Metrados Ejecutados y Programados

Descargar como xls, pdf o txt
Descargar como xls, pdf o txt
Está en la página 1de 20

RESUMEN DE METRADOS

Obra : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO, DISTRITO DE
ANCN - LIMA LIMA"
Cliente : MUNICIPALIDAD DISTRITAL DE ANCON
Lugar : LIMA - LIMA - ANCON
Fecha : FEBRERO-2017

METRADO
METRADO
Item DESCRIPCION Und. PROGRAMADO % DE AVANCE
EJECUTADOS
S
01 OBRAS PROVISIONALES
01.01 ALMACEN, OFICINA Y CASETA DE GUARDIANIA mes 4.00 4.00 100.00%
01.02 CARTEL DE OBRA IMPRESION BANNER DE 8.50Mx3.60M und 1.00 1.00 100.00%
02 PISTAS
02.01 TRABAJOS PRELIMINARES
02.01.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR EN PISTAS m2 8,413.06 8,413.06 100.00%
02.01.02 DEMOLICION DE CARPETA ASFALTICA DETERIORADA C/EQUIPO m2 1,992.63 1,992.63 100.00%
02.01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y MAQUINARIA glb 1.00 1.00 100.00%
02.02 MOVIMIENTO DE TIERRAS
02.02.01 CORTE A NIVEL DE SUBRASANTE EN TERRENO SUELTO m3 4,991.79 4,991.79 100.00%
02.02.02 PERFILADO Y COMPACTACION DE LA SUBRASANTE m2 8,413.06 8,413.06 100.00%
02.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINA m3 8,830.16 8,830.16 100.00%
02.03 PAVIMENTO FLEXIBLE
02.03.01 SUB BASE GRANULAR E=0.20 m m2 8,413.06 8,413.06 100.00%
02.03.02 BASE GRANULAR E=0.15 m m2 8,413.06 8,413.06 100.00%
02.03.03 IMPRIMACION ASFALTICA m2 8,413.06 8,413.06 100.00%
02.03.04 CARPETA ASFALTICA EN CALIENTE DE 2" m2 8,413.06 8,413.06 100.00%
02.04 VARIOS
02.04.01 REDUCTORES DE VELOCIDAD (GIVAS ASFALTICAS) L=6M und 8.00 8.00 100.00%
03 VEREDAS
03.01 TRABAJOS PRELIMINARES
03.01.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR EN VEREDAS m2 6,986.63 6,986.63 100.00%
03.01.02 DEMOLICION DE VEREDA DE CONCRETO EXISTENTE E=0.10M m2 3,739.07 3,739.07 100.00%
03.01.03 ELIMINACION DE MATERIAL PROCEDENTE DE DEMOLICIONES DE VEREDAS m3 523.47 523.47 100.00%
03.02 MOVIMIENTO DE TIERRAS
03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL P/ VEREDAS m3 1,397.33 1,397.33 100.00%
03.02.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINA m3 1,746.66 1,746.66 100.00%
03.02.03 CONFORMACION Y COMPACTACION DE SUBRASANTE P/VEREDAS m2 6,986.63 6,986.63 100.00%
03.03 VEREDAS DE CONCRETO
03.03.01 BASE GRANULAR E=0.10 m m2 6,986.63 6,986.63 100.00%
03.03.02 ENCOFRADO EN VEREDAS h=0.30 m. m2 1,190.24 1,190.24 100.00%
03.03.03 VEREDAS - CONCRETO f'c=175 kg/cm2 , E=0.10m INCLUYE ACABADO, BRUADO Y CURADO m2 6,881.03 6,881.03 100.00%
03.03.04 RAMPA DE ACCESO P/PERSONAS CON DISCAPACIDAD - CONCRETO F'C= 175 KG/CM2 m2 105.60 105.60 100.00%
03.03.05 JUNTA CON ASFALTO E=1" PARA VEREDAS m 1,590.00 1,590.00 100.00%
04 SARDINELES
04.01 TRABAJOS PRELIMINARES
04.01.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR EN SARDINELES m2 517.24 517.24 100.00%
04.02 MOVIMIENTO DE TIERRAS
04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL P/ SARDINELES m3 181.03 181.03 100.00%
04.02.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINA m3 226.29 226.29 100.00%
04.03 SARDINELES DE CONCRETO
04.03.01 ENCOFRADO DE SARDINEL SUMERGIDO (a=0.15m - h=0.35m) m2 1,379.33 1,379.33 100.00%
04.03.02 SARDINELES DE CONCRETO f'c=175 kg/cm2 m3 181.03 181.03 100.00%
04.03.03 CURADO DEL CONCRETO EN SARDINEL SUMERGIDO m2 1,724.18 1,724.18 100.00%
04.03.04 JUNTAS ASFALTICAS EN SARDINELES SUMERGIDOS E=1" m 309.75 309.75 100.00%
05 AREAS VERDES
05.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR EN AREAS VERDES m2 7,857.00 7,857.00 100.00%
05.02 SEMBRADO DE GRASS m2 7,857.00 7,857.00 100.00%
05.03 SEMBRADO DE PLANTONES und 569.00 569.00 100.00%
06 SEALIZACION
06.01 PINTURA LINEAL CONTINUA m 2,817.22 2,817.22 100.00%
06.02 PINTURA LINEAL DISCONTINUA m 486.00 486.00 100.00%
06.03 PINTURA SOBRE PAVIMENTO (Simbolos y Flechas) m2 360.40 360.40 100.00%
07 VARIOS
07.01 NIVELACION DE TAPA DE BUZONES und 16.00 16.00 100.00%
07.02 REPOSICION DE CAJA DOMICILIARIA DE AGUA und 291.00 291.00 100.00%
07.03 REPOSICION DE CAJA DOMICILIARIA DE DESAGUE und 291.00 291.00 100.00%
07.04 MITIGACION DE IMPACTO AMBIENTAL glb 1.00 1.00 100.00%
07.05 LIMPIEZA FINAL DE OBRA m2 23,256.69 23,256.69 100.00%
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

01 OBRAS PROVISIONALES
01.01 ALMACEN, OFICINA Y CASETA DE GUARDIANIA mes 4.00

Oficinas y almacenes para obra 4.00 --- --- --- --- --- 4.00

01.02 CARTEL DE OBRA IMPRESION BANNER DE 8.50Mx3.60M und 1.00 --- --- --- --- --- 1.00 1.00

02 PISTAS
02.01 TRABAJOS PRELIMINARES
02.01.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR EN PISTAS m2 8,413.06

VIAS
CALLE 1 (Frente Mz F) 1.00 152.25 6.00 --- --- --- 913.50
CALLE 1 (Frente Mz E) 1.00 207.17 6.00 --- --- --- 1,243.02
CALLE A (dos carriles) 2.00 148.32 6.00 --- --- --- 1,779.84
CALLE E 1.00 30.52 6.00 --- --- --- 183.12
CALLE A (Frente Mz G) 1.00 207.35 6.00 --- --- --- 1,244.10
CALLE A (Frente Mz C) 1.00 92.25 6.00 --- --- --- 553.50
CALLE A (Frente Mz B) 1.00 183.10 6.00 --- --- --- 1,098.60
CALLE C 1.00 48.25 5.60 --- --- --- 270.20
CALLE B 1.00 48.25 5.60 --- --- --- 270.20
CALLE 13 1.00 103.13 6.00 --- --- --- 618.78
CALLE ANCASH 1.00 39.70 6.00 --- --- --- 238.20

02.01.02 DEMOLICION DE CARPETA ASFALTICA DETERIORADA C/EQUIPO m2 1,992.63

VIAS
CALLE A (Carril Derecha) 1.00 148.32 6.30 --- --- --- 934.42
CALLE A (Carril Izquierda) 1.00 148.32 5.90 --- --- --- 875.09
CALLE E 1.00 30.52 6.00 --- --- --- 183.12

02.01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y MAQUINARIA glb 1.00 --- --- --- --- --- 1.00 1.00

02.02 MOVIMIENTO DE TIERRAS


02.02.01 CORTE A NIVEL DE SUBRASANTE EN TERRENO SUELTO m3 4,991.79

VIAS
CALLE 1 (Desde Calle Ancash - Calle E) 1.00 ver hoja de movimiento de tierra 770.14 770.14
CALLE 1 (Desde Calle E - Calle 15) 1.00 ver hoja de movimiento de tierra 991.91 991.91
CALLE A (Carril Derecho) 1.00 ver hoja de movimiento de tierra 383.15 383.15
CALLE A (Carril Izquierdo) 1.00 ver hoja de movimiento de tierra 339.13 339.13
CALLE E 1.00 ver hoja de movimiento de tierra 27.19 27.19
CALLE A (Desde Calle E - Calle 15) 1.00 ver hoja de movimiento de tierra 833.44 833.44
CALLE A (Desde Calle 15 - Calle 13) 1.00 ver hoja de movimiento de tierra 323.04 323.04
CALLE A (Desde Calle 11 - Calle 10) 1.00 ver hoja de movimiento de tierra 658.57 658.57
CALLE 13 1.00 ver hoja de movimiento de tierra 354.79 354.79
CALLE B 1.00 ver hoja de movimiento de tierra 110.41 110.41
CALLE C 1.00 ver hoja de movimiento de tierra 103.95 103.95
CALLE ANCASH 1.00 ver hoja de movimiento de tierra 96.07 96.07

02.02.02 PERFILADO Y COMPACTACION DE LA SUBRASANTE m2 8,413.06

VIAS
CALLE 1 (Frente Mz F) 1.00 152.25 6.00 --- --- --- 913.50
CALLE 1 (Frente Mz E) 1.00 207.17 6.00 --- --- --- 1,243.02
CALLE A (desde calle ancash - calle e) 2.00 148.32 6.00 --- --- --- 1,779.84
CALLE E 1.00 30.52 6.00 --- --- --- 183.12
CALLE A (Frente Mz G) 1.00 207.35 6.00 --- --- --- 1,244.10
CALLE A (Frente Mz C) 1.00 92.25 6.00 --- --- --- 553.50
CALLE A (Frente Mz B) 1.00 183.10 6.00 --- --- --- 1,098.60
CALLE C 1.00 48.25 5.60 --- --- --- 270.20
CALLE B 1.00 48.25 5.60 --- --- --- 270.20
CALLE 13 1.00 103.13 6.00 --- --- --- 618.78
CALLE ANCASH 1.00 39.70 6.00 --- --- --- 238.20

02.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINA m3 8,830.16


F.E.

Proviene de corte en pista en terreno normal 1.00 1.25 --- --- --- 4,991.79 6,239.74
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

Proviene de demolicion de carpeta asfaltica 2" 1.00 1.30 --- --- --- 1,992.63 2,590.42

02.03 PAVIMENTO FLEXIBLE


02.03.01 SUB BASE GRANULAR E=0.20 m m2 8,413.06

Igual que el rea de conformacin y compactacin de subrasante 1.00 --- --- --- 8,413.06 --- 8,413.06

02.03.02 BASE GRANULAR E=0.15 m m2 8,413.06

Igual que el rea de conformacin y compactacin de subrasante 1.00 --- --- --- 8,413.06 --- 8,413.06

02.03.03 IMPRIMACION ASFALTICA m2 8,413.06

Igual que el rea de conformacin y compactacin de subrasante 1.00 --- --- --- 8,413.06 --- 8,413.06

02.03.04 CARPETA ASFALTICA EN CALIENTE DE 2" m2 8,413.06

Igual que el rea de conformacin y compactacin de subrasante 1.00 --- --- --- 8,413.06 --- 8,413.06

02.04 VARIOS
02.04.01 REDUCTORES DE VELOCIDAD (GIVAS ASFALTICAS) L=6M und 8.00

Calle 1 2.00 --- --- --- --- --- 2.00

Calle A (Desde calle Ancash hasta Calle E) 2.00 --- --- --- --- --- 2.00
Calle A (Desde calle E hasta Calle 10) 4.00 --- --- --- --- --- 4.00

03 VEREDAS
03.01 TRABAJOS PRELIMINARES
03.01.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR EN VEREDAS m2 6,986.63

MZ F
Frente Calle Ancash 1.00 20.00 2.00 --- --- --- 40.00
Frente Calle 1 1.00 142.70 2.00 --- --- --- 285.40

MZ J
Frente Calle Ancash 1.00 38.60 2.00 --- --- --- 77.20
Frente Calle 1 1.00 141.15 2.00 --- --- --- 282.30
Frente Calle A 1.00 141.20 2.00 --- --- --- 282.40
Frente Calle E 1.00 38.68 1.20 --- --- --- 46.42

MZ E
Frente Calle 1 1.00 197.28 2.00 --- --- --- 394.56

MZ G
Frente Calle 1 1.00 197.15 2.00 --- --- --- 394.30
Frente Calle E 1.00 38.87 1.20 --- --- --- 46.64
Frente Calle "A" 1.00 197.30 2.00 --- --- --- 394.60
Frente Calle 15 1.00 38.88 1.50 --- --- --- 58.32

MZ I
Frente Calle E 1.00 38.30 1.20 --- --- --- 45.96
Frente Calle "A" 1.00 52.60 2.00 --- --- --- 105.20
Frente Calle C 1.00 38.33 1.20 --- --- --- 46.00
Frente Calle 5 1.00 52.77 1.50 --- --- --- 79.16

PARQUE 2
Frente Calle C 1.00 38.33 2.00 --- --- --- 76.66
Frente Calle "A" 1.00 53.33 2.00 --- --- --- 106.66
Frente Calle B 1.00 38.35 2.00 --- --- --- 76.70
Frente Calle 5 1.00 53.20 1.50 --- --- --- 79.80

MZ H
Frente Calle B 1.00 38.35 1.20 --- --- --- 46.02
Frente Calle A 1.00 60.38 2.00 --- --- --- 120.76
Frente Calle 15 1.00 38.20 1.50 --- --- --- 57.30
Frente Calle 5 1.00 60.30 1.50 --- --- --- 90.45
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

MZ C
Frente Calle 15 1.00 38.85 1.50 --- --- --- 58.28
Frente Calle 1 1.00 82.25 2.00 --- --- --- 164.50
Frente Calle A 1.00 82.25 2.00 --- --- --- 164.50
Frente Calle 13 1.00 38.83 1.50 --- --- --- 58.25

MZ D
Frente Calle 15 1.00 38.20 1.50 --- --- --- 57.30
Frente Calle A 1.00 82.25 2.00 --- --- --- 164.50
Frente Calle 13 1.00 38.18 1.50 --- --- --- 57.27
Frente Calle 5 1.00 82.25 1.50 --- --- --- 123.38

MZ B1
Frente Calle 13 1.00 93.03 1.50 --- --- --- 139.55
Frente Calle 1 1.00 88.96 2.00 --- --- --- 177.92
Frente Calle 11 1.00 93.20 1.50 --- --- --- 139.80
Frente Calle 5 1.00 89.00 1.50 --- --- --- 133.50

MZ B
Frente Calle 11 1.00 38.85 1.50 --- --- --- 58.28
Frente Calle 1 1.00 173.17 2.00 --- --- --- 346.34
Frente Calle A 1.00 173.08 2.00 --- --- --- 346.16
Frente Calle 10 1.00 38.82 1.50 --- --- --- 58.23

MZ A
Frente Calle A 1.00 173.08 2.00 --- --- --- 346.16
Frente Calle 11 1.00 38.20 1.50 --- --- --- 57.30
Frente Calle 5 1.00 173.13 1.50 --- --- --- 259.70
Frente Calle 10 1.00 38.33 1.50 --- --- --- 57.50

MARTILLOS 44.00 --- --- --- 17.85 --- 785.40

03.01.02 DEMOLICION DE VEREDA DE CONCRETO EXISTENTE E=0.10M m2 3,739.07

CALLE 1
MZ F 1.00 144.00 1.20 --- --- --- 172.80
MZ E 1.00 192.00 1.20 --- --- --- 230.40
MZ J 1.00 145.00 1.20 --- --- --- 174.00
MZ G 1.00 202.20 1.20 --- --- --- 242.64
MZ C 1.00 85.84 1.80 --- --- --- 154.51
MZ B1 1.00 50.00 1.35 --- --- --- 67.50
MZ B 1.00 177.60 1.50 --- --- --- 266.40

CALLE A
MZ J 1.00 145.00 1.20 --- --- --- 174.00

CALLE A
MZ I 1.00 16.90 1.20 --- --- --- 20.28
1.00 10.45 1.20 --- --- --- 12.54
MZ G 1.00 11.00 1.50 --- --- --- 16.50
1.00 8.30 1.50 --- --- --- 12.45
1.00 16.20 1.50 --- --- --- 24.30
1.00 8.00 3.30 --- --- --- 26.40
1.00 80.40 1.20 --- --- --- 96.48
1.00 23.80 1.50 --- --- --- 35.70
1.00 4.60 1.50 --- --- --- 6.90
MZ H 1.00 7.70 1.20 --- --- --- 9.24
1.00 8.20 1.20 --- --- --- 9.84
MZ C 1.00 19.14 1.50 5.00 --- --- 143.55
1.00 4.00 1.20 --- --- --- 4.80
1.00 8.00 1.20 --- --- --- 9.60
MZ D 1.00 29.30 1.20 --- --- --- 35.16
1.00 13.70 2.90 --- --- --- 39.73
1.00 32.00 1.50 --- --- --- 48.00
MZ B 1.00 9.50 1.20 --- --- --- 11.40
1.00 32.00 1.20 --- --- --- 38.40
1.00 8.00 1.20 --- --- --- 9.60
1.00 17.00 1.20 --- --- --- 20.40
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

1.00 24.20 1.20 --- --- --- 29.04


1.00 8.00 1.90 --- --- --- 15.20
MZ A 1.00 51.70 1.20 --- --- --- 62.04
1.00 4.30 3.30 --- --- --- 14.19
1.00 33.00 1.20 --- --- --- 39.60
1.00 8.00 3.20 --- --- --- 25.60
1.00 15.60 1.20 --- --- --- 18.72
1.00 7.70 1.20 --- --- --- 9.24
1.00 8.00 1.85 --- --- --- 14.80

CALLE 5
MZ I 1.00 59.60 1.55 --- --- --- 92.38
PARQUE 2 1.00 56.00 1.50 --- --- --- 84.00
MZ H 1.00 16.95 1.70 --- --- --- 28.82
1.00 15.55 1.70 --- --- --- 26.44
1.00 8.15 1.70 --- --- --- 13.86

CALLE 5
MZ D 1.00 19.00 1.75 --- --- --- 33.25
1.00 8.00 1.50 --- --- --- 12.00
1.00 8.00 1.50 --- --- --- 12.00
1.00 7.70 1.20 --- --- --- 9.24
1.00 24.10 1.65 --- --- --- 39.77
CALLE 5
PARQUE 1 1.00 87.85 2.00 --- --- --- 175.70
MZ A 1.00 8.00 1.10 --- --- --- 8.80
1.00 8.00 1.50 --- --- --- 12.00
1.00 8.00 1.10 --- --- --- 8.80
1.00 48.00 1.95 --- --- --- 93.60
1.00 24.00 1.20 --- --- --- 28.80
CALLE E
MZ J 1.00 42.40 1.00 --- --- --- 42.40
MZ G 1.00 42.70 1.00 --- --- --- 42.70
MZ I 1.00 42.70 1.00 --- --- --- 42.70

CALLE C
MZ I 1.00 42.75 2.45 --- --- --- 104.74

CALLE B
MZ H 1.00 3.75 3.55 --- --- --- 13.31
1.00 11.15 1.00 --- --- --- 11.15
1.00 7.20 0.65 --- --- --- 4.68
CALLE 15
MZ G 1.00 41.20 1.20 --- --- --- 49.44
MZ C 1.00 41.78 1.20 --- --- --- 50.14
MZ D 1.00 42.95 1.00 --- --- --- 42.95

CALLE 13
MZ D 1.00 40.00 2.45 --- --- --- 98.00
PARQUE 1 1.00 33.85 2.00 --- --- --- 67.70

CALLE 11
MZ B 1.00 10.50 1.50 --- --- --- 15.75

CALLE 10
MZ B 1.00 40.00 1.60 --- --- --- 64.00
MZ A 1.00 40.00 1.70 --- --- --- 68.00

ELIMINACION DE MATERIAL PROCEDENTE DE DEMOLICIONES DE


03.01.03
VEREDAS
m3 523.47

Factor
proviene de demolicion de veredas 1.00 --- 1.40 0.10 3,739.07 --- 523.47

03.02 MOVIMIENTO DE TIERRAS


03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL P/ VEREDAS m3 1,397.33

Proviene del rea de trazo, nivelacion de veredas 1.00 --- --- 0.20 6,986.63 --- 1,397.33
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

03.02.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINA m3 1,746.66


Factor
proviene de excavacion de veredas 1.00 --- 1.25 --- --- 1,397.33 1,746.66

03.02.03 CONFORMACION Y COMPACTACION DE SUBRASANTE P/VEREDAS m2 6,986.63

Proviene del area de trazo, nivelacion de veredas 1.00 --- --- --- 6,986.63 --- 6,986.63

03.03 VEREDAS DE CONCRETO


03.03.01 BASE GRANULAR E=0.10 m m2 6,986.63

Proviene del area de trazo, nivelacion de veredas 1.00 --- --- --- 6,986.63 --- 6,986.63

03.03.02 ENCOFRADO EN VEREDAS h=0.30 m. m2 1,190.24

MZ F
Frente Calle Ancash 1.00 20.00 --- 0.30 --- --- 6.00
Frente Calle 1 1.00 142.70 --- 0.30 --- --- 42.81

MZ J
Frente Calle Ancash 1.00 38.60 --- 0.30 --- --- 11.58
Frente Calle 1 1.00 141.15 --- 0.30 --- --- 42.35
Frente Calle A 1.00 141.20 --- 0.30 --- --- 42.36
Frente Calle E 1.00 38.68 --- 0.30 --- --- 11.60

MZ E
Frente Calle 1 1.00 197.28 --- 0.30 --- --- 59.18

MZ G
Frente Calle 1 1.00 197.15 --- 0.30 --- --- 59.15
Frente Calle E 1.00 38.87 --- 0.30 --- --- 11.66
Frente Calle "A" 1.00 197.30 --- 0.30 --- --- 59.19
Frente Calle 15 1.00 38.88 --- 0.30 --- --- 11.66

MZ I
Frente Calle E 1.00 38.30 --- 0.30 --- --- 11.49
Frente Calle "A" 1.00 52.60 --- 0.30 --- --- 15.78
Frente Calle C 1.00 38.33 --- 0.30 --- --- 11.50
Frente Calle 5 1.00 52.77 --- 0.30 --- --- 15.83

PARQUE 2
Frente Calle C 1.00 38.33 --- 0.30 --- --- 11.50
Frente Calle "A" 1.00 53.33 --- 0.30 --- --- 16.00
Frente Calle B 1.00 38.35 --- 0.30 --- --- 11.51
Frente Calle 5 1.00 53.20 --- 0.30 --- --- 15.96

MZ H
Frente Calle B 1.00 38.35 --- 0.30 --- --- 11.51
Frente Calle A 1.00 60.38 --- 0.30 --- --- 18.11
Frente Calle 15 1.00 38.20 --- 0.30 --- --- 11.46
Frente Calle 5 1.00 60.30 --- 0.30 --- --- 18.09

MZ C
Frente Calle 15 1.00 38.85 --- 0.30 --- --- 11.66
Frente Calle 1 1.00 82.25 --- 0.30 --- --- 24.68
Frente Calle A 1.00 82.25 --- 0.30 --- --- 24.68
Frente Calle 13 1.00 38.83 --- 0.30 --- --- 11.65

MZ D
Frente Calle 15 1.00 38.20 --- 0.30 --- --- 11.46
Frente Calle A 1.00 82.25 --- 0.30 --- --- 24.68
Frente Calle 13 1.00 38.18 --- 0.30 --- --- 11.45
Frente Calle 5 1.00 82.25 --- 0.30 --- --- 24.68

MZ B1
Frente Calle 13 1.00 93.03 --- 0.30 --- --- 27.91
Frente Calle 1 1.00 88.96 --- 0.30 --- --- 26.69
Frente Calle 11 1.00 93.20 --- 0.30 --- --- 27.96
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

Frente Calle 5 1.00 89.00 --- 0.30 --- --- 26.70

MZ B
Frente Calle 11 1.00 38.85 --- 0.30 --- --- 11.66
Frente Calle 1 1.00 173.17 --- 0.30 --- --- 51.95
Frente Calle A 1.00 173.08 --- 0.30 --- --- 51.92
Frente Calle 10 1.00 38.82 --- 0.30 --- --- 11.65

MZ A
Frente Calle A 1.00 173.08 --- 0.30 --- --- 51.92
Frente Calle 11 1.00 38.20 --- 0.30 --- --- 11.46
Frente Calle 5 1.00 173.13 --- 0.30 --- --- 51.94
Frente Calle 10 1.00 38.33 --- 0.30 --- --- 11.50

MARTILLOS 44.00 11.80 --- 0.30 --- --- 155.76

VEREDAS - CONCRETO f'c=175 kg/cm2 , E=0.10m INCLUYE ACABADO,


03.03.03
BRUADO Y CURADO
m2 6,881.03

Igual que el rea de apisonado de veredas 1.00 --- --- --- 6,986.63 --- 6,986.63

Descontar del area de concreto en rampas para personas con discapacidad 1.00 --- --- --- 105.60 --- 105.60

RAMPA DE ACCESO P/PERSONAS CON DISCAPACIDAD - CONCRETO F'C=


03.03.04
175 KG/CM2
m2 105.60

General 88.00 --- --- --- 1.20 --- 105.60

03.03.05 JUNTA CON ASFALTO E=1" PARA VEREDAS m 1,590.00

MZ F
Frente Calle Ancash 5.00 2.00 --- --- --- --- 10.00
Frente Calle 1 36.00 2.00 --- --- --- --- 72.00

MZ J
Frente Calle Ancash 10.00 2.00 --- --- --- --- 20.00
Frente Calle 1 36.00 2.00 --- --- --- --- 72.00
Frente Calle A 36.00 2.00 --- --- --- --- 72.00
Frente Calle E 10.00 1.20 --- --- --- --- 12.00

MZ E
Frente Calle 1 50.00 2.00 --- --- --- --- 100.00

MZ G
Frente Calle 1 50.00 2.00 --- --- --- --- 100.00
Frente Calle E 10.00 1.20 --- --- --- --- 12.00
Frente Calle "A" 50.00 2.00 --- --- --- --- 100.00
Frente Calle 15 10.00 1.50 --- --- --- --- 15.00

MZ I
Frente Calle E 10.00 1.20 --- --- --- --- 12.00
Frente Calle "A" 14.00 2.00 --- --- --- --- 28.00
Frente Calle C 10.00 1.20 --- --- --- --- 12.00
Frente Calle 5 14.00 1.50 --- --- --- --- 21.00

PARQUE 2
Frente Calle C 10.00 2.00 --- --- --- --- 20.00
Frente Calle "A" 14.00 2.00 --- --- --- --- 28.00
Frente Calle B 10.00 2.00 --- --- --- --- 20.00
Frente Calle 5 14.00 1.50 --- --- --- --- 21.00

MZ H
Frente Calle B 10.00 1.20 --- --- --- --- 12.00
Frente Calle A 16.00 2.00 --- --- --- --- 32.00
Frente Calle 15 10.00 1.50 --- --- --- --- 15.00
Frente Calle 5 16.00 1.50 --- --- --- --- 24.00

MZ C
Frente Calle 15 10.00 1.50 --- --- --- --- 15.00
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

Frente Calle 1 21.00 2.00 --- --- --- --- 42.00


Frente Calle A 21.00 2.00 --- --- --- --- 42.00
Frente Calle 13 10.00 1.50 --- --- --- --- 15.00

MZ D
Frente Calle 15 10.00 1.50 --- --- --- --- 15.00
Frente Calle A 21.00 2.00 --- --- --- --- 42.00
Frente Calle 13 10.00 1.50 --- --- --- --- 15.00
Frente Calle 5 21.00 1.50 --- --- --- --- 31.50

MZ B1
Frente Calle 13 24.00 1.50 --- --- --- --- 36.00
Frente Calle 1 23.00 2.00 --- --- --- --- 46.00
Frente Calle 11 24.00 1.50 --- --- --- --- 36.00
Frente Calle 5 23.00 1.50 --- --- --- --- 34.50

MZ B
Frente Calle 11 10.00 1.50 --- --- --- --- 15.00
Frente Calle 1 44.00 2.00 --- --- --- --- 88.00
Frente Calle A 44.00 2.00 --- --- --- --- 88.00
Frente Calle 10 10.00 1.50 --- --- --- --- 15.00

MZ A
Frente Calle A 44.00 2.00 --- --- --- --- 88.00
Frente Calle 11 10.00 1.50 --- --- --- --- 15.00
Frente Calle 5 44.00 1.50 --- --- --- --- 66.00
Frente Calle 10 10.00 1.50 --- --- --- --- 15.00

04 SARDINELES
04.01 TRABAJOS PRELIMINARES
04.01.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR EN SARDINELES m2 517.24

MZ F
Frente Calle Ancash 1.00 20.00 0.15 --- --- --- 3.00
Frente Calle 1 1.00 142.70 0.15 --- --- --- 21.41

MZ J
Frente Calle Ancash 1.00 38.60 0.15 --- --- --- 5.79
Frente Calle 1 1.00 141.15 0.15 --- --- --- 21.17
Frente Calle A 1.00 141.20 0.15 --- --- --- 21.18
Frente Calle E 1.00 38.68 0.15 --- --- --- 5.80

MZ E
Frente Calle 1 1.00 197.28 0.15 --- --- --- 29.59

MZ G
Frente Calle 1 1.00 197.15 0.15 --- --- --- 29.57
Frente Calle E 1.00 38.87 0.15 --- --- --- 5.83
Frente Calle "A" 1.00 197.30 0.15 --- --- --- 29.60
Frente Calle 15 1.00 38.88 0.15 --- --- --- 5.83

MZ I
Frente Calle E 1.00 38.30 0.15 --- --- --- 5.75
Frente Calle "A" 1.00 52.60 0.15 --- --- --- 7.89
Frente Calle C 1.00 38.33 0.15 --- --- --- 5.75
Frente Calle 5 1.00 52.77 0.15 --- --- --- 7.92

PARQUE 2
Frente Calle C 1.00 38.33 0.15 --- --- --- 5.75
Frente Calle "A" 1.00 53.33 0.15 --- --- --- 8.00
Frente Calle B 1.00 38.35 0.15 --- --- --- 5.75
Frente Calle 5 1.00 53.20 0.15 --- --- --- 7.98

MZ H
Frente Calle B 1.00 38.35 0.15 --- --- --- 5.75
Frente Calle A 1.00 60.38 0.15 --- --- --- 9.06
Frente Calle 15 1.00 38.20 0.15 --- --- --- 5.73
Frente Calle 5 1.00 60.30 0.15 --- --- --- 9.05
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

MZ C
Frente Calle 15 1.00 38.85 0.15 --- --- --- 5.83
Frente Calle 1 1.00 82.25 0.15 --- --- --- 12.34
Frente Calle A 1.00 82.25 0.15 --- --- --- 12.34
Frente Calle 13 1.00 38.83 0.15 --- --- --- 5.82

MZ D
Frente Calle 15 1.00 38.20 0.15 --- --- --- 5.73
Frente Calle A 1.00 82.25 0.15 --- --- --- 12.34
Frente Calle 13 1.00 38.18 0.15 --- --- --- 5.73
Frente Calle 5 1.00 82.25 0.15 --- --- --- 12.34

MZ B1
Frente Calle 13 1.00 93.03 0.15 --- --- --- 13.95
Frente Calle 1 1.00 88.96 0.15 --- --- --- 13.34
Frente Calle 11 1.00 93.20 0.15 --- --- --- 13.98
Frente Calle 5 1.00 89.00 0.15 --- --- --- 13.35

MZ B
Frente Calle 11 1.00 38.85 0.15 --- --- --- 5.83
Frente Calle 1 1.00 173.17 0.15 --- --- --- 25.98
Frente Calle A 1.00 173.08 0.15 --- --- --- 25.96
Frente Calle 10 1.00 38.82 0.15 --- --- --- 5.82

MZ A
Frente Calle A 1.00 173.08 0.15 --- --- --- 25.96
Frente Calle 11 1.00 38.20 0.15 --- --- --- 5.73
Frente Calle 5 1.00 173.13 0.15 --- --- --- 25.97
Frente Calle 10 1.00 38.33 0.15 --- --- --- 5.75

04.02 MOVIMIENTO DE TIERRAS


04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL P/ SARDINELES m3 181.03

MZ F
Frente Calle Ancash 1.00 20.00 0.15 0.35 --- --- 1.05
Frente Calle 1 1.00 142.70 0.15 0.35 --- --- 7.49

MZ J
Frente Calle Ancash 1.00 38.60 0.15 0.35 --- --- 2.03
Frente Calle 1 1.00 141.15 0.15 0.35 --- --- 7.41
Frente Calle A 1.00 141.20 0.15 0.35 --- --- 7.41
Frente Calle E 1.00 38.68 0.15 0.35 --- --- 2.03

MZ E
Frente Calle 1 1.00 197.28 0.15 0.35 --- --- 10.36

MZ G
Frente Calle 1 1.00 197.15 0.15 0.35 --- --- 10.35
Frente Calle E 1.00 38.87 0.15 0.35 --- --- 2.04
Frente Calle "A" 1.00 197.30 0.15 0.35 --- --- 10.36
Frente Calle 15 1.00 38.88 0.15 0.35 --- --- 2.04

MZ I
Frente Calle E 1.00 38.30 0.15 0.35 --- --- 2.01
Frente Calle "A" 1.00 52.60 0.15 0.35 --- --- 2.76
Frente Calle C 1.00 38.33 0.15 0.35 --- --- 2.01
Frente Calle 5 1.00 52.77 0.15 0.35 --- --- 2.77

PARQUE 2
Frente Calle C 1.00 38.33 0.15 0.35 --- --- 2.01
Frente Calle "A" 1.00 53.33 0.15 0.35 --- --- 2.80
Frente Calle B 1.00 38.35 0.15 0.35 --- --- 2.01
Frente Calle 5 1.00 53.20 0.15 0.35 --- --- 2.79

MZ H
Frente Calle B 1.00 38.35 0.15 0.35 --- --- 2.01
Frente Calle A 1.00 60.38 0.15 0.35 --- --- 3.17
Frente Calle 15 1.00 38.20 0.15 0.35 --- --- 2.01
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

Frente Calle 5 1.00 60.30 0.15 0.35 --- --- 3.17

MZ C
Frente Calle 15 1.00 38.85 0.15 0.35 --- --- 2.04
Frente Calle 1 1.00 82.25 0.15 0.35 --- --- 4.32
Frente Calle A 1.00 82.25 0.15 0.35 --- --- 4.32
Frente Calle 13 1.00 38.83 0.15 0.35 --- --- 2.04

MZ D
Frente Calle 15 1.00 38.20 0.15 0.35 --- --- 2.01
Frente Calle A 1.00 82.25 0.15 0.35 --- --- 4.32
Frente Calle 13 1.00 38.18 0.15 0.35 --- --- 2.00
Frente Calle 5 1.00 82.25 0.15 0.35 --- --- 4.32

MZ B1
Frente Calle 13 1.00 93.03 0.15 0.35 --- --- 4.88
Frente Calle 1 1.00 88.96 0.15 0.35 --- --- 4.67
Frente Calle 11 1.00 93.20 0.15 0.35 --- --- 4.89
Frente Calle 5 1.00 89.00 0.15 0.35 --- --- 4.67

MZ B
Frente Calle 11 1.00 38.85 0.15 0.35 --- --- 2.04
Frente Calle 1 1.00 173.17 0.15 0.35 --- --- 9.09
Frente Calle A 1.00 173.08 0.15 0.35 --- --- 9.09
Frente Calle 10 1.00 38.82 0.15 0.35 --- --- 2.04

MZ A
Frente Calle A 1.00 173.08 0.15 0.35 --- --- 9.09
Frente Calle 11 1.00 38.20 0.15 0.35 --- --- 2.01
Frente Calle 5 1.00 173.13 0.15 0.35 --- --- 9.09
Frente Calle 10 1.00 38.33 0.15 0.35 --- --- 2.01

04.02.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINA m3 226.29


Factor
Proviene de excavacin en terreno normal 1.00 --- --- 1.25 --- 181.03 226.29

04.03 SARDINELES DE CONCRETO


04.03.01 ENCOFRADO DE SARDINEL SUMERGIDO (a=0.15m - h=0.35m) m2 1,379.33

SARDINEL SUMERGIDO (cara que da frente a vereda)


MZ F
Frente Calle Ancash 1.00 20.00 --- 0.35 --- --- 7.00
Frente Calle 1 1.00 142.70 --- 0.35 --- --- 49.95

MZ J
Frente Calle Ancash 1.00 38.60 --- 0.35 --- --- 13.51
Frente Calle 1 1.00 141.15 --- 0.35 --- --- 49.40
Frente Calle A 1.00 141.20 --- 0.35 --- --- 49.42
Frente Calle E 1.00 38.68 --- 0.35 --- --- 13.54

MZ E
Frente Calle 1 1.00 197.28 --- 0.35 --- --- 69.05

MZ G
Frente Calle 1 1.00 197.15 --- 0.35 --- --- 69.00
Frente Calle E 1.00 38.87 --- 0.35 --- --- 13.60
Frente Calle "A" 1.00 197.30 --- 0.35 --- --- 69.06
Frente Calle 15 1.00 38.88 --- 0.35 --- --- 13.61

MZ I
Frente Calle E 1.00 38.30 --- 0.35 --- --- 13.41
Frente Calle "A" 1.00 52.60 --- 0.35 --- --- 18.41
Frente Calle C 1.00 38.33 --- 0.35 --- --- 13.42
Frente Calle 5 1.00 52.77 --- 0.35 --- --- 18.47

PARQUE 2
Frente Calle C 1.00 38.33 --- 0.35 --- --- 13.42
Frente Calle "A" 1.00 53.33 --- 0.35 --- --- 18.67
Frente Calle B 1.00 38.35 --- 0.35 --- --- 13.42
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

Frente Calle 5 1.00 53.20 --- 0.35 --- --- 18.62

MZ H
Frente Calle B 1.00 38.35 --- 0.35 --- --- 13.42
Frente Calle A 1.00 60.38 --- 0.35 --- --- 21.13
Frente Calle 15 1.00 38.20 --- 0.35 --- --- 13.37
Frente Calle 5 1.00 60.30 --- 0.35 --- --- 21.11

MZ C
Frente Calle 15 1.00 38.85 --- 0.35 --- --- 13.60
Frente Calle 1 1.00 82.25 --- 0.35 --- --- 28.79
Frente Calle A 1.00 82.25 --- 0.35 --- --- 28.79
Frente Calle 13 1.00 38.83 --- 0.35 --- --- 13.59

MZ D
Frente Calle 15 1.00 38.20 --- 0.35 --- --- 13.37
Frente Calle A 1.00 82.25 --- 0.35 --- --- 28.79
Frente Calle 13 1.00 38.18 --- 0.35 --- --- 13.36
Frente Calle 5 1.00 82.25 --- 0.35 --- --- 28.79

MZ B1
Frente Calle 13 1.00 93.03 --- 0.35 --- --- 32.56
Frente Calle 1 1.00 88.96 --- 0.35 --- --- 31.14
Frente Calle 11 1.00 93.20 --- 0.35 --- --- 32.62
Frente Calle 5 1.00 89.00 --- 0.35 --- --- 31.15

MZ B
Frente Calle 11 1.00 38.85 --- 0.35 --- --- 13.60
Frente Calle 1 1.00 173.17 --- 0.35 --- --- 60.61
Frente Calle A 1.00 173.08 --- 0.35 --- --- 60.58
Frente Calle 10 1.00 38.82 --- 0.35 --- --- 13.59

MZ A
Frente Calle A 1.00 173.08 --- 0.35 --- --- 60.58
Frente Calle 11 1.00 38.20 --- 0.35 --- --- 13.37
Frente Calle 5 1.00 173.13 --- 0.35 --- --- 60.60
Frente Calle 10 1.00 38.33 --- 0.35 --- --- 13.42

SARDINEL SUMERGIDO (cara que da frente a pista)


MZ F
Frente Calle Ancash 1.00 20.00 --- 0.05 --- --- 1.00
Frente Calle 1 1.00 142.70 --- 0.05 --- --- 7.14

MZ J
Frente Calle Ancash 1.00 38.60 --- 0.05 --- --- 1.93
Frente Calle 1 1.00 141.15 --- 0.05 --- --- 7.06
Frente Calle A 1.00 141.20 --- 0.05 --- --- 7.06
Frente Calle E 1.00 38.68 --- 0.05 --- --- 1.93

MZ E
Frente Calle 1 1.00 197.28 --- 0.05 --- --- 9.86

MZ G
Frente Calle 1 1.00 197.15 --- 0.05 --- --- 9.86
Frente Calle E 1.00 38.87 --- 0.05 --- --- 1.94
Frente Calle "A" 1.00 197.30 --- 0.05 --- --- 9.87
Frente Calle 15 1.00 38.88 --- 0.05 --- --- 1.94

MZ I
Frente Calle E 1.00 38.30 --- 0.05 --- --- 1.92
Frente Calle "A" 1.00 52.60 --- 0.05 --- --- 2.63
Frente Calle C 1.00 38.33 --- 0.05 --- --- 1.92
Frente Calle 5 1.00 52.77 --- 0.05 --- --- 2.64

PARQUE 2
Frente Calle C 1.00 38.33 --- 0.05 --- --- 1.92
Frente Calle "A" 1.00 53.33 --- 0.05 --- --- 2.67
Frente Calle B 1.00 38.35 --- 0.05 --- --- 1.92
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

Frente Calle 5 1.00 53.20 --- 0.05 --- --- 2.66

MZ H
Frente Calle B 1.00 38.35 --- 0.05 --- --- 1.92
Frente Calle A 1.00 60.38 --- 0.05 --- --- 3.02
Frente Calle 15 1.00 38.20 --- 0.05 --- --- 1.91
Frente Calle 5 1.00 60.30 --- 0.05 --- --- 3.02

MZ C
Frente Calle 15 1.00 38.85 --- 0.05 --- --- 1.94
Frente Calle 1 1.00 82.25 --- 0.05 --- --- 4.11
Frente Calle A 1.00 82.25 --- 0.05 --- --- 4.11
Frente Calle 13 1.00 38.83 --- 0.05 --- --- 1.94

MZ D
Frente Calle 15 1.00 38.20 --- 0.05 --- --- 1.91
Frente Calle A 1.00 82.25 --- 0.05 --- --- 4.11
Frente Calle 13 1.00 38.18 --- 0.05 --- --- 1.91
Frente Calle 5 1.00 82.25 --- 0.05 --- --- 4.11

MZ B1
Frente Calle 13 1.00 93.03 --- 0.05 --- --- 4.65
Frente Calle 1 1.00 88.96 --- 0.05 --- --- 4.45
Frente Calle 11 1.00 93.20 --- 0.05 --- --- 4.66
Frente Calle 5 1.00 89.00 --- 0.05 --- --- 4.45

MZ B
Frente Calle 11 1.00 38.85 --- 0.05 --- --- 1.94
Frente Calle 1 1.00 173.17 --- 0.05 --- --- 8.66
Frente Calle A 1.00 173.08 --- 0.05 --- --- 8.65
Frente Calle 10 1.00 38.82 --- 0.05 --- --- 1.94

MZ A
Frente Calle A 1.00 173.08 --- 0.05 --- --- 8.65
Frente Calle 11 1.00 38.20 --- 0.05 --- --- 1.91
Frente Calle 5 1.00 173.13 --- 0.05 --- --- 8.66
Frente Calle 10 1.00 38.33 --- 0.05 --- --- 1.92

04.03.02 SARDINELES DE CONCRETO f'c=175 kg/cm2 m3 181.03

MZ F
Frente Calle Ancash 1.00 20.00 0.15 0.35 --- --- 1.05
Frente Calle 1 1.00 142.70 0.15 0.35 --- --- 7.49

MZ J
Frente Calle Ancash 1.00 38.60 0.15 0.35 --- --- 2.03
Frente Calle 1 1.00 141.15 0.15 0.35 --- --- 7.41
Frente Calle A 1.00 141.20 0.15 0.35 --- --- 7.41
Frente Calle E 1.00 38.68 0.15 0.35 --- --- 2.03

MZ E
Frente Calle 1 1.00 197.28 0.15 0.35 --- --- 10.36

MZ G
Frente Calle 1 1.00 197.15 0.15 0.35 --- --- 10.35
Frente Calle E 1.00 38.87 0.15 0.35 --- --- 2.04
Frente Calle "A" 1.00 197.30 0.15 0.35 --- --- 10.36
Frente Calle 15 1.00 38.88 0.15 0.35 --- --- 2.04

MZ I
Frente Calle E 1.00 38.30 0.15 0.35 --- --- 2.01
Frente Calle "A" 1.00 52.60 0.15 0.35 --- --- 2.76
Frente Calle C 1.00 38.33 0.15 0.35 --- --- 2.01
Frente Calle 5 1.00 52.77 0.15 0.35 --- --- 2.77

PARQUE 2
Frente Calle C 1.00 38.33 0.15 0.35 --- --- 2.01
Frente Calle "A" 1.00 53.33 0.15 0.35 --- --- 2.80
Frente Calle B 1.00 38.35 0.15 0.35 --- --- 2.01
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

Frente Calle 5 1.00 53.20 0.15 0.35 --- --- 2.79

MZ H
Frente Calle B 1.00 38.35 0.15 0.35 --- --- 2.01
Frente Calle A 1.00 60.38 0.15 0.35 --- --- 3.17
Frente Calle 15 1.00 38.20 0.15 0.35 --- --- 2.01
Frente Calle 5 1.00 60.30 0.15 0.35 --- --- 3.17

MZ C
Frente Calle 15 1.00 38.85 0.15 0.35 --- --- 2.04
Frente Calle 1 1.00 82.25 0.15 0.35 --- --- 4.32
Frente Calle A 1.00 82.25 0.15 0.35 --- --- 4.32
Frente Calle 13 1.00 38.83 0.15 0.35 --- --- 2.04

MZ D
Frente Calle 15 1.00 38.20 0.15 0.35 --- --- 2.01
Frente Calle A 1.00 82.25 0.15 0.35 --- --- 4.32
Frente Calle 13 1.00 38.18 0.15 0.35 --- --- 2.00
Frente Calle 5 1.00 82.25 0.15 0.35 --- --- 4.32

MZ B1
Frente Calle 13 1.00 93.03 0.15 0.35 --- --- 4.88
Frente Calle 1 1.00 88.96 0.15 0.35 --- --- 4.67
Frente Calle 11 1.00 93.20 0.15 0.35 --- --- 4.89
Frente Calle 5 1.00 89.00 0.15 0.35 --- --- 4.67

MZ B
Frente Calle 11 1.00 38.85 0.15 0.35 --- --- 2.04
Frente Calle 1 1.00 173.17 0.15 0.35 --- --- 9.09
Frente Calle A 1.00 173.08 0.15 0.35 --- --- 9.09
Frente Calle 10 1.00 38.82 0.15 0.35 --- --- 2.04

MZ A
Frente Calle A 1.00 173.08 0.15 0.35 --- --- 9.09
Frente Calle 11 1.00 38.20 0.15 0.35 --- --- 2.01
Frente Calle 5 1.00 173.13 0.15 0.35 --- --- 9.09
Frente Calle 10 1.00 38.33 0.15 0.35 --- --- 2.01

04.03.03 CURADO DEL CONCRETO EN SARDINEL SUMERGIDO m2 1,724.18

MZ F
Frente Calle Ancash 1.00 20.00 0.50 --- --- --- 10.00
Frente Calle 1 1.00 142.70 0.50 --- --- --- 71.35

MZ J
Frente Calle Ancash 1.00 38.60 0.50 --- --- --- 19.30
Frente Calle 1 1.00 141.15 0.50 --- --- --- 70.58
Frente Calle A 1.00 141.20 0.50 --- --- --- 70.60
Frente Calle E 1.00 38.68 0.50 --- --- --- 19.34

MZ E
Frente Calle 1 1.00 197.28 0.50 --- --- --- 98.64

MZ G
Frente Calle 1 1.00 197.15 0.50 --- --- --- 98.58
Frente Calle E 1.00 38.87 0.50 --- --- --- 19.44
Frente Calle "A" 1.00 197.30 0.50 --- --- --- 98.65
Frente Calle 15 1.00 38.88 0.50 --- --- --- 19.44

MZ I
Frente Calle E 1.00 38.30 0.50 --- --- --- 19.15
Frente Calle "A" 1.00 52.60 0.50 --- --- --- 26.30
Frente Calle C 1.00 38.33 0.50 --- --- --- 19.17
Frente Calle 5 1.00 52.77 0.50 --- --- --- 26.39

PARQUE 2
Frente Calle C 1.00 38.33 0.50 --- --- --- 19.17
Frente Calle "A" 1.00 53.33 0.50 --- --- --- 26.67
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

Frente Calle B 1.00 38.35 0.50 --- --- --- 19.18


Frente Calle 5 1.00 53.20 0.50 --- --- --- 26.60

MZ H
Frente Calle B 1.00 38.35 0.50 --- --- --- 19.18
Frente Calle A 1.00 60.38 0.50 --- --- --- 30.19
Frente Calle 15 1.00 38.20 0.50 --- --- --- 19.10
Frente Calle 5 1.00 60.30 0.50 --- --- --- 30.15

MZ C
Frente Calle 15 1.00 38.85 0.50 --- --- --- 19.43
Frente Calle 1 1.00 82.25 0.50 --- --- --- 41.13
Frente Calle A 1.00 82.25 0.50 --- --- --- 41.13
Frente Calle 13 1.00 38.83 0.50 --- --- --- 19.42

MZ D
Frente Calle 15 1.00 38.20 0.50 --- --- --- 19.10
Frente Calle A 1.00 82.25 0.50 --- --- --- 41.13
Frente Calle 13 1.00 38.18 0.50 --- --- --- 19.09
Frente Calle 5 1.00 82.25 0.50 --- --- --- 41.13

MZ B1
Frente Calle 13 1.00 93.03 0.50 --- --- --- 46.52
Frente Calle 1 1.00 88.96 0.50 --- --- --- 44.48
Frente Calle 11 1.00 93.20 0.50 --- --- --- 46.60
Frente Calle 5 1.00 89.00 0.50 --- --- --- 44.50

MZ B
Frente Calle 11 1.00 38.85 0.50 --- --- --- 19.43
Frente Calle 1 1.00 173.17 0.50 --- --- --- 86.59
Frente Calle A 1.00 173.08 0.50 --- --- --- 86.54
Frente Calle 10 1.00 38.82 0.50 --- --- --- 19.41

MZ A
Frente Calle A 1.00 173.08 0.50 --- --- --- 86.54
Frente Calle 11 1.00 38.20 0.50 --- --- --- 19.10
Frente Calle 5 1.00 173.13 0.50 --- --- --- 86.57
Frente Calle 10 1.00 38.33 0.50 --- --- --- 19.17

04.03.04 JUNTAS ASFALTICAS EN SARDINELES SUMERGIDOS E=1" m 309.75

MZ F
Frente Calle Ancash 5.00 0.35 --- --- --- --- 1.75
Frente Calle 1 36.00 0.35 --- --- --- --- 12.60

MZ J
Frente Calle Ancash 10.00 0.35 --- --- --- --- 3.50
Frente Calle 1 36.00 0.35 --- --- --- --- 12.60
Frente Calle A 36.00 0.35 --- --- --- --- 12.60
Frente Calle E 10.00 0.35 --- --- --- --- 3.50

MZ E
Frente Calle 1 50.00 0.35 --- --- --- --- 17.50

MZ G
Frente Calle 1 50.00 0.35 --- --- --- --- 17.50
Frente Calle E 10.00 0.35 --- --- --- --- 3.50
Frente Calle "A" 50.00 0.35 --- --- --- --- 17.50
Frente Calle 15 10.00 0.35 --- --- --- --- 3.50

MZ I
Frente Calle E 10.00 0.35 --- --- --- --- 3.50
Frente Calle "A" 14.00 0.35 --- --- --- --- 4.90
Frente Calle C 10.00 0.35 --- --- --- --- 3.50
Frente Calle 5 14.00 0.35 --- --- --- --- 4.90

PARQUE 2
Frente Calle C 10.00 0.35 --- --- --- --- 3.50
Frente Calle "A" 14.00 0.35 --- --- --- --- 4.90
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

Frente Calle B 10.00 0.35 --- --- --- --- 3.50


Frente Calle 5 14.00 0.35 --- --- --- --- 4.90

MZ H
Frente Calle B 10.00 0.35 --- --- --- --- 3.50
Frente Calle A 16.00 0.35 --- --- --- --- 5.60
Frente Calle 15 10.00 0.35 --- --- --- --- 3.50
Frente Calle 5 16.00 0.35 --- --- --- --- 5.60

MZ C
Frente Calle 15 10.00 0.35 --- --- --- --- 3.50
Frente Calle 1 21.00 0.35 --- --- --- --- 7.35
Frente Calle A 21.00 0.35 --- --- --- --- 7.35
Frente Calle 13 10.00 0.35 --- --- --- --- 3.50

MZ D
Frente Calle 15 10.00 0.35 --- --- --- --- 3.50
Frente Calle A 21.00 0.35 --- --- --- --- 7.35
Frente Calle 13 10.00 0.35 --- --- --- --- 3.50
Frente Calle 5 21.00 0.35 --- --- --- --- 7.35

MZ B1
Frente Calle 13 24.00 0.35 --- --- --- --- 8.40
Frente Calle 1 23.00 0.35 --- --- --- --- 8.05
Frente Calle 11 24.00 0.35 --- --- --- --- 8.40
Frente Calle 5 23.00 0.35 --- --- --- --- 8.05

MZ B
Frente Calle 11 10.00 0.35 --- --- --- --- 3.50
Frente Calle 1 44.00 0.35 --- --- --- --- 15.40
Frente Calle A 44.00 0.35 --- --- --- --- 15.40
Frente Calle 10 10.00 0.35 --- --- --- --- 3.50

MZ A
Frente Calle A 44.00 0.35 --- --- --- --- 15.40
Frente Calle 11 10.00 0.35 --- --- --- --- 3.50
Frente Calle 5 44.00 0.35 --- --- --- --- 15.40
Frente Calle 10 10.00 0.35 --- --- --- --- 3.50

05 AREAS VERDES
05.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR m2 7,857.00

MZ F
Frente Calle Ancash 1.00 20.00 1.45 --- --- --- 29.00
Frente Calle 1 1.00 142.70 2.85 --- --- --- 406.70

MZ J
Frente Calle Ancash 1.00 38.60 3.25 --- --- --- 125.45
Frente Calle 1 1.00 141.15 2.70 --- --- --- 381.11
Frente Calle A 1.00 141.20 1.90 --- --- --- 268.28
Frente Calle E 1.00 38.68 2.40 --- --- --- 92.83

MZ E
Frente Calle 1 1.00 197.28 2.85 --- --- --- 562.25

MZ G
Frente Calle 1 1.00 197.15 2.70 --- --- --- 532.31
Frente Calle E 1.00 38.87 2.40 --- --- --- 93.29
Frente Calle "A" 1.00 197.30 1.85 --- --- --- 365.01
Frente Calle 15 1.00 38.88 1.85 --- --- --- 71.93

MZ I
Frente Calle E 1.00 38.30 2.50 --- --- --- 95.75
Frente Calle "A" 1.00 52.60 1.85 --- --- --- 97.31
Frente Calle C 1.00 38.33 1.45 --- --- --- 55.58
Frente Calle 5 1.00 52.77 2.65 --- --- --- 139.84

PARQUE 2
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

Frente Calle C 1.00 38.33 1.45 --- --- --- 55.58


Frente Calle "A" 1.00 53.33 1.85 --- --- --- 98.66
Frente Calle B 1.00 38.35 1.45 --- --- --- 55.61
Frente Calle 5 1.00 53.20 2.60 --- --- --- 138.32

MZ H
Frente Calle B 1.00 38.35 1.45 --- --- --- 55.61
Frente Calle A 1.00 60.38 1.85 --- --- --- 111.70
Frente Calle 15 1.00 38.20 1.85 --- --- --- 70.67
Frente Calle 5 1.00 60.30 2.60 --- --- --- 156.78

MZ C
Frente Calle 15 1.00 38.85 3.10 --- --- --- 120.44
Frente Calle 1 1.00 82.25 2.70 --- --- --- 222.08
Frente Calle A 1.00 82.25 1.85 --- --- --- 152.16
Frente Calle 13 1.00 38.83 1.85 --- --- --- 71.84

MZ D
Frente Calle 15 1.00 38.20 3.10 --- --- --- 118.42
Frente Calle A 1.00 82.25 1.85 --- --- --- 152.16
Frente Calle 13 1.00 38.18 1.85 --- --- --- 70.63
Frente Calle 5 1.00 82.25 2.60 --- --- --- 213.85

MZ B1
Frente Calle 13 1.00 93.03 1.85 --- --- --- 172.11
Frente Calle 1 1.00 88.96 2.70 --- --- --- 240.19
Frente Calle 11 1.00 93.20 1.85 --- --- --- 172.42
Frente Calle 5 1.00 89.00 2.60 --- --- --- 231.40

MZ B
Frente Calle 11 1.00 38.85 1.85 --- --- --- 71.87
Frente Calle 1 1.00 173.17 2.70 --- --- --- 467.56
Frente Calle A 1.00 173.08 1.85 --- --- --- 320.20
Frente Calle 10 1.00 38.82 1.95 --- --- --- 75.70

MZ A
Frente Calle A 1.00 173.08 1.85 --- --- --- 320.20
Frente Calle 11 1.00 38.20 1.85 --- --- --- 70.67
Frente Calle 5 1.00 173.13 2.65 --- --- --- 458.79
Frente Calle 10 1.00 38.33 1.95 --- --- --- 74.74

05.02 SEMBRADO DE GRASS m2 7,857.00

Proviene del area de trazo en areas verdes 1.00 --- --- --- 7,857.00 --- 7,857.00

05.03 SEMBRADO DE PLANTONES und 569.00

MZ F
Frente Calle Ancash 3.00 --- --- --- --- --- 3.00
Frente Calle 1 24.00 --- --- --- --- --- 24.00

MZ J
Frente Calle Ancash 6.00 --- --- --- --- --- 6.00
Frente Calle 1 23.00 --- --- --- --- --- 23.00
Frente Calle A 6.00 --- --- --- --- --- 6.00
Frente Calle E 24.00 --- --- --- --- --- 24.00

MZ E
Frente Calle 1 33.00 --- --- --- --- --- 33.00

MZ G
Frente Calle 1 6.00 --- --- --- --- --- 6.00
Frente Calle E 33.00 --- --- --- --- --- 33.00
Frente Calle "A" 6.00 --- --- --- --- --- 6.00
Frente Calle 15 33.00 --- --- --- --- --- 33.00

MZ I
Frente Calle E 6.00 --- --- --- --- --- 6.00
Frente Calle "A" 9.00 --- --- --- --- --- 9.00
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

Frente Calle C 6.00 --- --- --- --- --- 6.00


Frente Calle 5 9.00 --- --- --- --- --- 9.00

PARQUE 2
Frente Calle C 6.00 --- --- --- --- --- 6.00
Frente Calle "A" 9.00 --- --- --- --- --- 9.00
Frente Calle B 6.00 --- --- --- --- --- 6.00
Frente Calle 5 9.00 --- --- --- --- --- 9.00

MZ H
Frente Calle B 6.00 --- --- --- --- --- 6.00
Frente Calle A 10.00 --- --- --- --- --- 10.00
Frente Calle 15 6.00 --- --- --- --- --- 6.00
Frente Calle 5 10.00 --- --- --- --- --- 10.00

MZ C
Frente Calle 15 6.00 --- --- --- --- --- 6.00
Frente Calle 1 14.00 --- --- --- --- --- 14.00
Frente Calle A 6.00 --- --- --- --- --- 6.00
Frente Calle 13 14.00 --- --- --- --- --- 14.00

MZ D
Frente Calle 15 6.00 --- --- --- --- --- 6.00
Frente Calle A 14.00 --- --- --- --- --- 14.00
Frente Calle 13 6.00 --- --- --- --- --- 6.00
Frente Calle 5 14.00 --- --- --- --- --- 14.00

MZ B1
Frente Calle 13 15.00 --- --- --- --- --- 15.00
Frente Calle 1 15.00 --- --- --- --- --- 15.00
Frente Calle 11 15.00 --- --- --- --- --- 15.00
Frente Calle 5 15.00 --- --- --- --- --- 15.00

MZ B
Frente Calle 11 6.00 --- --- --- --- --- 6.00
Frente Calle 1 29.00 --- --- --- --- --- 29.00
Frente Calle A 6.00 --- --- --- --- --- 6.00
Frente Calle 10 29.00 --- --- --- --- --- 29.00

MZ A
Frente Calle A 6.00 --- --- --- --- --- 6.00
Frente Calle 11 29.00 --- --- --- --- --- 29.00
Frente Calle 5 6.00 --- --- --- --- --- 6.00
Frente Calle 10 29.00 --- --- --- --- --- 29.00

06 SEALIZACION
06.01 PINTURA LINEAL CONTINUA m 2,817.22

CALLE 1
Frente Manzana F 2.00 152.25 --- --- --- --- 304.50
Frente Manzana E 2.00 207.17 --- --- --- --- 414.34

CALLE A
Frente Manzana J 2.00 148.32 --- --- --- --- 296.64
Frente Manzana K,L,M 2.00 148.32 --- --- --- --- 296.64

CALLE A
Frente Manzana G 2.00 207.35 --- --- --- --- 414.70
Frente Manzana C 2.00 92.25 --- --- --- --- 184.50
Frente Manzana B 2.00 183.10 --- --- --- --- 366.20

Interseccion de Calle A y Calle E 2.00 30.52 --- --- --- --- 61.04
Calle C 2.00 48.25 --- --- --- --- 96.50
Calle B 2.00 48.25 --- --- --- --- 96.50
Calle 13 2.00 103.13 --- --- --- --- 206.26
Calle Ancash 2.00 39.70 --- --- --- --- 79.40

06.02 PINTURA LINEAL DISCONTINUA m 486.00


SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

CALLE 1
Frente Manzana F 18.00 3.00 --- --- --- --- 54.00
Frente Manzana E 25.00 3.00 --- --- --- --- 75.00

CALLE A
Frente Manzana J 18.00 3.00 --- --- --- --- 54.00
Frente Manzana K,L,M 18.00 3.00 --- --- --- --- 54.00

CALLE A
Frente Manzana G 22.00 3.00 --- --- --- --- 66.00
Frente Manzana C 10.00 3.00 --- --- --- --- 30.00
Frente Manzana B 22.00 3.00 --- --- --- --- 66.00

Interseccion de Calle A y Calle E 4.00 3.00 --- --- --- --- 12.00
Calle C 5.00 3.00 --- --- --- --- 15.00
Calle B 5.00 3.00 --- --- --- --- 15.00
Calle 13 10.00 3.00 --- --- --- --- 30.00
Calle Ancash 5.00 3.00 --- --- --- --- 15.00

06.03 PINTURA SOBRE PAVIMENTO (Simbolos y Flechas) m2 360.40

CALLE 1
cruce peatonal 24.00 3.00 0.50 --- --- --- 36.00
2.00 3.00 0.50 --- --- --- 3.00
seal de pare 2.00 --- --- --- 3.20 --- 6.40
flecha C 2.00 --- --- --- 2.30 --- 4.60

CALLE A (desde calle ancash - calle e)


cruce peatonal 24.00 3.00 0.50 --- --- --- 36.00
2.00 3.00 0.50 --- --- --- 3.00
seal de pare 2.00 --- --- --- 3.20 --- 6.40
flecha C 1.00 --- --- --- 2.30 --- 2.30
flecha D 1.00 --- --- --- 2.10 --- 2.10

CALLE A
cruce peatonal 60.00 3.00 0.50 --- --- --- 90.00
10.00 3.00 0.50 --- --- --- 15.00
seal de pare 5.00 --- --- --- 3.20 --- 16.00
flecha A 2.00 --- --- --- 1.80 --- 3.60
flecha B 2.00 --- --- --- 1.80 --- 3.60
flecha C 2.00 --- --- --- 2.30 --- 4.60
flecha D 4.00 --- --- --- 2.10 --- 8.40

CALLE B
cruce peatonal 12.00 3.00 0.50 --- --- --- 18.00
2.00 2.80 0.50 --- --- --- 2.80
seal de pare 2.00 --- --- --- 3.20 --- 6.40
flecha D 2.00 --- --- --- 2.10 --- 4.20

CALLE C
cruce peatonal 12.00 3.00 0.50 --- --- --- 18.00
2.00 2.80 0.50 --- --- --- 2.80
seal de pare 2.00 --- --- --- 3.20 --- 6.40
flecha D 2.00 --- --- --- 2.10 --- 4.20

CALLE 13
cruce peatonal 24.00 3.00 0.50 --- --- --- 36.00
4.00 3.00 0.50 --- --- --- 6.00
seal de pare 2.00 --- --- --- 3.20 --- 6.40
flecha A 1.00 --- --- --- 1.80 --- 1.80
flecha B 1.00 --- --- --- 1.80 --- 1.80
flecha C 2.00 --- --- --- 2.30 --- 4.60

07 VARIOS
07.01 NIVELACION DE TAPA DE BUZONES und 16.00

CALLE 1 1.00 --- --- --- --- --- 1.00


CALLE A (desde calle ancash - calle e) 7.00 --- --- --- --- --- 7.00
SUSTENTO DE METRADOS

"MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO DISTRITO DE
OBRA:
ANCN - LIMA LIMA"

NRO LARGO ANCHO ALTO AREA VOLUMEN


PARTIDA DESCRIPCION UND PARCIAL TOTAL
VECES (M) (M) (M) (M2) (M3)

CALLE A (desde calle e - calle 10) 8.00 --- --- --- --- --- 8.00

07.02 REPOSICION DE CAJA DOMICILIARIA DE AGUA und 291.00

MZ A 43.00 --- --- --- --- --- 43.00


MZ B 44.00 --- --- --- --- --- 44.00
MZ B1 7.00 --- --- --- --- --- 7.00
MZ C 20.00 --- --- --- --- --- 20.00
MZ D 20.00 --- --- --- --- --- 20.00
MZ E 25.00 --- --- --- --- --- 25.00
MZ F 18.00 --- --- --- --- --- 18.00
MZ G 48.00 --- --- --- --- --- 48.00
MZ H 16.00 --- --- --- --- --- 16.00
MZ I 14.00 --- --- --- --- --- 14.00
MZ J 36.00 --- --- --- --- --- 36.00

07.03 REPOSICION DE CAJA DOMICILIARIA DE DESAGUE und 291.00

MZ A 43.00 --- --- --- --- --- 43.00


MZ B 44.00 --- --- --- --- --- 44.00
MZ B1 7.00 --- --- --- --- --- 7.00
MZ C 20.00 --- --- --- --- --- 20.00
MZ D 20.00 --- --- --- --- --- 20.00
MZ E 25.00 --- --- --- --- --- 25.00
MZ F 18.00 --- --- --- --- --- 18.00
MZ G 48.00 --- --- --- --- --- 48.00
MZ H 16.00 --- --- --- --- --- 16.00
MZ I 14.00 --- --- --- --- --- 14.00
MZ J 36.00 --- --- --- --- --- 36.00

07.04 MITIGACION DE IMPACTO AMBIENTAL glb 1.00

General 1.00 --- --- --- --- --- 1.00

07.05 LIMPIEZA FINAL DE OBRA m2 23,256.69

Area de pistas 1.00 --- --- --- 8,413.06 --- 8,413.06


Area de veredas 1.00 --- --- --- 6,986.63 --- 6,986.63
Area de zona verde 1.00 --- --- --- 7,857.00 --- 7,857.00
METRADOS EJECUTADOS Y METRADOS PROGRAMADOS
Obra : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ASOCIACION PRO VIVIENDA VIRGEN DEL ROSARIO,
DISTRITO DE ANCN - LIMA LIMA"
Cliente : MUNICIPALIDAD DISTRITAL DE ANCON
Lugar : LIMA - LIMA - ANCON
Fecha : MARZO - 2017

METRADO
METRADO
Item DESCRIPCION Und. PROGRAMADO
EJECUTADOS
S
01 OBRAS PROVISIONALES
01.01 ALMACEN, OFICINA Y CASETA DE GUARDIANIA mes 4.00 4.00
01.02 CARTEL DE OBRA IMPRESION BANNER DE 8.50Mx3.60M und 1.00 1.00
02 PISTAS
02.01 TRABAJOS PRELIMINARES
02.01.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR EN PISTAS m2 8,413.06 8,413.06
02.01.02 DEMOLICION DE CARPETA ASFALTICA DETERIORADA C/EQUIPO m2 1,992.63 1,992.63
02.01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y MAQUINARIA glb 1.00 1.00
02.02 MOVIMIENTO DE TIERRAS
02.02.01 CORTE A NIVEL DE SUBRASANTE EN TERRENO SUELTO m3 4,991.79 4,991.79
02.02.02 PERFILADO Y COMPACTACION DE LA SUBRASANTE m2 8,413.06 8,413.06
02.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINA m3 8,830.16 8,830.16
02.03 PAVIMENTO FLEXIBLE
02.03.01 SUB BASE GRANULAR E=0.20 m m2 8,413.06 8,413.06
02.03.02 BASE GRANULAR E=0.15 m m2 8,413.06 8,413.06
02.03.03 IMPRIMACION ASFALTICA m2 8,413.06 8,413.06
02.03.04 CARPETA ASFALTICA EN CALIENTE DE 2" m2 8,413.06 8,413.06
02.04 VARIOS
02.04.01 REDUCTORES DE VELOCIDAD (GIVAS ASFALTICAS) L=6M und 8.00 8.00
03 VEREDAS
03.01 TRABAJOS PRELIMINARES
03.01.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR EN VEREDAS m2 6,986.63 6,986.63
03.01.02 DEMOLICION DE VEREDA DE CONCRETO EXISTENTE E=0.10M m2 3,739.07 3,739.07
03.01.03 ELIMINACION DE MATERIAL PROCEDENTE DE DEMOLICIONES DE VEREDAS m3 523.47 523.47
03.02 MOVIMIENTO DE TIERRAS
03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL P/ VEREDAS m3 1,397.33 1,397.33
03.02.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINA m3 1,746.66 1,746.66
03.02.03 CONFORMACION Y COMPACTACION DE SUBRASANTE P/VEREDAS m2 6,986.63 6,986.63
03.03 VEREDAS DE CONCRETO
03.03.01 BASE GRANULAR E=0.10 m m2 6,986.63 6,986.63
03.03.02 ENCOFRADO EN VEREDAS h=0.30 m. m2 1,190.24 1,190.24
03.03.03 VEREDAS - CONCRETO f'c=175 kg/cm2 , E=0.10m INCLUYE ACABADO, BRUADO Y CURADO m2 6,881.03 6,881.03
03.03.04 RAMPA DE ACCESO P/PERSONAS CON DISCAPACIDAD - CONCRETO F'C= 175 KG/CM2 m2 105.60 105.60
03.03.05 JUNTA CON ASFALTO E=1" PARA VEREDAS m 1,590.00 1,590.00
04 SARDINELES
04.01 TRABAJOS PRELIMINARES
04.01.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR EN SARDINELES m2 517.24 517.24
04.02 MOVIMIENTO DE TIERRAS
04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL P/ SARDINELES m3 181.03 181.03
04.02.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINA m3 226.29 226.29
04.03 SARDINELES DE CONCRETO
04.03.01 ENCOFRADO DE SARDINEL SUMERGIDO (a=0.15m - h=0.35m) m2 1,379.33 1,379.33
04.03.02 SARDINELES DE CONCRETO f'c=175 kg/cm2 m3 181.03 181.03
04.03.03 CURADO DEL CONCRETO EN SARDINEL SUMERGIDO m2 1,724.18 1,724.18
04.03.04 JUNTAS ASFALTICAS EN SARDINELES SUMERGIDOS E=1" m 309.75 309.75
05 AREAS VERDES
05.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR EN AREAS VERDES m2 7,857.00 7,857.00
05.02 SEMBRADO DE GRASS m2 7,857.00 7,857.00
05.03 SEMBRADO DE PLANTONES und 569.00 569.00
06 SEALIZACION
06.01 PINTURA LINEAL CONTINUA m 2,817.22 2,817.22
06.02 PINTURA LINEAL DISCONTINUA m 486.00 486.00
06.03 PINTURA SOBRE PAVIMENTO (Simbolos y Flechas) m2 360.40 360.40
07 VARIOS
07.01 NIVELACION DE TAPA DE BUZONES und 16.00 16.00
07.02 REPOSICION DE CAJA DOMICILIARIA DE AGUA und 291.00 291.00
07.03 REPOSICION DE CAJA DOMICILIARIA DE DESAGUE und 291.00 291.00
07.04 MITIGACION DE IMPACTO AMBIENTAL glb 1.00 1.00
07.05 LIMPIEZA FINAL DE OBRA m2 23,256.69 23,256.69