1.
HIE-ISOLDE SC Linac progress and commissioning in 2016 / Venturini Delsolaro, Walter (CERN) ; Bravin, Enrico (CERN) ; Delruelle, Nicolas (CERN) ; Elias, Michal (CERN) ; Fadakis, Eleftherios (CERN) ; Ferreira Somoza, Jose (CERN) ; Formenti, Fabio (CERN) ; Fraser, Matthew (CERN) ; Gayde, Jean-Christophe (CERN) ; Guillotin, Nicolas (CERN) et al.
After the first successful physics run with radioactive ion beams at HIE ISOLDE, in October 2015 [1], the staged deployment of the linac continued in 2016 by adding a second cryomodule and by refurbishing the first one. During the physics run with one cryomodule, the second cryomodule was being assembled. [...]
CERN-ACC-2017-351.- 2017 - 5 p. - Published in : 10.18429/JACoW-LINAC2016-WE1A05 Fulltext: PDF;
In : 28th Linear Accelerator Conference, East Lansing, Michigan, 25 - 30 Sep 2016, pp.WE1A05
2.
Status of Radioactive Ion Beam Post-Acceleration at CERN-ISOLDE / Kadi, Yacine (CERN) ; Andreazza, William (CERN) ; Bauche, Jeremie (CERN) ; Behrens, Antje (CERN) ; Bernardes, Ana (CERN) ; Ferreira Somoza, Jose (CERN) ; Formenti, Fabio (CERN) ; Fraser, Matthew (CERN) ; Garcia Borge, Maria (CERN) ; Guillotin, Nicolas (CERN) et al.
The HIE-ISOLDE project* (High Intensity and Energy ISOLDE) reached an important milestone in September 2016 when the first physics run was carried out with radioactive beams at 6 MV/m. This is the first stage in the upgrade of the REX post-accelerator, whereby the energy of the radioactive ion beams was increased from 3 to 5.5 MeV per nucleon. [...]
CERN-ACC-2017-247.- 2017 - 4 p. - Published in : 10.18429/JACoW-IPAC2017-WEOAA2 Fulltext: PDF;
In : 8th International Particle Accelerator Conference, Copenhagen, Denmark, 14 - 19 May 2017, pp.WEOAA2
3.
Status of the SRF systems at HIE-ISOLDE / Venturini Delsolaro, Walter (CERN) ; Arnaudon, Luca (CERN) ; Artoos, Kurt (CERN) ; Bertone, Caterina (CERN) ; Bousquet, Jean-Alexandre (CERN) ; Delruelle, Nicolas (CERN) ; Elias, Michal (CERN) ; Ferreira Somoza, Jose (CERN) ; Formenti, Fabio (CERN) ; Gayde, Jean-Christophe (CERN) et al.
The HIE-ISOLDE project has been approved by CERN in 2009 and gained momentum after 2011. The final energy goal of the upgrade is to boost the radioactive beams of REX-ISOLDE from the present 3 MeV/u up to 10 MeV/u for A/q up to 4.5. [...]
2015 - 7 p. - Published in : 10.18429/JACoW-SRF2015-TUBA01 Fulltext: PDF;
In : 17th International Conference on RF Superconductivity, Whistler, Canada, 13 - 18 Sep 2015, pp.TUBA01
4.
Upgrade of the CERN Superconducting Magnet Test Facility / Bajko, Marta (CERN) ; Benda, Vladislav (CERN) ; Bottura, Luca (CERN) ; Broche, Alexandre Joel (CERN) ; Formenti, Fabio (CERN) ; Giannelli, Sebastiano (CERN) ; Giloux, Christian (CERN) ; Kosmicki, Antoine (CERN) ; Goncalves Perez, Consuelo (CERN) ; Perez-Duenas, E (CERN) et al.
Abstract: The superconducting magnet test facility at CERN has hosted the series test of the majority of the LHC magnets. The facility has evolved, and is presently divided in two main areas: a vertical test facility, equipped with three vertical cryostats, and a horizontal test facility, with ten feedboxes for test of cryostated magnets in horizontal position. [...]
2017 - 7 p. - Published in : IEEE Trans. Appl. Supercond. 27 (2017) 9500307
In : Applied Superconductivity Conference, Denver, CO, USA, 4 - 9 Sep 2016, pp.9500307
5.
Status of the HIE-ISOLDE Linac / Venturini Delsolaro, Walter (CERN) ; Alberty, Luis (CERN) ; Arnaudon, Luca (CERN) ; Artoos, Kurt (CERN) ; Bauche, Jeremie (CERN) ; Bernardes, Ana (CERN) ; Bousquet, Jean-Alexandre (CERN) ; Bravin, Enrico (CERN) ; Calatroni, Sergio (CERN) ; Cantero, Esteban (CERN) et al.
The HIE-ISOLDE project aims at increasing the energy of the radioactive beams (RIB) of REX-ISOLDE from the present 3 MeV/u up to 10 MeV/u for A/q up to 4.5. This will be accomplished by means of a new superconducting linac, based on independently phased quarter wave resonators using the Nb sputtering on copper technology, and working at 101.28 MHz [...]
CERN-ACC-2014-376.- 2014 - 6 p. - Published in : (2014) , pp. THIOA03 Fulltext: thioa03_2 - PDF; thioa03 - PDF; External link: JACoW server
In : 27th Linear Accelerator Conference, Geneva, Switzerland, 31 Aug - 5 Sep 2014, pp.THIOA03
6.
The management of large cabling campaigns during the Long Shutdown 1 of LHC / Meroli, Stefano (CERN) ; Machado, Simao (CERN) ; Formenti, Fabio (CERN) ; Frans, Marten (CERN) ; Guillaume, Jean Claude (CERN) ; Ricci, Daniel (CERN)
The Large Hadron Collider at CERN entered into its first 18 month-long shutdown period in February 2013. During this period the entire CERN accelerator complex will undergo major consolidation and upgrade works, preparing the machines for LHC operation at nominal energy (7 TeV/beam). [...]
CERN-OPEN-2014-042.- Geneva : CERN, 2014 - 12 p. - Published in : JINST 9 (2014) C03042 Article: PDF; IOP Open Access article: PDF;
In : Topical Workshop on Electronics for Particle Physics, Perugia, Italy, 23 - 27 Sep 2013, pp.C03042

Zobacz też: podobne nazwiska autorów
179 Formenti, F
13 Formenti, F.
Czy powiadomić Cię o nowych wynikach dla tego wyszukiwania?
Ustaw własny alert email lub zaprenumeruj RSS feed.
Jeżeli nie znaleziono tego czego szukasz, spróbuj szukać na innych serwerach:
Formenti, Fabio w Amazon
Formenti, Fabio w CERN EDMS
Formenti, Fabio w CERN Intranet
Formenti, Fabio w CiteSeer
Formenti, Fabio w Google Books
Formenti, Fabio w Google Scholar
Formenti, Fabio w Google Web
Formenti, Fabio w IEC
Formenti, Fabio w IHS
Formenti, Fabio w INSPIRE
Formenti, Fabio w ISO
Formenti, Fabio w KISS Books/Journals
Formenti, Fabio w KISS Preprints
Formenti, Fabio w NEBIS
Formenti, Fabio w SLAC Library Catalog
Formenti, Fabio w Scirus