PT.

PRIMA POWER NUSANTARA BOQ FOR BACK UP CONTRACT CHANGE ORDER


Menara Enjiniring Lantai 7, Jl. Ciputat Raya No. 123 RT.01RW.08 Pondok Pinang JOB DESCRIPTION : FOUNDATION CLASS 6 PILED (T.48A) & (T.48B)
Kebayoran Lama, Jakarta Selatan 12310 CONTRACT NUMBER :
CONTRACT VALUE :
PEKERJAAN PENAMBAHAN TOWER SUTT 500 KV YANG TERDAMPAK
LOCATION : KM 17 SUTT MUARA TAWAR - CIBINONG
PROYEK KERETA CEPAT JAKARTA BANDUNG

CONTRACT ADDED REDUCED ADDENDUM


NO WORK ITEM UNIT UNIT PRICE DIFFERENCE REMARK NOTE
QTY PRICE QTY PRICE QTY PRICE QTY PRICE

(1) (2) (3) (4) (5) (6)=(4)x(5) (7) (8)=(4)x(7) (9) (10)=(4)x(9) (11) (12)=(4)x(11) (13)=(6)-(12) (11) (12)

I Foundation Class 6 Piled T.48A


- -
1 Geometry and Bouwplank, (incl Stub Setting) ls 4,706,670 1.00 4,706,670 0.00 - 0.00 - 1.00 4,706,670 - No Change
2 Handling Material Foundation from Stockyard to location m3 437,500 0.00 - 0.00 - 0.00 - 0.00 - - No Change
3 Test Concrete Cube ( 15 x 15 x 15 cm3 ) no 86,250 72.00 6,210,000 0.00 - 0.00 - 72.00 6,210,000 - No Change
4 Excavation of Soil m3 92,367 0.00 - 27.81 2,568,957 0.00 - 27.81 2,568,957 - 2,568,957 Added
5 Back Filling m3 69,427 0.00 - 12.30 854,185 0.00 - 12.30 854,185 - 854,185 Added
6 Compacted Sand , t = 10 cm m3 747,500 0.00 - 0.00 - 0.00 - 0.00 - - No Change
7 Lean Concrete K-100 (f'c = 7.4 MPa) , t = 5 cm m3 1,073,573 3.50 3,757,506 0.00 - 3.50 3,757,506 0.00 - 3,757,506 Reduced
8 Concrete K-225 m3 1,253,015 135.38 169,633,171 16.80 21,044,387 0.00 - 152.18 190,677,558 - 21,044,387 Added
9 Reinforced Steel : Pabrikasi kg 1,380 37338.27 51,526,813 0.00 - 0.00 - 37338.27 51,526,813 - No Change
10 Bored Pile dia 60 cm (Concrete K-225, Rebar, and Drilling) m' 1,528,942 400.00 611,576,800 26.00 39,752,492 0.00 - 426.00 651,329,292 - 39,752,492 Added
11 Formwork m2 1,092,500 80.60 88,055,500 2.20 2,403,500 0.00 - 82.80 90,459,000 - 2,403,500 Added
12 PVC dia 2 ich for grounding tower m 40,250 16.00 644,000 0.00 - 3.97 159,742 12.03 484,258 159,742 Reduced
13 Installed stake of concrete for Tower area no 575,000 4.00 2,300,000 0.00 - 0.00 - 4.00 2,300,000 - No Change
14 Dewatering Pile Cap ls 2,300,000 1.00 2,300,000 0.00 - 1.00 2,300,000 0.00 - 2,300,000 Reduced
15 Finishing and site clearing ls 1,150,000 1.00 1,150,000 0.00 - 0.00 - 1.00 1,150,000 - No Change
TOTAL I 941,860,459 66,623,521 6,217,248 1,002,266,733 - 60,406,274 Added
- -
II Foundation Class 6 Piled T.48B

1 Geometry and Bouwplank, (incl Stub Setting) ls 4,706,670 1.00 4,706,670 0.00 - 0.00 - 1.00 4,706,670 - No Change
2 Handling Material Foundation from Stockyard to location to m3 437,500 0.00 - 0.00 - 0.00 - 0.00 - - No Change
3 Test Concrete Cube ( 15 x 15 x 15 cm3 ) no 86,250 72.00 6,210,000 0.00 - 0.00 - 72.00 6,210,000 - No Change
4 Excavation of Soil m3 92,367 132.50 12,238,628 163.95 15,143,570 0.00 - 296.45 27,382,197 - 15,143,570 Added
5 Back Filling m3 69,427 37.25 2,586,156 136.61 9,484,596 0.00 - 173.86 12,070,752 - 9,484,596 Added
6 Compacted Sand , t = 10 cm m3 747,500 5.00 3,737,500 0.00 - 0.00 - 5.00 3,737,500 - No Change
7 Lean Concrete K-100 (f'c = 7.4 MPa) , t = 5 cm m3 1,073,573 2.50 2,683,933 0.00 - 0.00 - 2.50 2,683,933 - No Change
8 Concrete K-225 m3 1,253,015 105.38 132,042,721 80.21 100,498,381 0.00 - 185.59 232,541,102 - 100,498,381 Added
9 Reinforced Steel : Pabrikasi kg 1,380 24546.45 33,874,101 0.00 - 0.00 - 24546.45 33,874,101 - No Change
10 Bored Pile dia 60 cm (Concrete K-225, Rebar, and Drilling) m' 1,528,942 420.00 642,155,640 0.00 - 0.00 - 420.00 642,155,640 - No Change
11 Formwork m2 1,092,500 74.40 81,282,000 68.90 75,271,065 0.00 - 143.30 156,553,065 - 75,271,065 Added
12 PVC dia 2 ich for grounding tower m 40,250 16.00 644,000 0.00 - 4.00 161,000 12.00 483,000 161,000 Reduced
13 Installed stake of concrete for Tower area no 575,000 4.00 2,300,000 0.00 - 0.00 - 4.00 2,300,000 - No Change
14 Dewatering Pile Cap ls 2,300,000 1.00 2,300,000 0.00 - 0.00 - 1.00 2,300,000 - No Change
15 Finishing and site clearing ls 1,150,000 1.00 1,150,000 0.00 - 0.00 - 1.00 1,150,000 - No Change
TOTAL II 927,911,347 200,397,612 161,000 1,128,147,959 - 200,236,612 Added

GRAND TOTAL 1,869,771,806 267,021,134 6,378,248 2,130,414,692 - 260,642,886 Added

Note :
CONTRACT ADDED REDUCED ADDENDUM
NO WORK ITEM UNIT UNIT PRICE DIFFERENCE REMARK NOTE
QTY PRICE QTY PRICE QTY PRICE QTY PRICE

(1) (2) (3) (4) (5) (6)=(4)x(5) (7) (8)=(4)x(7) (9) (10)=(4)x(9) (11) (12)=(4)x(11) (13)=(6)-(12) (11) (12)

Knowing, Checked by, Compiled by,


PT. Prima Power Nusantara (Site Project Manager 1) Subcontractor
PT. Gracia Energi Nusantara

Achmad Syahroni Risman Cahya Ginanjar Bayu Aditya Putra ……………………………………


Project Manager Site Manager Site Engineer
PT. PRIMA POWER NUSANTARA MUTUAL CHECK 1 SUMMARY
Menara Enjiniring Lantai 7, Jl. Ciputat Raya No. 123 RT.01RW.08 Pondok JOB DESCRIPTION : FOUNDATION CLASS 6 PILED (T.48A) & (T.48B)
Pinang Kebayoran Lama, Jakarta Selatan 12310 CONTRACT NUMBER :
CONTRACT VALUE :
PEKERJAAN PENAMBAHAN TOWER SUTT 500 KV YANG TERDAMPAK
LOCATION : KM 17 SUTT MUARA TAWAR - CIBINONG
PROYEK KERETA CEPAT JAKARTA BANDUNG

QUANTITY
NO.
WORK ITEM UNIT MUTUAL REMARK NOTE
ITEM CONTRACT ADDED REDUCED
CHECK 1

(1) (2) (3) (4) (5) (6) (7)=(4)+(5)-(6) (8) (9)

7.13 FOUNDATION CLASS 6 PILED T.48A


-
1 Geometry and Bouwplank, (incl Stub Setting) ls 1.00 0.00 0.00 1.00 No Change
2 Handling Material Foundation from Stockyard to location m3 0.00 0.00 0.00 0.00 No Change
3 Test Concrete Cube ( 15 x 15 x 15 cm3 ) no 72.00 0.00 0.00 72.00 No Change
4 Excavation of Soil m3 0.00 27.81 0.00 27.81 Added Filling between exposed
5 Back Filling m3 0.00 12.30 0.00 12.30 Added bore pile at toll side
6 Compacted Sand , t = 10 cm m3 0.00 0.00 0.00 0.00 No Change
7 Lean Concrete K-100 (f'c = 7.4 MPa) , t = 5 cm m3 3.50 0.00 3.50 0.00 Reduced
8 Concrete K-225 m3 135.38 16.80 0.00 152.18 Added
9 Reinforced Steel kg 37338.27 0.00 0.00 37338.27 No Change
10 Bored Pile dia 60 cm (Concrete K-225, Rebar, and Drilling) m' 400.00 26.00 0.00 426.00 Added
Finishing Exposed Borepile m2 0.00 52.75 0.00 52.75 Added
11 Formwork m2 80.60 2.20 0.00 82.80 Added
- Base Formwork Ped
a. Perencanaan & Design Begesting ls 0.00 1.00 0.00 1.00 Added
b. Persiapan dan Mob De Mob Tenaga + Peralatan ls 0.00 1.00 0.00 1.00 Added
c. Pengadaan Strucktur Balok IWF 400 (10 Balok) kg 0.00 3564.00 0.00 3564.00 Added Support Structur
Analysis Report & Detail
d. Pengadaan & Pasang Chemical Anchor Pcs 0.00 160.00 0.00 160.00 Added Drawing
e. Plat Fangle set 0.00 20.00 0.00 20.00 Added
f. Jasa Pemasangan Plat Flange ls 0.00 70.00 0.00 70.00 Added
Setting & Ansembly Anchor ls 0.00 1.00 0.00 1.00 Added
Grouting Chimney m3 0.00 4.05 0.00 4.05 Added
Finishing With Skimcoat Exposed Chimney m2 0.00 143.75 0.00 143.75 Added
12 PVC dia 2 inch for grounding tower m 16.00 0.00 3.97 12.03 Reduced
13 Installed stake of concrete for Tower area no 4.00 0.00 0.00 4.00 No Change
14 Dewatering ls 1.00 0.00 1.00 0.00 Reduced
15 Finishing and site clearing ls 1.00 0.00 0.00 1.00 No Change
QUANTITY
NO.
WORK ITEM UNIT MUTUAL REMARK NOTE
ITEM CONTRACT ADDED REDUCED
CHECK 1

(1) (2) (3) (4) (5) (6) (7)=(4)+(5)-(6) (8) (9)

-
7.14 FOUNDATION CLASS 6 PILED T.48B

1 Geometry and Bouwplank, (incl Stub Setting) ls 1.00 0.00 0.00 1.00 No Change
2 Handling Material Foundation from Stockyard to location tower m3 0.00 0.00 0.00 0.00 No Change
3 Test Concrete Cube ( 15 x 15 x 15 cm3 ) no 72.00 0.00 0.00 72.00 No Change
4 Excavation of Soil m3 132.50 163.95 0.00 296.45 Added
5 Back Filling m3 37.25 136.61 0.00 173.86 Added
6 Compacted Sand , t = 10 cm m3 5.00 0.00 0.00 5.00 No Change
7 Lean Concrete K-100 (f'c = 7.4 MPa) , t = 5 cm m3 2.50 0.00 0.00 2.50 No Change
8 Concrete K-225 m3 105.38 80.21 0.00 185.59 Added
9 Reinforced Steel kg 24546.45 0.00 0.00 24546.45 No Change
10 Bored Pile dia 60 cm (Concrete K-225, Rebar, and Drilling) m' 420.00 0.00 0.00 420.00 No Change
11 Formwork m2 74.40 68.90 0.00 143.30 Added
Setting & Ansembly Anchor ls 0.00 1.00 0.00 1.00 Added
Grouting Chimney m3 0.00 4.05 0.00 4.05 Added
Finishing With Skimcoat Exposed Chimney m2 0.00 57.60 0.00 57.60 Added
12 PVC dia 2 ich for grounding tower m 16.00 0.00 4.00 12.00 Reduced
13 Installed stake of concrete for Tower area no 4.00 0.00 0.00 4.00 No Change
14 Dewatering ls 1.00 0.00 0.00 1.00 No Change
15 Finishing and site clearing ls 1.00 0.00 0.00 1.00 No Change

9.0 MISCELLANEOUS WORK (TO BE APPLIED AFTER INSTRUCTED BY ENGINEER)

9.10 Tower T.48 A Work


a Basement Seepage ls 0.00 1.00 0.00 1.00 Added
b Deepwel Box ls 0.00 1.00 0.00 1.00 Added
c Settlement at Pedestrian Ramp ls 0.00 1.00 0.00 1.00 Added
d Drain Pipe From Sumpit ls 0.00 1.00 0.00 1.00 Added
e Grounding ls 0.00 1.00 0.00 1.00 Added
f Concrete Retaining Wall Added
- Concrete K225 m3 0.00 21.06 0.00 21.06 Added
- Formwork m2 0.00 1213.60 0.00 1213.60 Added
- Reinforcement kg 0.00 138.24 0.00 138.24 Added
QUANTITY
NO.
WORK ITEM UNIT MUTUAL REMARK NOTE
ITEM CONTRACT ADDED REDUCED
CHECK 1

(1) (2) (3) (4) (5) (6) (7)=(4)+(5)-(6) (8) (9)

9.15 Tower T.48 B Work


a Stone Masonry Retaining Wall Riverside m3 0.00 30.60 0.00 30.60 Added

b Clearing Area For Marketing Office Adhi Commuter Property ls 0.00 1.00 0.00 1.00 Added
& prepare for erection
c Filling and Compacted Soil for erection work ls 0.00 1.00 0.00 1.00 Added
9.18 Urugan Tanah untuk Jalan Kerja (Kolam Renang) m3 100.00 0.00 100.00 0.00 Reduced
9.22 Stone Masonry (perbaikan kolam) m3 28.90 0.00 28.90 0.00 Reduced

Note :

Knowing, Checked by, Compiled by,


PT. Prima Power Nusantara (Site Project Manager 1) Subcontractor
PT. Gracia Energi Nusantara

Achmad Syahroni Risman Cahya Ginanjar Bayu Aditya Putra ……………………………………


Project Manager Site Manager Site Engineer
JOB DESCRIPTION : FOUNDATION CLASS 6 PILED (T.48A) & (T.48B)
CONTRACT NUMBER : 0
VOLUME CONTROL CONTRACT VALUE : 0
LOCATION : KM 17 SUTT MUARA TAWAR - CIBINONG

NO WORK ITEM REF. / DRAWING EQUATION / FORMULA ∑ VOLUME UNIT REMARK / NOTE

7.13 FOUNDATION CLASS 6 PILED T.48A

Geometry and Bouwplank,


1 1.00 ls
(incl Stub Setting)
Handling Material Foundation
2 0.00 m3
from Stockyard to location
Test Concrete Cube
3 72.00 no
(15x15x15 cm3 )
4 Excavation of Soil KCIC-WIKA-WIKON-ATN-CK17-P48A-03 V= T x ((L1+L2)/2) x P additional work
V= 2.5 x 1.3 x 8.9 = 27.81 m3

5 Back Filling KCIC-WIKA-WIKON-ATN-CK17-P48A-03 V= T x ((L1+L2)/2) x P additional work


V= 1.8 x 0.9 x 7.7 = 12.30 m3

7 Lean Concrete K-100 (f'c = 7.4 KCIC-WIKA-WIKON-ATN-CK17-P48A-03 0.00 m3 Reduce


MPa) , t = 5 cm No Needed

Page 6 of 26
JOB DESCRIPTION : FOUNDATION CLASS 6 PILED (T.48A) & (T.48B)
CONTRACT NUMBER : 0
VOLUME CONTROL CONTRACT VALUE : 0
LOCATION : KM 17 SUTT MUARA TAWAR - CIBINONG

NO WORK ITEM REF. / DRAWING EQUATION / FORMULA ∑ VOLUME UNIT REMARK / NOTE

8 Concrete K-225 KCIC-WIKA-WIKON-ATN-CK17-P48A-01


KCIC-WIKA-WIKON-ATN-CK17-P48A-02 1. PED
V= T x L x P

contract volume
V= 1.5 x 7.0 x 10.0 = 105.00 m3

2. CHIMNEY
V= T x L x P
V= 1.5 x 4.5 x 4.5 = 30.38 m3
135.38 m3

1. PED

additional volume
V= T x L x P
V= 1.5 x 7.0 x 11.6 = 121.80 m3

contract +
2. CHIMNEY
V= T x L x P
V= 1.5 x 4.5 x 4.5 = 30.38 m3
152.18 m3

16.80 m3 addditional volume

9 Reinforced Steel See Document Attachment (BBS-KM17)

10 Bored Pile dia 60 cm ∑Ln = Depth x n Pile


(Concrete K-225, Rebar, and

additional volume
∑L1 = 20.0 x 14.0 280.00 m'
Drilling)
∑L2 = 8.0 x 2.0 16.00 m'

contract +
∑L3 = 14.0 x 2.0 28.00 m'
∑L4 = 17.0 x 1.0 17.00 m'
∑L5 = 21.0 x 3.0 63.00 m'
∑L6 = 22.0 x 1.0 22.00 m'
∑L = 426.00 m'

∑An = (P+L) x 2 x T
11 Formwork KCIC-WIKA-WIKON-ATN-CK17-P48A-01
∑A1 ped = 18.6 x 2.00 x 1.50 55.80 m2 Side Ped Formwork &
∑A1 chm = 9.0 x 2.00 x 1.50 27.00 m2 Chimney

Page 7 of 26
JOB DESCRIPTION : FOUNDATION CLASS 6 PILED (T.48A) & (T.48B)
CONTRACT NUMBER : 0
VOLUME CONTROL CONTRACT VALUE : 0
LOCATION : KM 17 SUTT MUARA TAWAR - CIBINONG

NO WORK ITEM REF. / DRAWING EQUATION / FORMULA ∑ VOLUME UNIT REMARK / NOTE
Side Ped Formwork &
Chimney
∑A = 82.80 m2

Page 8 of 26
JOB DESCRIPTION : FOUNDATION CLASS 6 PILED (T.48A) & (T.48B)
CONTRACT NUMBER : 0
VOLUME CONTROL CONTRACT VALUE : 0
LOCATION : KM 17 SUTT MUARA TAWAR - CIBINONG

NO WORK ITEM REF. / DRAWING EQUATION / FORMULA ∑ VOLUME UNIT REMARK / NOTE

- Base Formwork Ped Attachment Reference Detail Drawing


Attachment Structur Support Analysis Report
a Perencanaan & Design
Begesting 88.90

b Persiapan dan Mob De


Mob Tenaga + Peralatan

c Pengadaan Strucktur
Balok IWF 400 (10 Balok) additional work

d Pengadaan & Pasang


Chemical Anchor

e Plat Fangle

Jasa Pemasangan Plat


f
Flange

Setting & Ansembly Anchor 1.00 ls additional work

V= P x L x t
Grouting Chimney additional work
V = 4.50 x 4.50 x 0.20 4.05 m3
PVC dia 2 inch for grounding ∑L = 1/4L Chimney+ T Chimney + L Ped
12 KCIC-WIKA-WIKON-ATN-CK17-GS-01 Reduce
tower ∑L = 1.13 + 1.50 + 7.00 x 1.25 12.03 m'
Reduce
14 Dewatering 0.00 ls
No Needed

7.14 FOUNDATION CLASS 6 PILED T.48B

Geometry and Bouwplank,


1 1.00 ls
(incl Stub Setting)
Handling Material Foundation
2 0.00 m3
from Stockyard to location
Test Concrete Cube
3 72.00 no
(15x15x15 cm3 )
V= T x ((L1+L2)/2) x P additional work
4 Excavation of Soil KCIC-WIKA-WIKON-ATN-CK17-P48B-02 296.45 m3
V= 3.9 x 7.7 x 10.0 =
Vb = Ve - (Vp+Vc1) additional work
5 Back Filling KCIC-WIKA-WIKON-ATN-CK17-P48A-02 173.86 m3
Vb= 296.5 - 75.0 + 47.59

Page 9 of 26
JOB DESCRIPTION : FOUNDATION CLASS 6 PILED (T.48A) & (T.48B)
CONTRACT NUMBER : 0
VOLUME CONTROL CONTRACT VALUE : 0
LOCATION : KM 17 SUTT MUARA TAWAR - CIBINONG

NO WORK ITEM REF. / DRAWING EQUATION / FORMULA ∑ VOLUME UNIT REMARK / NOTE

0 KCIC-WIKA-WIKON-ATN-CK17-P48A-03 0.00 m3 Reduce


0 No Needed

0 0 KCIC-WIKA-WIKON-ATN-CK17-P48A-01
KCIC-WIKA-WIKON-ATN-CK17-P48A-02 1. PED
V= T x L x P

contract volume
V= 1.5 x 7.0 x 10.0 = 105.00 m3

2. CHIMNEY
V= T x L x P
V= 1.5 x 4.5 x 4.5 = 30.38 m3
135.38 m3

1. PED

additional volume
V= T x L x P
V= 1.5 x 7.0 x 11.6 = 121.80 m3

contract +
2. CHIMNEY
V= T x L x P
V= 1.5 x 4.5 x 4.5 = 30.38 m3
152.18 m3

16.80 m3 addditional volume

90 See Document Attachment (BBS-KM17)

Page 10 of 26
JOB DESCRIPTION : FOUNDATION CLASS 6 PILED (T.48A) & (T.48B)
CONTRACT NUMBER : 0
VOLUME CONTROL CONTRACT VALUE : 0
LOCATION : KM 17 SUTT MUARA TAWAR - CIBINONG

NO WORK ITEM REF. / DRAWING EQUATION / FORMULA ∑ VOLUME UNIT REMARK / NOTE

90 See Document Attachment (BBS-KM17)

10 ∑Ln = Depth x n Pile

additional volume
∑L1 = 20.0 x 14.0 280.00 m'
0 ∑L2 = 8.0 x 2.0 16.00 m'

contract +
∑L3 = 14.0 x 2.0 28.00 m'
∑L4 = 17.0 x 1.0 17.00 m'
∑L5 = 21.0 x 3.0 63.00 m'
∑L6 = 22.0 x 1.0 22.00 m'
∑L = 426.00 m'

∑An = (P+L) x 2 x T
11 Formwork KCIC-WIKA-WIKON-ATN-CK17-P48A-01
∑A1 ped = 18.6 x 2.00 x 1.50 55.80 m2 Side Ped Formwork &
∑A1 chm = 9.0 x 2.00 x 1.50 27.00 m2 Chimney
∑A = 82.80 m2

- 0 Attachment Reference Detail Drawing


Attachment Structur Support Analysis Report
a
0

b
0

c
0 additional work

d
0

e0

f0

0 1.00 ls additional work

V= P x L x t
0 additional work
V = 4.50 x 4.50 x 0.20 4.05 m3
∑L = 1/4L Chimney+ T Chimney + L Ped
00 KCIC-WIKA-WIKON-ATN-CK17-GS-01 Reduce
∑L = 1.13 + 1.50 + 7.00 x 1.25 12.03 m'
Reduce
00 0.00 ls
No Needed

Page 11 of 26
JOB DESCRIPTION : FOUNDATION CLASS 6 PILED (T.48A) & (T.48B)
CONTRACT NUMBER : 0
VOLUME CONTROL CONTRACT VALUE : 0
LOCATION : KM 17 SUTT MUARA TAWAR - CIBINONG

NO WORK ITEM REF. / DRAWING EQUATION / FORMULA ∑ VOLUME UNIT REMARK / NOTE

Note :

Page 12 of 26
CALCULATION SHEET

Pembangunan T/L 500kv BEKASI


No. Contract :
Project : Tower Line SUTET 500 Kv BEKASI
Item Work : Tower Foundation
No. Tower :
Type Tower / Class : T.48A SSP5+24 Class 6 ( Bore Pile ) 19.5 M'
VOLUME
NO URAIAN PEKERJAAN / SKETS PERHITUNGAN VOLUME
KONTRAK

1 Pengukuran Bouwplank (berikut Stub Setting)


2 Mobilisasi Alat Bor
3 Mobilisasi Alat Bor (antar lokasi Tower)
4 Pekerjaan Bore Pile
5 Pengadaan dan Pemasangan Casing
6 Cutting Kepala Bore Pile
7 Pasang/Bongkar Casing

8 Pekerjaan Tanah P L T
a. Galian tanah Biasa m3 Leg 1 > x x m'

9 Urugan Pasir, t = 10 cm m3 Leg A, B, C dan D


Volume 1 le > 0.00 x 7.00 x 0.10 m'
> - x 1.00 leg

10 Lantai Kerja m3 Leg A, B, C dan D


Beton Adukan 1 : 3 : 5 (B.O), t = 5 cm Volume 1 le > 0.00 x 7.00 x 0.05 m'
> - x 1.00

11 Beton K225 Leg A, B, C dan D ( 4 bh )


a. Bottom Pad Volume Beton
7.00
a. > 7.00 x 10.00 x 1.50
1.50
10.00

13/26
CALCULATION SHEET

Pembangunan T/L 500kv BEKASI


No. Contract :
Project : Tower Line SUTET 500 Kv BEKASI
Item Work : Tower Foundation
No. Tower :
Type Tower / Class : T.48A SSP5+24 Class 6 ( Bore Pile ) 19.5 M'
VOLUME
NO URAIAN PEKERJAAN / SKETS PERHITUNGAN VOLUME
KONTRAK
4.50
b. Chimney c. > 4.50 x 4.50 x 1.50

Jumlah Volume

1.50 Jumlah Volume Total = > 135.380


0.8 -
c. Bore Pike Titik Bor Per Leg 0 titik
Volume Beton Bore Pile Dia 40
a. > 3.14 x 0.40 x 0.40 x 1.00
1m
Panjang 435.00 m' Jumlah

Jumlah Volume Total = > 217.500

12 Bekisting

a. Pad a. > 7.00 x 1.50 x 2 sisi


1.50

b. Pad 7.00
b. > 10.00 x 1.50 x 2 sisi
1.50
10.00
c. Chimney 4.50 c. > 4.50 x 1.50 x 4 sisi

1.50
1 Tower > 1 x 78.00 m2

13 Besi Beton Data perhitungan terlampir > 1 x - kg

14/26
CALCULATION SHEET

Pembangunan T/L 500kv BEKASI


No. Contract :
Project : Tower Line SUTET 500 Kv BEKASI
Item Work : Tower Foundation
No. Tower :
Type Tower / Class : T.48A SSP5+24 Class 6 ( Bore Pile ) 19.5 M'
VOLUME
NO URAIAN PEKERJAAN / SKETS PERHITUNGAN VOLUME
KONTRAK

15/26
T/L 500kv BEKASI

PERHITUNGAN VOLUME VOLUME ACTUAL

1.00 Tower
1.00 Ls
Towe
1.00
r
435.00 M'
12.00 M'
1.00 Buah
12.00 Titik

= 0.00 m3
0.00 m3 - m3

= 0.00 m3
= 0.00 m3 - m3

= 0.00 m3
= 0.00 m3 - m3

= 105.00 m3

16/26
T/L 500kv BEKASI

PERHITUNGAN VOLUME VOLUME ACTUAL

= 30.38 m3

Jumlah Volume 1 leg = 135.38 m3

x 1 = 135.38 m3 135.38 m3

m' = 0.50 m3

Jumlah Volume = 217.50 m3

x 1 = 217.50 m3 217.50 m3

= 21.00 m2

= 30.00 m2

= 27.00 m2

= 78.00 m2
Jumlah 78.00 m2 78.00 m2
Jumlah = - - kg

17/26
T/L 500kv BEKASI

PERHITUNGAN VOLUME VOLUME ACTUAL

18/26
CALCULATION SHEET

Pembangunan T/L 500kv BEKASI


No. Contract :
Project : Tower Line SUTET 500 Kv BEKASI
Item Work : Tower Foundation
No. Tower :
Type Tower / Class : T.48B SSP5+24 Class 6 ( Bore Pile ) 19.5 M' 24titik
VOLUME
NO URAIAN PEKERJAAN / SKETS PERHITUNGAN VOLUME
KONTRAK

1 Pengukuran Bouwplank (berikut Stub Setting)


2 Mobilisasi Alat Bor
3 Mobilisasi Alat Bor (antar lokasi Tower)
4 Pekerjaan Bore Pile
5 Pengadaan dan Pemasangan Casing
6 Cutting Kepala Bore Pile
7 Pasang/Bongkar Casing

8 Pekerjaan Tanah P L T
a. Galian tanah Biasa m3 Leg 1 > 10.00 x 5.00 x 4.00 m'

9 Urugan Pasir, t = 10 cm m3 Leg A, B, C dan D


Volume 1 le > 10.00 x 5.00 x 0.10 m'
> 5.00 x 1.00 leg

10 Lantai Kerja m3 Leg A, B, C dan D


Beton Adukan 1 : 3 : 5 (B.O), t = 5 cm Volume 1 le > 10.00 x 5.00 x 0.05 m'
> 2.50 x 1.00

11 Beton K225 Leg A, B, C dan D ( 4 bh )


a. Bottom Pad Volume Beton
5.00
a. > 5.00 x 10.00 x 1.50
1.50
10.00

19/26
CALCULATION SHEET

Pembangunan T/L 500kv BEKASI


No. Contract :
Project : Tower Line SUTET 500 Kv BEKASI
Item Work : Tower Foundation
No. Tower :
Type Tower / Class : T.48B SSP5+24 Class 6 ( Bore Pile ) 19.5 M' 24titik
VOLUME
NO URAIAN PEKERJAAN / SKETS PERHITUNGAN VOLUME
KONTRAK
4.50
b. Chimney c. > 4.50 x 4.50 x 5.46

Jumlah Volume

5.46 Jumlah Volume Total = > 185.590


0.6 -
c. Bore Pike Titik Bor Per Leg 24 titik
Volume Beton Bore Pile Dia 40
a. > 3.14 x 0.30 x 0.30 x 1
1m
Panjang 468.00 m' Jumlah

Jumlah Volume Total = > 131.040

12 Bekisting

a. Pad a. > 5.00 x 1.50 x 2 sisi


1.50

b. Pad 5.00
b. > 10.00 x 1.50 x 2 sisi
1.50
10.00
c. Chimney 4.50 c. > 4.50 x 5.46 x 4 sisi

5.46
1 Tower > 1 x 143.30 m2

13 Besi Beton Data perhitungan terlampir > 1 x - kg

20/26
CALCULATION SHEET

Pembangunan T/L 500kv BEKASI


No. Contract :
Project : Tower Line SUTET 500 Kv BEKASI
Item Work : Tower Foundation
No. Tower :
Type Tower / Class : T.48B SSP5+24 Class 6 ( Bore Pile ) 19.5 M' 24titik
VOLUME
NO URAIAN PEKERJAAN / SKETS PERHITUNGAN VOLUME
KONTRAK

14 Urugan Kembali dan Perataan Tanah LC + Sand Pad Chimney CM Atas


Beton Tertimbun 7.50 + 75.00 + 110.59 - 63.00

3.11 0.40
Galian = 5.00 x 10.00 x 4.00

Total
4.00 -
Volume Urugan 48B
-
-

1.50
0.05
0.10
5.00
15 Disposal Tanah Bekas Galian Disposal Tanah Bekas Galian

16 Pemasangan Batu Kali (masonry Wall)

0.5 Panjang 12.00 m'


Talud A 0.50 + 1.00 x 2.00 x 12.00
2

A 2.00 B 1.00 x 0.70 x 12.00

Volume Pasangan Batu Kali Talu


21/26
CALCULATION SHEET

Pembangunan T/L 500kv BEKASI


No. Contract :
Project : Tower Line SUTET 500 Kv BEKASI
Item Work : Tower Foundation
No. Tower :
Type Tower / Class : T.48B SSP5+24 Class 6 ( Bore Pile ) 19.5 M' 24titik
VOLUME
NO URAIAN PEKERJAAN / SKETS PERHITUNGAN VOLUME
KONTRAK
Panjang 6.00 m' kolam B 1.00 x 0.70 x 6.00

B 0.70 Volume Pasangan Batu Kali Talud Sungai & Perkuatan Ponda

1.00
17 Pemasangan Grounding Resistance 1 Buah :

18 Sand Bag Kolam Material Pasir 20 m3 Manpower


Karung 900 lmbr Alat Berat
Terpal 144 m2 Operator
Semen 10 zak

19 Setting dan Pemasangan Angkur Tamplate

22/26
T/L 500kv BEKASI

PERHITUNGAN VOLUME VOLUME ACTUAL

1.00 Tower
1.00 Ls
Towe
1.00
r
468.00 M'
- M'
1.00 Buah
- Titik

= 200.00 m3
200.00 m3 200.00 m3

= 5.00 m3
= 5.00 m3 5.00 m3

= 2.50 m3
= 2.50 m3 2.50 m3

= 75.00 m3

23/26
T/L 500kv BEKASI

PERHITUNGAN VOLUME VOLUME ACTUAL

= 110.59 m3

Jumlah Volume 1 leg = 185.59 m3

x 1 = 185.59 m3 185.59 m3

m' = 0.28 m3

Jumlah Volume = 131.04 m3

x 1 = 131.04 m3 131.04 m3

= 15.00 m2

= 30.00 m2

= 98.30 m2

= 143.30 m2
Jumlah 143.30 m2 143.30 m2
Jumlah = - - kg

24/26
T/L 500kv BEKASI

PERHITUNGAN VOLUME VOLUME ACTUAL

= 130.09 m3

= 200.00 m3

= 69.91 m3

= 69.91 m3 69.91 m3

= 130.09 m3 130.09 m3

m3

= 18.00 m3

= 8.40 m3

Volume Pasangan Batu Kali Talud Sungai = 26.40 m3


25/26
T/L 500kv BEKASI

PERHITUNGAN VOLUME VOLUME ACTUAL

= 4.20 m3

Volume Pasangan Batu Kali Talud Sungai & Perkuatan Pondasi kolam = 30.60 m3 30.60 m3

Jumlah = 1.00 1.00 bh

Manpower 20 HO
2,5 jam
1 hr

26/26