Saudi Aramco Typical Inspection Plan

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 10
At a glance
Powered by AI
The document outlines Saudi Aramco's typical inspection plan and procedures for pressure testing of atmospheric and low pressure tanks.

The document provides inspection responsibilities and requirements for contractors to follow when performing pressure testing of tanks for Saudi Aramco.

The main steps involved in pressure testing of tanks include: document review, material receiving, pre-test inspection, cleaning, filling and pressurization, visual inspection at test pressure, leak testing, de-pressurization and disposal, and lay-up.

SAUDI ARAMCO ID/PIEU -30-Oct-2017 -REV. 2017.06.00(Standards Cutoff -June 30, 2017) Rev.2017.06.

00 30-Jun-17

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Pressure Testing of Tanks (Atmospheric & Low Pressure) SATIP-A-004-06 30-Oct-17 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW SPECIAL PROCESS (PRESSURE TESTING) REQUIRES BEST QUALITY PRACTICE, CPI & EFFICIENT METHODS IN PROCEDURES. PROPOSE BEST METHODS

Pressure Testing Procedure


a) Test Procedure
1.1 SAIC-A-2001 SAIC-A-2001 RH RH
b) Pressure Test
Diagram

1.2 Review of Test Package Preparation SAIC-A-2003 SAIC-A-2003 RH R

1.3 Lay-Up Procedure SAIC-A-2007 SAIC-A-2007 RH RH

2.0 MATERIAL RECEIVING

2.1 Verify Test Medium (Water Quality) SAIC-A-2008 SAIC-A-2008 RH R Use SATR-A-2014 & SAIC-A-007 requirements

3.0 APPLICATION

Use SATR-A-2007 - Include D-100 Applicable Forms &


3.1 Pre-Test Inspection of Tanks SAIC-A-2026 SAIC-A-2026 H H take baseline measurements BEFORE/DURING/AFTER
Filling.

3.2 Cleaning/flushing prior to hydrotest SAIC-L-2017 SAIC-L-2017 H W Use SATR-A-2008

Test Preparation & Verification of Testing Use SATR-A-2001, A-2002, SATR-A-2003, SATR-A-
3.3 SAIC-A-2009 SAIC-A-2009 H W
equipment (incl safety reqmts) 2004, SATR-A-2005, & SATR-A-2006

Use SAIC-A-2013 for Hydrotest.


3.4 Filling & Pressurization SAIC-A-2013 SAIC-A-2013 W W

3.5 Filling & Pressurization SAIC-A-2020 SAIC-A-2020 W W Use SAIC-A-2020 for Pneumatic test.

Form SATR-A-2001 is a mofified version or merging of


3.6 Visual Inspection at Test Pressure SAIC-A-2015 SAIC-A-2015 H H
forms SA-2642 ENG & SA-2642-1.

Leak Test (after Pneumatic Testing) at 5- SAIC-A-2024, SAIC-A-2024, Use SATR-A-2010 - In conjunction with SATIP-A-004-05
3.7 H H
10 psig SAIC-A-2023 SAIC-A-2023 as applicable.

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -30-Oct-2017 -REV. 2017.06.00(Standards Cutoff -June 30, 2017) Rev.2017.06.00 30-Jun-17

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Pressure Testing of Tanks (Atmospheric & Low Pressure) SATIP-A-004-06 30-Oct-17 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

4.0 POST- TEST

4.1 De-Pressurization & Water Disposal SAIC-A-2017 SAIC-A-2017 W S

4.2 Lay-Up SAIC-A-2018 SAIC-A-2018 H W Use SATR-A-2009 - Coating considerations

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
1
of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3
representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative
4
in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H 100% Hold Point for QC Inspection or Test. R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -30-Oct-2017 -REV. 2017.06.00(Standards Cutoff -June 30, 2017)

Saudi Aramco: Company General Use


Rev.2017.06.00

###

Saudi Aramco: Company General Use


30-Jun-17

Saudi Aramco: Company General Use


30-Oct-17 30-Oct-17

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -30-Oct-2017 -REV. 2017.06.00(Standards Cutoff -June 30, 2017)

Saudi Aramco: Company General Use


Rev.2017.06.00

###

Saudi Aramco: Company General Use


30-Jun-17

Saudi Aramco: Company General Use


30-Oct-17 30-Oct-17

Saudi Aramco: Company General Use