In 2000, auditors looked at non-completion of the project, non-accrual of intended benefits and widespread mismanagement of payment to contractors, particularly with reference to construction of the project up to headworks [barrage]. The report had not been discussed by the Odisha State Assembly's Public Account Committee as of August 2008.
In 2008, auditors noted that "due to delay in acquisition of land / nonacquisition of land, nonreceipt of forest land clearance and poor contract management, the project remained incomplete at various stages with investment of Rs 1695.61 crore (March 2008) resulting in cost overrun by Rs 1461.97 crore (626 per cent) and time overrun by 17 years."<ref>http://www.cag.gov.in/html/cag_reports/orissa/rep_2008/civil_chap_3.pdf {{Bare URL PDF|date=March 2022}}</ref>