1.
PLAN - from LS2 to RUN3-LS3 and outcomes from the first RUN3-LS3 PLAN exercise / Dos Santos Pedrosa, Fernando (CERN) ; Borglund, Ayla (CERN) ; Daudin, Benoit (CERN) ; Vergara Fernandez, Estrella (CERN) ; Tock, Jean-Philippe (CERN) ; Foraz, Katy (CERN) ; Bernardini, Marzia (CERN) ; Lanza Herrero, Rodrigo (CERN)
The CERN-wide coordination of the programmed stops requires a tool to centralize and collect all the activities at a macroscopic scale. It includes the activities foreseen during Long Shutdowns (LS) and Year End Technical Stops (YETS).The CERN tool named PLAN centralises all the activities foreseen by the Groups, to have a global strategic view, assessing priorities across CERN. [...]
2023 - Published in : JACoW IPAC 2023 (2023) TUPM074 Fulltext: PDF;
In : 14th International Particle Accelerator Conference (IPAC 2023), Venice, Italy, 7 - 12 May 2023, pp.TUPM074
2.
Run3 Installation Coordination / Tock, Jean-Philippe (CERN) ; Bedel, Cyrille Patrick (CERN) ; Bernardini, Marzia (CERN) ; Etheridge, John Robert (CERN) ; Fessia, Paolo (CERN) ; Lambert, Anna (CERN) ; Loertscher, Yves (CERN) ; Masterson, Raoul (Ministere des affaires etrangeres et europeennes (FR)) ; Modena, Michele (CERN) ; Roesler, Stefan (CERN) et al.
After reminding the mandate and the scope of the Run3 Installation Coordinator, the Run3 team members and their respective assignments will be present-ed [...]
CERN-ACC-NOTE-2022-0037.
- 2022. - 4 p.
Full text
3.
PLAN Tool / Baltasar Dos Santos Pedrosa, Fernando (CERN) ; Masterson, Raoul (Ministere des affaires etrangeres et europeennes (FR)) ; Tock, Jean-Philippe (CERN) ; Daudin, Benoit (CERN) ; Klem, Doreen (CERN) ; Lanza, Richard
To complete its mission, the Run3 Installation Coordination team needs a tool to centralize and collect, at a macroscopic scale, all activities to be performed in the programmed stops for Run3 and LS3, including those postponed from LS2. [...]
CERN-ACC-NOTE-2022-0040.
- 2022. - 3 p.
Full text
4.
Processes and Tools to Manage CERN Programmed Stops Applied to the Second Long Shutdown of the Accelerator Complex / Vergara Fernandez, Estrella (CERN) ; Ansel, Antoine (CERN) ; Barberan Marin, Maria (CERN) ; Bernardini, Marzia (CERN) ; Chemli, Samy (CERN) ; Coupard, Julie (CERN) ; Foraz, Katy (CERN) ; Hay, David (CERN) ; Jimenez, José (CERN) ; Mcfarlane, David (CERN) et al.
The preparation and follow-up of CERN accelerator complex programmed stops require clear processes and methodologies. The LHC and its Injectors were stopped in December 2018, to maintain, consolidate and upgrade the different equipment of the accelerator chain. [...]
2022 - 4 p. - Published in : JACoW IPAC 2022 (2022) 2048-2051 Fulltext: PDF;
In : 13th International Particle Accelerator Conference (IPAC 2022), Bangkok, Thailand, 12 - 17 Jun 2022, pp.2048-2051
5.
Configuration management of the CERN accelerators complex on the road to long shutdown 3 / Perrot, A L (CERN) ; Bartolomé-Jimenez, S (CERN) ; Birtwistle, T (CERN) ; Chemli, S (CERN) ; Feral, B (CERN) ; Garcia Gavela, H (CERN) ; Oliveira, J (CERN) ; Ronfaut, V (CERN)
The Configuration Management of the LHC and its injectors ensures a clear and coherent representation of the CERN accelerators at a given point in time. It has been evolving steadily. [...]
2023 - 3 p. - Published in : JACoW IPAC 2023 (2023) MOPL028 Fulltext: PDF;
In : 14th International Particle Accelerator Conference (IPAC 2023), Venice, Italy, 7 - 12 May 2023, pp.MOPL028
6.
Interlock System Upgrades at the CERN Accelerator Complex During Long Shutdown 2 / Uythoven, Jan (CERN) ; Antoine, Alain (CERN) ; Martin, Christophe (CERN) ; Mirana Fontan, Adrian (CERN) ; Mompo, Richard (CERN) ; Romera Ramírez, Iván (CERN) ; Secondo, Raffaello (CERN)
The CERN accelerator complex stopped operation at the end of 2018 for the Long Shutdown 2 (LS2), allowing for the LHC Injector Upgrade program (LIU) and consolidation work to be accomplished. A gradual restart of the different accelerators is ongoing in 2021, culminating with the LHC foreseen to be back in operation early 2022. [...]
Geneva : JACoW, 2021 - 4 p. - Published in : JACoW IPAC '21 (2021) 3316-3319 Fulltext: PDF;
In : 12th International Particle Accelerator Conference (IPAC 2021), Online, 24 - 28 May 2021, pp.3316-3319
7.
Programmed Stops Coordination: from Preparation to Completion / Vergara Fernandez, Estrella (CERN) ; Bernardini, Marzia (CERN) ; Chemli, Samy (CERN) ; Corso, Jean-Pierre (CERN) ; Coupard, Julie (CERN) ; Etheridge, John Robert (CERN) ; Grillot, Serge (CERN) ; Muttoni, Yvon (CERN) ; Nicquevert, Bertrand (CERN) ; Perrot, Anne-Laure (CERN) et al.
The exploitation of the CERN accelerator complex requires programmed stops of the operation, to execute various activities as standard maintenances, upgrades, consolidations and projects implementations [...]
CERN-ACC-NOTE-2022-0036.
- 2022. - 5 p.
Full text
8.
Planning of Interventions With the Atlas Expert System / Asensi Tortajada, Ignacio (CERN ; Valencia U.) ; Rummler, Andre (CERN) ; Solans Sanchez, Carlos (CERN) ; Torres Pais, Jose (Valencia U.)
The ATLAS Technical Coordination Expert System is a tool for the simulation of the ATLAS experiment infrastructure that combines information from diverse areas such as detector control (DCS) and safety systems (DSS), gas, water, cooling, ventilation, cryogenics, and electricity distribution. It allows the planning of an intervention during technical stops and maintenance periods, and it is being used during the LS2 to provide an additional source of information for the planning of interventions. [...]
2020 - 4 p. - Published in : 10.18429/JACoW-ICALEPCS2019-MOCPR03 Fulltext: PDF;
In : 17th Biennial International Conference on Accelerator and Large Experimental Physics Control Systems (ICALEPCS), New York, United States, 5 - 11 Oct 2019, pp.MOCPR03
9.
New Coordination Tools to Prepare the Programmed Stops in the LHC and its Injectors / Chemli, Samy (CERN) ; Bernardini, Marzia (CERN) ; Birtwistle, Thomas (CERN) ; Bolognesi, Andrea (CERN) ; Brito de Palma, Bernardo (CERN) ; Bustamante, Sebastien (CERN) ; Coupard, Julie (CERN) ; Foraz, Katy (CERN) ; Kleszcz, Emil (CERN) ; Kotsolakos, Nikitas (CERN) et al.
The LHC and its Injectors are submitted to an overall lifecycle of three to four years of physics delivery to Experiments with a two-year long stop, also known as Long Shutdown (LS). The years of physics delivery are ended by a programmed stop for the immediate preventive and corrective maintenance, also known as (Extended)-Year-End Technical Stop - (E)YETS. [...]
2018 - 4 p. - Published in : 10.18429/JACoW-IPAC2018-MOPMF044 Fulltext: PDF;
In : 9th International Particle Accelerator Conference, Vancouver, Canada, 29 Apr - 4 May 2018, pp.MOPMF044
10.
HL-LHC Planned Activities during LS2 - Accelerator / Béjar Alonso, I (CERN)
Geneva : CERN, 2015 Published version from CERN: PDF;
In : Chamonix 2014: LHC Performance Workshop, pp.284-287

Non hai trovato quello che cercavi? Prova la ricerca su altri server:
recid:2886988 in Amazon
recid:2886988 in CERN EDMS
recid:2886988 in CERN Intranet
recid:2886988 in CiteSeer
recid:2886988 in Google Books
recid:2886988 in Google Scholar
recid:2886988 in Google Web
recid:2886988 in IEC
recid:2886988 in IHS
recid:2886988 in INSPIRE
recid:2886988 in ISO
recid:2886988 in KISS Books/Journals
recid:2886988 in KISS Preprints
recid:2886988 in NEBIS
recid:2886988 in SLAC Library Catalog