poligonal se han iniciado desde el vértice “V-A” donde se
visualizaban los vértices B y Jde la poligonal, también se ubicó el Tribach en cada una de los
vértices uno a uno tomando lecturas reiterativas de ida y vuelta para controlar la posición de
cada vértice, este procedimiento se ha ejecutado hasta tener todas las medidas de los vértices.
RESUMEN EJECUTIVO
Página | 62
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
La Poligonal cuenta con diez vértices, con una longitud total de 2698 m y un área de 255391
m2.
Error de CierreAngular: Tolerancia Angular:
ERROR ANGULAR TOLERANCIA ANGULAR
-0.0027778 0.0061498
Por lo cual podemos concluir que el error angular está dentro de los límites permitidos.
RESUMEN EJECUTIVO
Página | 63
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
11.6 Nivelación
Requisitos del Equipo de Nivel
Para una correcta nivelación se debe contar con un nivel de ingeniero que debe estar dotado
de una serie de instrumentos geométricos, los cuales deben guardar ciertas condiciones para
su efectividad y su fácil corrección, con la finalidad principal de medir y/o visualizar
horizontalidades; por tanto consideraremos el eje óptico, el de figura y el eje vertical de
rotación, además, la línea de fe y el hilo horizontal del retículo; los cuales deberán presentar las
siguientes características en general:
El eje óptico debe ser paralelo al eje de figura.
El eje vertical de rotación del anteojo, debe ser perpendicular a la línea de fe.
La línea de fe de la ampolleta de nivel, debe ser paralela al eje óptico.
El hilo horizontal de la retícula debe ser perpendicular al eje vertical de rotación.
Errores de Nivelación
Los errores de nivelación pueden ser causados por diversos factores así como ambientales,
antrópicos, los cuales se han tenido en cuenta al momento de realizar la nivelación en la zona
de estudio, entre ellos tenemos:
Instrumento descorregido
Hundimiento del trípode o de los puntos
Puntos de cambio mal ubicados
Error al no tener centrada la burbuja en el momento de leer, cosa que ocurre
generalmente con instrumentos que tienen tornillo de trabajo.
Error por lectura en mira
Al golpear el trípode.
Por malas anotaciones en el registro
Por errores de calculo
Longitud de las visuales
Terreno
Medio ambiente.
Procedimientos realizados en la Nivelación
La nivelación de los BMS de apoyo así como los vértices de la poligonal fuerealizada en una
sola ruta, partiendo del BM oficial del IGN (CHA-A 6), para luego dirigirse hacia el V-A que se
encuentra en la Av. Victoria y seguir el recorrido hasta llegar al Bm-01, esta ruta de nivelación
se encuentra detallada de manera gráfica en plano Top 03 (Plano de BM y ruta de nivelación)
que se encuentra en los anexos.
RESUMEN EJECUTIVO
Página | 64
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
La red de nivelación dentro del área de estudio fue amarrada a un BM oficial del Instituto
Geográfico Nacional IGN, el BM (CHA-A 6) cuenta con una cota de 145.1042 m.s.n.m. dicho
BM se encuentra ubicado frente a la carretera Chancay-Alpamarca, entre los pueblos de
Chancay y Huaral, incrustada en la entrada de una casa, en el descanso de la escalera. Para
mejor ubicación ver el plano TOP-03(Plano de BM y ruta de nivelación).
El error de cierre de la nivelación de los BMS y los vértices de la poligonal para una distancia
recorrida de 6.38 km es de 1.00 mm lo cual es aceptable para una nivelación de Primer Orden
Clase I, la cual tiene como error máximo tolerable para dicha distancia de nivelación 8mm. Por
lo tanto el error de la nivelación esta dentro de lo permitido lo cual permitirá realizar su
respectiva compensación. Los cálculos de la nivelación han sido calculados en Excel y se
presentaran en la parte de anexos.
RESUMEN DE NIVELACION
BM DE APOYO HUARAL-NOR
ESTE
PUNTO COTA
IGN 145.104
BM-01 171.634
BM-02 175.303
BM-03 181.100
BM-04 178.934
BM-05 185.475
BM-06 175.738
BM-07 176.188
BM-08 176.364
BM-09 169.880
PUNTO COTA
V-A 170.466
V-B 172.257
V-C 173.712
V-D 177.528
V-E 175.664
V-F 179.887
V-G 179.779
V-H 173.576
V-I 170.942
V-J 168.575
RESUMEN EJECUTIVO
Página | 65
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
Rutas de Nivelación
RESUMEN EJECUTIVO
Página | 66
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
12 METRADO BASE
12.1 METRADO BASE DE AGUA POTABLE
RESUMEN EJECUTIVO
Página | 67
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 68
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 69
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 70
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
RESUMEN EJECUTIVO
Página | 71
INSTALACION Y REHABILITACION DEL SISTEMA DE
MUNICIPALIDAD AGUA POTABLE Y ALCANTARILLADO DEL SECTOR
PROVINCIAL DE NOR ESTE PERIFERICO, DE LA CIUDAD DE HUARAL
HUARAL PROVINCIA DE HUARAL
13 ESTUDIO DE SUELOS
13.1 DESCRIPCION Y OBJETIVO
Concluido con los trabajos de campo, correspondiente a todos los sectores del área del
proyecto de acuerdo a los términos de referencia y las consideraciones propuestas tanto por
los proyectistas como por la supervisión, se han desarrollado las actividades referente al
estudio de mecánica de suelos para el desarrollo del proyecto “Construcción y
Rehabilitación del Sistema de Agua Potable y Alcantarillado del Sector Nor Este
Periférico de la Ciudad de Huaral Provincia de Huaral”.
Los afloramientos rocosos solo se da en Cerro san Cristóbal conformados por rocas
graníticas a granodioriticas.
Las tuberías a instalarse tanto para agua potable como para alcantarillado, serán de PVC, y
las únicas estructuras de concreto serán los buzones, así mismo la clasificación del suelo,
servirá para la cuantificación de las condiciones de excavación para las obras lineales.
El marco geológico generalizado del área de estudio, está conformado por depósitos
cuaternarios de origen eluvio coluvial, conformado por gravas arenosas de variada
graduación.
Fm. Huarochiri
Gpo. Rimac
RELACION DE CALICATAS
C-2 ESQUINA PSJE. SAN JUAN- CALLE PARQUE LOS SUEÑOS 1,40
En todas las calicatas se han tomado las muestras correspondientes, con la finalidad
de evaluar macroscópicamente en campo y para la ejecución de los ensayos
granulométricos y análisis químico de suelos, para la evaluación de la agresividad al
concreto.
CUADRO N02
CUADRO N03
CUADRO N04
CUADRO N05
La evaluación de la agresividad del suelo, se ha determinado, con los resultados de los análisis
químicos de suelos, para el caso de las estructuras de concreto.
Agresividad al Concreto
La agresividad del suelo al concreto, es función directa del contenido de sulfatos. Para la
determinación del grado de agresividad del suelo al concreto, se establecerá la comparación
con los valores permisibles establecidos por las normas internacionales, para lo cual se adjunta
el cuadro de valores estándares que se utiliza en el desarrollo de los proyectos con estructuras
de concreto.
Presencia en el Grado de
ppm Observaciones
suelo agresividad
0-1000 Leve
1000-2000 Moderado Ataque directo al concreto de
Sulfatos
2000-20000 Severo las estructuras
Los análisis y ensayos se han realizado en los lugares que a continuación se mencionan:
14 PANEL FOTOGRAFICO
Foto N0 01: Ubicando punto de control, calle San Martin para el levantamiento respectivo del
área de estudio.
Foto N0 02: Haciendo un chequeo de las coordenadas para el punto de cambio en la Calle Los
Geranios .Tomando con coordenadas con el GPS.
Foto N0 03:La imagen muestra alumbrados públicos en la parte del cerro San Cristóbal
Foto N0 06: Vista panorámica de la Calle Nueva Esperanza, se observa que en esta calle esta
asfaltada, cuenta con veredas y jardines. Asimismo, las casas que en su mayoría son de
material noble cuentan con los servicios básicos como son agua potable y alcantarillado
Foto N0 07: la imagen muestra viviendas de material noble en el Pasaje Las Mercedes, en este
pasaje las viviendas cuentan con el servicio agua potable, alcantarillado, luz y alumbrado
público.
Foto N0 09:Vista panorámica de la parte Nor Este de Huaral visto desde el cerro San Cristóbal
Foto N0 10:Vista panorámica de la calle Benjamín Doing Lossio desde las proximidades a la
falda del cerro San Cristóbal
Foto N0 12: Ubicación del canal de riego en la Calle N0 1, como se puede visualizar en la
imagen hay domicilios que votan sus aguas residuales a este canal aprovechando la cercanía
de este.
Foto N0 15: Calle San Martin; se observa un buzón, que pertenece a la red existente de
alcantarillado, en buen estado.
Foto N0 16: Calle Micaela Bastidas, se encuentran terrenos abandonados y eriazos con gran
cantidad de desmonte lo cual genera mal aspecto, el servicio de electricidad se brinda a través
de postes mal diseñados y mal instalados.
Foto N0 17: Vista panorámica del área de estudio visto desde el cerro San Cristóbal
Foto N0 18: Visualización de los terrenos o lotes abandonados, ubicados dentro del en el área
donde se realizara el proyecto.
Foto N0 19: Limite del proyecto, lugar donde se culmina el límite de la ejecución de la obra,
representado por una carretera aplanada sin asfaltada.
Foto N0 20:Calle Hipólito Unánue, algunas de las viviendas están en proceso de construcción
es por ello que se observa ladrillos y agregados fuera de algunas de las viviendas, esta zona no
cuenta con alumbrado publico
Foto N0 21: Pasaje Túpac Amaru, se observa tuberías colocadas inadecuadamente, cuenta
con caja de conexión domiciliaria.
Foto N0 22: Pasaje s/n ubicado en las faldas del cerro San Cristóbal, se encuentran buzones
en el medio de la vía de acceso lo cual permite el transporte de las aguas residuales por medio
de las tuberías subterráneas instaladas, éste pasaje cuenta con alumbrado público.
Foto N0 23: Pasaje M. Arévalo es un pasaje angosto, cuenta con alumbrado público, algunas
viviendas cuentan con vereda y el material predominante de las viviendas es noble.
Foto N0 24:Av. Los Naturales, bueno vista panorámica debido a que se observa la presencia
de jardines y veredas, así como alumbrado público y servicio de electricidad.
Foto N0 26:Pasaje Las Rosas se encuentran pocas viviendas de material noble, cuentan con
alumbrado publico
Foto N0 27: Pasaje Gamarra, mostrando viviendas de material noble algunas se encuentran
abandonadas, el tipo desuelo que presenta este pasaje es compactado sin asfaltado.
Foto N0 28: Calle S/n 1, se visualiza viviendas de diferentes tipos de materiales ya sean estos
de material noble o quincha, esta calle no cuenta con alumbrado público, se observa el
desmonte y basura lo cual genera mala imagen a la calle.
Foto N0 29: Se visualiza el cruce de la Calle Circunvalación Norte con la Av. Los Naturales, los
tipos de vivienda son de material noble, la calle es totalmente asfaltada, la movilización se
realiza a través de vehículos livianos como son los mototaxis.