Economic Viability of Simple Tidal Stream Energy PDF
Economic Viability of Simple Tidal Stream Energy PDF
Economic Viability of Simple Tidal Stream Energy PDF
Participants:
LOG+1 Limited
ALSTOM Power Limited
WUMTIA
The work described in this report was carried out with an Applied Research grant under
the DTI Technology Programme: New and Renewable Energy, which is managed by
AEAT Energy & Environment. The views and judgements expressed in this report are
those of the participants and do not necessarily reflect those of the DTI or AEAT Energy
.
& Environment.
1.
ABSTRACT
This tidal stream energy project has compared the overall economics of two
horizontal axis tidal turbine devices: a fixed pitch, bi-directional, variable speed
turbine generator device with a variable pitch, variable speed turbine generator
device that rotates to face into the tidal flow.
The project has established, theoretically, the extent to which the loss in energy
conversion efficiency of the simpler to construct fixed pitch device is
counterbalanced by a reduction in capital and O&M costs and whether the system is
technically feasible and sufficiently economic to warrant further development.
The conclusion is that the simple fixed pitch, bi-directional device is competitive on a
life cycle cost basis and worthy of further consideration.
2.
EXECUTIVE SUMMARY
2.1
Objectives
The project compares a generic axial, fixed pitch, bi-directional, variable speed
turbine generator device with a generic axial, variable pitch turbine generator device
that rotates to face into the tidal flow. The principal objective is to identify the
circumstances and extent to which the simple bi-directional device may be
competitive with the variable pitch device on a lifetime cost basis.
2.2
Introduction
This collaborative project involves the Wolfson Unit for Marine Technology and
Industrial Aerodynamics (WUMTIA) of the University of Southampton, ALSTOM
Power Ltd - Technology Centre and LOG+1. While not party to the grant
arrangements with the DTI, E.ON UK Power Technology Ltd. on behalf of E.ON UK
Renewables Developments Ltd., has provided a utility perspective and Converteam
Ltd has provided information on generators and power conversion aspects.
The agreed project scope was limited to horizontal axis tidal turbines (HATT), and
did not include consideration of alternative approaches such as vertical axis turbines
or oscillating hydrofoil systems.
In order to control the performance of a turbine in variable flow conditions such as
are typical of a tidal stream, it is necessary to alter the angle of attack of the blades
relative to the flow. This can be achieved using a variable-pitch system, with
attendant problems of sealing, mechanical complexity, increased cost and reduced
reliability, or by using a simple rotor with fixed pitch blades, the rotational speed of
which is altered to achieve a specific relationship between current speed and rotor
rotational speed.
The hydrodynamic performance of a sub-sea device will only be one parameter in
the lifetime cost of each system. The marine environment is particularly aggressive
towards equipment operating within it for extended periods with limited access or
opportunity for routine inspection and maintenance.
The Operation and Maintenance (O&M) element of the lifetime cost of a tidal stream
concept may well be greater than the significant contribution of O&M costs to the
cost per kWh anticipated for offshore wind energy, and be a major determinant in
the commercial viability of tidal stream energy. A commercially successful HATT
system will need a very high level of reliability and accessibility, with the longest
periods between routine maintenance inspections consistent with optimum wholelife economics. The premise is that the lowest capital and operating costs are more
likely to be achieved if the marine components are kept simple.
The project has attempted to identify and quantify the trade-offs between reliability,
efficiency and cost of generic HATTs. The overall economic performance will depend
Results from Monte Carlo simulations of device availability, together with cost
estimates for capital and maintenance costs, were fed into the cost comparison
spreadsheet to provide a comparative cost and revenue performance for each
machine in the context of a farm of 30 devices, each rated at 1MW, having a 20m
diameter rotor, and operating in a tidal stream with a maximum flow speed of 2.5
m/s. Costs common to the two device types were included at this stage. For cost
modelling purposes two turbines were assumed to be attached to a common
mounting. This arrangement was chosen to reflect the fact that many proposed
devices feature one or more pairs of contra rotating turbines to minimise the net
torque transmitted to the mounting structure.
Fault Tree Analysis (FTA) was chosen in preference to Failure Mode and Effect
Analysis (FMEA) for the reliability elements of this study because it was considered
easier to construct a generic analysis. Use of the FTA technique allows a generic
failure to be described without detailed consideration of the precise nature of the
failure.
FTA is a top-down technique in which a specific top-level fault is identified (in this
case, lack of electrical output to the grid when such output would be expected), and
all combinations of lower-level fault causing the top-level fault are identified. In
contrast, FMEA is a bottom-up approach in which all possible faults of all
components are identified, and the implications of each fault are assessed, for
example providing the answer to the question What is the effect of a mechanical
failure of a main gearbox third-stage planet gear axle?, FMEA and FTA may in most
cases be regarded as providing equivalent information, but meaningful FMEA
requires the existence of a fairly detailed design definition of the system; implying
loss of generality for the study.
In order to assess overall failure probabilities for the study devices a generic fault
tree was created, and the individual fault conditions featured in the tree were
ascribed probabilities of occurrence, derived from published data for comparable
equipment in a North Sea Oil production context. The generic fault tree could be
reconfigured to represent fixed pitch or variable pitch devices and the overall failure
probability was then recalculated automatically.
2.4
Main Results
The principal objective of this study has been to identify any circumstances under
which simple but less efficient devices offer competitive life cycle performance to
complex but more efficient ones.
Comparison of the variable and fixed pitch design indicates that the energy yield
from the fixed pitch design is likely to be up to 10% less than that for the variable
pitch design. With a generator of a given capacity, this difference could be
accommodated by an increase of about 1.0 m in rotor diameter over the 20mbaseline diameter.
The comparative system cost analysis has demonstrated that the relative merit of
the two approaches depends upon the assessment criteria adopted and may be
summarised as follows:
The variable pitch, variable rotational speed machine (with an energy capture
performance notionally 10% better than that of the fixed pitch machine)
produces more energy in a given period than the fixed pitch, variable
rotational speed machine, unless the absolute reliability of both machines is
very low,
The fixed pitch machine always offers lower initial capital cost and unplanned
maintenance cost than the variable pitch machine,
The fixed pitch machine offers lower cost per unit of electricity generated
unless the absolute reliability of both machines is very high,
The percentage increase in energy capture using the variable pitch machine is
generally much less than the notional 10% difference given perfectly reliable
machines; relative performances encountered during the study implied that
the variable pitch machine would generally produce 4 7% more energy than
the fixed pitch machine, although its worst performance produced 1% less
energy.
The discrepancy between the notional and calculated performances arises because
the availability of the variable-pitch machine is lower than the availability of the
fixed-pitch machine, so some or all of the variable-pitch machines theoretical
energy capture advantage is lost. The availability depends upon reliability and
accessibility, but the relative importance of accessibility itself depends on overall
reliability. In general the higher the overall reliability of both devices the greater the
relative energy capture of the variable pitch machine. The 7% improvement quoted
was associated with the highest reliability assumed in the study, and the 1% worse
performance reflected the lowest reliability used. For reliability modelling purposes
the variable pitch machine is treated as a variant of the fixed pitch machine.
Although uncertainties exist in the absolute reliability values, it is considered that
the relative reliabilities of fixed pitch and variable pitch machines have been well
represented for study.
The baseline case consisted of a farm of 30 off 1 MW turbine units configured with
an active DC link and two network bridges, each serving 15 of the turbines. The
variable pitch option also allowed turbine axis rotation in yaw, so as to always face
into the tidal stream. The baseline case, using the calculated hydrodynamic capacity
factor of 22.8% for the fixed and 24.5% for the variable concept and mean failure
rates, shows an overall energy production of 53 and 55 GWh per year respectively.
Using these energy production figures the cost of electricity is 119 /MWh for the
fixed pitch concept, compared to 129 /MWh for the variable pitch concept over a 10
year operating period, and 94 /MWh and 104 /MWh respectively for a 15 year
period.
The results shown in the study are based on 110% of rated power being achieved at
peak spring current velocity. This is based on the assumption that (consistent with
diesel generator set practice) the generator may be operated at such a power output
without damage, providing the operation at over 100% rating is of limited duration,
and at sufficiently infrequent intervals that the design winding temperatures are not
exceeded. The economically optimum design of tidal stream turbine system will
probably not require peak spring tide current speeds to generate its rated power, but
the definition of the true economic optimum device may well depend upon the
precise stream parameters at its intended operational location. Therefore the rated
speed has been taken to be the peak spring current speed for the purposes of this
study.
It is recognised that the hydrodynamic capacity factors could be increased by using
a generator rated at below the maximum power available in the stream, and this
could lead to a lower cost of electricity. This aspect has not been considered in this
study.
2.5
Conclusions
This tidal stream energy project has compared an axial, fixed pitch, bi-directional,
variable speed turbine generator device with an axial, variable pitch, turbine
generator device that rotates to face into the tidal flow. The project has established,
theoretically, the extent to which the loss in energy conversion efficiency of the
simpler to construct fixed pitch device is counterbalanced by a reduction in capital
and O&M costs and whether the system is technically feasible and sufficiently
economic to warrant further development.
The project compared the best theoretical hydrodynamic solution to the capture of
energy from a tidal stream with a simple alternative solution that would cost less to
manufacture and should be expected to be more reliable during its operational life.
The conclusion was that the simple fixed pitch device was competitive on a life cycle
cost basis and worthy of further consideration.
A number of tidal stream concepts under development address the problem of
reverse tidal flow by including a mechanism to change the blade pitch by 180 deg or
more. While this will do away with the cost and reliability implications of a rotator
mechanism, it requires a compromise on the blade section that will result in a
reduction in the energy yield compared with the best hydrodynamic solution. This
would seem to reinforce the case for further consideration of the fixed pitch, bidirectional, variable speed turbine generator device.
Tidal stream devices are likely to be located well away from centres of population
and the established transmission and distribution network. The availability of grid
connections at a date and cost that does not prevent commercial deployment of tidal
stream and other renewable energy devices has to be urgently addressed by the DTI
and Ofgem.
Tidal power is arguably one of the more expensive in capacity terms of the available
technologies, certainly at this stage of its development. While commercial
deployment of devices will help to drive down the capital and operating costs, tidal
power will need additional support while the successful concepts become
competitive renewable energy options. The Government is proposing differentiated
Recommendations
10
3.
CONTENTS PAGE
1. ABSTRACT .............................................................................................................................4
2. EXECUTIVE SUMMARY .................................................................................................5
3. CONTENTS PAGE ........................................................................................................... 11
4. GLOSSARY ......................................................................................................................... 12
5. PROJECT BACKGROUND ............................................................................................14
6.
APPENDIX B:
11
4.
GLOSSARY
Abbreviation
BEM
DNV
DSV
FTA
FMEA
HATT
LRU
LSP
OHL
O&M
OEM
OREDA
RIB
SCADA
TSR
Term
Blade Element
Momentum
Description
Hydrodynamic analysis code which
matches knowledge of the change in a
fluid's axial and swirl momentum with the
lift and drag performance of a blade
section.
Det Norske Veritas
A Norwegian based Classification Society.
Dive Support Vessel Class of ship associated with offshore
operations typically featuring a Dynamic
Positioning system, diver support facilities
and 150 tonne crane.
Fault Tree Analysis
A top-down technique in which specific
top-level faults are specified and all lower
level faults causing it are identified.
Failure Mode &
A bottom-up technique in which all
Effects Analysis
component faults are identified and the
implications of each fault is assessed.
Horizontal Axial
A tidal stream turbine with a horizontal
Tidal Turbine
rotor shaft.
Line Replaceable
An individual tidal stream turbine that can
Unit
be replaced in the event of failure or at the
end of its design life.
Lifting Surface
Hydrodynamic analysis code based on
Panel
quadrilateral boundary elements that solves
Laplace's equation for potential flow.
Overhead Line
As opposed to buried or submerged cable.
Operation and
Control of the day to day operation of the
Maintenance
tidal stream farm and the
maintenance/replacement of all equipment
during the life of the project.
Original Equipment Manufacturers of the equipment used in a
Manufacturer
tidal stream farm.
Offshore Reliability
A database developed by a number of
Database
leading oil companies.
Rigid Inflatable Boat Boat with rigid hull and large inflatable
tubes down each side.
Supervisory Control Controls and monitors all the equipment in
and Data
the tidal stream farm.
Acquisition
Tip Speed Ratio
Ratio of the rotational speed at the blade tip
to
the onset (undisturbed) speed of the tidal
current.
12
Term
Azimuthing
Description
The ability of a HATT to turn so that its axis is aligned with the
flow of the tidal stream.
Cavitation
The formation of vapour cavities when the local static pressure
(due to high local flow speeds) reduces to that of the fluid's
vapour pressure.
Hydrodynamic A measure of the efficiency of the rotor in capturing energy from
Efficiency
the tidal stream. It is calculated as the (total energy produced by
the rotor over a full tidal cycle) divided by (energy produced by
the rotor operating at its rated power over the same time). It
therefore does not take account of mechanical or electrical losses
in the system, or reliability and availability factors.
Monte Carlo
A system used to predict reliability and availability levels based
on the laws of probability.
Tidal Ellipse
Refers to a polar plot of the variation in tidal stream strength and
direction over a tidal cycle.
13
5.
PROJECT BACKGROUND
5.1
Introduction
Project Objectives
basis. This will in turn require the project to identify and quantify the trade-offs
between reliability, efficiency and cost of generic HATTs through the application of a
system approach. The overall economic performance will depend to a varying extent
on all aspects of the installation, operation, maintenance and decommissioning
approaches adopted.
While revenue assumptions have been made to derive comparative financial returns
from the two approaches, the most important output from the project is likely to be
the estimated cost of electricity delivered to the grid over each system lifetime,
assumed to be 20 years.
5.3
Project Process
When considering the Initial Project Specification, and the general concept of a tidal
current turbine, it is tempting to use modern wind turbines as models for
assumptions; some modern medium-sized wind turbines are operating routinely at
similar power and/or torque levels to the generic tidal device, so it might be
expected that certain major components or subsystems (e.g. gearbox) could be
translated into tidal current service with little or no modification.
This approach is of limited use; the conditions experienced by a tidal turbine are not
simply direct analogues of those experienced by a wind turbine, scaled by some
function of relative density and current speed. For example, tidal current velocities
are predictable over very long timescales and are not subject to random excursions
over these values, whereas wind velocity is an expression of a series of stochastic
processes, including random gusts. The tidal turbine arguably therefore needs
lower structural margins on rotor blades. Conversely, the tidal-turbine working
environment is corrosive, with suspended solids leading to at least the possibility of
15
erosive damage over the lifetime of the device. Another important consideration for
tidal turbines is the presence of marine life.
A comparison of some of the factors affecting wind and tidal stream turbines is
given in Table 5.1 below:
Feature
~1.25 kg/m3
~1025 kg/m3
~25m/s
2-5m/s
~12m/s
2-5m/s
50m/s +
Variation of velocity
with time
Stochastic, variable in
magnitude and direction
over timescales of the
order of seconds to
years.
Rotor diameter
(typical)
90-120m
Fluid density
Max velocity during
normal operation
Velocity for rated
output
Max velocity during
life
16
5.5
Unlike a wind turbine, the tidal stream turbine, being submerged, will have neither a
direct visual effect nor a noise effect on human beings in normal conditions. There
are, however, a number of areas in which submerged devices could have potentially
significant environmental impacts or raise safety considerations for other maritime
users and activities. Such areas include: ecology, pollution, coastal processes and
interference with the tidal flow, noise and navigation safety considerations. Such
issues will need to be taken into account in selecting a location for an individual tidal
stream turbine or an array of turbines, and are likely to have cost and time
implications. There is not likely however, to be a significant difference between the
environmental impacts of the two devices compared in this study; environmental
impacts are not considered further in this report.
5.6
As stated in Path to Power, the June 2006 BWEA report on wave and tidal power,
The UK possesses some 35% of Europes wave resource and 50% of its tidal
resource. BWEA, using data from the Carbon Trusts Marine Energy Challenge
(MEC), estimates that 3GW of wave and tidal capacity could be installed in the UK by
2020. .
In the long term, 3% to 5% of current UK electricity demand could be
met by tidal stream energy.
While there is clearly a substantial UK resource of tidal stream energy, by its nature
it tends to be located close to headlands in the west and north of the UK, which in
turn are less accessible from the existing grid infrastructure. Each location clearly
also has its own characteristics, with some such as Portland Bill being very
asymmetric in current speed and direction. The tidal ellipse for a specific location is
likely to be a major determinant of the technology to be applied, with the facility for
the devices to be rotated to meet the flow direction being much more important in
some locations than others.
5.7
17
5.8
Information was gathered on existing tidal stream energy capture devices and the
following were selected as offering the most direct comparison with the two HATT
devices being considered in the study.
Tidal Stream Turbines promotes a horizontal shaft two bladed turbine of 1 to 2 MW
for current design of 20m diameter rotors. The concept has undergone initial river
tests and water tank testing of a scale device is planned for 2006. Each turbine unit
is mounted on a horizontal structure attached to the main upright, the whole unit
being semi-submersible and attached to a gravity foundation on the seabed, which
will a llow the turbine to turn to follow the tidal flow. The turbine generator unit is
raised to the surface for maintenance purposes using the buoyancy of the nacelle.
Marine Current Turbines (MCT), probably the most advanced of the current
developers, offer 1MW horizontal shaft axial flow turbine units under the names
Seagen and Sea Array. Two full-size commercial units are due to be installed in
Strangford Narrows in Northern Ireland shortly. The turbine units, mounted in pairs
on a monopile, use variable pitch blades with a sufficient range of pitch change to
operate in both tidal flow directions. The structure includes a mechanism to raise
the turbines to the surface for maintenance purposes.
SMD Hydrovision has a horizontal shaft 2 bladed fixed pitch turbine with 18 m
diameter rotors device called TidEL, which comprises two 500 kW turbines mounted
on a frame designed to float clear of the seabed and to move in such a way as to
follow the tidal flow.
Figure 5.1
right)
Marine Current Turbines (above left) and 1/10 scale model TidEL (above
18
Swan Turbines Ltd are developing a horizontal shaft three bladed turbine. The
current programme is to develop a 350kW medium scale demonstrator unit,
together with modelling and cost optimisation by summer 2006. The plan is then to
install a pre-commercial system of 1 MW capacity between 2008 and 2010. Each
turbine unit is mounted on a frame attached to the seabed. The emphasis is on
simplicity and a gearless low speed generator, offering high efficiency over a range
of speeds, has been developed. The unit will be raised the surface for maintenance
purposes. It is not known whether the unit can rotate to follow the tidal flow or the
nature of its blade design, with fixed or variable pitch blades.
Hammerfest Strom AS is a joint venture between ABB, Rolls Royce, Statoil and
Sintcef. A 300 kW horizontal shaft axial flow turbine was installed off the coast of
Norway in 2003. The submerged structure weighs 120 tonnes and has gravity
footings of 200 tonnes. The three-bladed rotor is 20 m in diameter with a variable
pitch range that allows it to operate in both tidal flow directions. We do not have
any information on the performance of this prototype device.
Figure 5.2
right)
Tidal Generation Ltd is developing a 1 MW horizontal shaft three blade fixed pitch
turbine. A 1MW prototype unit is due to be installed at the European Marine Energy
Centre in Orkney in 2006. Commercial units are planned by 2010. Each turbine unit is
mounted on the frame attached to the seabed. The frame is a lightweight structural
design for easy installation and removal and is designed to follow the tidal flow.
Tidal Hydraulic Generators Ltd are developing a horizontal shaft axial flow turbine of
between 250 kW and 1 MW depending on stream velocity for an array of five 6mdiameter rotors. A prototype unit is planned for 2007 to be followed by a 10 MW
farm by 2009. The turbine units are mounted on a frame attached the seabed that
can be installed or lifted within a day. No information is available on whether the
blades are fixed or variable pitch to facilitate bi-directional flow.
19
5.9
This project is quite deliberately not specific to any existing or proposed device,
although it requires certain assumptions to be made. A conceptual generic tidal
turbine was defined, to the level of block diagrams, sketch layouts and some basic
performance and structural calculations, to provide a basis for cost and reliability
estimates, and to ensure that assumptions made in order to perform the study were
realistic. Some of the assumptions are also the subject of sensitivity studies.
The generic devices take the form of horizontal axis turbine assemblies each having
a single, un-shrouded rotor driving an electrical generator via an appropriate
mechanical transmission system. For the fixed-pitch machine, the rotor blades are
set at a fixed pitch, whilst for the variable-pitch machine, a mechanism and control
equipment is provided to allow the blade pitch to be continuously adjusted in order
to maximise energy extraction from the tidal stream and the nacelle is able to rotate
about the vertical axis so that the rotor axis is always in line with the current flow.
The designs for both the fixed pitch and variable pitch options use cage type
induction generators connected to power conversion electronics systems to provide
a 50Hz supply to the grid from the variable-frequency generator output, over a fairly
wide range of input rotational speeds. For the variable pitch option it would be
possible to operate the turbine at fixed speed and use a simple cage
induction generator connected directly to the grid. However, the directly-connected
asynchronous (cage) induction generator could only operate to generate power over
a narrow range of rotational speeds close to the synchronous speed, with little
opportunity to maintain optimum tip speed ratio over the range of tidal conditions
encountered. The hydrodynamic capacity factor for this type of installation would
be much lower than for the option including power electronics, and the directly
connected option was therefore not considered further for this study.
5.10
The initial outline for the project proposed two variants; Option 1 being a fixed-pitch
device and Option 2 being a variable-pitch device with the following idealised
parameters:
Blade Pitch
Flow Direction
Rotor Axis
Rotor Axis Depth
Maximum Rotor Diameter
Nacelle Body
Current Speed
Starting
Table 5.2
OPTION 1
Fixed
0 and 180 degrees
OPTION 2
Variable
0 degrees
Horizontal
20m
20m
2.5m diameter by 6m long
0 to 5 m/s
Self-start at current speeds > 1m/s
20
In order to frame the project, a specification was created for a generic device. The
values quoted below are considered reasonable initial assumptions for a device to
operate in some of the more attractive UK sites, but should not be interpreted as
representing the economically optimum device. The values quoted in Table 5.3
below should be considered to be generic and are not necessarily completely
consistent with each other.
The choice of 2.5m/s rated velocity was determined by study of Reference 1, with the
intention of making the study applicability as wide as possible; in terms of peak
spring tidal velocity Vsp, 2.5 m/s is exceeded by 41 of the 57 sites listed, together
accounting for more than 95% of UK tidal stream resource.
The partners identified the 20m rotor diameter and 1MW unit rated power per device
early in the project and, for the purposes of whole life cost analysis, deployment of
30 such devices to make a 30MW wind farm. These assumptions are consistent with
the prototype device and large array definitions in the 2006 BWEA report The Path
to Power. The Path to Power identifies four stages of marine renewable
deployment in the UK. The capacity definitions for these stages of deployment are:
Prototype devicesingle pre-commercial device up to 1MW in size
Small arraysmall arrays up to 5MW in total export capacity
Large arraylarge arrays up to 30MW in total export capacity
Significant projectcommercial projects in excess of 30MW
Parameter
Value
Unit
1
2.5
MW
m/s
2.0
20
4
10
m
m
Water depth
Number of blades
40
3
Transmission voltage
Cable distance from device to shore
33
5
kV
km
30
Table 5.3
Device assumptions
The power conversion solution selected will comprise rectifier equipment located in
each turbine nacelle, which will convert the variable frequency AC output from each
induction generator to DC at about 3.3kV. The DC output from each unit is connected
via a common link to a single network bridge that converts the output from the tidal
stream farm to 50Hz AC. This network bridge may be located either on a dedicated
21
platform located centrally in the tidal stream farm, or onshore if the farm is close to
land. The output from this bridge is connected to the grid via a step-up transformer
to raise the output voltage to 33kV or 132kV.
22
6.
6.1
Hydrodynamic
Hydrodynamic Performance of HATT - Predictions
6.1.1 Summary
This WUMTIA study was the key element of Work Package 1, with the objective of
providing:
An understanding of the hydrodynamic behaviour of horizonta l axis tidal
turbines through use of basic theory, Blade Element Momentum (BEM)
analysis and finally a Lifting Surface Panel (LSP) code, and
An answer to the relevant question of by how much a mechanically complex
controllable pitch turbine outperforms a simple fixed pitch, bi-directional
system.
WUMTIA initially confirmed the basic theory, identified relevant computational tools
and developed a methodology to define the turbine blades and analyse tidal
behaviour. Validation studies were carried out using BEM and LSP code. The
developed tool for investigating tidal behaviour was used to investigate a number of
different concept HATTs. A study of comparative performance has shown that the
use of a variable pitch system has only a limited influence on the delivered energy.
However, the ability to vary the pitch allows machine power to be limited to its rated
value for higher current speeds.
6.1.2 Background
The performance of devices that use the kinetic energy associated with a current or
wind the performance is that of a low-head (wind or tidal) turbine. In this case the
available power P for a given device capture area A and associated wind/current
velocity V is
P = Cp 12 AV3
where the power coefficient Cp is a measure of the overall hydrodynamic efficiency
of the device. This will depend on the tip speed ratio (blade tip speed to current
velocity), Mueller, (2005). The theoretical (Betz) maximum efficiency is 0.59 with
practical values lower than this. The much greater density of water results in a tidal
turbine being able to generate comparable amounts of power to a wind turbine with,
for example, 20% of the diameter of a wind turbine and in a current of 30% of the
wind speed.
The gravitational attractions of the moon and sun, as the earth rotates, generate
local tidal currents converting potential into kinetic energy. The magnitude of the
local tidal range is influenced strongly by the local seabed bathymetry and shoreline
orientation. The local behaviour of tides is controlled by dominant semidiurnal
(period 12hrs and 25 mins) and diurnal periods and with monthly variations in
maximum and minimum range (spring and neap tides). Predicting the time of local
high and low tides and to a lesser extent their magnitude has occurred for many
centuries. It is this predictability that makes the use of tidal energy attractive. The
23
key is the behaviour of the local tidal range, back flow and secondary induced flows.
It is usual that tidal currents will be most strongly associated with close-to-shore
locations that ease the problem of connecting the generating system to the local
electricity network. Although tidal energy is the main source of marine currents,
additional oceanic (geostrophic) currents such as the Gulf Stream could also offer
possible locations although these will more usually be associated with deep water.
The amount of energy that can be extracted from a given location will be associated
with the appropriate selection of possible type/capacity of the extraction device. For
example, estuarine barrage schemes are able to extract significant amounts of
power; the La Rance scheme in France has a generation capacity of 240MW based
on a basin area of 22km2 and a tidal range of 8.55m. However, other types of device,
principally variations on vertical or horizontal axis rotating systems, will only be able
to extract energy associated with that of the mean current within their capture area.
For horizontal axis machines, this will be controlled by their blade diameter and for
vertical axis machines by their height and diameter. The complete reversal of flow
will result in times when the local current is below a critical value for viable
operation of the device. In addition the tidal range will possibly constrain a
minimum water depth in which the device can operate and likewise the magnitude
of the current will drop in rough proportion to the increase in local water depth.
6.1.3 HATT Concepts
There are four main strategies for operating HATT:
(1)
Fixed rpm, fixed pitch:
(2)
Fixed rpm, variable pitch: as tidal current increases, control pitch to
maximise energy capture within the rated power of the generator.
(3)
Variable rpm, fixed pitch: as tidal current increases, control rpm to
maximise energy capture within the rated power of the generator.
(4)
Variable rpm, variable pitch: as tidal current varies control both rpm and
pitch to:
a. Maximise energy capture within the rated power of the generator.
b. Maximise power within generator set limit.
The variable direction of the tidal current; primarily reversing by 180 degrees
through the tidal period gives the following design options:
Fixed pitch devices can also either azimuth the complete nacelle about the
vertical axis to face the tidal flow or weathervane the whole turbine system.
Alternatively the nacelle could have a fixed orientation at a given site, to
24
minimise yaw effects over the tidal cycle, with the blade section shape
designed to work as a bi-directional device.
An interesting design choice for bi-directional devices is whether to use a high
performance asymmetric section with much poorer performance when working in
opposite direction flow or use a symmetrical section that performs the same in both
directions.
6.1.4 Available computational tools and analysis
The following computational tools were used by WUMTIA during the analysis:
Blade Element Momentum Code (BEM) - existing Fortran code developed and
validated for predicting performance of stall regulated wind turbine blades as
a series of DTI/EU contracts up to the mid-90s.
PropGen - an in-house code to automate the process of defining a rotational
propeller or turbine blade originally developed to produce marine propeller
geometry suitable for use with Palisupan and other codes, and modified to
generate a horizontal axis wind turbine/tidal turbine with a final prescribed
wake pitch specified by the user.
Palisupan - a surface panel code developed by Turnock initially to investigate
ship rudder/ propeller interaction which provides a reasonable compromise
between computational effort and physical accuracy in modelling the flow
interaction achieved by the use of a lifting surface panel method.
Adaptflexi - a powerful geometry manipulation system that its purpose
designed to generate high-quality surface panels and RANS (Reynolds
Averaged Navier Stokes) meshes. Palisupan is integrated within its
environment to automate a geometry definition and post-processing analysis.
Panvise - a visualisation tool matched with Adaptflexi and Palisupan.
Cp Comparison
Figure 6.1
0.5
0. 45
Fixed
0.4
0. 35
Variable
0.3
Cp
0. 25
0.2
0. 15
0.1
0. 05
0
0
10
TSR
25
12
14
16
18
26
There are limitations imposed by the scale of the study and for the devices in
question there is only limited operational experience available so the design
constraints associated with, for example, marine growth had to be estimated. The
objective of the optimisation study is to maximise power output through a complete
tidal cycle. As shown in the previous study, power is proportional to the cube of
tidal current speed and so the highest possible power is only generated for a limited
amount of time.
One of the constraints of HATT arises from the relatively low stream kinetic energy
extraction efficiency. The most advanced devices operating today are targeting an
efficiency of around 40-45%; however the Betz theorem limits efficiency to 59.6%.
The following strategy was adopted for selecting viable blade designs: design and
select section, optimise planform/pitch/blade setting, evaluate selected blade
performance, evaluate the blade loading, modify section thickness, modify blade
root and, finally, check performance.
The main constraint on selected blade shape is the ability to withstand the applied
design load, the control of which is through selection of a suitable thickness/chord
ratio. Altering the blade taper can control the root bending moment. A further
constraint for the variable pitch device is the method by which the hydrodynamic
shape is merged into the necessary circular cross-section at the blade root to allow
for blade pitch change. It was only possible to make a rough assessment of the
likely performance degradation of the proposed new bi-directional sections with
cavitation number.
Experimental evidence suggests that tidal turbines may experience strong and
unstable sheet and cloud cavitation, and tip vortices at a shallow depth of shaft
submergence. Acceptable levels of cavitation on marine current turbines are not yet
clear. Another factor to be considered is how different blade materials will respond
to possible cavitation erosion.
The tidal cycle performance analysis program, developed as part of Work Package 1,
was further modified to include a final control strategy. This strategy assumes that
the rate of revolution of the blade can be modified within prescribed rpm limits,
typically plus or minus 50%, to find the tip speed ratio that gives maximum delivered
power. A further refinement is that this can be modified to limit power output at a
rated power, typically chosen to be 10% above rated value.
6.2.2 Blade Parameters and Optimisation Tools
The optimisation study required a series of suitable shape definition parameters. A
reasonable blade shape for a tidal turbine, based on a wind turbine, had been found
in the first series of investigations. The method of parametrically adjusting this
shape provided a reasonable approach for determining which blade shape
parameters should be chosen.
27
The basic BEM code, cwind, used in the first phase, was extensively reworked and a
series of 9 variants (tidal_bemv1:9) were developed to facilitate an automatic
optimisation approach.
A spreadsheet was developed to allow the full geometric shape definition required
for the surface panel code to be developed from the same parameters found in the
optimisation study. The shape was specified at 10 spanwise stations starting at an
initial hub/blade diameter ratio of 0.2. A later study confirmed that only small gains
in performance are obtained if smaller values are used (2%). In a real design this
region is primarily structural and contributes a limited amount to performance.
The overall pitch setting of the blade, along with the blade tip speed ratio (TSR),
determines the thrust and power developed. These were dimensionalised in terms
of, for this study, three blades with a maximum diameter of 20m. Blade chord, pitch
and thickness were required for the blade at each spanwise station. Together with a
specified section sha pe, known for the variable pitch blade and derived for the bidirectional blade, this allowed a ruled shape to be constructed. Variations in shape
were controlled by modifying the blade taper, area, pitch and thickness.
The optimisation process explored the geometric design space as well as the range
of TSR and blade pitch settings. The execution of the analysis required an iterative
solution to capture the necessary operating angle of attack for each section. This
was accomplished, resulting in a simple strategy of exploring each variable at equal
separation between a minimum and maximum constraint. Typically, such a global
search created of the order of 33,000 evaluations. Once an optimum had been found,
2 or 3 additional cycles of user specified progressive refinement was usually
sufficient to finalise the design. The large number of evaluations gives a clear
indication of the sensitivity of the design space to the various choices of design/flow
variables.
6.2.3 Bi-directional fixed pitch tidal turbine blade
The most important component of the bi-directional concept is the identification of a
section shape that works equally well in both forward and reverse tidal directions.
Such a shape requires 180deg rotational symmetry about its mid-chord. Previous
work at the University of Southampton has developed a similar concept for use with
rim driven marine thrusters.
In this work, the 2D section analysis code, Xfoil, was used to analyse the
performance of a range of angles of attack up to the initial onset of stall (separated
flow). This section lift and drag performance is required by the BEM code. A
sensitivity study was carried out for the effect of thickness/chord ratio (t/c) on lift and
drag. It was found that the section shape performed best at its design t/c. In
principle, a section shape could be optimised for each of the required spanwise t/c.
This was beyond the resources of this study but would be required for a final design.
The analysis carried out of this numerically developed bi-directional section does not
allow prediction of performance beyond stall. This information is important in being
28
able to predict such performance parameters as turbine starting torque and runaway
speed. However, section performance beyond stall can be extrapolated based on
knowledge of measured section performance. It is well documented for wind
turbines that experimentally measured 2D stall parameters under-predict the section
lift beyond stall on a real blade. This is because the rotating blade causes spanwise
flow within the stalled region on the downstream face of the blade. This effect was
measured in the early 1990s at the University of Southampton and was used to
make an estimate of the likely behaviour beyond stall. For a limited number of
cases, the sensitivity of this assumption was assessed by varying the values used in
the section performance curve.
Figures 6.2 and 6.3 show the performance (Cp vs. TSR and Ct vs. TSR) for the final
blade shape. The shape of the curve reflects the performance of the section with a
more limited range of operation without stalled flow. However, at the maximum
power condition (N=17rpm, U=2.5m/s) all of the sections are operating on or close to
their optimum angle of attack (eg max lift/drag ratio). Figure 6.4 shows the torque
generated with a 2.5 m/sec current.
Power Coefficient, Cp
Structural analysis was assessed using the surface panel code. Figure 6.5 shows a
typical output indicating local surface pressure variation. This can be imported
directly as a load map for use with a commercial finite element analysis code.
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
0
6
TSR
Figure
Figure 6.2 Cp performance of Optimum Bi-directiona l blade
29
10
Thrust Coefficient, Ct
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
0
TS R
Torque, MNm
0.6
0.5
0.4
0.3
0.2
0.1
0
0
10
15
RPM, N
30
20
25
10
A
simpler
beam theory
approach was used to find the
appropriate
spanwise
t/c
variation. It is worth noting
that the design loading case is
driven by the maximum
spring tide (rather than
extreme events as required
for
wind
turbines).
Hydrodynamic
loads
(primarily
in
the
flow
direction)
rather
than
centripetal loads dominate in
the radial direction.
This
allows greater mass to be
placed at higher radii and
reduces the need for small t/c
towards tip. As a result the t/c
Figure 6.5 Pressure map
distribution
for
the
bidirectional blade can have a much smaller variation and the section will be operating
in its known range.
The surface panel analysis also provides a check of performance against that
predicted by the BEM code. Definition of the correct downstream turbine wake is
important for obtaining satisfactory performance. Fortunately, BEM analysis can
supply most of the necessary information to construct such a wake. The
construction of a suitable LSP mesh requires considerable care to achieve a high
quality mesh with regular quadrilaterals that control panel size, aspect ratio, low
skew, lack of planarity and proximity. The low pitch of the blade and its intersection
with the assumed hub provided a considerable challenge.
6.2.4 Variable pitch turbine blade
A similar approach was followed for the variable pitch blade with the
planform\optimisation resulting in a significant improvement in performance giving
a maximum Cp of 0.49, Figures 6.6, 6.7 & 6.8. Figure 6.9 shows the optimum pitch
angle setting as the tip speed ratio varies.
31
Power Coefficient, Cp
0.6
0.5
0.4
0.3
0.2
0.1
0
0
10
15
20
25
30
20
25
30
40
50
60
TSR
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
0
10
15
TSR
Torque, MNm
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
0
10
20
30
RPM, N
32
25
20
15
10
5
0
-5
10
15
20
25
30
-10
TSR
T
0.5R 2U 02
QR
0.5R 2U 03
34
Power Coefficient, Cp
0.6
0.5
0.4
0.3
Variable Pitch
0.2
Bi-directional
0.1
0
0
10
15
20
25
30
TSR
Fixed
RPM
(17.0)
Constant
Pitch
166
156
167
Variable
RPM
Constant
Pitch
177
163
177
The total capacity is taken to be the rated power over 29.4 x 24 hours. For the three
rated generators of 1.14, 1.0 and 0.68 MW the energy they could have absorbed
would be 802, 704, 481 MWh respectively.
For the purposes of the economic
assessment hydrodynamic capacity factors of 23% and 25% were used for the bidirectional and variable pitch devices; based on a rated 1MW generator capacity (802
MWh) and 20m blades. Hydrodynamic capacity factors assume 100% reliability and
100% availability. It is worth noting that a 1m increase in blade diameter will allow
the bi-directional device to capture the same amount of energy as the best
performing 20m variable pitch devices.
35
36
7.
7.1
Generic block diagrams have been developed to illustrate the main relationships
between the various elements of the fixed-pitch and variable-pitch approaches.
These relationships have been quantified to allow important design considerations
to be identified, e.g. cooling requirements and size of components. The purpose of
the block diagrams is to indicate the main generic influences exerted by each
element on the others, without causing the diagrams to be specific to a particular
solution. For example, the heat flow from the generator to the nacelle volume may
in practice take place as a fluid flow of air circulated by the generator cooling-fan, if
the machine is so equipped.
Atmosphere
SEA
Rotor
blade
Main
shaft
seal
Nacelle
volume
Pitch
joint
Rotor
shaft
Main
gearbox
Hub
Bearings
Main
shaft
brake
Nacelle
switchgear
Cable
Generator
Shore
Hydrodynami c ef fect
Ancillaries
Mechanical power
Force / t orque
E lectric power
Heat t ransf er
Fluid f low
Nacelle
structure
Figure 7.1
Rotator
Pylon
Base
SEABED
Variable--Pitch Machines
Initial Conce ptual Block Diagram for Fixed and Variable
Components specific to
variable pitch device
The block diagrams do not represent all possible solutions, e.g. where a generator is
designed for direct drive. Each device includes components and systems not
directly part of the main power flow path, but important for practical operation.
Some of these features are listed below. The list is not exhaustive; some of the items
are optional, some complementary, or alternative means to achieve the same end. In
some cases the details of the equipment described by a particular heading will differ
between the fixed pitch and variable pitch systems. This study assumes common
37
components between fixed pitch and variable pitch designs unless commonality is
impractical or implicitly precluded.
Examples of ancillary components and systems that might feature in a tidal current
turbine include: rotor brake (capable of stopping rotor), rotor lock (prevents rotation
of already stationary rotor), bilge pump, nacelle pressurisation system, rotor shaft
seal, inflatable rotor shaft seal, cathodic protection system, anti-condensation
heater, navigation/anti-collision lights, control system, deployment/retrieval related
systems (e.g. winch, ballast pump), condition monitoring system, nacelle rotator
system and brake. Some of these components are indicated explicitly on the initial
system block diagram above, whilst others could be considered to be included in the
Ancillaries block.
An un-shrouded tidal turbine for 1MW power output is unlikely to turn faster than 20
rpm, and may well turn more slowly. Most conventional e lectric generators require
an input shaft speed two orders of magnitude higher. Appropriate arrangements
must therefore be provided to generate electrical power in a suitable form for
onward transmission. There are several ways in which this problem may be
addressed.
For both fixed and variable pitch devices, the main power flow is from the tidal
stream to the grid, via a rotor, transmission, generator and electrical interface
(generator and some form of power conditioning). These items are analogous with
early wind turbine experience and there are several approaches for these
components, provided the concepts for transmission, power conditioning and
generator are technically consistent. The concepts for a practical fixed pitch and a
practical variable pitch device considered in this report may not be strictly optimal
for a practical machine, but will be reasonable initial assumptions. The main options
for the transmission and generator type are listed below.
Possible Gearbox / Generator
Combinations
TwoTwo-stage gearbox
(ratio 1:6 4 max)
ThreeThree-stage gearbox
(ratio 1:512 max)
Unlikely
Possible
Unlikely
Feasible option
Feasible option
Feasible option
Induction (asynchronous)
DoublyDoubly-fed induction
Synchronous
Table 7.1
Permanent magnet generators with direct drive or single stage gearbox options
were considered but discarded for the purposes of this project, but they may well
reappear as permanent-magnet generators become better developed. The main
issue related to the control of the permanent magnet generators under fault
conditions; necessary increases in rating for the power electronics to cope with the
higher voltages generated during overspeed could undo the economic premise of
the fixed pitch device.
38
The induction generator was chosen to avoid the need for regular brush
replacement, which would be an intrinsic feature of either a suitable synchronous
generator or the doubly-fed induction generator options.
The use of fixed speed, directly connected, induction generators for the variablepitch option was considered. However, the reduction in revenue (due to the lower
capacity factor) together with the need to purchase reactive power from the grid
made this option less attractive than using a variable pitch, variable speed
generation system with power conversion equipment. Hence for the variable pitch
turbine, the studies were conducted using variable speed turbines with induction
generators connected to the grid via power conversion equipment.
7.2
At the very outset of this project, it was thought that there would be a significant
difference between the generator and power conversion systems required for the
fixed pitch and variable pitch devices, with the system for the variable pitch device
likely to be analogous to the doubly fed induction generator systems used for
modern wind turbines. The system for the fixed pitch, bi-directional, variable speed
device was expected to require more complex, and expensive, power conversion
electronics.
In discussion with Converteam, however, it became clear that the same generator
and power conversion system approach could be applied to either the fixed pitch or
the variable pitch device. A number of different systems were considered in
conjunction with Converteam, including the following:
Option
The first option was a simple system consisting of a single
Option 1
turbine, AC generator and power converter with a step up transformer. This
arrangement is usually used in near to shore, low-power projects, and would
be suitable for a pilot project or technology demonstrator. It would be a poor
choice for a farm as there is no opportunity to take benefit from the common
costs of a farm installation.
39
Option 2 The second option, involving multiple generators each with a dedicated
power converter, would provide a high level of system flexibility, allowing
generators to rotate at different speeds as well as individual generators to be
shut down. However the system is complex and it would be a high-cost solution
with no cable or transformer redundancy.
40
to a single network bridge that converts the output from the tidal stream farm to
50Hz AC. This network bridge may be located either on a dedicated platform located
centrally in the tidal stream farm, or onshore if the farm is close to land. The output
from this bridge is connected to the Distribution Network.
7.3
42
by the relevant Distribution Operator for connection and the levels referred to in the
documents listed discussed and adhered to.
G75:
7.5
The device mounting structures have been assumed to be either a monopile with
one or more devices per pile (sketches a & b below), or mounted on cross-arms or a
semi-submersible structure anchored to the seabed and allowed to swing with the
current direction (sketches c & d below) . The variable pitch devices mounted on a
monopile will have rotating mechanisms to turn the devices during slack water to
face the next tide tidal flow. The cost of the two installation methods has been
assumed to be similar, within the scope of this project.
There are numerous proprietary approaches to the provision of maintenance access
to tidal turbines, some the subject of patent applications or grants. Nothing in this
report should be regarded as a comment on any specific system. However, the
maintenance access systems may be divided into three broad categories, which will
have different costs relating to the type and size of boat/ship/crane and time taken to
carry out the operations:
43
Maintenance of the tidal turbine with the device mounted in the operational position
will be affected by weather conditions, the mounting concept and resulting
accessibility. For the purposes of this project, we have assumed that it will be
necessary to remove the device from the mounting structure and either carry out
repairs to the device on a surface vessel, or return it to shore. In the latter case a
replacement device could be installed in the same operation.
A related issue is the provision of appropriate facilities to allow safe human access
to the interior of the installation. The project has recognised the importance from
both a cost and safety perspective of minimising the use of divers in the
construction and maintenance process but detailed consideration is outside the
scope of this project.
44
7.6
In deriving a cost for the operation and maintenance (O&M) for a tidal stream
turbine device it has been necessary to make a number of assumptions since no
units have yet been installed anywhere on a commercial basis, and hence there are
no data bases or track records that can used. The scheduled O&M cost has been
calculated on the assumption that a tidal stream farm comprising 30 off 1MW
individual units is installed at a location 5km off the UK coast line, and that a suitable
overhead line connection is available close to the shore. Scheduled maintenance has
been based on an annual service visit to each turbine module with a major overhaul
every five years when the complete turbine nacelle would be removed from its
mounting and taken to a shore facility. Note, however, that costs of such operations
are modelled as constant annual fees that are applied as average per-period cash
flows.
The design of the turbine nacelle mounting system has not been defined as part of
this study, but the same support system is assumed for both fixed pitch and variable
pitch turbines, enabling a valid comparison between the maintenance costs of both
types of turbine to be made. To keep maintenance costs to an economic level, and to
minimise delays due to adverse weather, the turbine mounting support system
would be designed so that turbine nacelles can be brought to the surface and be decoupled from their mountings without the use of divers or a floating crane. However,
it is assumed that divers would carry out an inspection of each turbine support
structure every 5 years. This maintenance regime is seen as a conservative cost
basis. The intention would be to include sufficient monitoring equipment to enable
the annual maintenance visit and 5 year overhaul periods to be extended so that
scheduled visits to each turbine could be extended to once every 5 years and the
major overhaul period extended to 10 -15 years.
Control, monitoring and operation of the tidal stream farm is assumed to be from a
remote facility that is an existing generating plant and that the operators of that
plant could monitor/control the tidal stream farm without additional manpower
resources. A high level of SCADA equipment would be included in each tidal stream
turbine to ensure that all the important parameters were available both to operators
in the control centre and to maintenance staff.
For the purposes of this study the major mechanical and electrical components
housed in the nacelle, along with the rotor blades, were considered as a single
replaceable unit for the purposes of maintenance, and have been termed a Line
Replaceable Unit (LRU). In the event of a failure of a component in the LRU, or for
some aspects of scheduled maintenance, the LRU would be removed as a complete
unit by a support vessel and either repaired or returned to shore for more major
servicing. To maximise the availability of the complete system, the support vessel
could install a serviceable LRU to replace that removed for maintenance/repair.
The scheduled maintenance requirements for each turbine are based on typical
scheduled maintenance requirements for offshore wind turbine units with
appropriate modifications for tidal stream turbines. Estimates of the frequency and
45
costs of unscheduled outages have been calculated using the Monte Carlo
simulation method. This estimates the probability of failure for each type of turbine
and the time taken before the unit is returned to service (failures solely causing
degradation of output are not modelled). Using this system, and allocating an
average cost for each intervention to repair a failed component, the unscheduled
maintenance costs for fixed and variable pitch turbines can be calculated.
The total scheduled O&M cost for a tidal stream farm of 30 units is estimated at
1.125m p.a. for a fixed-pitch installation, and 1.209m p.a. for a variable-pitch
installation. The costs have been derived from maintenance cost data for offshore
wind farms, which operate in a similar environment. This equates to an annual cost
per LRU of 5% of initial capital cost. The unscheduled outage costs for a tidal stream
farm have been estimated using North Sea Oil installation reliability data. The data
were used to provide an estimate of the number of failures, and thus number of
interventions, per period.
Unscheduled maintenance costs are modelled as a percentage of LRU cost (to reflect
an average cost of repair) plus a fixed fee per intervention (to reflect any special
charter/hire provisions or specialised crew fees which may be applicable). These
figures include the cost of intervention for unscheduled outages and the loss of
electricity production for the unit downtime. Overall availability is modelled as
scheduled availability (95% used for all cases) multiplied by unscheduled availability,
which is derived from the Monte Carlo simulation. This depends on device reliability
and repair probability, which in turn was based on the probability of suitable sea
conditions (when the significant wave height was less than 1m).
7.7
Decommissioning considerations
It is almost inevitable that the landlord for any of these devices around the UK will
be the Crown Estate, who will include as a requirement of the lease or licence an
obligation to decommission the offshore installation, but not necessarily the cables,
on completion of its useful life. This requirement is in the process of being
reinforced through a DTI consultation. On the assumption that the mounting
structure will consist of a monopile, the requirement is likely to be to remove the
structure to a level some distance below that of the surrounding seabed. This
requirement will of course be common to both the fixed pitch and variable pitch
devices. A notional sum has been included in the cost model.
7.8
System design
design assumptions
The list below details the main assumptions used in the performance of this project,
in addition to those in the Background above.
46
Assumption
Fundamentals
Output takes the form of
electricity.
Remarks
Exclude outputs in the form of mechanical
power, compressed gas, hydraulic power, heat,
electrolysed hydrogen, desalinated water,
chemical reaction product or other energy
vector or commercially valuable commodity
50Hz, appropriate voltage & frequency limits etc.
for compliance with Grid and Distribution Code.
Neglects variation that may occur between
individual sites in a farm. Implies that applicable
data for UK conditions are readily for the study.
47
48
8.
8.1
The development and use of tidal turbines will require economic justification at a
variety of levels. The development of the tidal turbines and their installation
methods will require Original Equipment Manufacturers (OEM) to be satisfied that a
viable market exists for their products. At the other extreme the electrical utilities
that will buy the output and potentially develop, own and operate the tidal farms
will need to be satisfied that the electricity produced by the tidal turbines can be
utilised for an economic return in an auditable manner. If this utility business
rationale is not satisfied then the market will not develop and the OEMs will not be
attracted. For the purposes of this study the business model has been created from
the electrical utility viewpoint, with the sole revenue source for the business deriving
from the sale of electrical energy into a grid system and the relevant renewable
financial support/incentive mechanism.
The purpose of this study is to assess the relative economic performance of two
broadly similar devices that are physically different in detail. It is thus clearly
necessary to consider all factors having a significant impact on the cost of the
devices and on the revenue earned by the devices. Since the devices only generate
revenue in the context of a working farm, it is also important to appreciate costs
and benefits that are common, or broadly similar between the two devices. These
additional costs and benefits affect the sensitivity of the study result to the
differences between the machines.
Reliability and availability simulations, together with cost estimates for capital and
maintenance costs, are fed into a spreadsheet, which provides a comparison of cost
and revenue performance for each machine in the context of a farm of a specified
number of machines installed according to a user-defined schedule and (if so
desired) automatically replaced at the end of their useful life (which may differ
between the fixed- and variable-pitch machines). Costs common to both machine
types are included at this stage. The spreadsheet model run duration was chosen to
be 30 years to encompass the assumed 25-year mounting life and so to allow costs
for decommissioning to be included.
Fault Tree Analysis (FTA) was chosen in preference to Failure Modes and Effect
Analysis (FMEA) for the reliability elements of this study because it was considered
easier to construct a generic analysis. To use FMEA, it is necessary to consider in
detail each failure mode of each important component, which implies a level of
detail design definition inconsistent with the aims of this study. The FTA technique
allows a generic failure to be described without detailed consideration of the precise
nature of the failure.
The block diagram at Figure 8.1 below describes the solution process followed.
49
Figure 8.1
VARIABLE
FTA1
Reliability
RMC1
BOTH
Gearbox
Generator
Block diagram 2a
FIXED
FTA1
Reliability
RMC1
Accessibility
Assessment
Yield
Availability
Maintenance
Yield
Availability
Maintenance
Cost Comparison
GREEN items refer
to data for
VARIABL E pitch
m achine
KEY:
FTA1 = Fault tree analysis spreadsheet
RMC1 = Monte Carlo analysis spreadsheet
Blockdiagram2a = Generic tidal turbine system
initial design tool
Gearbox1 = Epicyclic gearbox initial design tool
50
RED items
refer to data for
FIXED pitch
m achine
Accessibility
Assessment
Installed
machines will not
always be
accessible/repaira
ble owing to
weather
conditions
8.2
The simulation model used to predict reliability and availability levels for tidal
stream turbine farms is based on the Monte Carlo method, described in Appendix
A. The result of any Monte Carlo activity is always a simulation of the process, not
an analysis of it. In principle, two successive Monte Carlo simulations of the same
event with identical initial conditions will produce different answers. These answers
will, however, be such as to permit the estimation of a true value within some
confidence interval.
Monte Carlo techniques are generally most suitable for situations where the
probability equations for the process are intractable or, possibly, not capable of
explicit formulation. The complexity of this approach increases geometrically with
the probable number of failures during the device lifetime. The explicit calculation
method also becomes more complex if the probabilities of each event are
themselves functions of some other variable.
A situation that was considered as part of this study was the effect of seasonal
weather conditions on the repairability of the device, assessed for the purposes of
the study by assuming that repair probability PUA is a function of elapsed time. The
underlying assumption is that whilst the possibility of repair depends on the
availability of appropriate spare parts and other resources, an overriding
consideration is simply whether the device is accessible in order for the repair to be
performed. For example, a device which fails at the onset of winter is likely to be out
of commission longer than one which fails identically at the height of summer,
simply because weather conditions preclude maintenance access to the former
device.
For this study, several mode lling approaches were considered before construction of
the actual models. All the models use the concept of time measured in periods,
with values chosen to be of significance to the desired outcome. No specific
timescale is explicitly defined for a period; it needs to be long enough to allow
modelling of a meaningful proportion of the device lifetime, but short enough to
capture detail. An instance of unserviceability can never be shorter than a complete
period, so use of excessively long periods will lead to unrealistically low estimates of
device availability. It is vital that values of transition probabilities used in the
simulations are scaled to match the period chosen for the series of experiments. For
this reason, use of excessively short periods not only results in extra computer time,
but also implies that failure probabilities (as entered) become negligibly small.
Typical period and experiment durations used for this study included:
240 periods (20 years with 1 period 1 month)
312 periods (6 years with 1 period 1 week)
1560 periods (30 years with 1 period 1 week)
The reliability of the fixed and variable concepts was assessed using data taken from
the OREDA handbook (Ref. 10). This handbook is a DNV publication providing
statistical data from Offshore Oil & Gas operations (ENI, BP, Exxon, Norsk Hydro,
Phillips, Statoil, Shell, TotalFinaElf). The data are considered to be High quality
51
reliability data for both topside and sub sea equipment, giving failure modes,
observed number of failures, failure rate, uncertainty limits etc. Data are given as
number of failures in 106 hours, for mean, upper and lower values (90% confidence).
An example of the OREDA failure rates and the overall calculated failure rates for the
concepts is shown in Table 8.1 below.
OREDA Data
Fixed
52
143
3
Mean
Max
Min
No of failures *
Variable
71
194
5
Unplanned Availability
Fixed
Variable
92.6%
90.1%
81.1%
74.5%
99.6%
99.4%
*Mean number of failures per device over 30 years, determined from the Monte
Carlo simulation. This was converted, assuming a constant failure rate, to a number
of failures per turbine per unit time for cost modelling purposes.
Table 8.1
8.3
Units
MW
%
Years
Fixed Pitch
Farm
30
23
15*
2006
10%
Variable Pitch
Farm
30
25
15*
2006
10%
* 15 years for principal LRU life, other elements have longer assumed lives.
Table 8.2
Financial assumptions
52
Figure 8.2
Initial cost: Incurred at the start of the project, and covers elements such as land
purchase, construction of roads, buildings, transformer bunds and similar items
which could be considered to have infinite life within the context of a tidal
turbine farm.
Farm-level capital equipment (FLCE): Paid once at start of project and upon FLCE
life expiry. Includes items associated with farm operation but having finite life,
such as grid connection equipment, workboats and so on.
Shore-based equipment (SBE): Covers purchase and replacement of items
associated with individual turbines but located ashore, the prime example being
the network bridge equipment.
Mounting: A device designed to hold one or more turbines, having a finite life but
modelled as having zero failure rate. The variable pitch mounting includes
provision for rotating the nacelle.
Line replaceable unit (LRU): Essentially, the turbine plus directly associated
power generation and conversion equipment (gearbox, generator, device bridge
and ancillaries), all located subsea and having a finite life, finite failure rate and
weather-dependent access restrictions.
The costs have been estimated for the fixed and variable concepts. For the purposes
of the cost modelling results these costs have been factored to produce an overall
cost of 1.250m/MW for the fixed concept, which then produced a cost of
1.318m/MW for the variable concept. This represents a 5.4% increase in cost for
the variable pitch concept compared to the fixed pitch concept (consideration of the
original cost estimates showed the components added or increased in cost relative
to the fixed pitch items to represent a premium over the fixed pitch prices of about
7.5%; the overall effect including the items common to both solutions was then
about 5.4%).
Cost of connection to the grid was modelled using the assumption that the
connection would cost 120,000 per megawatt capacity, leading to a connection cost
for the farm as modelled of 3.6 million. This assumption requires caution in its
application because it is only a typically average cost for a 10MW to 20MW
53
installation. For smaller sites the cost of connection could be understated and for
larger sites, including the 30MW farm modelled, it could be overstated. It should be
recognised that the minimum cost of a connection at the present time (2006) is likely
to fall within the range 1 million - 2 million, and may be greater if the particular
circumstances dictate the installation of a significant length of overhead line. In
some circumstances, the connection cost could preclude the financial viability of an
otherwise attractive tidal farm. Annex E of Reference 15 discusses this topic further.
The cost estimates for a farm with 30 off 1MW units, with 2 units per mounting is
shown in Table 8.3 below. Operation & maintenance assumptions and estimates are
shown in Table 8.4.
Cost Item
Farm cost
Cost
Fixed
Variable
3,750,000
3,750,000 3,750,000
4,500,000
4,500,000 4,500,000
150,000
15
15
2,250,000 2,250,000
Mounting - Fixed
300,000
15
Mounting - Variable
322,500
750,000
806,250
Table 8.3
Cost estimates
54
Fixed
Variable
4,500,000
15
30
4,837,500
22,500,000
30
24,187,500
Total
37,500,000 39,525,000
Cost/MW
1,250,000 1,317,500
Operation and
Maintenance
Routine O&M
(per MW/year)
Major servicing
Intervals
p.a.
Variable Pitch
Total Cost (2006 )
40,300
5 yrs
included in above
included in above
Unscheduled
Interventions
(/intervention)
as required
24,000
25,700
Fixed annual
farm running
cost
p.a.
320,000
320,000
Rates
DeDecommissioning
costs, per
mounting
p.a
At yr 25 after
mounting
commissioning
included in above
25,000
included in above
25,000
55
Case
Description
1.0
1.1
1.2
6.4
9.0
9.1
9.2
9.7
Table 8.5
Number of failures
Annual Energy Total Energy Production
Hydrodynamic
per device over
Production
(25 yr)
Reliability
farm life
Capacity Factor
Availability
MWh
MWh
OREDA Fixed Variable Fixed Variable Fixed Variable Fixed Variable
Fixed
Variable
Mean
Max
Min
Min
Min
Min
Min
Min
1766
4838
112
112
112
112
112
112
23%
23%
23%
23%
23%
23%
23%
23%
25%
25%
25%
25%
25%
25%
25%
25%
88%
77%
95%
91%
95%
95%
95%
95%
86%
71%
94%
88%
94%
94%
94%
94%
52,641
46,108
56,663
54,340
56,663
56,663
56,663
56,663
55,044
45,557
60,721
56,738
60,721
60,721
60,721
60,721
Case
Description
Discount rate + 10%
Reliability
OREDA
1.0
1.1
1.2
6.4
9.0
9.1
9.2
9.7
Mean
Max
Min
Min
Min
Min
Min
Min
Table 8.6
1288
3564
66
66
66
66
66
66
Cost of electricity
55,044
45,557
60,721
56,738
60,721
60,721
60,721
60,721
94.00
150.00
68.67
71.09
65.46
66.72
66.10
55.23
128.95
218.89
91.44
97.05
88.37
88.63
87.74
70.50
103.97
188.82
68.73
73.04
65.74
66.91
66.34
55.15
1,316,031
1,152,692
1,416,579
1,358,503
1,416,579
1,416,579
1,416,579
1,416,579
1,376,109
1,138,916
1,518,019
1,418,458
1,518,019
1,518,019
1,518,019
1,518,019
8.4
In some respects the tidal turbine industry of 2006 is comparable to the wind
industry of the early 1970s, with a large number of possible permutations of the
various design options, a diversity of approach and a shortage of hard evidence as
to which approaches are likely to have a commercial future.
The principal objective of this study has been to identify any circumstances under
which simple but less efficient devices offer competitive life cycle performance to
complex but more efficient ones. The results demonstrate that the relative merit of
the two approaches depends upon the assessment criteria adopted and may be
summarised as follows, within the range of performance parameters studied:
The variable pitch machine (with an energy capture performance shown to be
notionally 10% better than that of the fixed pitch machine in the rotor
hydrodynamic study) produces more energy in a given period than the fixed
pitch machine, unless the absolute reliability of both machines is very low,
The fixed pitch machine always offers lower initial capital cost and unplanned
maintenance cost than the variable pitch machine,
The fixed pitch machine offers lower cost per unit of electricity generated unless
the absolute reliability of both machines is very high,
The percentage increase in energy capture using the variable pitch machine is
generally much less than the notional 10% difference given perfectly reliable
fixed and variable pitch machines; relative performances encountered during the
study implied that the variable pitch machine would generally produce 4 7%
more energy than the fixed pitch machine, although its worst performance
produced 1% less energy.
The cost analysis shows that to be economically viable the reliability of a real device
must equal or better the best reliability assumed for the study. This would seem to
be a challenging target, but it should be noted that the study configurations
incorporate no redundancy; it is possible that the overall reliability of a real device
could be significantly improved given careful detail design and the incorporation of
redundant features in specific areas.
It is recognised that the hydrodynamic capacity factors could be increased by
limiting the power output from the rotor, and using a generator rated at below the
maximum potential power available in the tidal stream. This would require a rematching of the rotor diameter to the generator, but should have the effect of
reducing the cost of electricity. Further consideration would need to be given to the
matching of the power conversion equipment, fault cases where the power output
exceeded the limit, and the impact on capital cost.
As indicated above, the variable-pitch variable-speed machine is superior in terms of
capital cost per MWh to the fixed-pitch variable-speed machine when the reliability
of both machines is very high. However, within the study, the maximum
improvement calculated for the variable-pitch machine was a cost per MWh less
than 4% better than for the fixed-pitch machine. Within the limitations of the study,
the fixed-pitch approach offers the more robust design concept, with the
theoretically better performance of the variable pitch device only being delivered
when high absolute reliability is consistently achieved. This reinforces the view that
it may be beneficial for designs to start simple (more robust and reliable) and later
on to become more sophisticated. Wind turbine development followed a similar
path.
Additional remuneration for renewable generation over the commodity price of
electricity generated is currently via an obligation on electricity suppliers to purchase
a specified portion of their supplies as renewable generation in the form of
Renewable Obligation Certificates (ROCs). At present there is no differentiation
between technologies but as electricity suppliers all face the same cost pressures
they tend to follow each others choices. Currently this choice is predominantly
wind.
The Government proposes to amend the Renewables Obligation (RO) following the
recent Energy Review and has issued a consultation proposing differentiated
support levels to different renewable technologies and give additional certainty on
long-term ROC prices. These changes to the RO will require new primary legislation
and so will not be introduced until towards the end of this decade at the earliest.
Tidal power, whilst having a popular appeal in terms of green-ness perception and
environmental impact, is arguably one of the more expensive in capacity terms of
the available technologies, certainly at this stage of its development. Its merits as
part of a renewable portfolio lie in the predictability of the energy source allied to the
perception that it is a development area whose time has come. While commercial
deployment of devices will help to drive down the capital and operating costs, tidal
power will need additional support while the successful concepts become
competitive renewable energy options. Therefore higher value ROCs should be
introduced for marine renewable technologies and be sustained while successful
concepts achieve their potential.
Although the options analysed produced a variety of outcomes, there is sufficient
encouragement to further investigate the fixed pitch device. The following activities
offer logical steps to the implementation of a commercially successful tidal turbine
device:
Further refinement of the economic analysis methods used to determine
parameters for an optimised device,
Develop design specifications for a tidal stream turbine system and apply
suitable processes to optimise the design point for a given set of tidal conditions,
Undertake further reliability modelling to determine plant redundancy
requirements,
Undertake model testing of bi-directional sections both for cavitation
performance and overall performance to confirm that predicted in the study,
Install a reduced scale version of the device (around 20 30% full scale) in the
field, probably with a dump load rather than a grid connection. Test results will
be used to finalise the design of the prototype unit,
58
59
9.
BIBLIOGRAPHY
Identifier
These references have been used in the study and are included for further
information.
Title
Phase 2 UK Tidal
Stream Energy
Resource Assessment
Design of Direct-driven
Permanent-magnet
Generators for Wind
Turbines
(PhD Thesis)
Calculation of Different
Generator Systems for
Wind Turbines with
Particular Reference to
Low-Speed
Permanent-Magnet
Machines
(Dr.-Ing Technical
Dissertation)
Author / Originating
Organisation
Remarks
Anders Grauers
Chalmers University of
Technology
Department of Electric
Power Engineering
Stephan Jckel
Technical University of
Darmstadt
2002
ISBN 3-8322-1512-3
Pub. Shaker Verlag
2003
60
Wind Energy
Explained
J.F. Manwell
J.G. McGowan
A.L.Rogers
2002
Principles of Electric
Machines and Power
Electronics
P.C. Sen
Professor of Electrical
Engineering
Queens University
Kingston, Ontario,
Canada
1989
Marine Energy
Challenge Marine
Energy Glossary
Richard Boud
Entec UK Ltd
10
OREDA Offshore
Reliability Data 4th
Edition
SINTEF Industrial
Management for the
OREDA Consortium
Distributed by Det
Norske Veritas
ISBN 82-14-02705-5
11
HSE Offshore
Technology Report
2001/030
13
Waves,Tides and
Shallow Water
Processes, 2nd Edition
Pub. Butterworth
Heinemann in
association with the
Open University
ISBN 0-7506-4281-5
14
Total Design
Integrated Methods for
Successful Product
Engineering
Stuart Pugh
15
61
APPENDIX A:
A1.
The term Monte Carlo is used to describe methods of solution using the laws of
probability to reach a statistical estimate of a desired quantity. The basic principle is
that a process may be simulated by an average of a series of random events if
certain characteristics of the events are appropriate to the process being simulated.
The Monte Carlo simulation runs the process a large number of times, assigning
random values to the events and taking an average of all the outcomes. The result of
any Monte Carlo activity is always a simulation of the process, not an analysis of it.
In principle, two successive Monte Carlo process runs of the same event with
identical initial conditions will produce different answers. The average result for the
large number of processes run converges to a common solution. Monte Carlo
techniques are generally most suitable for situations where the probability equations
for the process are intractable or, possibly, not capable of explicit formulation.
For example, if (as is required for this study), it is desired to estimate the proportion
of its lifetime for which a device will be operating correctly, and the number of
occasions during that period when it will become necessary to repair the device, it is
in principle possible to construct a tree showing the probability of each of the
following circumstances:
1. Device operates without failure for whole design lifetime
2. Device operates for most of design lifetime, fails, but cannot be repaired
before design lifetime expires
3. Device operates for most of design lifetime, fails, is repaired, and operates for
remainder of life
4. Device operates for most of design lifetime, fails, is repaired, fails again and
cannot be repaired
5. (and so on...)
Figure A.1 below illustrates the situation for a device, which may be in either of two
mutually exclusive states, state A (available) or state U (unserviceable). The
transition AU, with probability PAU , represents failure, and the transition UA, with
probability PUA, represents repair. The overall lifetime of the device TT comprises N
equal time intervals I. The time during which the device is available is TA. The
availability of the device overall is given by TA/T T. The device starts in state A, and
in any given interval I its probability of failure is constant and is described as (PAU)I.
The probability of device failure over its complete lifetime TT is denoted by (PAU) T
note the single subscript.
The diagram gives expressions for the probability of each outcome. By definition,
the sum of the probabilities of all possible outcomes (i.e. including those not shown
in the diagram) is unity. It is apparent that the complexity of this approach increases
geometrically with the probable number of failures during the device lifetime.
Note that the probability expressions given in the diagram cannot in general be
evaluated without knowledge of the intermediate times t1...tn. By definition, these are
62
unknown, because they represent the times to random failure events, and
(potentially random) repair times following each failure event. The explicit
calculation method also becomes more complex if the probabilities of each event
are themselves functions of some other variable. A situation considered as part of
this study is the effect of seasonal weather conditions on the repairability of the
device, assessed for the purposes of the study by assuming that P UA is a function of
elapsed time. The underlying assumption is that whilst the possibility of repair
depends on the availability of appropriate spare parts and other resources, an
overriding consideration is simply whether the device is accessible in order for the
repair to be performed. For example, a device which fails at the onset of winter is
likely to be out of commission longer than one which fails identically at the height of
summer, simply because weather conditions preclude maintenance access to the
former device.
Final State
Overall probability
Availability
A
(no failure)
(1-PAU ) T = (1-PAU) I N
TT /TT (100%)
U
(one
unrepaired
failure)
t1/TT
A
(one
repaired
failure)
U
(one
repaired
failure,
one
unrepaired
failure)
A
(two
repaired
failures)
START
A
A
A
(PAU ) t1
(PUA) t2-
First failure
t1
t1
First repair
U A
(PAU ) t3-
t2
t2
(PUA) t4-
t3
Second
failure
A
U
t3
U
U A
Second repair
t4
(etc.)
Figure A.1
63
For this study, several mode lling approaches were considered before construction of
the actual models used. Consideration of the various conditions in which a tidal
turbine might exist led to the concept of an eighteen state model, representing the
machine throughout its life cycle. The eighteen state model was considered to be
comprehensive, but as a result included conditions which would probably have little
effect on the outcome of the comparative study. The complexity of the model
increases rapidly with increasing number of states (in part, because the number of
possible transitions increases geometrically with the number of possible states), and
it was considered that the additional information provided by this model did not
justify the extra complexity relative to a simple system. The eighteen state model
encouraged the development of a notation to identify the various states, which was
preserved (with one modification) for subsequent work.
Elimination of the (assumed) least frequently encountered states from the eighteen
state model led to the development of a five state model. Contemplation of this
model led to the conclusion that it still represented excessive detail for the purpose
of this study (although either the eighteen state or five state models might be
worth further study in the context of an investigation focused on the detailed
economics of a particular device).
All the models use the concept of time measured in periods, with values chosen to
be of significance to the desired outcome. No specific timescale is explicitly defined
for a period; it needs to be long enough to allow modelling of a meaningful
proportion of the device lifetime, without the creation of excessively large computer
files, but short enough to capture detail. An instance of unserviceability can never be
shorter than a complete period, so use of excessively long periods will lead to
unrealistically low estimates of device availability.
64
It is vital that values of transition probabilities used in the simulations are scaled to
match the period chosen for the series of experiments. For this reason, use of
excessively short periods not only results in extra computer time, but also implies
that failure probabilities (as entered) become negligible. As an example, a device
with a failure probability of 0.0001 per hour has a 50% probability of failure after a
period of 6931 hours (0dp), or about 9 months. To model the same device at
periods equivalent to one second, the failure rate per period must be entered as
0.00000003. A failure rate of 0.0001 per hour is possibly too high for economic
viability of a tidal turbine. Typical period and experiment durations used for this
study included:
240 periods (20 years with 1 period 1 month)
312 periods (6 years with 1 period 1 week)
1560 periods (30 years with 1 period 1 week)
A2.1 Eighteen-state model
Figure A.1 below shows the main features of the eighteen state model. The various
states are identified and described fully in the table below. An important feature of
this model was that each state was associated with a three-by-three matrix
expressing the output as scaled full (i.e. whatever would be expected given the
conditions at the time), degraded or zero, and the accessibility of the device as
irrelevant, accessible for repair or inaccessible for repair.
The CD & DC transitions (and corresponding pairs between other states) were to be
determined by a random or partially random variable; these transitions representing
occasions when the weather and/or sea state became unsuitable or suitable to
permit safe access to the device..
65
Scaled full
output
Accessibility
irrelevant
Degraded
output
F
H
Zero output
I
K
M
L
N
Y
Figure A2
Certain transitions (shown with dashed arrows in the diagram) were solely the result
of operator action. It was contemplated that operator strategy might affect overall
farm economics, by (for example) only permitting limited degradation before
shutting the machine down. However, a machine having been repaired or
reconditioned was assumed to be returned to service as soon as possible without
operator action. It was assumed that the probability of destruction would always be
lower from a non-operational than from an operational state.
The effect of operator strategy, whilst possibly of importance to the operator of a
tidal turbine farm (and an interesting topic for study in its own right), is not directly
y
relevant to the aims of this study, so for this purpose represents an undesirable
complication.
66
Notation
Description
Accessible?
Output
Remarks
100%
0%
0%
0%
Failed completely
0%
Failed completely
0%
0%
0%
Commissioning
0%
Interrupted commissioning
0%
Decommissioning
0%
Interrupted decommissioning
0%
67
0100%
0100%
0100%
0100%
Decommissioned
0%
Out of water?
Destroyed
0%
Table A1
Whilst the above forms a comprehensive representation of the life cycle of a device,
most of the time must be spent in state A for economic viability. It is questionable
what value may be had from the fine detail of the minority of the time spent not
operating.
A2.2 Five-state model
A significant difference between the eighteen state and the five state models was
that for the five state model, accessibility was no longer considered as an explicit
feature of the solution. Seven of the eighteen states in the eighteen state model
directly corresponded with seven of the other states, the sole distinction being
whether repair operations were possible. The model could be simplified by replacing
the duplicated states with variable transition probabilities, such that (for example) a
low value for repair probability could correspond to winter conditions and an
inaccessible device, whilst a higher value might reflect summer conditions.
It was also recognised that some of the states were trivial for the purpose of
calculating device availability and maintenance. For example, logically, a device
having been repaired would indeed spend a short time in state B (serviceable but
shut down) before being returned to full operation, but in practice the amount of
time spent in B would be short (of the order of a few hours) compared to a time
step of the Monte Carlo simulation (of the order of a week, or perhaps a month).
The result of these considerations was the model shown at Figure A3 below.
Operating states are as described for the eighteen state model above, except that
the accessibility of the device is not explicitly known from the operating state.
The diagram includes notations for the probabilities of various transitions (omitted
from the eighteen state diagram for clarity).
Note that PVW where V=W represents the probability that the machine will remain in
its present state. Also, PKK may be related to the mean time to repair the machine. PII
and PCK may be related to the accessibility of the machine owing to weather
conditions (although these also depend on the availability of parts and labour to
conduct a repair).
68
PAA
PAZ
PAC
Degraded
output
Zero output
Figure A3
PCC
PAI
C
PCZ
PCK
PCI
PII
PKA
PKK
PIK
PKZ
I
PI Z
P ZZ=1
Five-state model
Probabilities of transitions between the various states are also shown in Table A2
below.
Initial state
Final state
Table A2
PAA
PAC
PAI
PA Z
PCC
PCI
PCK
PCZ
PII
PIK
PI Z
PKA
PKK
PKZ
The total number of possible sequences for a run of N time periods is thus 4N,
although some of these sequences are trivial, and if the objective is to estimate the
availability and number of repair events, it is likely that many sequences will be
69
equivalent. However, it should be remembered that the above model, run with time
periods representing one week for 52 periods, i.e. representing one full year of
operation, could produce in principle any of approximately 2x1031 possible
outcomes, ignoring the fact that, as implied above, some of the outcomes are
impossible.
This example highlights how complex even an apparently simple model such as the
above may be in practice. It was considered desirable to simplify the model even
further for the purposes of this study.
A2.3 Two-state model
PAA
Figure A4
A
PAU
Zero output
Scaled full
output
The five-state model may be simplified further by assuming that the probability of
device destruction is identical for each device, and in any event sufficiently small to
have little effect on the overall farm economics. It may be argued that, for the
purpose of calculating device availability, it matters little whether a device has
failed (state I) or is under repair (state K), because in neither case is it
generating. The foregoing arguments imply a three-state model, which is working
normally, working at reduced output or not working. As a final simplification,
ignoring the state of degraded operation results in a two-state model (with a
change of notation), which is either in state A (available and operating) or state U
(unserviceable). This forms the basis of the model used for most of this study, Figure
A4.
PUA
U
PUU
Two-state model
Again, PVW V=W represents the probability that the machine will remain in its present
state. Probabilities of transitions between the various states are also shown in the
table below.
For this model, PA U (failure probability per time increment) may be constant, or could
in principle be a function of some other variable. For example, PAU could be a
function of elapsed time chosen to simulate general wear and deterioration or
perhaps to replicate the well-known bathtub failure rate curve.
70
Initial state
Final state
A
PAA (=1(=1-PAU)
PA U
P UA
P UU (=1(=1-P UA)
Table A5
PUA is perhaps best represented as a function of elapsed time. It may then represent
the effects of bad weather precluding access to the device for part of the year.
For much of the work conducted in support of this study, PUA was modelled as:
PUA =PUAmax-(A1[sin(2(A4t +A3)/TT)]M )
where
PUAmax = maximum value of PUA allowed for the given series of experiments
A1
= Arbitrary constant, controlling the minimum value of P UA for the series of
experiments
A3
= Arbitrary constant, controlling the phase shift of the PUA curve
A4
= Arbitrary constant, controlling the period of the PUA curve
t
= Elapsed time
TT
= Total time (in periods)
M
= Exponent (positive integer) Note that the value of A4 differs by a factor of 2
for a given P UA curve period, according to whether the exponent is even.
This function was chosen to give a reasonable degree of control over the form of the
PUA curve without the user having to input a large number of arbitrary constants.
For example, the idea was considered of allowing the user to input a separate PUA for
each period of the experiment, or at least for a recurring subset of the experimental
periods, so allowing (for example) repair probabilities to be defined for each
calendar month. This would add seven degrees of freedom to the model (versus the
sinusoidal model described above), but would not necessarily clarify the results.
Reference 11 was used to estimate a range of access probabilities for a notional
device in likely UK locations. Correspondence between the power-sine PUA function
incorporated in the Monte Carlo simulation and the access probabilities calculated
from Reference 11 over the course of a calendar year varied; in some cases a close
match was obtained whilst in others the power-sine formulation could replicate the
maximum and minimum or the mean values, but did not otherwise display good
correspondence with the Reference 11 function.
71
APPENDIX B:
CASES ASSESSED
The various cases assessed are summarized in the table below. The complete run
plan (and results, when available) was populated into a spreadsheet containing full
details of assumed costs etc. In general, all run inputs matched those for Case 1.0
unless otherwise specified, with the main exceptions that overall device availability
and expected number of failures vary according to failure rate, accessibility and (for
those cases modelling no unscheduled maintenance) maintenance interval.
Case
For all runs, equipment was ordered so as to produce maximum farm output as
soon as possible, and automatic re-ordering of all equipment except mountings was
permitted, so each run modelled a farm generating for a twenty-five year period
within an overall run duration of thirty years, including decommissioning of all
installed mountings (but not including any other site decommissioning cost
element). Note that the individual cases were not calculated in the order listed in
Table B1 below.
List of Cases Assessed
1.0
1.1
1.2
2.0
2.1
2.2
Description
Remarks
3.1
3.2
4.1
4.2
4.3
4.4
5.1
72
5.2
6.0
6.1
6.2
6.3
6.4
6.5
7.0
7.1
7.2
8.0
8.1
8.2
9.0
9.1
9.2
9.3
9.4
9.5
9.6
9.7
Table B1
Cases assessed
73