Metrado y Presupuesto Losa
Metrado y Presupuesto Losa
Metrado y Presupuesto Losa
03.02.02 RELLENO Y COMPACTACION CON MATERIAL PROPIO, CON EQUIPO m2 1.00 1.00 20.00 36.00 0.10 72.00 72.00
03.02.03 ELIMINACION DE MATERIAL EXCEDENTE m2 1.00 1.40 20.00 36.00 0.20 201.60 201.60
05.00 PINTURA
05.01 PINTURA EN MARCAS PARA LAS TRES DISCIPLINAS ml 492.11
FULBITO
ml 1.00 1.00 108.00 108.00
ml 1.00 3.00 19.00 57.00
ml 1.00 2.00 1.60 3.20
ml 1.00 1.00 11.31 11.31
VOLEY
ml 1.00 1.00 54.00 54.00
ml 1.00 2.00 9.00 18.00
BASQUET
ml 1.00 1.00 86.00 86.00
ml 1.00 1.00 102.00 102.00
ml 1.00 2.00 16.85 33.70
ml 1.00 1.00 18.90 18.90 492.11
06.00 CARPINTERIA METALICA
ARCOS(INC. MALLA), TABLERO DE BASQUET(INC. MALLA), PARANTES DE
06.01 GLOB 1.00 1.00 1.00
VOLEY(INC. MALLA)
08.00 TRIBUNAS
08.01 MOVIMIENTO DE TIERRAS
08.01.01 EXCAVACION ZAPATAS DE COLUMNAS Y VIGAS m3 107.35
EXCAVACION ZAPATAS
EJE A-A m3 1.00 10.00 Area= 2.2500 m2 2.30 51.75
EJE B-B m3 1.00 10.00 Area= 2.2500 m2 1.60 36.00
EXCAVACION VIGAS
EJE 1-1 AL EJE 10-10 m3 1.00 10.00 0.80 4.90 0.50 19.60 107.35
08.03.02 COLUMNAS
08.03.02.01 ENCOFRADO m2 39.75
EJE A-A m2 1.00 10.00 Perim.= 1.5000m 1.65 24.75
EJE B-B m2 1.00 10.00 Perim.= 1.5000m 1.00 15.00 39.75
08.03.02.02 CONCRETO m3 3.31
EJE A-A m3 1.00 10.00 Area= 0.1250 m2 1.65 2.06
EJE B-B m3 1.00 10.00 Area= 0.1250 m2 1.00 1.25 3.31
08.03.02.03 ACERO fy=4200 kg/cm2 kg 1.00 VER PLANILLA DE METRADOS 626.35
08.03.03 VIGAS
08.03.03.01 ENCOFRADO m2 71.05
EJE 1-1 AL EJE 10-10 m2 1.00 10.00 1.45 4.90 71.05 71.05
08.03.03.02 CONCRETO m3 5.39
EJE 1-1 AL EJE 10-10 m2 1.00 10.00 0.25 4.90 0.40 4.90
ESQUINAS TRIANGULARES DEBAJO LOSA TRIBUNA m2 1.00 10.00 Area= 0.1969 m2 0.25 0.49 5.39
08.03.03.03 ACERO fy=4200 kg/cm2 kg 1.00 VER PLANILLA DE METRADOS 711.48
09.00 VARIOS
09.01 FLETE kg 1.00
TRANSPORTE LOCAL DESDE PROVEEDOR HASTA OBRA kg 1.00 1.00 1.00 1.00
10.00 OBRAS VARIAS
10.01 LIMPIEZA DE OBRA m2 1.00 1.00 35.00 42.00 1,470.00 1,470.00
10.02 ELIMINACION DE MATERIAL EXCEDENTE FORMA MANUAL m3 231.70
m3 1.00 1.00 16.55 50.00 0.20 231.70 231.70
Item Descripción Und. Metrado Precio S/. Parcial S/. Sub-Total S/. Total S/.
09 VARIOS 3,457.30
09.01 FLETE 3,457.30
09.01.01 FLETE TERRESTRE kg 34,573.02 0.10 3,457.30