Title Commissioning of the First Klystron-Based X-Band Power Source at CERN
Author(s) Kovermann, J (CERN) ; Catalan-Lasheras, N (CERN) ; Curt, S (CERN) ; Doebert, S (CERN) ; Naon, M (CERN) ; McMonagle, G (CERN) ; Paju, E (CERN) ; Rey, S (CERN) ; Riddone, G (CERN) ; Schirm, K (CERN) ; Syratchev, I (CERN) ; Timeo, L (CERN) ; Wuensch, W (CERN) ; Hamdi, A (Saclay) ; Peauger, FF (Saclay) ; Eichner, J (SLAC) ; Haase, A (SLAC) ; Sprehn, D (SLAC)
Publication 2012
Imprint 20 May 2012
Number of pages 3
In: Conf. Proc. C1205201 (2012) pp.THPPC060
In: 3rd International Particle Accelerator Conference, New Orleans, LA, USA, 20 - 25 May 2012, pp.3428
Subject category Accelerators and Storage Rings
Accelerator/Facility, Experiment CLIC
Abstract A new klystron based X-band rf power source operating at 11.994 GHz has been installed and started to be commissioned at CERN in collaboration with CEA Saclay and SLAC for CLIC accelerating structure tests. The system comprises a solid state high voltage modulator, an XL5 klystron developed by SLAC, a cavity based SLED type pulse compressor, the necessary low level rf system including rf diagnostics and interlocks and the surrounding vacuum, cooling and controls infrastructure. The system is designed to produce up to 50 MW rf pulses of 1500 ns pulse width and 50 Hz repetition rate. After pulse compression, up to 100 MW of rf power at 250 ns pulse width will be available in the structure test bunker. This paper describes in more detail this setup and the process of commissioning which is necessary to arrive at the design performance.
Copyright/License publication: (License: CC-BY)

Email contact: [email protected]


 Запись создана 2012-07-05, последняя модификация 2024-10-25


%(x_sitename) ссылка:
Загрузка полного текстаPublished version from JaCoW