Alameda de los Conquistadores N 409 - Dpto 104

PRESUPUESTO RESUMEN DE OBRA

OBRA BUNGALOWS SEDE PLAYA

UBICACIN: SAN ANTONIO - CAETE - LIMA

PROPIETARIO: RCC

FECHA: 05 DE SETIEMBRE 2016

1.00 PRESUPUESTO DE ARQUITECTURA. $725,244.46

VALOR DE VENTA: $725,244.46


GASTOS GENERALES 12.00%: $87,029.34
UTILIDAD 8.50%: $61,645.78
SUB TOTAL $873,919.57
IGV 18%. $157,305.52
COSTO TOTAL POR CADA BUNGALOW: $1,031,225.10

COSTO POR 02 BUNGALOW: $2,062,450.19


Jr. Alameda de los Conquistadores N 409 - Dpto 104

PRESUPUESTO DE OBRA
ARQUITECTURA

OBRA BUNGALOWS SEDE PLAYA

UBICACIN: SAN ANTONIO - CAETE - LIMA

PROPIETARIO: RCC

FECHA: MARZO 2017

PART. UBICACIN UND. CANT. P. UNIT. PARCIAL TOTAL

01.00 MUROS Y TABIQUES

09.01 MUROS KK DE SOGA. M2 1,546.85 50.00 77,342.43 77,342.43

02.00 COMPLEMENTOS

02.01 FORJADO GRADAS DE ESCALERA ML. 61.05 38.50 2,350.43 3,256.01

02.02 SARDINEL DE DUCHA ML. 25.80 35.10 905.58

03.00 REVOQUES 198,039.45

03.01 TARRAJEO DE MUROS INTERIORES M2 2,561.91 28.11 72,002.47

03.02 TARRAJEO DE MUROS EXTERIORES M2 495.38 31.82 15,760.39

03.03 TARRAJEO CIELO RASO M2 884.57 30.24 26,749.44

03.04 TARRAJEO FONDO DE ESCALERA M2 61.05 29.16 1,779.91

03.05 VESTIDURA DE DERRAMES MUROS ML 984.25 17.19 16,914.34

03.06 TARRAJEO DE COLUMNAS Y PLACAS M2 1,401.95 33.11 46,418.43

03.07 TARRAJEO DE VIGAS M2 542.40 33.95 18,414.47

04.00 PISOS Y CONTRAPISOS 134,292.15

04.01 CONTRAPISO DE 48 MM. M2 1,334.32 28.00 37,360.96

04.02 PISO PULIDO M2 218.70 32.49 7,105.56

04.03 PISO DE CERAMICO 0.44X0.44 m2 1,120.79 46.21 51,791.71

04.04 PISO DE CERAMICO 0.30x0.30 M2 68.09 68.00 4,630.12

04.05 ZOCALO CERAMICO 30X30 M2 411.65 56.58 23,291.32

04.06 CONTRAZOCALO CERAMICO H=0.10 ML. 525.32 19.25 10,112.49

05.00 COBERTURAS 2,852.60

05.01 COBERTURA LADRILLO PASTELERO ASENTADO C/MEZCA M2 67.12 42.50 2,852.60

06.00 CARPINTERIA DE MADERA 63,750.40

06.01 PUERTAS CONTRAPLACADAS UND 78.00 380.00 29,640.00

06.02 TECHO DE TERRAZA SOL Y SOMBRA M2. 41.98 280.00 11,754.40

06.03 CLOSET PARA DORMITORIOS h=2.45 ML. 62.10 360.00 22,356.00

06.04 MUEBLES DE COCINA ML 798.00

07.00 CARPINTERIA METALICA Y VIDRIOS EN ALUMINIO ANONIZADO NATURAL 177,248.17

07.01 m2. 443.50 292.71 129,814.67

VENTANA SISTEMA CORREDIZO SOBRE PAFLON DE AL DE 2" Y RODAMIENTO DE


BRONCE, GUIA SUPERIOR CON PORTAFELPA, BOTON DE CIERRE, CRISTAL
TEMPLADO INCOLORO DE 6 MM GUIA EMBUTIDAS EN ALFEIZAR Y DINTEL

M2.
07.02 26.35 410.00 10,803.50

MAMPARA DE ALUMINIO Y CRISTAL TEMPLADO INCOLORO 10MM. GUIA INFERIOR


Y SUPERIOR EMBUTIDA EN PISO Y DINTEL RESPECTIVAMENTE, PAFLON INFERIOR
DE 4" RODAMIENTOS DE BRONCE, TIRADOR EMBUTIDO CIRCULAR DE 3",
CERRADURA DE EMBUTIR A PISO

07.03 BARANDAS ESCALERA ML 244.20 150.00 36,630.00

08.00 CERRAJERIA 572.08


08.01 CERRADURA DE MANIJA, BOTON Y LLAVE, DE EMBUTIR, ACABADO ACERADO. UND 16.00 26.06 416.96
08.02 CERRADURA DE MANIJA PARA BAO, DE EMBUTIR, ACABADO ACERADO. UND 8.00 19.39 155.12

09.00 PINTURA LATEX EMPASTADO 67,891.18

09.01 PINTURA LATEX EN MUROS INTERIORES M2 2,561.91 10.00 25,619.10

09.02 PINTURA LATEX EN MUROS EXTERIORES M2 495.38 12.00 5,944.51

09.03 PINTURA LATEX EN COLUMNAS, VIGAS Y PLACAS M2 1,401.95 12.50 17,524.33

09.04 PINTURA LATEX EN ESCALERAS M2 12.50 0.00

09.05 PINTURA LATEX EN CIELO RASO M2 884.57 12.00 10,614.86

09.06 PINTURA ESMALTE COLOR BLANCO (PUERTAS) M2. 334.22 24.50 8,188.39

VALOR DE OBRA: $ 725,244.46


METRADOS ARQUITECTURA

OBRA PARTHENON
UBICACIN: SAN MIGUEL - LIMA
PROPIETARIO:
FECHA: MARZO 2017

PART. UBICACIN UND. CANT. LONG. ANCHO ALTO PARCIAL TOTAL. OBSERV.

01.00 OBRAS PROVISIONALES


01.01 OFICINA DE OBRA MES 3.00 3.00
01.03 VESTUARIOS Y SERVICIOS HIGIENICOS PARA OBRA MES 3.00 3.00
01.04 ALMACEN DE OBRA MES 3.00 3.00

02.00 TRABAJOS PRELIMINARES


02.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS VIAJE 2.00 2.00

04.00 SEGURIDAD DE OBRA


04.01 EQUIPOS DE PROTECCION INDIVIDUAL JGO. 60.00 60.00
04.02 EQUIPOS DE PROTECCION COLECTIVA GLB 1.00 1.00
04.03 SEALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 1.00
04.04 RECURSOS PARA RESPUESTAS ANTE EMERGENCIA EN SEGURIDAD GLB 1.00 1.00
Y SALUD DURANTE EL TRABAJO

05.00 TRABAJOS PERMANENTES


05.01 TRAZO, NIVELES Y REPLANTEO M2 1,583.25
PLANTA BAJA 283.64
PISO 1 192.29
PISO 2 204.64
PISO 3 204.64
PISO 4 204.64
PISO 5 204.64
AZOTEA 204.64
TECHOS 84.12

05.01 LIMPIEZA PERMANENTE EN OBRA MES 3.00 3.00


05.02 ELIMINACION DE DESMONTE DURANTE LA OBRA (2 VIAJES X SEMANAX 8M3 C/U) M3. 192.00 192.00

06.00 MUROS Y TABIQUES


06.01 MUROS KK DE SOGA. M2 1,546.85
PLANTA BAJA
Eje 1 1.00 3.00 0.15 3.00 9.00 144.28
Eje 2 1.00 3.00 0.15 0.40 1.20
1.00 3.00 0.15 3.00 9.00
1.00 2.08 0.10 2.65 5.51
Eje 3 1.00 1.80 0.15 2.15 3.87
1.00 2.20 0.15 2.15 4.73
1.00 1.98 0.15 2.65 5.25
1.00 1.13 0.15 2.65 2.99
1.00 5.05 0.10 2.65 13.38
Eje 3' 1.00 4.34 0.15 2.65 11.50
Eje 4 1.00 1.45 0.15 2.65 3.84
1.00 2.46 0.15 3.00 7.38
Calle Condesa 1.00 8.04 0.15 3.00 24.12
Eje A 1.00 2.50 0.15 3.00 7.50
Eje A' 1.00 1.45 0.10 2.65 3.84
Eje B' 1.00 0.30 0.10 2.65 0.80
1.00 1.45 0.10 2.65 3.84
1.00 3.15 0.15 3.00 9.45
1.00 5.69 0.15 3.00 17.07
PRIMER NIVEL
Eje 1 1.00 2.65 0.15 3.00 7.95 258.98
1.00 2.65 0.20 2.43 6.44
1.00 1.90 0.20 2.43 4.62
1.00 2.09 0.20 2.43 5.08
1.00 2.20 0.20 2.43 5.35
Inter 1-2 1.00 2.65 0.15 2.43 6.44
1.00 2.75 0.15 2.43 6.68
Eje 2 1.00 2.65 0.15 3.00 7.95
1.00 5.80 0.15 2.43 14.09
Inter 2-2' 1.00 1.75 0.10 2.43 4.25
Eje 2' 1.00 0.60 0.15 2.03 1.22
1.00 0.55 0.15 2.13 1.17
1.00 0.65 0.15 2.43 1.58
Inter 2'-3 1.00 2.48 0.15 2.43 6.03
1.00 1.25 0.15 2.43 3.04
1.00 1.50 0.15 2.43 3.65
1.00 2.75 0.15 2.43 6.68
1.00 2.20 0.10 2.43 5.35
Eje 3' 1.00 2.60 0.15 2.43 6.32
Eje 4 1.00 5.75 0.15 2.13 12.25
1.00 4.20 0.15 2.43 10.21
1.00 3.50 0.15 2.13 7.46
Eje A 1.00 5.18 0.15 3.00 15.54
1.00 0.50 0.15 2.43 1.22
Inter A-A' 1.00 2.65 0.10 2.43 6.44
Eje A' 1.00 2.00 0.15 2.43 4.86
1.00 3.78 0.15 2.43 9.19
1.00 1.20 0.15 2.43 2.92
Eje B 1.00 1.88 0.15 2.43 4.57
1.00 2.65 0.15 2.43 6.44
Inter B-B' 1.00 1.20 0.15 2.43 2.92
1.00 0.60 0.10 2.43 1.46
Eje C 1.00 1.93 0.15 2.43 4.69
1.00 1.70 0.15 1.23 2.09
Inter C-C' 1.00 4.68 0.15 2.43 11.37
Eje C' 1.00 2.65 0.15 2.43 6.44
Eje C'' 1.00 2.20 0.15 2.43 5.35
1.00 1.55 0.15 2.43 3.77
Inter C''-D 1.00 0.80 0.15 2.43 1.94
Eje D' 1.00 0.63 0.10 2.43 1.53
1.00 2.10 0.10 2.43 5.10
1.00 0.75 0.10 2.43 1.82
Eje E 1.00 1.70 0.15 0.93 1.58
1.00 1.52 0.15 2.43 3.69
1.00 4.85 0.15 2.43 11.79
2.00 0.90 0.15 2.13 3.83
1.00 1.35 0.15 2.03 2.74
1.00 0.90 0.15 2.13 1.92

SEGUNDO - TERCER - CUARTO NIVEL


Eje 1 3.00 1.90 0.20 2.43 13.85 694.58
3.00 2.80 0.20 2.43 20.41
3.00 1.50 0.20 2.43 10.94
Inter 1-2 3.00 2.65 0.15 2.43 19.32
3.00 2.80 0.15 2.43 20.41
Eje 2 3.00 2.80 0.15 3.00 25.20
3.00 1.80 0.15 2.43 13.12
Inter 2-2' 3.00 1.80 0.15 2.43 13.12
Eje 2' 3.00 1.35 0.15 0.93 3.77
3.00 1.20 0.15 2.43 8.75
Inter 2'-3 3.00 2.80 0.15 2.43 20.41
3.00 1.45 0.15 2.43 10.57
3.00 2.80 0.15 2.43 20.41
3.00 2.80 0.15 2.43 20.41
3.00 1.70 0.15 2.43 12.39
3.00 0.50 0.10 2.43 3.65
Eje 3 3.00 1.25 0.15 2.43 9.11
Eje 3' 3.00 2.60 0.15 2.43 18.95
Eje 4 3.00 5.95 0.15 2.13 38.02
3.00 4.20 0.15 2.43 30.62
3.00 4.00 0.15 2.13 25.56
Inter A-A' 3.00 2.65 0.10 2.43 19.32
Eje A' 3.00 1.45 0.15 2.43 10.57
3.00 3.78 0.15 2.43 27.56
3.00 0.50 0.15 2.43 3.65
Eje B 3.00 5.08 0.15 2.43 37.03
Inter B-C 3.00 1.15 0.15 2.43 8.38
3.00 0.60 0.10 2.43 4.37
Eje C 3.00 2.15 0.15 2.43 15.67
3.00 2.60 0.15 1.23 9.59
3.00 0.85 0.15 2.43 6.20
Eje C' 3.00 2.80 0.15 2.43 20.41
Eje C'' 3.00 2.38 0.15 2.43 17.35
3.00 2.85 0.15 2.43 20.78
Inter C''-D 3.00 0.85 0.15 2.43 6.20
Eje D' 3.00 0.70 0.15 2.43 5.10
3.00 2.10 0.15 2.43 15.31
3.00 1.25 0.15 2.43 9.11
3.00 1.30 0.15 2.43 9.48
Inter D-E' 3.00 3.33 0.15 2.43 24.28
Eje E 3.00 1.70 0.15 0.93 4.74
3.00 1.52 0.15 2.43 11.08
3.00 1.60 0.15 2.43 11.66
3.00 3.25 0.15 2.43 23.69
3.00 1.20 0.15 0.53 1.91
3.00 0.90 0.15 2.13 5.75
3.00 1.35 0.15 1.13 4.58
3.00 1.40 0.15 0.43 1.81

QUINTO NIVEL
Eje 1 1.00 1.90 0.20 2.43 4.62 231.53
1.00 2.80 0.20 2.43 6.80
1.00 1.50 0.20 2.43 3.65
Inter 1-2 1.00 2.65 0.15 2.43 6.44
1.00 2.80 0.15 2.43 6.80
Eje 2 1.00 2.80 0.15 3.00 8.40
1.00 1.80 0.15 2.43 4.37
Inter 2-2' 1.00 1.80 0.15 2.43 4.37
Eje 2' 1.00 1.35 0.15 0.93 1.26
1.00 1.20 0.15 2.43 2.92
Inter 2'-3 1.00 2.80 0.15 2.43 6.80
1.00 1.45 0.15 2.43 3.52
1.00 2.80 0.15 2.43 6.80
1.00 2.80 0.15 2.43 6.80
1.00 1.70 0.15 2.43 4.13
1.00 0.50 0.10 2.43 1.22
Eje 3 1.00 1.25 0.15 2.43 3.04
Eje 3' 1.00 2.60 0.15 2.43 6.32
Eje 4 1.00 5.95 0.15 2.13 12.67
1.00 4.20 0.15 2.43 10.21
1.00 4.00 0.15 2.13 8.52
Inter A-A' 1.00 2.65 0.10 2.43 6.44
Eje A' 1.00 1.45 0.15 2.43 3.52
1.00 3.78 0.15 2.43 9.19
1.00 0.50 0.15 2.43 1.22
Eje B 1.00 5.08 0.15 2.43 12.34
Inter B-C 1.00 1.15 0.15 2.43 2.79
1.00 0.60 0.10 2.43 1.46
Eje C 1.00 2.15 0.15 2.43 5.22
1.00 2.60 0.15 1.23 3.20
1.00 0.85 0.15 2.43 2.07
Eje C' 1.00 2.80 0.15 2.43 6.80
Eje C'' 1.00 2.38 0.15 2.43 5.78
1.00 2.85 0.15 2.43 6.93
Inter C''-D 1.00 0.85 0.15 2.43 2.07
Eje D' 1.00 0.70 0.15 2.43 1.70
1.00 2.10 0.15 2.43 5.10
1.00 1.25 0.15 2.43 3.04
1.00 1.30 0.15 2.43 3.16
Inter D-E' 1.00 3.33 0.15 2.43 8.09
Eje E 1.00 1.70 0.15 0.93 1.58
1.00 1.52 0.15 2.43 3.69
1.00 1.60 0.15 2.43 3.89
1.00 3.25 0.15 2.43 7.90
1.00 1.20 0.15 0.53 0.64
1.00 0.90 0.15 2.13 1.92
1.00 1.35 0.15 1.13 1.53
1.00 1.40 0.15 0.43 0.60

AZOTEA
Eje 1 1.00 2.06 0.20 2.43 5.01 217.49
1.00 2.85 0.20 2.43 6.93
1.00 1.45 0.20 2.30 3.34
Inter 1-2 1.00 1.65 0.15 2.43 4.01
1.00 0.65 0.15 2.43 1.58
Eje 2 1.00 1.35 0.15 1.03 1.39
1.00 1.80 0.15 2.30 4.14
1.00 1.05 0.15 2.43 2.55
Eje 2' 1.00 3.00 0.15 2.30 6.90
Inter 2'-3 1.00 3.50 0.15 2.43 8.51
1.00 2.65 0.15 2.43 6.44
Eje 3 1.00 2.50 0.15 2.30 5.75
1.00 2.55 0.15 1.20 3.06
1.00 1.40 0.15 2.43 3.40
Eje 3' 1.00 3.00 0.15 2.43 7.29
Eje 4 1.00 16.00 0.15 1.20 19.20
Eje A 1.00 8.00 0.20 2.30 18.40
Eje A' 1.00 6.43 0.15 2.43 15.62
Eje B 1.00 1.05 0.15 2.43 2.55
Inter B-C 1.00 2.10 0.15 2.43 5.10
Eje C 1.00 4.85 0.15 2.43 11.79
1.00 3.00 0.15 2.30 6.90
Eje C' 1.00 2.80 0.15 2.43 6.80
Eje C'' 1.00 4.50 0.15 2.43 10.94
Inter C''-D 1.00 2.30 0.15 2.43 5.59
1.00 5.20 0.15 2.30 11.96
Eje D' 1.00 4.01 0.15 2.43 9.74
1.00 2.40 0.15 1.20 2.88
Inter D-E' 1.00 1.65 0.15 2.43 4.01
Eje E 1.00 13.10 0.15 1.20 15.72
473.77
07.00 COMPLEMENTOS
07.01 FORJADO GRADAS DE ESCALERA ML. 61.05
ESCALERA 1 6.00 8.10 48.60
ESCALERA 2 1.00 6.60 6.60
ESCALERA 3 1.00 5.85 5.85

07.02 SARDINEL DE DUCHA ML. 25.80


PLANTA BAJA 1.00 1.20 0.10 0.35 1.20
PISO 1 3.00 1.20 0.10 0.35 3.60
1.00 0.90 0.10 0.35 0.90
PISO 2-3-4 9.00 1.20 0.10 0.35 10.80
3.00 0.90 0.10 0.35 2.70
PISO 5 3.00 1.20 0.10 0.35 3.60
1.00 0.90 0.10 0.35 0.90
AZOTEA 1.00 1.20 0.10 0.35 1.20
1.00 0.90 0.10 0.35 0.90

08.00 REVOQUES
08.01 TARRAJEO DE MUROS INTERIORES M2 CARAS 2,561.91
PLANTA BAJA
Eje 3 1.00 1.88 2.00 2.15 8.06 163.24
1.00 2.28 2.00 2.15 9.78
1.00 2.06 2.00 2.65 10.89
1.00 1.21 2.00 2.65 6.39
1.00 5.10 2.00 2.65 27.03
Eje 3' 1.00 4.42 2.00 2.65 23.40
Eje 4 1.00 1.45 2.00 2.65 7.69
Eje A' 1.00 1.45 2.00 2.65 7.69
Eje B 1.00 0.30 2.00 2.65 1.59
1.00 1.45 2.00 2.65 7.69
1.00 3.15 2.00 3.00 18.90
1.00 5.69 2.00 3.00 34.14
PRIMER NIVEL
Eje 1 1.00 2.65 1.00 3.00 7.95 452.90
1.00 2.65 2.00 2.43 12.88
1.00 2.00 1.00 2.43 4.86
1.00 2.09 1.00 2.43 5.08
1.00 2.20 1.00 2.43 5.35
Inter 1-2 1.00 2.65 2.00 2.43 12.88
1.00 2.75 2.00 2.43 13.37
Eje 2 1.00 2.65 2.00 3.00 15.90
1.00 5.80 2.00 2.43 28.19
Inter 2-2' 1.00 1.75 2.00 2.43 8.51
Eje 2' 1.00 0.60 2.00 2.03 2.44
1.00 0.55 2.00 2.13 2.34
1.00 0.65 2.00 2.43 3.16
Inter 2'-3 1.00 2.48 2.00 2.43 12.05
1.00 1.25 2.00 2.43 6.08
1.00 1.50 2.00 2.43 7.29
1.00 2.75 2.00 2.43 13.37
1.00 2.20 2.00 2.43 10.69
Eje 3' 1.00 2.60 2.00 2.43 12.64
Eje 4 1.00 5.75 2.00 2.13 24.50
1.00 4.20 2.00 2.43 20.41
1.00 3.50 2.00 2.13 14.91
Eje A 1.00 5.18 1.00 3.00 15.54
1.00 0.50 1.00 2.43 1.22
Inter A-A' 1.00 2.65 2.00 2.43 12.88
Eje A' 1.00 2.00 2.00 2.43 9.72
1.00 3.78 2.00 2.43 18.37
1.00 1.20 2.00 2.43 5.83
Eje B 1.00 1.88 2.00 2.43 9.14
1.00 2.65 2.00 2.43 12.88
Inter B-B' 1.00 1.20 2.00 2.43 5.83
1.00 0.60 2.00 2.43 2.92
Eje C 1.00 1.93 2.00 2.43 9.38
1.00 1.70 2.00 1.23 4.18
Inter C-C' 1.00 4.68 2.00 2.43 22.74
Eje C' 1.00 2.65 2.00 2.43 12.88
Eje C'' 1.00 2.20 2.00 2.43 10.69
1.00 1.55 2.00 2.43 7.53
Inter C''-D 1.00 0.80 2.00 2.43 3.89
Eje D' 1.00 0.63 2.00 2.43 3.06
1.00 2.10 2.00 2.43 10.21
1.00 0.75 2.00 2.43 3.65
Eje E 1.00 1.70 1.00 0.93 1.58
1.00 1.52 1.00 2.43 3.69
1.00 4.85 1.00 2.43 11.79
2.00 0.90 1.00 2.13 3.83
1.00 1.35 1.00 2.03 2.74
1.00 0.90 1.00 2.13 1.92

SEGUNDO - TERCER - CUARTO NIVEL


Eje 1 3.00 1.90 1.00 2.43 13.85 1,184.53
3.00 2.80 1.00 2.43 20.41
3.00 1.50 1.00 2.43 10.94
Inter 1-2 3.00 2.65 2.00 2.43 38.64
3.00 2.80 2.00 2.43 40.82
Eje 2 3.00 2.80 2.00 3.00 50.40
3.00 1.80 2.00 2.43 26.24
Inter 2-2' 3.00 1.80 2.00 2.43 26.24
Eje 2' 3.00 1.35 2.00 0.93 7.53
3.00 1.20 2.00 2.43 17.50
Inter 2'-3 3.00 2.80 2.00 2.43 40.82
3.00 1.45 2.00 2.43 21.14
3.00 2.80 2.00 2.43 40.82
3.00 2.80 2.00 2.43 40.82
3.00 1.70 2.00 2.43 24.79
3.00 0.50 2.00 2.43 7.29
Eje 3 3.00 1.25 2.00 2.43 18.23
Eje 3' 3.00 2.60 2.00 2.43 37.91
Eje 4 3.00 5.95 1.00 2.13 38.02
3.00 4.20 1.00 2.43 30.62
3.00 4.00 1.00 2.13 25.56
Inter A-A' 3.00 2.65 2.00 2.43 38.64
Eje A' 3.00 1.45 2.00 2.43 21.14
3.00 3.78 2.00 2.43 55.11
3.00 0.50 2.00 2.43 7.29
Eje B 3.00 5.08 2.00 2.43 74.07
Inter B-C 3.00 1.15 2.00 2.43 16.77
3.00 0.60 2.00 2.43 8.75
Eje C 3.00 2.15 2.00 2.43 31.35
3.00 2.60 2.00 1.23 19.19
3.00 0.85 2.00 2.43 12.39
Eje C' 3.00 2.80 2.00 2.43 40.82
Eje C'' 3.00 2.38 2.00 2.43 34.70
3.00 2.85 2.00 2.43 41.55
Inter C''-D 3.00 0.85 2.00 2.43 12.39
Eje D' 3.00 0.70 2.00 2.43 10.21
3.00 2.10 2.00 2.43 30.62
3.00 1.25 2.00 2.43 18.23
3.00 1.30 2.00 2.43 18.95
Inter D-E' 3.00 3.33 2.00 2.43 48.55
Eje E 3.00 1.70 1.00 0.93 4.74
3.00 1.52 1.00 2.43 11.08
3.00 1.60 1.00 2.43 11.66
3.00 3.25 1.00 2.43 23.69
3.00 1.20 1.00 0.53 1.91
3.00 0.90 1.00 2.13 5.75
3.00 1.35 1.00 1.13 4.58
3.00 1.40 1.00 0.43 1.81

QUINTO NIVEL
Eje 1 1.00 1.90 1.00 2.43 4.62 394.84
1.00 2.80 1.00 2.43 6.80
1.00 1.50 1.00 2.43 3.65
Inter 1-2 1.00 2.65 2.00 2.43 12.88
1.00 2.80 2.00 2.43 13.61
Eje 2 1.00 2.80 2.00 3.00 16.80
1.00 1.80 2.00 2.43 8.75
Inter 2-2' 1.00 1.80 2.00 2.43 8.75
Eje 2' 1.00 1.35 2.00 0.93 2.51
1.00 1.20 2.00 2.43 5.83
Inter 2'-3 1.00 2.80 2.00 2.43 13.61
1.00 1.45 2.00 2.43 7.05
1.00 2.80 2.00 2.43 13.61
1.00 2.80 2.00 2.43 13.61
1.00 1.70 2.00 2.43 8.26
1.00 0.50 2.00 2.43 2.43
Eje 3 1.00 1.25 2.00 2.43 6.08
Eje 3' 1.00 2.60 2.00 2.43 12.64
Eje 4 1.00 5.95 1.00 2.13 12.67
1.00 4.20 1.00 2.43 10.21
1.00 4.00 1.00 2.13 8.52
Inter A-A' 1.00 2.65 2.00 2.43 12.88
Eje A' 1.00 1.45 2.00 2.43 7.05
1.00 3.78 2.00 2.43 18.37
1.00 0.50 2.00 2.43 2.43
Eje B 1.00 5.08 2.00 2.43 24.69
Inter B-C 1.00 1.15 2.00 2.43 5.59
1.00 0.60 2.00 2.43 2.92
Eje C 1.00 2.15 2.00 2.43 10.45
1.00 2.60 2.00 1.23 6.40
1.00 0.85 2.00 2.43 4.13
Eje C' 1.00 2.80 2.00 2.43 13.61
Eje C'' 1.00 2.38 2.00 2.43 11.57
1.00 2.85 2.00 2.43 13.85
Inter C''-D 1.00 0.85 2.00 2.43 4.13
Eje D' 1.00 0.70 2.00 2.43 3.40
1.00 2.10 2.00 2.43 10.21
1.00 1.25 2.00 2.43 6.08
1.00 1.30 2.00 2.43 6.32
Inter D-E' 1.00 3.33 2.00 2.43 16.18
Eje E 1.00 1.70 1.00 0.93 1.58
1.00 1.52 1.00 2.43 3.69
1.00 1.60 1.00 2.43 3.89
1.00 3.25 1.00 2.43 7.90
1.00 1.20 1.00 0.53 0.64
1.00 0.90 1.00 2.13 1.92
1.00 1.35 1.00 1.13 1.53
1.00 1.40 1.00 0.43 0.60

AZOTEA
Eje 1 1.00 2.06 1.00 2.43 5.01 366.39
1.00 2.85 1.00 2.43 6.93
1.00 1.45 1.00 2.30 3.34
Inter 1-2 1.00 1.65 2.00 2.43 8.02
1.00 0.65 2.00 2.43 3.16
Eje 2 1.00 1.35 2.00 1.03 2.78
1.00 1.80 2.00 2.30 8.28
1.00 1.05 2.00 2.43 5.10
Eje 2' 1.00 3.00 2.00 2.30 13.80
Inter 2'-3 1.00 3.50 2.00 2.43 17.01
1.00 2.65 2.00 2.43 12.88
Eje 3 1.00 2.50 2.00 2.30 11.50
1.00 2.55 2.00 1.20 6.12
1.00 1.40 2.00 2.43 6.80
Eje 3' 1.00 3.00 2.00 2.43 14.58
Eje 4 1.00 16.00 1.00 1.20 19.20
Eje A 1.00 8.00 1.00 2.30 18.40
Eje A' 1.00 6.43 2.00 2.43 31.25
Eje B 1.00 1.05 2.00 2.43 5.10
Inter B-C 1.00 2.10 2.00 2.43 10.21
Eje C 1.00 4.85 2.00 2.43 23.57
1.00 3.00 2.00 2.30 13.80
Eje C' 1.00 2.80 2.00 2.43 13.61
Eje C'' 1.00 4.50 2.00 2.43 21.87
Inter C''-D 1.00 2.30 2.00 2.43 11.18
1.00 5.20 2.00 2.30 23.92
Eje D' 1.00 4.01 2.00 2.43 19.49
1.00 2.40 2.00 1.20 5.76
Inter D-E' 1.00 1.65 2.00 2.43 8.02
Eje E 1.00 13.10 1.00 1.20 15.72

08.02 TARRAJEO DE MUROS EXTERIORES M2 495.38

PLANTA BAJA
Eje 1 1.00 3.00 2.00 3.00 18.00 88.42
Eje 2 1.00 3.00 2.00 0.40 2.40
1.00 3.00 2.00 3.00 18.00
1.00 2.08 2.00 2.65 11.02
Eje 4 1.00 2.46 2.00 3.00 7.38
Calle Condesa 1.00 8.04 2.00 3.00 24.12
Eje A 1.00 2.50 2.00 3.00 7.50

PRIMER NIVEL
Eje 1 1.00 2.65 1.00 3.00 7.95 65.54
1.00 2.00 1.00 2.43 4.86
1.00 2.20 1.00 2.43 5.35
1.00 2.09 1.00 2.43 5.08
Eje A 1.00 5.18 1.00 3.00 15.54
1.00 0.50 1.00 2.43 1.22
Eje E 1.00 1.70 1.00 0.93 1.58
1.00 1.52 1.00 2.43 3.69
1.00 4.85 1.00 2.43 11.79
2.00 0.90 1.00 2.13 3.83
1.00 1.35 1.00 2.03 2.74
1.00 0.90 1.00 2.13 1.92

SEGUNDO - TERCER - CUARTO NIVEL


Eje 1 3.00 1.90 1.00 2.43 13.85 204.62
3.00 2.80 1.00 2.43 20.41
3.00 1.50 1.00 2.43 10.94
Eje 4 3.00 5.95 1.00 2.13 38.02
3.00 4.20 1.00 2.43 30.62
3.00 4.00 1.00 2.13 25.56
Eje E 3.00 1.70 1.00 0.93 4.74
3.00 1.52 1.00 2.43 11.08
3.00 1.60 1.00 2.43 11.66
3.00 3.25 1.00 2.43 23.69
3.00 1.20 1.00 0.53 1.91
3.00 0.90 1.00 2.13 5.75
3.00 1.35 1.00 1.13 4.58
3.00 1.40 1.00 0.43 1.81
QUINTO NIVEL
Eje 1 1.00 1.90 1.00 2.43 4.62 68.21
1.00 2.80 1.00 2.43 6.80
1.00 1.50 1.00 2.43 3.65
Eje 4 1.00 5.95 1.00 2.13 12.67
1.00 4.20 1.00 2.43 10.21
1.00 4.00 1.00 2.13 8.52
Eje E 1.00 1.70 1.00 0.93 1.58
1.00 1.52 1.00 2.43 3.69
1.00 1.60 1.00 2.43 3.89
1.00 3.25 1.00 2.43 7.90
1.00 1.20 1.00 0.53 0.64
1.00 0.90 1.00 2.13 1.92
1.00 1.35 1.00 1.13 1.53
1.00 1.40 1.00 0.43 0.60
AZOTEA
Eje 1 1.00 2.06 1.00 2.43 5.01 68.59
1.00 2.85 1.00 2.43 6.93
1.00 1.45 1.00 2.30 3.34
Eje 4 1.00 16.00 1.00 1.20 19.20
Eje A 1.00 8.00 1.00 2.30 18.40
Eje E 1.00 13.10 1.00 1.20 15.72

08.03 TARRAJEO CIELO RASO M2 884.57


PLANTA BAJA 1.00 2.60 7.14 18.56 160.36
1.00 2.50 4.30 10.75
1.00 3.35 7.70 25.80
1.00 3.45 4.30 14.84
1.00 2.85 7.55 21.52
1.00 1.50 2.50 3.75
1.00 1.60 2.45 3.92
1.00 5.60 7.44 41.66
1.00 4.55 4.30 19.57

PISO 1 1.00 2.60 2.70 7.02 134.36


1.00 2.50 4.70 11.75
1.00 3.35 6.13 20.54
1.00 3.45 4.70 16.22
1.00 2.85 2.85 8.12
1.00 1.50 2.90 4.35
1.00 2.00 2.45 4.90
1.00 5.50 7.44 40.92
1.00 4.95 4.15 20.54

PISO 2-3-4 3.00 134.36 403.07 403.07

PISO 5 1.00 2.60 2.70 7.02 148.03


1.00 2.50 4.70 11.75
1.00 3.35 6.13 20.54
1.00 0.95 1.80 1.71
1.00 3.45 4.70 16.22
1.00 2.85 2.85 8.12
1.00 1.75 2.90 5.08
1.00 4.70 2.45 11.52
1.00 5.50 7.44 40.92
1.00 4.95 4.15 20.54
1.00 1.40 3.30 4.62
AZOTEA 1.00 2.15 2.77 5.96 38.76
1.00 3.03 3.35 10.15
1.00 1.05 2.80 2.94
1.00 4.95 3.45 17.08
1.00 1.60 1.65 2.64

08.04 TARRAJEO FONDO DE ESCALERA M2 61.05


1.00 61.05

08.05 VESTIDURA DE DERRAMES MUROS ML 984.25


PLANTA BAJA
Ventanas
VA - 1 2.00 2.20 0.30 10.00 83.55
V-2 2.00 1.00 1.80 11.20
V-1 2.00 1.45 1.80 13.00
VA - 1 2.00 0.60 0.30 3.60

Puertas
P - 1a 5.00 0.70 2.10 24.50
P-1 1.00 0.70 2.10 4.90
0.00
Mamparas
M-1 1.00 3.00 2.60 8.20
M-2 1.00 2.95 2.60 8.15

PRIMER PISO
Ventanas
V-11 1.00 0.60 1.40 4.00 146.10
VA-2 1.00 0.50 0.30 1.60
VA-3 1.00 0.55 0.30 1.70
V-10 1.00 5.25 1.30 13.10
V-9 1.00 1.30 1.20 5.00
V-8 1.00 1.20 1.50 5.40
VA-1 2.00 0.60 0.30 3.60
V-7 1.00 0.25 1.20 2.90
V-3 1.00 1.70 1.60 6.60
V-4 2.00 0.90 1.30 8.80
V-5 1.00 1.35 1.40 5.50
V-6 1.00 4.40 1.30 11.40

Puertas
P-7 6.00 0.90 2.10 30.60
P-1 5.00 0.70 2.10 24.50
P-6 2.00 1.00 2.10 10.40

Mamparas
M-3 2.00 1.30 2.10 11.00

PISO 2-3-4
Ventanas
VA-2 3.00 1.00 0.50 0.30 4.80 516.90
VA-3 3.00 1.00 0.55 0.30 5.10
V-9 3.00 3.00 1.30 1.20 45.00
V-8 3.00 1.00 1.20 1.50 16.20
VA-1 3.00 1.00 0.60 0.30 5.40
V-5 3.00 2.00 1.35 1.40 33.00
V-6 3.00 1.00 4.40 1.30 34.20
V-16 3.00 1.00 0.65 1.50 12.90
V-12 3.00 1.00 1.70 1.90 21.60
V-14 3.00 1.00 5.40 2.00 44.40
V-12 3.00 1.00 1.70 1.90 21.60
V-15 3.00 1.00 5.25 2.00 43.50

Puertas
P-7 3.00 6.00 0.90 2.10 108.00
P-1 3.00 5.00 0.70 2.10 84.00
P-6 3.00 2.00 1.00 2.10 37.20

PISO 5
Ventanas
VA-2 1.00 0.50 0.30 1.60 161.60
VA-3 1.00 0.55 0.30 1.70
V-9 3.00 1.30 1.20 15.00
V-8 1.00 1.20 1.50 5.40
VA-1 2.00 0.60 0.30 3.60
V-5 2.00 1.35 1.40 11.00
V-6 1.00 4.40 1.30 11.40
V-16 1.00 0.65 1.50 4.30
V-12 1.00 1.70 1.90 7.20
V-14 1.00 5.40 2.00 14.80
V-13 1.00 1.90 1.20 6.20
V-15 1.00 5.25 2.00 14.50

Puertas
P-7 4.00 0.90 2.10 24.00
P-1 4.00 0.70 2.10 22.40
P-6 2.00 1.00 2.10 12.40
P-8 1.00 0.95 2.10 6.10

AZOTEA
Ventanas
VA-2 1.00 0.50 0.30 1.60 76.10
V-9 3.00 1.30 1.20 15.00
VA-1 1.00 0.60 0.30 1.80
V-5 1.00 1.35 1.40 5.50
V-17 1.00 1.85 1.40 6.50
V-18 1.00 1.05 1.40 4.90

Puertas
P-7 3.00 0.90 2.10 18.00
P-1 2.00 0.70 2.10 11.20
P-9 2.00 0.80 2.10 11.60

08.06 TARRAJEO DE COLUMNAS Y PLACAS M2 1401.95


COLUMNAS
C-1 2.00 0.60 0.25 18.68 63.51
C-2 1.00 0.60 0.25 18.68 31.76
C-3 1.00 0.50 0.25 18.68 28.02
C-4 1.00 0.40 0.40 18.68 29.89
C-5 2.00 1.50 0.15 18.68 123.29
C-6 2.00 0.60 0.25 18.68 63.51
C-7 1.00 0.50 0.15 18.68 24.28

PLACAS
P-1 1.00 7.55 0.20 18.68 289.54
P-2 1.00 4.85 0.20 18.68 188.67
P-3 1.00 3.20 0.20 18.68 127.02
1.00 2.05 0.15 18.68 82.19
1.00 3.20 0.20 18.68 127.02
1.00 2.45 0.25 18.68 100.87
1.00 1.60 0.25 18.68 69.12

MUROS
CORTE 2-2 1.00 3.42 0.20 2.70 19.55
1.00 1.40 0.20 2.70 8.64
1.00 0.73 0.20 2.70 5.02
CORTE 3-3 1.00 0.95 0.20 2.70 6.21
MURO DESNIVEL 1.00 2.50 0.15 1.10 5.83

CISTERNA
MURO M-6 1.00 1.60 5.00 8.00

08.07 TARRAJEO DE VIGAS M2 542.40


ENCOFRADO PLANTA BAJA
VIGA V-1 1.00 0.25 0.53 7.69 7.00 84.00
VIGA V-2 1.00 0.25 0.53 7.55 6.87
VIGA V-3 1.00 0.25 0.53 7.43 6.76
VIGA V-4 1.00 0.25 1.00 11.32 20.94
VIGA V-5 1.00 0.25 0.53 6.00 5.46
VIGA V-6 1.00 0.15 1.00 15.30 26.78
VIGA V-A 1.00 0.50 0.00 2.80 0.28
CORTE 1-1 0.00
CORTE 2-2 3.00 0.25 0.00 4.30 3.23
CORTE 3-3 4.00 0.25 0.00 3.40 3.40
CORTE 4-4 1.00 0.15 0.60 1.60 0.24
CORTE 5-5 0.00
CORTE 6-6 1.00 0.25 0.00 9.60 2.40
CORTE 7-7 1.00 0.25 0.00 2.60 0.65
CORTE 8-8 0.00

ENCOFRADO PISO 1 AL 4
VIGA V-5 1.00 0.25 0.53 6.26 5.70 339.98
VIGA V-9 1.00 0.28 0.53 12.50 11.69
VIGA V-3 1.00 0.25 0.53 7.44 6.77
VIGA V-10 1.00 0.25 0.53 5.00 4.55
VIGA V-11 1.00 0.25 0.53 12.42 11.30
VIGA V-12 1.00 0.25 0.63 15.50 17.21
VIGA V-13 1.00 0.25 0.53 8.18 7.44
VIGA - B 1.00 0.50 5.50 0.55
CORTE 1-1 2.00 0.15 2.80 0.84
CORTE 2-2 3.00 0.25 18.00 13.50
CORTE 3-3 2.00 0.25 3.40 1.70
CORTE 4-4 1.00 0.15 1.60 0.24
CORTE 5-5 0.00
CORTE 6-6 1.00 0.35 5.50 1.93
CORTE 7-7 0.00
CORTE 8-8 1.00 0.25 0.90 0.23
CORTE 9-9 1.00 0.20 6.80 1.36

ENCOFRADO PISO 5
VIGA V-15 1.00 0.25 0.53 4.16 3.79 76.12
VIGA V-9 1.00 0.25 0.53 12.50 11.38
VIGA V-3 1.00 0.25 0.53 7.44 6.77
VIGA V-10 1.00 0.25 0.53 3.70 3.37
VIGA V-11 1.00 0.25 0.53 12.42 11.30
VIGA V-14 1.00 0.25 0.53 5.50 5.01
VIGA V-13 1.00 0.25 0.53 8.20 7.46
VIGA V-12 1.00 0.25 0.53 15.50 14.11
VIGA V-16 1.00 0.25 0.53 6.10 5.55
VIGA - C 1.00 0.50 5.50 0.55
CORTE 1-1 2.00 0.15 2.80 0.84
CORTE 2-2 1.00 0.25 4.20 1.05
CORTE 3-3 1.00 0.25 2.45 0.61
CORTE 4-4 1.00 0.15 1.60 0.24
CORTE 11-11 1.00 0.25 2.30 0.58
CORTE 12-12 1.00 0.40 3.30 1.32
CORTE 7-7 1.00 0.25 3.40 0.85
CORTE 9-9 1.00 0.20 6.80 1.36

ENCOFRADO AZOTEA
VIGA V-17 1.00 0.25 0.53 8.44 7.68 42.30
VIGA V-18 1.00 0.25 0.53 8.06 7.33
VIGA V-19 1.00 0.25 0.53 7.44 6.77
VIGA V-20 1.00 0.25 0.53 5.00 4.55
CORTE 3-3 1.00 0.25 6.00 1.50
CORTE 4-4 1.00 0.15 0.60 1.60 1.52
CORTE 13-13 1.00 0.50 0.60 8.80 11.44
CORTE 8-8 1.00 0.25 6.00 1.50

09.00 PISOS Y CONTRAPISOS M2 1,334.32


09.01 CONTRAPISO DE 48 MM.
PLANTA BAJA
ESTACIONAMIENTOS 1.00 271.00 271.00
PRIMER NIVEL
AREA 1.00 183.32 183.32
SEGUNDO AL CUARTO NIVEL
AREA 3.00 176.00 528.00
QUINTO NIVEL
AREA 1.00 176.00 176.00
AZOTEA
AREA 1.00 176.00 176.00

09.02 PISO PULIDO


PLANTA BAJA 218.70
AREA 1.00 218.70 218.70

09.03 PISO DE CERAMICO 0.44X0.44 M2 1,120.79


PLANTA BAJA 1.00 50.00 50.00
PRIMER NIVEL 1.00 171.85 171.85
SEGUNDO AL CUARTO NIVEL 3.00 163.96 491.88
QUINTO NIVEL 1.00 164.08 164.08
AZOTEA 1.00 169.72 169.72
ESCALERA 1.00 73.26 73.26

09.04 PISO DE CERAMICO 0.30x0.30 M2 68.09


PLANTA BAJA 1.00 2.30 2.30
PRIMER NIVEL 1.00 11.47 11.47
SEGUNDO AL CUARTO NIVEL 3.00 12.04 36.12
QUINTO NIVEL 1.00 11.92 11.92
AZOTEA 1.00 6.28 6.28

09.05 ZOCALO CERAMICO 30X30 M2 411.65


PLANTA BAJA 1.00 5.98 2.70 16.15
PRIMER NIVEL 1.00 29.02 2.43 70.52
SEGUNDO AL CUARTO NIVEL 3.00 29.82 2.43 217.39
QUINTO NIVEL 1.00 29.52 2.43 71.73
AZOTEA 1.00 14.76 2.43 35.87

09.06 CONTRAZOCALO CERAMICO H=0.10 ML. 525.32


LONGITUD 1.00 437.77 525.32

10.00 COBERTURAS
10.01 COBERTURA LADRILLO PASTELERO ASENTADO C/MEZCA M2 67.12
M2. 1.00 67.12

11.00 CARPINTERIA DE MADERA


11.01 PUERTAS CONTRAPLACADAS M2. 167.11
P-1 26.00 0.70 2.10 38.22
P - 1a 4.00 0.70 2.10 5.88
P-2 1.00 3.15 2.30 7.25
P-3 1.00 5.40 2.30 12.42
P-4 1.00 3.00 2.30 6.90
P-5 1.00 5.00 2.30 11.50
P - 6 10.00 1.00 2.10 21.00
P - 7 31.00 0.90 2.10 58.59
P - 8 1.00 0.95 2.10 2.00
P - 9 2.00 0.80 2.10 3.36
78.00

11.02 MUEBLE DE COCINA ML 12.00


4.00 3.00 12.00

11.03 TECHO DE TERRAZA SOL Y SOMBRA M2. 41.98


1.00 1.00 1.00 41.98

11.08 CLOSET PARA DORMITORIOS h=2.43 ML. 62.10


PRIMER NIVEL 1.00 2.35 2.35
1.00 2.45 2.45
1.00 1.50 1.50
1.00 2.00 2.00
1.00 2.50 2.50
SEGUNDO AL CUARTO NIVEL 3.00 2.35 7.05
3.00 1.55 4.65
3.00 2.45 7.35
3.00 2.00 6.00
3.00 2.50 7.50
3.00 1.55 4.65
QUINTO NIVEL 1.00 2.35 2.35
1.00 1.60 1.60
1.00 2.00 2.00
1.00 2.50 2.50
1.00 1.60 1.60
AZOTEA 1.00 2.70 2.70
1.00 1.35 1.35

07.00 CARPINTERIA METALICA EN ALUMINIO ANONIZADO NATURAL


07.01 VENTANA SISTEMA CORREDIZO SOBRE PAFLON DE AL DE 2" Y RODAMIENTO DE BRONCE, GUIA SUPERIOR m2. 443.50
CON PORTAFELPA, BOTON DE CIERRE, CRISTAL TEMPLADO INCOLORO DE 6 MM GUIA EMBUTIDAS EN
ALFEIZAR Y DINTEL

VA - 1 m2. 13.00 0.60 0.30 23.40


VA - 2 m2. 6.00 0.50 0.30 9.60
VA - 3 m2. 5.00 0.55 0.30 8.50
VA - 4 m2. 3.00 0.95 1.50 14.70
V-1 m2. 2.00 1.80 1.45 13
V-2 m2. 2.00 1.80 1.00 11.2
V-3 m2. 1.00 1.50 1.70 6.4
V-4 m2. 2.00 1.30 0.90 8.8
V-5 m2. 1.00 1.40 1.35 5.5
V-6 m2. 1.00 1.30 4.40 11.4
V-7 m2. 1.00 1.50 0.25 3.5
V-8 m2. 5.00 1.50 1.20 27
V-9 m2. 15.00 1.50 1.30 84
V-10 m2. 1.00 1.30 5.25 13.1
V-11 m2. 1.00 1.40 0.60 4
V-12 m2. 4.00 1.90 1.70 28.8
V-13 m2. 4.00 1.90 1.20 24.8
V-14 m2. 4.00 2.00 5.40 59.2
V-15 m2. 4.00 2.00 5.25 58
V-16 m2. 4.00 1.50 0.65 17.2
V-17 m2. 1.00 1.40 1.85 6.5
V-18 m2. 1.00 1.40 1.05 4.9

07.02 MAMPARA DE ALUMINIO Y CRISTAL TEMPLADO INCOLORO 10MM. GUIA INFERIOR Y SUPERIOR EMBUTIDA EN M2. 26.35
PISO Y DINTEL RESPECTIVAMENTE, PAFLON INFERIOR DE 4" RODAMIENTOS DE BRONCE, TIRADOR
EMBUTIDO CIRCULAR DE 3", CERRADURA DE EMBUTIR A PISO

M-1 1.00 3.00 2.60 8.20


M-2 1.00 2.95 2.10 7.15
M-3 2.00 1.30 2.10 11.00

07.03 BARANDA DE ESCALERA ML 244.20


4.00 61.05

13.00 CERRAJERIA
13.01 CERRADURA DE MANIJA, BOTON Y LLAVE, DE EMBUTIR, ACABADO ACERADO. UND 16.00 16.00 16.00
13.02 CERRADURA DE MANIJA PARA BAO, DE EMBUTIR, ACABADO ACERADO. UND 8.00 8.00 8.00

14.00 PINTURA LATEX EMPASTADO


14.01 PINTURA LATEX EN MUROS INTERIORES M2 2561.91
Area 1.00 2561.91

14.02 PINTURA LATEX EN MUROS EXTERIORES M2 495.38


Area 1.00 495.38

14.03 PINTURA LATEX EN COLUMNAS, VIGAS Y PLACAS M2 1401.95


AREA 1.00 1401.95

14.04 PINTURA LATEX EN CIELO RASO M2 884.57


AREA 1.00 884.57

14.05 PINTURA ESMALTE COLOR BLANCO (PUERTAS) M2. CARAS 334.22


AREA 1.00 1.00 2.00 1.00 167.11