Saudi Aramco Typical Inspection Plan
Saudi Aramco Typical Inspection Plan
Saudi Aramco Typical Inspection Plan
00 30-Jun-17
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
Pressure Testing of Tanks (Atmospheric & Low Pressure) SATIP-A-004-06 30-Oct-17 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
1.0 DOCUMENT REVIEW SPECIAL PROCESS (PRESSURE TESTING) REQUIRES BEST QUALITY PRACTICE, CPI & EFFICIENT METHODS IN PROCEDURES. PROPOSE BEST METHODS
2.1 Verify Test Medium (Water Quality) SAIC-A-2008 SAIC-A-2008 RH R Use SATR-A-2014 & SAIC-A-007 requirements
3.0 APPLICATION
Test Preparation & Verification of Testing Use SATR-A-2001, A-2002, SATR-A-2003, SATR-A-
3.3 SAIC-A-2009 SAIC-A-2009 H W
equipment (incl safety reqmts) 2004, SATR-A-2005, & SATR-A-2006
3.5 Filling & Pressurization SAIC-A-2020 SAIC-A-2020 W W Use SAIC-A-2020 for Pneumatic test.
Leak Test (after Pneumatic Testing) at 5- SAIC-A-2024, SAIC-A-2024, Use SATR-A-2010 - In conjunction with SATIP-A-004-05
3.7 H H
10 psig SAIC-A-2023 SAIC-A-2023 as applicable.
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
Pressure Testing of Tanks (Atmospheric & Low Pressure) SATIP-A-004-06 30-Oct-17 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
1
of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3
representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative
4
in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H 100% Hold Point for QC Inspection or Test. R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
###
###